Revision History
Revision date Revised by Approved by Description of change
01/20/2022 Paige Tadlock Jonianne Bustillos Change in need for multimedia
equipment for PowerPoint
02/08/2022 Paige Tadlock Jonianne Bustillos Measures of success
Phases or Timeline
MODIFIED FROM
Fast Foundation for Project Management – Statement of Work
Reference The Fast Forward MBA in Project Management
Filename: 603612800.docx 1 of 4
Statement of Work and Plan [Summer Launch Meeting]
Last Revised: [02/08/2022]
Work to Be Performed
All project tasks
2. Determine how many people are attending Paige Tadlock (PM) 02/07/2022
4. Decide how ads will be voted upon Paige Tadlock (PM) 02/25/2022
5. Plan meeting agenda structure and flow Paige Tadlock (PM) 03/17/2022
Out of scope activities that are critical to the success of the project
2. Connect projector for presentation and check microphones and internet service
Meeting agenda/schedule 03/17/2022 Organize information and topics into easily understood steps
that lead to final result. Ensure that main purpose for meeting is
understood and achieved.
PowerPoint presentation 04/29/2022 Each member of the project management team is responsible
for their own slide and information that they must share.
Presentation must be reviewed by Paige (PM) in order to
alleviate mistakes and misinformation.
Voting upon advertisements 02/25/2022 Having a set way to vote already planned ahead of time will
prevent confusion and will ensure consistency and organization
throughout the entire process instead of wasting time to decide
the guidelines for casting votes.
MODIFIED FROM
Fast Foundation for Project Management – Statement of Work
Reference The Fast Forward MBA in Project Management
Filename: 603612800.docx 2 of 4
Statement of Work and Plan [Summer Launch Meeting]
Last Revised: [02/08/2022]
Risk Analysis
Multimedia devices are not Project management team Schedule time with IT before meeting to
working properly on day of unable to visually provide ensure that things are working correctly
meeting information and marketing team
unable to show potential
advertisements
Marketing team unable to The goal for the meeting will not Making deadline for advertisements months
submit potential ads before the be attained before launch and meeting to ensure that
meeting everything is completed before the launch in
June
Team member is ill and cannot Unexpected adjustments At least a week before the meeting, get
come to meeting to present needing to be made, resulting in together with team to discuss final drafts of
slides team being less prepared slides for the meeting so every team
member can collaborate and know the
information on every slide and not just their
own
Office space is scheduled too Nowhere to present the Scheduling the sufficient office space
close to meeting date and information and be able to significantly in advanced to ensure
there is not availability achieve the goals for the meeting availability meets needs
before the summer launch
Measures of Success
MODIFIED FROM
Fast Foundation for Project Management – Statement of Work
Reference The Fast Forward MBA in Project Management
Filename: 603612800.docx 3 of 4
Statement of Work and Plan [Summer Launch Meeting]
Last Revised: [02/08/2022]
Stakeholder Analysis
Name & Role Major Responsibility or Contribution
[Internal Affair] Companywide product launch for the summer. Needed a
Customer meeting for marketing team and project management to
collectively design the plan for advertisements for launch.
[Jonianne Bustillos] Develop guidelines to be followed and executed in order to be
Sponsor/Marketing held to quality criteria.
[Paige Tadlock] Guide, support, and execute the production of the presentation
Management and meeting in order to achieve goal for meeting
Team Present information and execute voting on advertisements that
will be chosen for summer launch.
Assumptions
Assumption: Team members will be knowledgeable enough on the information to be able to inform
others
Impact if assumption is incorrect: The goal for the meeting will not be achieved and it could impact
the success of the launch
Assumption: All multimedia equipment will function correctly at meeting
Impact if assumption is incorrect: The information and advertisements will not be accurately
delivered
Assumption: Having the meeting in May gives us enough time to be prepared for the launch
Impact if assumption is incorrect: Launch is late
Assumption: Only one meeting is suffice for planning the launch advertisements
Impact if assumption is incorrect: Launch is not as successful as we had hoped