Professional Documents
Culture Documents
Cost Sheets (Road) - V2
Cost Sheets (Road) - V2
Note:
Assumed hauling distance is 3 km. If actual
hauling distance is shorter or longer than 3 km, the
time of dump truck will be adjusted accordingly
based on the hauling cycle time analysis.
Item No./Description : 101(1) Removal of Structures and Obstruction (other than concrete)
Unit of Measurement : cu.m.
Output per hour : 10 cu.m.
Note:
Assumed hauling distance is 3 km. If actual
hauling distance is shorter or longer than 3 km, the
time of dump truck will be adjusted accordingly
based on the hauling cycle time analysis.
Note:
Assumed hauling distance is 3 km. If actual
hauling distance is shorter or longer than 3 km, the
time of dump truck will be adjusted accordingly
based on the hauling cycle time analysis.
Note:
Assumed hauling distance is 3 km. If actual
hauling distance is shorter or longer than 3 km, the
time of dump truck will be adjusted accordingly
based on the hauling cycle time analysis.
Note:
Assumed hauling distance is 3 km. If actual
hauling distance is shorter or longer than 3 km, the
time of dump truck will be adjusted accordingly
based on the hauling cycle time analysis.
Note:
Assumed hauling distance is 3 km. If actual
hauling distance is shorter or longer than 3 km, the
time of dump truck will be adjusted accordingly
based on the hauling cycle time analysis.
A. Labor
B. Equipment
Note:
Assumed hauling distance is 3 km. If actual
hauling distance is shorter or longer than 3 km, the
time of dump truck will be adjusted accordingly
based on the hauling cycle time analysis.
A. Labor
B. Equipment
Note:
Assumed hauling distance is 3 km. If actual
hauling distance is shorter or longer than 3 km, the
time of dump truck will be adjusted accordingly
based on the hauling cycle time analysis.
Note:
Assumed hauling distance is 3 km. If actual
hauling distance is shorter or longer than 3 km, the
time of dump truck will be adjusted accordingly
based on the hauling cycle time analysis.
Item No./Description : 101(2)g Removal of Pipes other than Pipe Culverts (PVC/GI/Asbestos, up to 200mm Ø), L=10 ft.
Unit of Measurement : ea.
Output per hour : 2 ea.
Note:
Assumed hauling distance is 3 km. If actual
hauling distance is shorter or longer than 3 km, the
time of dump truck will be adjusted accordingly
based on the hauling cycle time analysis.
Note:
Assumed hauling distance is 3 km. If actual
hauling distance is shorter or longer than 3 km, the
time of dump truck will be adjusted accordingly
based on the hauling cycle time analysis.
Item No./Description : 101(3)a.2 Removal of Existing PCC Pavement, 0.23m thk. (for Reblocking at intermittent section)
Unit of Measurement : sq.m.
Output per hour : 30 sq.m.
Note:
Assumed hauling distance is 3 km. If actual
hauling distance is shorter or longer than 3 km, the
time of dump truck will be adjusted accordingly
based on the hauling cycle time analysis.
Note:
Assumed hauling distance is 3 km. If actual
hauling distance is shorter or longer than 3 km, the
time of dump truck will be adjusted accordingly
based on the hauling cycle time analysis.
Note:
Assumed hauling distance is 3 km. If actual
hauling distance is shorter or longer than 3 km, the
time of dump truck will be adjusted accordingly
based on the hauling cycle time analysis.
Note:
Assumed hauling distance is 3 km. If actual
hauling distance is shorter or longer than 3 km, the
time of dump truck will be adjusted accordingly
based on the hauling cycle time analysis.
Note:
Assumed hauling distance is 3 km. If actual
hauling distance is shorter or longer than 3 km, the
time of dump truck will be adjusted accordingly
based on the hauling cycle time analysis.
Note:
Assumed hauling distance is 3 km. If actual
hauling distance is shorter or longer than 3 km, the
time of dump truck will be adjusted accordingly
based on the hauling cycle time analysis.
Note:
Assumed hauling distance is 3 km. If actual
hauling distance is shorter or longer than 3 km, the
time of dump truck will be adjusted accordingly
based on the hauling cycle time analysis.
Note:
Assumed hauling distance is 3 km. If actual
hauling distance is shorter or longer than 3 km, the
time of dump truck will be adjusted accordingly
based on the hauling cycle time analysis.
Note:
Assumed hauling distance is 3 km. If actual
hauling distance is shorter or longer than 3 km, the
time of dump truck will be adjusted accordingly
based on the hauling cycle time analysis.
Note:
Assumed hauling distance is 3 km. If actual
hauling distance is shorter or longer than 3 km, the
time of dump truck will be adjusted accordingly
based on the hauling cycle time analysis.
Note:
Assumed hauling distance is 3 km. If actual
hauling distance is shorter or longer than 3 km, the
time of dump truck will be adjusted accordingly
based on the hauling cycle time analysis.
Item No./Description : 102(3)d Roadway Excavation (Surplus Hard Rock) - Blasting (Tunnel Excavation)
Unit of Measurement : cu.m.
Output per hour : 1.65 cu.m.
Note:
Assumed hauling distance is 3 km. If actual
hauling distance is shorter or longer than 3 km, the
time of dump truck will be adjusted accordingly
based on the hauling cycle time analysis.
A. Labor
B. Equipment
A. Labor
Note:
*) The component quantity of items of work involved such as item 404/405/509 shall be based on the
actual design of the shoring.
**) Costing of this item shall be based on the standard Detailed Unit Price Analysis (DUPA) of item 404/405/509
as processed component pay item.
B. Equipment
Note:
a.) The assume dimesion of area to be provided with cofferdam is 12m x 12m square with
Steel Sheet Piles depth of 12m at 48 kg./m.
b.) The quantity of component materials requirement may vary depending on the actual
design of Cribbing/Cofferdamming.
a. Common Borrow (w/ 25% Shrinkage Factor) cu.m. 1.25 400.00 500.00
a. Selected Borrow (w/ 25% Shrinkage Factor) cu.m. 1.25 420.00 525.00
a. Selected Borrow (w/ 25% Shrinkage Factor) cu.m. 1.25 420.00 525.00
F. Materials
F. Materials
Item No./Description : 204 Portland Cement Stabilized Road Mix Base Course
Unit of Measurement : cu.m.
Output per hour : 15 cu.m.
Item No./Description : 206 Portland Cement Treated Plant Mix Base Course
Unit of Measurement : cu.m.
Output per hour : 15 cu.m.
F. Materials
Item No./Description : 303(4) Bituminous Seal Coat (Asphalt Cement Penetration Grade 120-150)
Unit of Measurement : m.t.
Output per hour : 0.30 m.t.
Item No./Description : 304(2) Bituminous Surface Treatment (Asphalt Cement Penetration Grade 120-150)
Unit of Measurement : m.t.
Output per hour : 0.30 m.t.
Item No./Description : 305(3) Bituminous Penetration Macadam Pavement (RC Cut-back Asphalt)
Unit of Measurement : m.t.
Output per hour : 0.30 m.t.
b. (0.07)(1.05) = 0.07
c. (0.0075)(35.29) = 0.26, say 0.30
b. (0.10)(1.05) = 0.10
c. (0.0075)(35.29) = 0.26, say 0.30
Item No./Description : 306(1) Aggregates for Bituminous Road Mix Surface Course
Unit of Measurement : m.t.
Output per hour : 12 m.t.
Item No./Description : 306(2) Bituminous Material for Bituminous Road Mix Surface Course
Unit of Measurement : m.t.
Output per hour : 1 m.t.
Item No./Description : 307 Bituminous Plant Mix Surface Course-General (50mm thk.)
Unit of Measurement : sq.m.
Output per hour : 171.30 sq.m.
a. (0.05)(0.08)(2.335)(1.05) = 0.00981
b. (0.05)(0.79)(1.05) = 0.041
c. (0.05)(0.19)(1.05) = 0.010
d. (0.07)(0.05)(35.29)(1.05) = 0.130
e. (9.50)(0.05)(2.335)(1.05) = 1.165
a. (0.05)(0.10)(2.335)(1.05) = 0.01226
b. (0.05)(0.79)(1.05) = 0.041
c. (0.05)(0.19)(1.05) = 0.010
d. (0.07)(0.05)(35.29)(1.05) = 0.130
e. (9.50)(0.05)(2.335)(1.05) = 1.165
a. (0.05)(0.07)(2.335)(1.05) = 0.00858
b. (0.05)(0.79)(1.05) = 0.041
c. (0.05)(0.19)(1.05) = 0.010
d. (0.07)(0.05)(35.29)(1.05) = 0.130
e. (9.50)(0.05)(2.335)(1.05) = 1.165
a. (0.05)(0.10)(2.335)(1.05) = 0.01226
b. (0.05)(0.79)(1.05) = 0.041
c. (0.05)(0.19)(1.05) = 0.010
d. (0.07)(0.05)(35.29)(1.05) = 0.130
e. (9.50)(0.05)(2.335)(1.05) = 1.165
a. (0.03)(0.08)(2.335)(1.05) = 0.00588
b. (0.03)(0.79)(1.05) = 0.025
c. (0.03)(0.19)(1.05) = 0.006
d. (0.07)(0.03)(35.29)(1.05) = 0.078
e. (9.50)(0.03)(2.335)(1.05) = 0.699
a. (0.04)(0.08)(2.335)(1.05) = 0.00785
b. (0.04)(0.79)(1.05) = 0.033
c. (0.04)(0.19)(1.05) = 0.008
d. (0.07)(0.04)(35.29)(1.05) = 0.104
e. (9.50)(0.04)(2.335)(1.05) = 0.932
a. (0.05)(0.08)(2.335)(1.05) = 0.00981
b. (0.05)(0.79)(1.05) = 0.041
c. (0.05)(0.19)(1.05) = 0.010
d. (0.07)(0.05)(35.29)(1.05) = 0.130
e. (9.50)(0.05)(2.335)(1.05) = 1.165
Item No./Description : 311(1)a.1 PCC Pavement (Plain) - Conventional Method, 150mm thk.
Unit of Measurement : sq.m.
Output per hour : 107.33 sq.m.
Item No./Description : 311(1)a.2 PCC Pavement (Plain) - Conventional Method, 200mm thk.
Unit of Measurement : sq.m.
Output per hour : 80.50 sq.m.
Item No./Description : 311(1)a.3 PCC Pavement (Plain) - Conventional Method, 230mm thk.
Unit of Measurement : sq.m.
Output per hour : 70 sq.m.
Item No./Description : 311(1)a.4 PCC Pavement (Plain) - Conventional Method, 250mm thk.
Unit of Measurement : sq.m.
Output per hour : 64.40 sq.m.
Item No./Description : 311(1)a.5 PCC Pavement (Plain) - Conventional Method, 280mm thk.
Unit of Measurement : sq.m.
Output per hour : 14.38 sq.m. divided by 4
Item No./Description : 311(1)a.6 PCC Pavement (Plain) - Conventional Method, 300mm thk.
Unit of Measurement : sq.m.
Output per hour : 53.67 sq.m.
Item No./Description : 311(1)b.1 PCC Pavement (Plain) - Using Concrete Paver, 230mm thk.
Unit of Measurement : sq.m.
Output per hour : 90 sq.m.
Item No./Description : 311(1)b.2 PCC Pavement (Plain) - Using Concrete Paver, 250mm thk.
Unit of Measurement : sq.m.
Output per hour : 82.80 sq.m.
Item No./Description : 311(1)b.3 PCC Pavement (Plain) - Using Concrete Paver, 280mm thk.
Unit of Measurement : sq.m.
Output per hour : 73.93 sq.m.
Item No./Description : 311(1)b.4 PCC Pavement (Plain) - Using Concrete Paver, 300mm thk.
Unit of Measurement : sq.m.
Output per hour : 69 sq.m.
Item No./Description : 311(1)c PCC Pavement (Plain) - Conventional Method, 150mm thk.
Unit of Measurement : sq.m.
Output per hour : 12 sq.m.
These pay items are variable in dimensions based on the actual condition
which combines component items, hence standard estimate should be based on
the standard Detailed Unit Price Analysis (DUPA) of each component items, such
as item 103(3), 404 & 405. See attached DUPA.
Further, these items with unit of measure as each in the Blue Book is
recommended to be broken down separately by component items such as item
103(3) - Foundation Fill, 404 - Reinforcing Steel Bar and 405 - Structural Concrete
Class "A" (Minor Structures) in the summary of quantities in the preparation of
design plans.
DETAILED UNIT PRICE ANALYSIS (DUPA)
a. 580mm dia. C.I. Manhole Cover with Frame set 1.00 5,700.00 5,700.00
Item No./Description : 503(a) Drainage Steel Grating with Frame (675mm x 975mm Sump Grating)
Unit of Measurement : set
Output per hour : 0.25 set
Item No./Description : 503(b) Drainage Steel Grating with Frame (715mm x 2000mm Trench Grating)
Unit of Measurement : set
Output per hour : 0.125 set
Item No./Description : 504(1)a Removing, Cleaning, Stockpiling Salvaged Culvert Pipe (24" dia) - 610mm
Unit of Measurement : l.m.
Output per hour : 3 l.m.
Item No./Description : 504(1)b Removing, Cleaning, Stockpiling Salvaged Culvert Pipe (30" dia.) - 760mm
Unit of Measurement : l.m.
Output per hour : 2.50 l.m.
Item No./Description : 504(1)c Removing, Cleaning, Stockpiling Salvaged Culvert Pipe (36" dia.) - 910mm
Unit of Measurement : l.m.
Output per hour : 2 l.m.
Item No./Description : 504(1)d Removing, Cleaning, Stockpiling Salvaged Culvert Pipe (42" dia.) - 1070mm
Unit of Measurement : l.m.
Output per hour : 2 l.m.
Item No./Description : 504(1)e Removing, Cleaning, Stockpiling Salvaged Culvert Pipe (48" dia.) - 1220mm
Unit of Measurement : l.m.
Output per hour : 1.50 l.m.
Item No./Description : 504(2)a Removing, Cleaning and Re-laying Salvaged Culvert Pipe (24" dia.) - 610mm
Unit of Measurement : l.m.
Output per hour : 1.50 l.m.
Item No./Description : 504(2)b Removing, Cleaning and Re-laying Salvaged Culvert Pipe (30" dia.) - 760mm
Unit of Measurement : l.m.
Output per hour : 1.25 l.m.
Item No./Description : 504(2)c Removing, Cleaning and Re-laying Salvaged Culvert Pipe (36" dia.) - 910mm
Unit of Measurement : l.m.
Output per hour : 1 l.m.
Item No./Description : 504(2)d Removing, Cleaning and Re-laying Salvaged Culvert Pipe (42" dia.) - 1070mm
Unit of Measurement : l.m.
Output per hour : 1 l.m.
Item No./Description : 504(2)e Removing, Cleaning and Re-laying Salvaged Culvert Pipe (48" dia.) - 1220mm
Unit of Measurement : l.m.
Output per hour : 0.75 l.m.
Item No./Description : 504(3)a Cleaning Culvert Pipe in place (610mm dia.) - Half Silted
Unit of Measurement : l.m.
Output per hour : 8 l.m.
Item No./Description : 504(3)b Cleaning Culvert Pipe in place (760mm dia.) - Half Silted
Unit of Measurement : l.m.
Output per hour : 5.25 l.m.
Item No./Description : 504(3)c Cleaning Culvert Pipe in place (910mm dia.) - Half Silted
Unit of Measurement : l.m.
Output per hour : 3.75 l.m.
Item No./Description : 504(3)d Cleaning Culvert Pipe in place (1070mm dia.) - Half Silted
Unit of Measurement : l.m.
Output per hour : 2.75 l.m.
Item No./Description : 504(3)e Cleaning Culvert Pipe in place (1220mm dia.) - Half Silted
Unit of Measurement : l.m.
Output per hour : 2 l.m.
Item No./Description : 504(3)f Cleaning Culvert Pipe in place (1520mm dia.) - Half Silted
Unit of Measurement : l.m.
Output per hour : 1.50 l.m.
a. Timber Sheet Piles, ave. dia. 395mm bd.ft. 52.25 40.00 2,090.00
b. Coco Log - 2 uses m. 1.00 350.00 175.00
c. Lumber (Falsework) - 4 uses bd.ft. 16.00 40.00 160.00
d. Nail/Spike (1 kg./100 bd.ft. of Lumber) kg. 0.16 68.00 10.88
Item No./Description : 509(c) Concrete Sheet Pile, furnished and driven - 0.50m x 0.35m
Unit of Measurement : l.m.
Output per hour : 1.15 l.m.
Item No./Description : 600(3) Concrete Curb and Gutter, Type A (Cast in place) - National Road
Unit of Measurement : l.m.
Output per hour : 10.30 l.m.
Item No./Description : 603(3)a Metal Guardrails (Metal Beam) including Concrete Post
Unit of Measurement : l.m.
Output per hour : 4.20 l.m.
a. Lumber, 8" x 8" x 5.5' Treated Post (Tanguile) bd.ft. 14.67 90.00 1,320.30
b. Lumber, 3" x 8" Plank (Tanguile) - Untreated bd.ft. 6.67 55.00 366.85
c. Carriage Bolt, 1/2"Ø x 12" pc. 1.60 350.00 560.00
Miscellaneous (5% of Materials) 112.36
a. 3-Strand Galvanized Barbed Wire, Ga. 12.5 l.m. 1.00 15.00 15.00
b. 50mmx50mmx6mm Angle Bar kg. 0.58 48.00 27.84
c. Ga. 9 Twisted Wire Fastener pc. 0.39 81.15 31.65
Miscellaneous (2% of Materials, Welding Rod & etc.) 1.49
Item No./Description : 604(4) Fencing (Gates) - (Height 3m. & Length 4.24m.)
Unit of Measurement : ea.
Output : 1 ea.
Item No./Description : 611(1) Trees (Furnishing and Transplanting), 150mm dia. or less
Unit of Measurement : ea.
Output per hour : 1 ea.
Item No./Description : 613 Concrete Joint Sealant (Hot Poured Elastic and Cold-Applied Types)
Unit of Measurement : kg.
Output per hour : 20 kg.
.
Designation No. of Person No. of Hours Hourly Rate Amount
A. Labor
a. Erosion Control Net CGN 400 w/ 5 % wastage sq.m. 1.05 110.00 115.50
(Price includes bamboo pegs)
a. Erosion Control Net CGN 700 w/ 5 % wastage sq.m. 1.05 156.00 163.80
(Price includes bamboo pegs)
0.00
0.00
0.00