Dear Sirs,
PROJECT TITLE : CADANGAN MEMBAIKPULIH 1, UNIT BANGUNAN PERJABAT 2 TINGKAT DIATAS LOT
743, SEK 23, DTL, GEORGETOWN, PULAU PINANG.
DATE : 31st MAY 2022 VENUE : BUILDING NO 7 SITE / THE GLASS HOUSE
PRESENT
NAME COMPANY EMAIL CONTACT
TOMMY KOAY PPH tommy@pph.com.my 012-4939908
JESSICA PPH jessica@theprestige.my 012-4103157
THOR SAW KHIM 7DSM tskhim@7dsmgroup.com 016-4455789
SITI NOR HADIANA CHAN 7DSM chanadiana@gmail.com 017-4017606
PPH MS JESSICA
POSITION :
1.3 CLIENT PIC ON SITE CONTACT NO PPH ONLY MR TOMMY KOAY AS DONE
CONTACT PERSON AND
WHATSAPP GROUP REPORT
/ EMAIL TO CC TO MS
JESSICA
1.4 DATE OF REMOVAL OF ALL VALUE PPH TO SHIFT THE VALUE ITEM TARGET ON
ITEMS BACK TO FACTORY BY PPH 2/06/2022
1.5 HOTEL PEAK SEASON THAT NOT PPH SCHOOL HOLIDAY IN JUNE INF
SUITATLE TO WORK 2022 AND TO CONFIRM
OTHER PEAK SEASON AGAIN
2.2 FIRST FLOOR SLAB REPAIR 7DSM TO BE RE CHECK ON SITE REF TOILET SLAB
SOFIT
RESUBMIT MOS
WITH PHOTO
INCLUDED
STAIRCASE
STRUCURE
REPAIR WORKS
NEW MOS
EMAILED
2.5 STRUCTURE REPAIR – COLUMN 7DSM MOS HAS BEEN SUBMITTED 17/05/2022
SHALL PROCEED HACKING
WORKS AFTER REMOVAL OF
VALUE GOODS ON SITE
PPH PENDING :
REQUEST CONFIRMATION
ON THE BELOW BEFORE
EXERCUTION OF WORKS
1) PENDING DATE OF
REMOVAL OF
VALUABLE MATERIAL
BY CLIENT
2) IF THE REMOVAL OF
PARTITION WALL IS
CONFIRM ,
PROPOSED TO
DEMOLISH WALL
BEFORE START
REPAIRING COLUMN
QUOTATION APPROVED ON VO NO 1
20/05/2022
START WORK : 13/06/2022
COMPLETION : 10DAYS
3.3 SEWARAGE WORK SHALL BE PPH PPH SHALL DECIDE ON THE PENDING
ARRANGE AND RECONFIRM ON FINISHING MATERIAL CONFIRMATION
SURFACE FINISHING MATERIAL EXPECTATION FROM CLIENT
7DSM SHALL PROVIDE
DRAWING AND LEVELING
BEFORE START WORK
2ND MOCK UP TO
BE DONE ON
SUN SHINING
AREA 24/05/2022
IN PROGRESS :
1) SLAB
CASTING
DONE ON
23/05/2022
C) DETAIL SHOP
DRAWING AND
POSITIONING OF THE
LAY OUT VARIES
FROM ORIGINAL
DRAWING
SUMMARY OF RFCA
1) TOILET INCLOMING
PIPING WORKS
2) PAINTING WORKS
3) WALL DEMOLISHING
WORKS
4) STAIRCASE WALL
REPAIR , PLYWOOD
WALL REMOVAL ,
STAIRCASE
TRUCTURE
REPAIRING WORKS
1) SITE CLEARANCE
2) ELECTRICAL SUPPLY
ISSUE
3) PERMIT APPLICATION
( MPPP )
PREPARED BY
7DSM PROJECTS SDN BHD
SITI CHAN
_________________________________________________________________________________________________
The meeting minutes was read and confirmed without any amendment.
Name : ___________________________________
Date : ___________________________________
Company Chop :