Monitoring and Evaluation
There is a prevalent notion in the current planning practice of the Philippines: rather
than a continuous/cyclical process, planning is considered as a simple process of producing a
plan document or project with ‘time start’ and ‘time finish’ elements.
Monitoring and Evaluation involves decisions on what needs to be done, why, how by
whom and when. The Monitoring and Evaluation and implementation plan for the Local
Disaster Risk Reduction and Management Plan of Isabela City will be drawn up against
strategic objectives of LDRRMP to support the implementation of activities towards the
achievement of outcomes.
Monitoring and evaluation will be done through committee and council meetings to
ensure the transparency and progress of programs, projects, and activities of the four
thematic areas of disaster risk reduction and management framework.
99
THEMATIC AREA: DISASTER PREVENTION AND MITIGATION
PROGRAM, PROJECT AND ACTIVITY (PPA): Conduct Community Exposure and Vulnerability
Assessment
BASELINE ASSUMPTIONS/ OBJECTIVELY TARGETS DATA COLLECTION FREQUENCY OPR/PPR RESOURCES
RISKS VERIFIABLE SOURCES METHODS AND NEEDED
INDICATORS AUDIENCE
TO REPORT
TO
Annually to Administrative
Lack of trainings Inventory of Buildings After LDRRMC; CDRRMO, expenses for
Established by the buildings established CEO, Activity Disaster CEO training and
buildings LDRRMCs in Isabela CDRRMO Report; Site Prevention inspection
members City Inspection and (Materials,
Mitigation Venue, meals,
Committee and
transportation)
Crops in Lack of trainings Inventory of Barangays CAgO, After Annually to CDRRMO, Administrative
Isabela by the crops with crop CDRRMO Activity LDRRMC; CAgO expenses for
City LDRRMCs farming in Report; Site Disaster training and
members Isabela Inspection Prevention inspection
City and (Materials,
Mitigation Venue, meals,
Committee and
transportation)
100
PROGRAM, PROJECT AND ACTIVITY (PPA): Conduct Rapid Earthquake Damage Assessment
System
BASELINE ASSUMPTIONS/ OBJECTIVELY TARGETS DATA COLLECTION FREQUENCY OPR/PPR RESOURCES
RISKS VERIFIABLE SOURCES METHODS AND NEEDED
INDICATORS AUDIENCE
TO REPORT
TO
Administrative
LDRRMC Lack of trainings No. of Members of Annually to expenses for
members by the LDRRMC the Local After LDRRMC; CDRRMO training and
LDRRMCs members Disaster Risk CDRRMO Activity Disaster inspection
members trained on Reduction Report; Site Prevention (Materials,
REDAS and Inspection and Venue, meals,
Management Mitigation and
Council Committee transportation)
PROGRAM, PROJECT AND ACTIVITY (PPA): Installation of Early Warning System per hazards
BASELINE ASSUMPTIONS/ OBJECTIVELY TARGETS DATA COLLECTION FREQUENCY OPR/PPR RESOURCES
RISKS VERIFIABLE SOURCES METHODS AND NEEDED
INDICATORS AUDIENCE
TO REPORT
TO
101
City has legal Mitigation
basis for risk Committee
reduction
land use and
resettlement
PROGRAM, PROJECT AND ACTIVITY (PPA): Conduct Hazard and Capacity Analysis and
Assessment
BASELINE ASSUMPTIONS/ OBJECTIVELY TARGETS DATA COLLECTION FREQUENCY OPR/PPR RESOURCES
RISKS VERIFIABLE SOURCES METHODS AND NEEDED
INDICATORS AUDIENCE
TO REPORT
TO
102
PROGRAM, PROJECT AND ACTIVITY (PPA): Conduct Risk Assessment in the Community
BASELINE ASSUMPTIONS/ OBJECTIVELY TARGETS DATA COLLECTION FREQUENCY OPR/PPR RESOURCES
RISKS VERIFIABLE SOURCES METHODS AND NEEDED
INDICATORS AUDIENCE
TO REPORT
TO
PROGRAM, PROJECT AND ACTIVITY (PPA): Conduct Building and Infrastructure Inspection
BASELINE ASSUMPTIONS/ OBJECTIVELY TARGETS DATA COLLECTION FREQUENCY OPR/PPR RESOURCES
RISKS VERIFIABLE SOURCES METHODS AND NEEDED
INDICATORS AUDIENCE
TO REPORT
TO
103
buildings in Isabela Disaster (meals, venue,
established City Prevention and
and transportation)
Mitigation
Committee
PROGRAM, PROJECT AND ACTIVITY (PPA): Construction riverbank protection along Baluno
and Aguada river
BASELINE ASSUMPTIONS/ OBJECTIVELY TARGETS DATA COLLECTION FREQUENCY OPR/PPR RESOURCES
RISKS VERIFIABLE SOURCES METHODS AND NEEDED
INDICATORS AUDIENCE
TO REPORT
TO
PROGRAM, PROJECT AND ACTIVITY (PPA): Construction of seawall along the coastal
barangays in Isabela City
BASELINE ASSUMPTIONS/ OBJECTIVELY TARGETS DATA COLLECTION FREQUENCY OPR/PPR RESOURCES
RISKS VERIFIABLE SOURCES METHODS AND NEEDED
INDICATORS AUDIENCE
TO REPORT
TO
104
PROGRAM, PROJECT AND ACTIVITY (PPA): Memorandum of Agreement/Understanding
with lending agencies for disaster finance for government institution/facilities, emergency
vehicles, equipment, and responders
BASELINE ASSUMPTIONS/ OBJECTIVELY TARGETS DATA COLLECTION FREQUENCY OPR/PPR RESOURCES
RISKS VERIFIABLE SOURCES METHODS AND NEEDED
INDICATORS AUDIENCE
TO REPORT
TO
PROGRAM, PROJECT AND ACTTIVITY (PPA): Develop DRRM and CCA information,
education, communication (IEC) and advocacy plans
BASELINE ASSUMPTIONS/ OBJECTIVELY TARGETS DATA COLLECTION FREQUENCY OPR/PPR RESOURCES
RISKS VERIFIABLE SOURCES METHODS AND NEEDED
INDICATORS AUDIENCE TO
REPORT TO
PROGRAM, PROJECT AND ACTTIVITY (PPA): Conduct drills and exercises for all stakeholders
regularly.
BASELINE ASSUMPTIONS/ OBJECTIVELY TARGETS DATA COLLECTION FREQUENCY OPR/PPR RESOURCES
RISKS VERIFIABLE SOURCES METHODS AND NEEDED
INDICATORS AUDIENCE TO
REPORT TO
PROGRAM, PROJECT AND ACTTIVITY (PPA): Conduct trainings on Urban Search and Rescue
BASELINE ASSUMPTIONS/ OBJECTIVELY TARGETS DATA COLLECTION FREQUENCY OPR/PPR RESOURCES
RISKS VERIFIABLE SOURCES METHODS AND NEEDED
INDICATORS AUDIENCE TO
REPORT TO
BDRRMC Insufficient No. of personnel BDRRMC After Output Annually to CDRRMO Administrative
LDRRMC training trained Urban LDRRMC Activity LDRRMC expenses for
equipment Search and Report training
during the Rescue Disaster (Equipment
conduct of Preparedness Materials,
Urban Search Committee Venue and
and Rescue transportation
Training meals)
105
PROGRAM, PROJECT AND ACTTIVITY (PPA): Conduct trainings on Collapsed Structure Search and
Rescue
BASELINE ASSUMPTIONS/ OBJECTIVELY TARGETS DATA COLLECTION FREQUENCY OPR/PPR RESOURCES
RISKS VERIFIABLE SOURCES METHODS AND NEEDED
INDICATORS AUDIENCE TO
REPORT TO
BDRRMC Insufficient No. of personnel BDRRMC After Output Annually to CDRRMO Administrative
LDRRMC training trained LDRRMC Activity LDRRMC expenses for
equipment Collapsed Report training
during the Structure Search Disaster (Equipment
conduct of and Rescue Preparedness Materials,
Collapsed Committee Venue and
Structure Search transportation
and Rescue meals)
BDRRMC Insufficient No. of personnel BDRRMC After Output Annually to CDRRMO Administrative
LDRRMC training trained as First LDRRMC Activity LDRRMC expenses for
equipment Responder Report training
during the Disaster (Equipment
conduct of First Preparedness Materials,
Responder Committee Venue and
Training transportation
meals)
PROGRAM, PROJECT AND ACTTIVITY (PPA): Conduct trainings on Community-Based Disaster Risk
Reduction and Management
BASELINE ASSUMPTIONS/ OBJECTIVELY TARGETS DATA COLLECTION FREQUENCY OPR/PPR RESOURCES
RISKS VERIFIABLE SOURCES METHODS AND NEEDED
INDICATORS AUDIENCE TO
REPORT TO
BDRRMC Scheduling of No. of personnel BDRRMC, After Output Annually to CDRRMO Administrative
LDRRMC Instructors from trained in LDRRMC Activity LDRRMC expenses for
OCD conducting Report training
RDANA Disaster (Materials,
Preparedness Transportation,
Committee Venue and
meals)
PROGRAM, PROJECT AND ACTTIVITY (PPA): Conduct trainings on Emergency Operations Center
Course
106
BASELINE ASSUMPTIONS/ OBJECTIVELY TARGETS DATA COLLECTION FREQUENCY OPR/PPR RESOURCES
RISKS VERIFIABLE SOURCES METHODS AND NEEDED
INDICATORS AUDIENCE TO
REPORT TO
BDRRMC Scheduling of No. of personnel BDRRMC, After Output Annually to CDRRMO Administrative
LDRRMC Instructors from trained in LDRRMC Activity LDRRMC expenses for
OCD managing Report training
Emergency Disaster (Materials,
Operation Preparedness Transportation,
Center Committee Venue and
meals)
BDRRMC Scheduling of No. of personnel BDRRMC, After Output Annually to CDRRMO Administrative
LDRRMC Instructors from trained in LDRRMC Activity LDRRMC expenses for
OCD Incident Report training
Command Disaster (Materials,
System Preparedness Transportation,
Committee Venue and
meals)
PROGRAM, PROJECT AND ACTTIVITY (PPA): Conduct trainings on Swift Water Search and Rescue
BASELINE ASSUMPTIONS/ OBJECTIVELY TARGETS DATA COLLECTION FREQUENCY OPR/PPR RESOURCES
RISKS VERIFIABLE SOURCES METHODS AND NEEDED
INDICATORS AUDIENCE TO
REPORT TO
BDRRMC Scheduling of No. of personnel BDRRMC, After Output Annually to CDRRMO Administrative
LDRRMC Instructors from trained in Swift LDRRMC Activity LDRRMC expenses for
other agency Water Search Report training
and Rescue Disaster (Materials,
Preparedness Transportation,
Committee Venue and
meals)
BDRRMC Lack of No. of Barangay BDRRMC, After Output Annually to CDRRMO Administrative
commitment have trained Activity LDRRMC expenses for
from the Emergency Report training
Barangay Response Team Disaster (Materials,
Council Preparedness Transportation,
Committee Venue and
meals)
PROGRAM, PROJECT AND ACTTIVITY (PPA): Conduct trainings on All-Hazard Disaster Response
BASELINE ASSUMPTIONS/ OBJECTIVELY TARGETS DATA COLLECTION FREQUENCY OPR/PPR RESOURCES
RISKS VERIFIABLE SOURCES METHODS AND NEEDED
INDICATORS AUDIENCE TO
REPORT TO
LDRRMC Insufficiency of No. of LDRRMC BDRRMC, After Output Annually to CDRRMO Administrative
LDRRMC on Members Activity LDRRMC expenses for
responding of trained on All Report training
different hazard Hazard Response Disaster
107
Preparedness (Materials,
Committee Transportation,
Venue and
meals)
PROGRAM, PROJECT AND ACTTIVITY (PPA): Conduct of Evacuation Center and Camp Management
Training
BASELINE ASSUMPTIONS/ OBJECTIVELY TARGETS DATA COLLECTION FREQUENCY OPR/PPR RESOURCES
RISKS VERIFIABLE SOURCES METHODS AND NEEDED
INDICATORS AUDIENCE TO
REPORT TO
LDRRMC Scheduling of No. of personnel LDRRMC After Output Annually to CDRRMO Administrative
Instructors from trained in Activity LDRRMC expenses for
other agency Evacuation Report training
Center and Disaster (Materials,
Camp Preparedness Transportation,
Management Committee Venue and
meals)
LDRRMC Lack of No. of LDRRMC LDRRMC Minutes Output Annually to CDRRMO Administrative
participation Member LDRRMC expenses for
between other attended the meeting
line agency LDRRMC Disaster (Materials,
meeting Preparedness Transportation,
Committee Venue and
meals)
LDRRMC Lack of No. of Members LDRRMC Minutes Output Annually to CDRRMO Administrative
participation attended the LDRRMC expenses for
between other Disaster meeting
line agency Committee Disaster (Materials,
Meeting Preparedness Transportation,
Committee Venue and
meals)
108
PROGRAM, PROJECT AND ACTTIVITY (PPA): Conduct workshops on Contingency Planning
BASELINE ASSUMPTIONS/ OBJECTIVELY TARGETS DATA COLLECTION FREQUENCY OPR/PPR RESOURCES
RISKS VERIFIABLE SOURCES METHODS AND NEEDED
INDICATORS AUDIENCE TO
REPORT TO
LDRRMC Insufficient Data No. of LDRRMC After Output Annually to CDRRMO Administrative
required during Contingency Activity LDRRMC expenses for
the Formulation Plan Formulated Report, Training and
of Contingency Disaster workshop
Plan Preparedness (Materials,
Committee Transportation,
Venue and
meals)
LDRRMC Updating of the LDRRM Plan LDRRMC After Output Annually to CDRRMO Administrative
Local Disaster Updated Activity LDRRMC expenses for
Risk Reduction Report, workshop
and Minutes Disaster (Materials,
Management Preparedness Transportation,
Plan Committee Venue and
meals)
PROGRAM, PROJECT AND ACTTIVITY (PPA): Conduct of Public Service Continuity Plan
Training
BASELINE ASSUMPTIONS/ OBJECTIVELY TARGETS DATA COLLECTION FREQUENCY OPR/PPR RESOURCES
RISKS VERIFIABLE SOURCES METHODS AND NEEDED
INDICATORS AUDIENCE TO
REPORT TO
LDRRMC Insufficient Data No. of agency LDRRMC After Output Annually to CDRRMO Administrative
regarding Public with Public Activity LDRRMC expenses for
Service Service Report Training and
Continuity Plan Continuity Plan Disaster workshop
Formulation Preparedness (Materials,
Committee Transportation,
Venue and
meals)
PROGRAM, PROJECT AND ACTTIVITY (PPA): Conduct of Disaster Risk Communication Training
BASELINE ASSUMPTIONS/ OBJECTIVELY TARGETS DATA COLLECTION FREQUENCY OPR/PPR RESOURCES
RISKS VERIFIABLE SOURCES METHODS AND NEEDED
INDICATORS AUDIENCE
TO REPORT
TO
109
PROGRAM, PROJECT AND ACTTIVITY (PPA): Construction/Establishment of DRRM
Operations Center
BASELINE ASSUMPTIONS/ OBJECTIVELY TARGETS DATA COLLECTION FREQUENCY OPR/PPR RESOURCES
RISKS VERIFIABLE SOURCES METHODS AND NEEDED
INDICATORS AUDIENCE TO
REPORT TO
LDRRMC Lack of existing DRRM Operation LDRRMC Program Site Inspection Annually to CDRRMO, Construction
DRRM Operation Center of works LDRRMC CEO Materials and
Center Established Labor
Disaster
Preparedness
Committee
PROGRAM, PROJECT AND ACTTIVITY (PPA): Conduct of Evacuation Center and Camp Management
Plan Workshop
BASELINE ASSUMPTIONS/ OBJECTIVELY TARGETS DATA COLLECTION FREQUENCY OPR/PPR RESOURCES
RISKS VERIFIABLE SOURCES METHODS AND NEEDED
INDICATORS AUDIENCE TO
REPORT TO
PROGRAM, PROJECT AND ACTTIVITY (PPA): Stockpiling and pre-positioning of Food and Non-Food
Items
BASELINE ASSUMPTIONS/ OBJECTIVELY TARGETS DATA COLLECTION FREQUENCY OPR/PPR RESOURCES
RISKS VERIFIABLE SOURCES METHODS AND NEEDED
INDICATORS AUDIENCE TO
REPORT TO
LDRRMC Lack of Existing No. of LDRRMC Program Inspection Annually to CDRRMO, Construction
Warehouse Warehouse of works LDRRMC CEO Materials and
constructed Labor
Disaster
Preparedness
Committee
LDRRMC Lack of Existing No. of LDRRMC Program Inspection Annually to CDRRMO, Construction
Evacuation Evacuation of works LDRRMC CEO Materials and
Center Center ,CSWDO Labor
constructed Disaster
110
Preparedness
Committee
Response
Clusters
Response
Clusters
100% of Lack of knowledge No. of 100% of After Assessment, Annually to LDRRMC, Administrative
affected by Incident affected Activity site LDRRMC IMT expenses for
areas LDRRMC/BDRRMC Command areas Report inspection; site inspection
established Members on Facilities established Incident Disaster
establishing established Action Plan Response
Incident Command during Committee
facilities disaster/plan
event Response
Clusters
LDRRMC, Lack of No. of trained CDRRMO, After Output Annually to LDRRMC, Administrative
BDRRMC personnel personnel in LDRRMC Activity LDRRMC CDRRMO expenses for
trained in Pre- PDRA Report the meeting
disaster Risk Disaster (Venue and
Assessment Response Meals
Committee
111
Response
Clusters
PROGRAM, PROJECT AND ACTTIVITY (PPA): Conduct Rapid Damage Assessment and Needs
Analysis
BASELINE ASSUMPTIONS/ OBJECTIVELY TARGETS DATA COLLECTION FREQUENCY OPR/PPR RESOURCES
RISKS VERIFIABLE SOURCES METHODS AND NEEDED
INDICATORS AUDIENCE TO
REPORT TO
LDRRMC, Lack of No. of trained LDRRMC, After RDANA Forms Annually to LDRRMC, Administrative
BDRRMC personnel personnel in BDRRMC Activity LDRRMC CDRRMO expenses for
trained in Rapid RDANA Report site inspection
Damage Disaster (transportation
Assessment and Response and Meals)
Needs Analysis Committee
Response
Clusters
LDRRMC, Lack of Man No. of personnel LDRRMC EOC Plan, Output Annually to LDRRMC, Administrative
BDRRMC power and and equipment After LDRRMC CDRRMO expenses for
equipment in in Emergency Activity Activation (
Emergency Operation Report Disaster Materials,
Operation Center Response Meals
Center Committee
Response
Clusters
PROGRAM, PROJECT AND ACTTIVITY (PPA): Distribution of food and non-food items (F/NFIs)
BASELINE ASSUMPTIONS/ OBJECTIVELY TARGETS DATA COLLECTION FREQUENCY OPR/PPR RESOURCES
RISKS VERIFIABLE SOURCES METHODS AND NEEDED
INDICATORS AUDIENCE TO
REPORT TO
100%
affected Lack of food and Inventory of 100% After Output Annually to CDRRMO, Procurement
population non-food food Food and non- affected Activity LDRRMC CSWDO of food and
item food item population Report non-food
Disaster item
Response
Committee
Response
Clusters
PROGRAM, PROJECT AND ACTTIVITY (PPA): Provisions of tents as temporary shelters for
internally displaced population (IDP)
BASELINE ASSUMPTIONS/ OBJECTIVELY TARGETS DATA COLLECTION FREQUENCY OPR/PPR RESOURCES
RISKS VERIFIABLE SOURCES METHODS AND NEEDED
INDICATORS AUDIENCE
TO REPORT
TO
100% Lack of tent for Inventory of 100% Situation Annually to CDRRMO, Procurement
affected temporary Tent for affected Report/s LDRRMC CSWDO of Tent
population shelters for temporary population with and
internally shelters attached Output Disaster LDRRMC
112
displaced list of Response Response
population established Committee Clusters
(IDP) IDPs in
temporary Response
shelters Clusters
PROGRAM, PROJECT AND ACTTIVITY (PPA): Establishment of child-friendly spaces and other
learning areas in the evacuation centers
BASELINE ASSUMPTIONS/ OBJECTIVELY TARGETS DATA COLLECTION FREQUENCY OPR/PPR RESOURCES
RISKS VERIFIABLE SOURCES METHODS AND NEEDED
INDICATORS AUDIENCE
TO REPORT
TO
Evacuation Lack of child- Inventory of No. of Situation Assessment, Annually to CDRRMO, Administrative
Center friendly spaces evacuation child- Report/s site LDRRMC CSWDO expenses for
and other center with learning with inspection and site inspection
learning areas child-friendly spaces attached Disaster LDRRMC (transportation
in the spaces and established list of Response Response and meals)
evacuation other at established Committee Clusters
centers learning evacuation child-
areas centers learning Response
spaces Clusters
100% Lack of interest No. of IDP’s IDP’s Situation Assessment, Annually to CSWDO Administrative
affected from the attended the Report/s Interview LDRRMC and NGO expenses for
population internally livelihood- with training
displaced oriented attached Disaster (materials,
persons in activities list of Response venue and
livelihood- IDPs Committee meals)
oriented trained
activities livelihood Response
programs Clusters
PROGRAM, PROJECT AND ACTTIVITY (PPA): Conduct of medical consultation and nutritional
assessment.
BASELINE ASSUMPTIONS/ OBJECTIVELY TARGETS DATA COLLECTION FREQUENCY OPR/PPR RESOURCES
RISKS VERIFIABLE SOURCES METHODS AND NEEDED
INDICATORS AUDIENCE
TO REPORT
TO
100% Lack of medical No. of IDP’s IDP’s Situation Assessment, Annually to CSWDO, Procurement
affected supplies, served during Report/s Interview LDRRMC CHO of medical
population equipment and medical with supplies,
medicines, consultation attached list Disaster equipment
and of IDPs Response and medicines
Nutritional served during Committee and Needs
assessment. Medical during
consultation Response Nutrition
and Nutrition Clusters Assessment
assessment
PROGRAM, PROJECT AND ACTTIVITY (PPA): Conduct of traumatic and/or psychological stress
debriefings.
BASELINE ASSUMPTIONS/ OBJECTIVELY TARGETS DATA COLLECTION FREQUENCY OPR/PPR RESOURCES NEEDED
RISKS VERIFIABLE SOURCES METHODS AND
INDICATORS AUDIENCE
TO REPORT
TO
113
100% Lack of personnel No. of client 100% After Output, Annually to CSWDO, Administrative
affected trained in mental attended in affected Activity interview LDRRMC NGO, expenses for
individual health and traumatic individual Report CHO Focus group
psycho support and/or Disaster discussion/workshop
psychological Response (Materials, Venue and
stress Committee meals)
debriefing
Response
Clusters
PROGRAM, PROJECT AND ACTTIVITY (PPA): Develop and conduct of psychosocial programs
and/or referral systems.
BASELINE ASSUMPTIONS/ OBJECTIVELY TARGETS DATA COLLECTION FREQUENCY OPR/PPR RESOURCES NEEDED
RISKS VERIFIABLE SOURCES METHODS AND
INDICATORS AUDIENCE
TO REPORT
TO
100% Lack of No. of people 100% After Output, Annually to CSWDO, Administrative
affected personnel who are affected Activity Interview LDRRMC NGO, expenses for
individual trained in undergoing individual Report CHO Group
psychosocial trauma Disaster discussion/workshop
programs debriefing Response (Materials, Venue
(critical incident Committee and meals)
stress
debriefing) Response
Clusters
PROGRAM, PROJECT AND ACTTIVITY (PPA): Design and implement temporary livelihood and/or
income generating activities
BASELINE ASSUMPTIONS/ OBJECTIVELY TARGETS DATA COLLECTION FREQUENCY OPR/PPR RESOURCES
RISKS VERIFIABLE SOURCES METHODS AND NEEDED
INDICATORS AUDIENCE TO
REPORT TO
100% Insufficient No. of individual 100% After Output, Annually to CSWDO, Administrative
affected design program participate affected Activity Interview LDRRMC NGO, expenses for
individual for temporary during the individual Report training
livelihood. implementation (Materials,
of livelihood Venue and
program meals)
PROGRAM, PROJECT AND ACTTIVITY (PPA): Coordinate the formulation of the Strategic Action
Plan for disaster affected areas
BASELINE ASSUMPTIONS/ OBJECTIVELY TARGETS DATA COLLECTION FREQUENCY OPR/PPR RESOURCES
RISKS VERIFIABLE SOURCES METHODS AND NEEDED
INDICATORS AUDIENCE TO
REPORT TO
Administrative
45 Lack Strategic No. of barangay 45 Progress Output Annually to CDRRMO, expenses for
barangays Action Plan formulated barangays report LDRRMC; CPDO training
Disaster (Materials,
Rehabilitation Venue and
Committee meals)
PROGRAM, PROJECT AND ACTTIVITY (PPA): Identify and provide suitable relocation sites for
affected population
BASELINE ASSUMPTIONS/ OBJECTIVELY TARGETS DATA COLLECTION FREQUENCY OPR/PPR RESOURCES
RISKS VERIFIABLE SOURCES METHODS AND NEEDED
INDICATORS AUDIENCE
TO REPORT
TO
114
Administrative
45 No identify No. of 45 Progress Assessment, Annually to CDRRMO, expenses for
barangays suitable possible barangays Report Site LDRRMC; CSWDO, assessment
relocation site suitable inspection Disaster NHA, (Transportation
relocation Rehabilitation CAO and meals)
site Committee
PROGRAM, PROJECT AND ACTTIVITY (PPA): Conduct trainings for social preparation of
communities and those that will be relocated to reduce conflict
BASELINE ASSUMPTIONS/ OBJECTIVELY TARGETS DATA COLLECTION FREQUENCY OPR/PPR RESOURCES
RISKS VERIFIABLE SOURCES METHODS AND NEEDED
INDICATORS AUDIENCE TO
REPORT TO
Administrative
45 Formulation of Social 45 Progress Assessment, Annually to CDRRMO, expenses for
barangays protocols for Preparation of barangays Report Site inspection LDRRMC; CSWDO, training
social preparation Communities Disaster NHA, (Materials,
of communities and those that Rehabilitation CPDO, CEO Venue and
will be Committee meals)
relocated
protocols
formulated
PROGRAM, PROJECT AND ACTTIVITY (PPA): Conduct trainings for social preparation of
communities and those that will be relocated to reduce conflict
BASELINE ASSUMPTIONS/ OBJECTIVELY TARGETS DATA COLLECTION FREQUENCY OPR/PPR RESOURCES
RISKS VERIFIABLE SOURCES METHODS AND NEEDED
INDICATORS AUDIENCE
TO REPORT
TO
Administrative
45 Formulation of No. of host 45 Progress Assessment, Annually to CDRRMO, expenses for
barangays protocols/guidelines communities barangays Report Site LDRRMC CSWDO, training
for social preparation attended on inspection NHA, (Materials,
of communities social Disaster CPDO, Venue and
preparation Rehabilitation CEO meals)
Committee
PROGRAM, PROJECT AND ACTTIVITY (PPA): Rehabilitation of damage infrastructure and other
public utilities and facilities
BASELINE ASSUMPTIONS/ OBJECTIVELY TARGETS DATA COLLECTION FREQUENCY OPR/PPR RESOURCES
RISKS VERIFIABLE SOURCES METHODS AND NEEDED
INDICATORS AUDIENCE
TO REPORT
TO
115
PROGRAM, PROJECT AND ACTTIVITY (PPA): Rehabilitation of damage infrastructure and other
public utilities and facilities
BASELINE ASSUMPTIONS/ OBJECTIVELY TARGETS DATA COLLECTION FREQUENCY OPR/PPR RESOURCES
RISKS VERIFIABLE SOURCES METHODS AND NEEDED
INDICATORS AUDIENCE
TO REPORT
TO
116