Professional Documents
Culture Documents
INTERNAL LININGS
5
4
3
2
1
0 25/05/01 ALI A.FATTAH J.DWYER ABDUL AZIZ AL AMERI ISSUED FOR IMPLEMENTATION
A 13/09/00 ALI A.FATTAH J.DWYER ABDUL AZIZ AL AMERI ISSUED FOR COMMENTS
Rev Date WRITTEN BY CHECKED BY APPROVED BY STATUS
DD/MM/YY
DOCUMENT REVISIONS
Sections changed in last revision are identified by a vertical line in the left margin
DGS-6600-020/FH
Rev.
CONTENTS
1. GENERAL .................................................................................................................................................................................... 4
1.1 INTRODUCTION ......................................................................................................................................................................4
1.2 PURPOSE ................................................................................................................................................................................4
1.3 DEFINITIONS ..........................................................................................................................................................................4
2. CODES AND STANDARDS....................................................................................................................................................... 5
3. REFERENCE DOCUMENTS.................................................................................................................................................... 7
7. DOCUMENTATION................................................................................................................................................................... 7
8. HANDLING .................................................................................................................................................................................. 8
9. EXECUTION................................................................................................................................................................................ 8
DGS-6600-020/FH
Rev.
DGS-6600-020/FH
Rev.
1. GENERAL
1.1 Introduction
This Specification covers the general design, materials, surface preparation, application, and
testing requirements for lining the internal surfaces of shop and field fabricated tanks, pressure
vessels and other equipment in a shop or jobsite environment.
1.2 Purpose
The materials and procedures specified herein are provided to protect the internal surfaces of
carbon steel tanks, pressure vessels, and equipment from corrosion and to prevent the possibility
of product contamination.
1.3 Definitions
For the purposes of this Specification, the following definitions shall apply:
1.3.1 APPLICATION DATA — Application instructions, recommendations and guidelines described in
the published literature of the lining materials Manufacturer, referenced industry standards and any
specific requirements noted in this Specification and any drawings issued to the LINING
CONTRACTOR.
1.3.2 COMPANY — ABU DHABI GAS INDUSTRIES LTD. (GASCO).
1.3.3 CONCESSION REQUEST - A deviation requested by the SUBCONTRACTOR, usually after
receiving the contract package or purchase order. Often, it refers to an authorization to use, repair,
recondition, reclaim, or release materials, components or equipment already in progress or
completely manufactured but which does not meet or comply with ADNOC requirements. A
CONCESSION REQUEST is subject to COMPANY approval.
1.3.4 CONTRACTOR — The party which carries out all or part of the Design, Engineering,
Procurement, Construction, Construction or Management of the Project.
1.3.5 CORROSION ENGINEER - The engineer in the CONTRACTOR’S organization responsible for the
development and/or the maintenance of the Specification.
1.3.6 DESIGN TEMPERATURE - The temperature for which the tank is designed and which is shown on
the tank drawings. This temperature shall not be used for selecting the lining systems.
1.3.7 DFT MEASUREMENT -The average value of three readings recorded by the use of a properly
calibrated dry film thickness gauge. The readings shall be within a 150 mm radius and evenly
spread out from a given spot.
1.3.8 DRY FILM THICKNESS (DFT) -The dry film thickness of the lining. In the absence of a specified
range, the value stated shall mean a minimum value. The maximum value shall not be more than
1.5 times the stated value.
1.3.9 LINING CONTRACTOR - The party responsible for the lining work, including surface preparation,
application and inspection in accordance with this Specification.
1.3.10 MAXIMUM OPERATING TEMPERATURE - The maximum operating temperature (MOT) is the
same as the normal operating temperature. However, if upset conditions are stated on the P&ID’s,
then the highest temperature during upset conditions shall be considered as the maximum
operating temperature, superseding the normal operating temperature. The maximum operating
temperature shall be used for selection of the lining system.
1.3.11 PROJECT – To be defined.
DGS-6600-020/FH
Rev.
DGS-6600-020/FH
Rev.
ASTM D4285 Test Method for Indicating Oil or Water in Compressed Air
DGS-6600-020/FH
Rev.
3. REFERENCE DOCUMENTS
The following reference documents, to the extent specified herein, form a part of this Specification.
When an edition date is not indicated for a document, the latest edition in force at the time that
LINING CONTRACTOR proposal is submitted shall apply.
PROJECT SPECIFICATIONS
♦ DGS.6600.010 Painting
♦ DGS.6710.001 Preservation and Export Packing Specification
4. DOCUMENT PRECEDENCE
The LINING CONTRACTOR shall notify the CONTRACTOR of any apparent conflict between this
Specification, the related data sheets, the Codes and Standards and any other specifications noted
herein. Resolution and/or interpretation precedence shall be obtained from the CONTRACTOR in
writing before proceeding with the design/manufacture.
In case of conflict, the order of precedence shall be:
♦ This Specification
♦ APPLICATION DATA
♦ Industry codes and standards
7. DOCUMENTATION
The LINING CONTRACTOR shall assume unit responsibility and overall guarantee for the internal
linings.
The LINING CONTRACTOR shall transmit all relevant purchase order documents including
specifications to his SUBVENDORS and SUBCONTRACTORS.
DGS-6600-020/FH
Rev.
8. HANDLING
Preparation for shipment of all lined items shall be in accordance with the LINING
CONTRACTOR'S standards. LINING CONTRACTOR shall be solely responsible for the adequacy
of the preparation for shipment provisions with respect to materials and application, and to provide
equipment at the destination in ex-works condition when handled by commercial carriers.
Adequate protection of lined equipment shall be provided to prevent mechanical damage and
atmospheric corrosion in transit and at the job site.
Preparation for shipment and packing will be subject to inspection and rejection by
COMPANY'S/CONTRACTOR'S inspectors. All costs of lined equipment occasioned by such
rejection shall be to the account of the LINING CONTRACTOR.
After inspection and test, equipment shall be completely free of water and dry before start of
preparation for shipment.
All equipment and material shall be preserved and export packed in accordance with Preservation
and Export Packing Specification DGS.6710.001.
9. EXECUTION
In case of conflicting requirements between the documents related to the APPLICATION DATA,
the LINING CONTRACTOR shall submit all conflicting information to the CONTRACTOR for
resolution. If the published literature of the LINING MANUFACTURER does not contain required
information, LINING CONTRACTOR shall obtain additional information from the parent corporate
office of the LINING MANUFACTURER if the local LINING MANUFACTURER is a licensee or a
subsidiary of a multinational organization and transmit the same to the CONTRACTOR. Any
deviations from or changes to LINING MANUFACTURER'S published literature shall be subject to
CONTRACTOR'S review, acceptance or rejection without comment, explanation and/or
justification. (Note: Where recommendations, instructions and guidelines are given in permissive
language such as 'may', 'should', and 'recommended', compliance with those recommendations,
instructions and guidelines shall be considered mandatory unless otherwise instructed by the
CONTRACTOR.)
Resolution of any technical conflicts between documents and selection of any option from available
options (especially testing) shall be by the CORROSION ENGINEER and the COMPANY.
The LINING CONTRACTOR shall inform the CONTRACTOR of any potential problem requiring a
design modification at the time of design or fabrication.
The LINING CONTRACTOR is solely responsible for supply of installed and consumable materials,
equipment (air compressor, after cooler, blast cleaning, dehumidifying, ventilation, spray etc.),
tools, instruments and labor (application, supervision, quality control etc.) and each and every item
of expense to supply, apply, cure and check the integrity of the entire lining system in accordance
with this Specification. Application of the lining system consists of, by way of example but not by
limitation, surface conditioning, degreasing, removal of water solubles, blast cleaning, priming (if
applicable), lining application, full cure and quality checks and any repairs.
The lining application shall be performed after fabrication and pressure testing.
DGS-6600-020/FH
Rev.
DGS-6600-020/FH
Rev.
11.2 Degreaser
The degreaser shall be a waterbased biodegradable cleaner such as Carboline Surface Cleaner
No. 3 or Sipco-Devoe DEVREP88.
11.3 Abrasives
Abrasives shall be composed of clean, hard particles free from foreign substances such as dirt, oil,
grease, toxic substances, organic matter, mill scale, soil and water soluble salts. The pH of the
abrasive materials shall be below 6.2. The moisture content of the selected abrasive shall not
exceed 0.5 percent by weight. The conductivity of deionized water extract of the abrasive material
shall not exceed 150 micro-Siemens/cm.
Abrasive shall be supergarnet for blast cleaning all surfaces. Silica sand, copper slag, and steel
shot shall not be used.
The abrasive must be capable of producing the degree of cleanliness and surface profile specified.
The abrasive partical size and type shall be suitable to obtain the anchor profile
recommended by the lining materials manufacturer. Lining materials manufacturer
recommendations regarding abrasive selection shall be utilized and all deviations from
these recommendations require a concession request.
11.5 Equipment
Blasting equipment for floor shall be portable automatic blast cleaning machine such as BlasTrac.
Spray equipment shall be maintained in good working order and shall be comparable to that
described in the APPLICATION DATA. Worn spray nozzles, tips, etc. shall be replaced.
DGS-6600-020/FH
Rev.
12. DEHUMIDIFICATION
Surfaces must be maintained at least 3°C above the dew point, immediately before and during the
lining installation and remain in this condition during curing. To comply with this requirement,
dehumidifying equipment shall be at the site. The capacity of the dehumidifying equipment shall be
as recommended by the dehumidifying equipment manufacturer. Dehumidification equipment shall
be capable of achieving relative humidity levels below 60 percent.
The humidity inside the tank shall be maintained at 80 percent or lower. Lining application may be
permitted on a case-by-case basis by the CONTRACTOR when the relative humidity is between
80 and 85 percent. Lining application is not permitted when the humidity is above 85 percent.
13. VENTILATION
During all blast cleaning operations, ventilation shall be maintained to allow adequate visibility and
for safety. Flexible ventilation ducts shall be used to allow the point of extraction to be reasonably
close to the blaster. The ventilation ducts shall be arranged so that dead spaces do not exist.
DGS-6600-020/FH
Rev.
14. Lighting
Lighting during blast cleaning and lining application must be electrically safe and provide suitable
illumination for all work. Low voltage lights, approved by the CONTRACTOR, shall be used. High
voltage lights shall not be used inside the item being lined. All circuit boxes and switches shall be
located outside.
DGS-6600-020/FH
Rev.
DGS-6600-020/FH
Rev.
DGS-6600-020/FH
Rev.
17.6 Recoating
Drying times between coats shall be in accordance with the APPLICATION DATA.
Unless otherwise approved by the CORROSION ENGINEER, the minimum recoating time shall be
at least 24 hours and the maximum recoating time shall not exceed 75 percent of the longest
recoating time stated in the APPLICATION DATA.
DGS-6600-020/FH
Rev.
18. CURING
The LINING CONTRACTOR is solely responsible for full curing of the lining system including
repaired areas.
The curing shall be in accordance with the APPLICATION DATA.
The LINING CONTRACTOR shall transfer custody and control of the tank to the CONTRACTOR
after full cure of the lining systems and when the lining systems are in ready-to-use condition.
20. INSPECTION
DGS-6600-020/FH
Rev.
DGS-6600-020/FH
Rev.
DO NOT WELD
(Date of application)
The marking letters shall be at least 150 mm high and in contrasting color. Marking shall be
applied at all nozzles and shall be in English and Arabic.
22. GUARANTEE
The CONTRACTOR shall guarantee performance of the linings (shop and field) for a period of five
years from the date of provisional acceptance by the COMPANY when the entire materials
selection, materials application, selection of the APPLICATOR, supervision of the APPLICATOR
and all tasks related to the lining are under 100 % control of the CONTRACTOR.
DGS-6600-020/FH
Rev.
a. The estimate amounts of rust breakthrough on a coating and of total apparent rust (rust
breakthrough plus underfilm rust) exceeds ISO 4628-3 rust scale Ri0, (0.0 % area rusted).
b. Appearance of defects in the lining such as blistering, peeling, flaking, intercoat delamination,
muderacking, etc. affecting the overall integrity of the lining.
The repair procedure and the extent or repair shall be subject to approval by COMPANY. All
defective spots shall be repaired. In case defects occur all over the surface, the entire surface shall
be refurbished.
The degree of blistering shall be evaluated in accordance with ISO 4628-2. The degree of cracking
and flaking in a lining shall be evaluated in accordance with ISO 4628-4 and 4628-5, respectively.
The CONTRACTOR shall undertake to recommence all or part of the lining work subject to
agreement with COMPANY, at any time during the guarantee period. “Recommence” is
understood to mean blast cleaning, supply and application of the lining in conformity with the
present Specification, on site and at the expense of the CONTRACTOR.
Final acceptance shall in principle take place when the guarantee period expires. A detailed
inspection of all painted SURFACES before the guarantee period expires shall then be carried out.
Remedial actions, if any, shall be decided based on the results of the inspection.
DGS-6600-020/FH
Rev.
APPENDIX 1
A1-1.0 SCOPE
This Appendix covers the requirements for surface preparation and application of a
glass-reinforced epoxy internal lining system for crude oil storage tank floor areas, first
course of the shell and bearing plates for the roof support legs.
The requirements stated in this Appendix are specific to the fiberglass reinforced epoxy
lining systems and shall be considered as additional to the basic requirements stated in the
main body of this Specification.
Primer type and material shall be as stated in the APPLICATION DATA. The primer shall
not contain zinc or lead pigments.
The glass fibers shall have a silane finish with binder, soluble in the epoxy resin to be used.
The glass-reinforcement shall be fiber-glass matting or fabric weighing 300 to 450 grams
per square meter. The glass fiber surfacing veil, to be used on top of the main matting
layers, shall be of a weight of 25 to 30 grams per square meter. The glass content of the
glass-reinforced epoxy lining shall be in the range of 25-35% by weight, excluding the
resin-rich surface seal coat.
The use of chopped fiber-glass strands, chopped rovings or glass flakes is not acceptable.
The epoxy putty or mortar used for filling, contouring and smoothing of steel surfaces shall
be manufactured from the same epoxy grade as used for the lining system, with a suitable
filler material.
The LINING CONTRACTOR shall submit detailed APPLICATION DATA and product
specifications for selected primers, resins, additives, seal coats, glass matting, putties, and
construction details for CONTRACTOR’S review and approval. Data for mechanical
strength (notably flexural strength), chemical resistance, evidence of service experience of
the proposed system, and repair procedures for defective or damaged areas shall also be
submitted.
DGS-6600-020/FH
Rev.
A1-3.2 APPLICATION
Glass reinforced epoxy lining for the tank bottom shall not be installed when the steel
surface temperature is below 10°C or above 50°C.
To obtain the best adhesion and ultimate chemical resistance of the laminate, it is imperative
that the installations are carried out under dry conditions and that all necessary precautions
shall be taken by the LINING CONTRACTOR to ensure that water does not come into contact
with the uncured resin.
The sequence of steps for the application of the fiberglass reinforced epoxy lining shall be as
follows:
The glass-reinforced epoxy lining shall be a wet hand lay-up system of epoxy resin and
glass matting or fabric.
Each layer of glass matting or surfacing veil shall be embedded into the resin with a roller to
remove entrapped air, folds and wrinkles, and to ensure proper wetting of the matting and
veil. The final seal coat shall be sprayed and not rolled.
DGS-6600-020/FH
Rev.
The LINING CONTRACTOR shall submit APPLICATION DATA and details of their proposed
lining system regarding application, compliance with, or deviation from the above stated
basic requirements, for CONTRACTOR’S review and approval. The LINING CONTRACTOR
shall also detail their proposed procedures/techniques with respect to laminate lining of
bearing plates for roof support legs, epoxy grouting and radius requirements, chamfering of
the lining top on the shell, sequence and timing of application, and curing requirements.
A1-4.0 TESTING/INSPECTION
A1-4.1 GENERAL
Visual inspection of materials, equipment for surface preparation and for lining application
and protective clothing shall be carried out to ensure compliance with this Specification and
APPLICATION DATA.
A system of controlled issue of resin batches during the work shall be arranged, to ensure
appropriate cover and equal lining thickness on each section of the tank floor.
The dry film thickness shall be measured before and after final seal coat application to verify
adequate coverage of the minimum 300, maximum 500 microns thickness seal coat.
The total system thickness at any individual location shall not be less than 1.5 mm and shall
not be more than 2.2 mm.
Hardness spot checks with a Barcol tester shall be carried out on the cured lining.
DGS-6600-020/FH
Rev.
APPENDIX 2
System System name Surface 1st coat of Lining 2nd coat of Lining Total system
No. Preparation minimum DFT of
(Profile, lining material,
microns) microns
1 Phenolic epoxy Sa3 Phenolic epoxy, Phenolic epoxy, 300 µ
(75 to 100 µ) polyamine cured polyamine cured
(150 µ) (150 µ)
2 Phenolic epoxy-FD Sa3 Phenolic epoxy, Phenolic epoxy, 300 µ
(75 to 100 µ) polyamine cured polyamine cured
(Food grade) (Food grade)
(150 µ) (150 µ)
3 Phenolic epoxy-AR Sa3 Phenolic epoxy - AR Phenolic epoxy - AR 350 µ
(75 to 100 µ) polyamine cured polyamine cured
and and
abrasion resistant) abrasion resistant)
(175 µ) (175 µ)
4 Epoxy, amine adduct Sa3 Amine adduct epoxy Amine adduct epoxy 300 µ
(75 to 100 µ) (150 µ) (150 µ)
5 Epoxy, amine adduct - Sa3 Fiberglass 1500 µ
FRP (100 to 125 µ) reinforced amine
cured epoxy (See
Appendix 1)
DGS-6600-020/FH
Rev.
APPENDIX 3
DGS-6600-020/FH
Rev.
DGS-6600-020/FH