Professional Documents
Culture Documents
Cost Management: By: Engr - Faiz Rasul
Cost Management: By: Engr - Faiz Rasul
Planning
Cost Management
Plan Cost Magmt Plan
Planning
It focuses to find the less costly way to do the same thing. In Other words, this
technique asks “ How can we decrease the cost on the project while
maintaining the same scope.
- Analogous Estimation.
- Parametric Estimation.
- Bottom up Estimation.
- Direct Cost.
- Indirect Cost.
- Contingency Reserves
- Management Reserves
Basic Parameters
CV = EV - AC
SV = EV - PV
CPI= EV/AC
SPI= EV/PV
CV = +ve (Under Budget) CPI >1 ( Under Budget)
CV = -ve (Over Budget) CPI < 1(Over Budget)
CV = 0 (On Budget) CV = 1 (On Budget)
Actual cost for Project is 57,000$. What is Schedule Performance Index &
Cost Performance index of the Project?
A. 350
B. -75
C. 400
D. -50
BAC= 150,000 USD.06 months after the Project Start, you find our that PV =
40,000 & you have spent an actual cost of 38,000 USD. If CPI = 1.22, then what
will be your earned value cost.
• Construct 05 Rooms
• Budget for Project = 5,000$
• Project Duration = 05 Months
Start $ $ $ $ $ END
1000 1000 1000 1000 1000
M1 M2 M3 M4 M5
Budget = $ 5,000
$
1000
Start END
$
1000
M1 M2 M3 M4 M5
PV = 1,000$ (1 Room)
EV= 1,000$ (1 Room done)
AC= 950$ (What spent)
CV=50, SV=0, CPI=1.05, SPI=1 By: Engr.Faiz Rasul
E: pmp@cmsofficial.com, Ph.: 00966599454518
After Month-2
Budget = $ 5,000
$ $
1000 1000
Start END
$ $
1000 1000
M1 M2 M3 M4 M5
PV = 2,000$ (2 Room)
EV= 2,000$ (2 Room done)
AC= 2,000$ (What spent)
CV=0, SV=0, CPI=1, SPI=1 By: Engr.Faiz Rasul
E: pmp@cmsofficial.com, Ph.: 00966599454518
After Month- 3
Budget = $ 5,000
$ $ $
1000 1000 1000
Start $ 500 END
$ $
1000 1000
M1 M2 M3 M4 M5
PV = 3,000$ (3 Room)
EV= 2,500$ (2.5 Room done)
AC= 2,800$ (What spent)
CV= -300, SV= -500, CPI= 0.89, SPI= 0.83
Now Lets Move on to Next Concepts
of Earned Value Analysis:
Estimate To Complete.
Budget = $ 5,000
$ $
$
1000 1000
1000
Start END
$ $
$ 500 $ $
$ 500
M1 M2 M3 M4 M5
ETC = BAC – EV
Hint* = ( Total Value of work – Work Done = Remaining Work)
By: Engr.Faiz Rasul
E: pmp@cmsofficial.com, Ph.: 00966599454518
Now When You have Actual Cost Till Date & You know
Estimate to Complete also, Can you Predict How much
will be the Estimate At complétion of Project?:
Estimate at Completion= EAC = How Much we have spent+ How much more we need to Spend
Budget = $ 5,000
$ $
$
1000 1000
1000
Start END
$ $
$ 500 $ $
$ 500
M1 M2 M3 M4 M5
If at initially planned rate then?
EAC = AC + ETC If at Current rate then?
or AC + (BAC-EV) = 2,800 + (5000-2500) = 5,300$ EAC = BAC / CPI= 5000 / 0.89 = 5,617 $
Sample Questions:
On Your Project EV = 3500 , AC= 4000 & PV= 3850. Project Budget at completion
is 20,000 USD. If Cost performance index is expected to be same as it is, then
what is Estimate at completion.
CV = EV- AC
99.99% possibility
SV= EV-PV
CPI= EV/AC
SPI = EV/PV
ETC= BAC-EV
EAC= AC+ETC , EAC= AC + (BAC-EV), EAC = BAC/CPI
VAC = BAC – EAC