Client Consultant MEP Contractor Project Name & No.

Main Contractor
RENOVATION OF DAR AL
KUTUB

CHECK SHEET FOR: Form No. :


INSTALLATION OF DUCTWORK, DAMPERS, INSULATION, REFRIGERNT
PIPING, SUPPORT & ACCESSORIES INCLUDING LEAK TESTING Rev. No. :

CONTRACTOR Page No. :


SUBCONTRACTOR X X

Section of work: Location:

INSTALLATION OF DUCTWORK, DAMPERS, INSULATION,


REFRIGERNT PIPING, SUPPORT & ACCESSORIES INCLUDING
LEAK TESTING

SR Checked by Checked by
ITEM DATE
#
S/C CONT. Consultant

A. PREPARATION & INSTALLATION

1. Ensure that the material is as per approved material submittal.

2. Ensure drawings used for installation are current and approved.

3. Check that only properly fabricated fittings are used for change in directions,
shapes, sizes, and connections.
4. The joints and flanges are correctly made, jointed, and sealed (All transverse
joints and longitudinal seams ).
Check that duct joints are sealed externally before applying insulation with
5.
approval sealant.
6. Check fixing of supports and spacing as per approved drawings & submittal.

7 check sleeves are installed for ducts passing through walls/partitions as


required / as per approved drawings.

8 Check acoustic lining is properly fastened and undamaged.

Insulation is applied as per manufacturer's instructions and finished smooth


9
and straight without any damages.

Check nuts, bolts, screws, brackets drop rods etc, are tight and aligned
10
properly.

All the access doors, fire dampers, VCD's, VAV etc. are installed as per
11 approved drawings specifications and manufacturer’s instructions as
applicable.

12 Flexible duct connectors are provided at building expansion joints.

13 Ensure that the Identification & labeling are provided for duct works.
For S/C QA/QC: Date: For CONTRACTOR QA/QC: Date For Consultant Representative: Date:

Name: Sign: Name: Sign Name Sign: