Professional Documents
Culture Documents
Drainage System
(Topic 1: Sanitary Fixture Units and Pipe
Sizing)
1 Water sewage system
Sewage system
It is the arrangement provided in a house or building for
collecting or conveying waste water through drain pipes by
gravity, to join either a public sewer or a domestic septic tank is
termed as house drainage or building drainage
Soil pipe:
A soil pipe is a pipe through which
human excreta flows
Waste Pipe:
It is a pipe which carries only the liquid
waste. It does not carry human excreta
Vent pipe:
It is a pipe which is provided for the purpose of
the ventilation of the system. A vent is open at
top and bottom, to facilitate exit of foul gases. It
is carried at least one meter higher than the roof
level.
2 Type of water discharge’s pipe
3 Avoid the entry of foul gases from the sewer or the septic tank
1. P trap
2. Q trap
3. S trap
5 Component of waste water discharge system
- According to use
1. Floor trap (Nahni)
2. Gully trap
3. Intercepting traps
4. Grease traps
Nahni Trap
5 Component of waste water discharge system
Gully Trap
6 Type of discharge system in building
– In no case should the fixture drain size be reduced to less than that of the
discharge orifice, for to do so would cause a reduction in the rate of fixture
discharge.
– Instead, the size of the fixture trap and the fixture drain should be slightly
larger than that of the discharge orifice so that they will not affect the
discharge rate adversely after a moderate degree of fouling in normal service.
7. Fixture Drain
Stack Capacities:
– In any event, as soon as the water enters the stack, the force of
gravity rapidly accelerates it downward, and as it falls, the water
assumes the form of a sheet around the wall of the stack, leaving the
center of the pipe open for the flow of air.
– This sheet of water continues to accelerate until the frictional force
exerted by the wall of the stack on the falling sheet of water equals the
force of gravity.
9. Drainage stack and branches
Stack Capacities:
– The investigation from both F.M. Dawson and Dr. Hunter, in entirely
independent, came to the conclusion that slugs of water, with their
accompanying violent pressure fluctuations, did not occur until the
stack flowed one-quarter to one-third full. Most model codes have
based their stack loading tables on a value of r = ¼ or 7/24 (Table
1-2).
– Based on the computed drainage stack flow capacity for stacks
flowing 7/24 full at terminal velocity, the corresponding number of
fixture units may be determined from design load charts or Tables
1-3 so as to establish the total load which may be placed on a tall
drainage stack.
9. Drainage stack and branches
Design load: the capacity of stack pipe diameter corresponding to the ratio of the cross-
sectional area of the sheet of water to the cross-sectional area of the stack (r)
9. Drainage stack and branches
Stack Capacities:
The procedure for sizing a multistory stack (greater than three floors) is:
– First to size the horizontal branches connected to the stack. This is done
by totaling the fixture units connected to each branch and using the
corresponding figure in column 2 of Table 1-3.
– Next, total all of the fixture units connected to the stack and determine
the size from the same table, under column 4.
– Check the next column, total at one branch interval, to determine if this
maximum is exceeded by any of the branches.
– If it is exceeded, the stack as originally determined must be increased at
least one size, or the loading of the branches must be redesigned so the
maximum conditions are satisfied
9. Drainage stack and branches
Example 1-3:
Calculate the total number of DFU, and size the horizontal branch connecting
the two adjacent bathrooms, knowing that, the total fixture unit of each
bathroom consists of (water closet, bidet, lavatory and bathtub or shower) = 8
FUs
Solution:
Total fixture unit of two adjacent bath rooms connected to
the same horizontal branch pipe is : 8 x 2 = 16 FU’s.
As can be seen from table 1-3 for any horizontal branches, the 3” can handle
up to 20DFU but, due to the presence of the W.C.’s the 4” pipe diameter is
selected which can handle up to 160 DFU
9. Drainage stack and branches
Sizing stack in a 12-story building, with one offset
between the fifth and sixth floors and another offset
below the street floor as shown in figure. Step:
4) Size and slope the offset below the street floor the same as
a building drain.
9. Slope for horizontal drainage piping
These minimum slopes are required to maintain a velocity of flow greater than 2
fps for scouring action.
Table 1-5 gives the approximate discharge rates and velocities in sloping drains
based on the Manning formula for half-full pipe and n = 0.015.
9. Slope for horizontal drainage piping
9. Load for drainage piping
─ Sanitary building drains are designed to flow half full at peak load. To avoid backup of flow
from the building drain into branches, each branch connection to the building drain should
be made to its upper half or its air-space portion.
─ This may be achieved for 90 degrees branch connections by means of a one-sixth bend
and a 45 degrees Y branch or a long-sweep one-quarter bend and a Y branch. The Y-
branch fitting may be rotated so that the branch is at 45 degrees angle above the
horizontal when the one-sixth bend is to be used and at a vertical angle when the long-
sweep one-quarter bend is to be used.
─ Less invert elevation is lost with the one-sixth bend and Y combination
03. Drainage System
(Topic 2: Vent System)
1 Introduction
Example 2-1
Determine the size of the main vent that will serve 30 fixture
units in case:
Example 2-2
How large is the main vent required for
fixture consisting 4 water closets, 4
lavatories, 3 showers and 2 kitchen
sinks installed on the first floor of a two
storey building 6.0m high?
6. Drainage stack and branches
Solution 2-2
– Solving for total fixture units with
the aid of table 16.7
4 x 4WC =16FUs
1 x 4LV = 4FUs
2 x 3SW = 6FUs
2 x 2KS = 4FUs
Total = 30FUs
Example 2-3
Determine the size of the main vent required for a drainage
installation serving 90 fixture units installed on the first floor
of a 5 storey building with height of 19m.
Solution 2-3
– Referring to the Table 2-1, it shows that a 100mm (4”) pipe could
serve up to 100 FUs.
– Under the column of vent pipe require 63mm (2 ½”) could ventilate
100FUs as high as 30.5m
– Therefore, specify 63mm (2 ½ ”) vent pipe
7 Traps
─ The only separation between the unpleasant and dangerously unhealthy gases
in sanitary drainage pipes and the air breathed by room occupants is the water
caught in the fixture trap after each discharge from a fixture. Sufficient water
must flow, especially in water closets, to keep this residual water clean.
─ Consideration should
be given to such
criteria as the local
climatic conditions,
type of roof, slope of
roof, location of pipe
chases, and available
ceiling space to
install piping.
1 Roof leader
(a) a single wall surface (b) two opposing walls of (c) two adjoining walls of equal height
unequal height
2 Roof drainage system
Solution 3-2:
Area supplied by a drain pipe = (Area of the balcony) +(area of the
adjacent wall)+ Part of the roof area
= [(2x10)x5] + [((15x2)/2)x5)+65 =240 m2 ,
The gutters can have shapes other than semicircular provided that the
flow area is maintained equal to the flow area of a gutter with a
semicircular shape given in Table 19.4.
For the length of gutter more than 15.2m (for example 20m), rain
water has to travel a long way. It might be overloaded and
overflow.
Type of underground
Drainage For buildings
Separated Sewer
& rain water
system Combined
Sewer + Rain water
2 Connections of the rain water drain
In the case of combined system (Sewer + Rain water),
rainwater must be connected to the foul water drain
through a back inlet gully, to prevent the smell as
shown in Fig. 4.1.
Grease Traps
─ Special gullies for the collection of grease are not
required for houses, but for canteen kitchens
where the waste water from the sinks and
dishwashers contains a considerable amount of
grease they are essential.
Where:
Q= flow rate ft3/sec.
A = Wetted area ft2, (half pipe cross sectional area)
n = roughness of surface (table below)
R = Hydraulics radius (Area/wetted perimeter).
S= Slope 0.5 -1% from Chezy formula
Value of Manning “n”
4 Hydraulics radius R
4 Hydraulics radius R
5 Channel slope S
From the above formula , it is clear that the flow down is caused by
the difference in potential energy or gravity . On the other hand the
variable n known as Manning s, is a measure of the roughness of the
channel.
Note:
PVC pipe is used where n = 0.01, flow Running half full & recommended slope is 1% .
6
Design underground sewer pipe system:
Table for Estimating the demand in water supply system
(Can be used to convert the DFU to gpm or L/s)
6 Design underground sewer pipe system:
Example 4-1
Water at the rate of 0.1m3 /s flows through a 1m pipe diameter vitrified
sewer when the sewer pipe is half- full. Find the slope of the water, if
Manning’s n is 0.013
Solution 4-2
- Given discharge Q = 0.1m3 /s
- Diameter of pipe D =1m
Area of flow A = (3.14/8)(1)2 = 0.393m2
- Wet parameter P = (3.14)(D/2) = 3.14/2 = 1.57m
Hydraulic radius RH =A/P = 0.393/1.57 = D/4 = 0.25m
- Manning coefficient n = 0.013
Slope S can be determine by:
So:
Discharge value
of circular pipe
(Running Haft
Full) using
Manning Eq for
n = 0.009
Discharge value of circular pipe (Running Haft Full) using Manning Eq for n = 0.012
Discharge value of
circular pipe
(Running Haft Full)
using Manning Eq
for n = 0.013
7 Manholes