Progress Report of Maintenace For The Month of August-2022
Progress Report of Maintenace For The Month of August-2022
Sr.No Name of Equipment Date PTW No. Details of Work carried out Remarks
SF6 CB along with adjacent isolators, CT junction boxes cleaning, terminal
1 E2Q1 along with Isolators 8/1/2022 Nil checks, physical parameters checks and dusting, blowering will be carried Routine Maintenace as per
out. schedule.
Emergency shut down on hotspot at D2Q10, UCH Line, nut bolts were
2 E3Q1 along with Isolators 8/2/2022 471 melted and jointed, Dropper T-connector assembly changed with new Emergent work
one.
Control room AC supply failed due to RCB was not holding, trooble shoot
6 Control Room AC supply fail from DB. 8/9/2022 480 the matter, find one phase of F/Standing as unit was pinched/broken, Emergent work
repair the wire and matter resolved.
220V Battery Bank-I Specific Gravity check, voltage reading & general Routine Maintenace as per
7 220V DC Battery Bank-I 8/10/2022 481
battery terminal cleaning and dusting job will be carried out. schedule.
10 Switch yard De-Watering 8/14/2022 Nil Switch Yard De-Water work carried out, to empty trenches after heavy Routine Maintenace as per
rain fall. schedule.
SF6 CB along with adjacent isolators, CT junction boxes cleaning, terminal
11 E1Q1 along with Isolators 8/15/2022 Nil checks, physical parameters checks and dusting, blowering will be carried Routine Maintenace as per
out. schedule.
1.160MVA T/F T-1 general inspection, fan noise check and LCC cleaning,
dusting and blowering will be carried out. Routine Maintenace as per
14 160MVA T/F both 8/18/2022 Nil 2.160MVA T/F T-2 general inspection, fan noise check and LCC cleaning, schedule.
dusting and blowering will be carried out.
Heavy rain fall and flood water escalation, protection and necessary
16 220/132KV Switch Yard area 8/22/2022 Nil emergent basis work carried out. Rain/Flood Emergency
Heavy rain fall and flood water escalation, protection and necessary
17 220/132KV Switch Yard area 8/23/2022 Nil emergent basis work carried out, Restoration of system and envoled in Rain/Flood Emergency
activities related to flood water control and sand bags filling etc and
other a large number of works for system healthiness.
De-Watering from 220/132KV switch yard area trenches and open area
18 220/132KV Switch Yard area 8/24/2022 Nil work carried out. Rain/Flood Emergency
De-Watering from 220/132KV switch yard area trenches and open area
19 220/132KV Switch Yard area 8/25/2022 Nil work carried out. Emergent work
De-Watering from 220/132KV switch yard area trenches and open area
20 220/132KV Switch Yard area 8/26/2022 Nil Emergent work
work carried out.
Control House Building AC Units De-Watering from 220/132KV switch yard area trenches and open area
21 8/29/2022 Nil work carried out. Emergent work
22 Emergency Diesel Generator 8/30/2022 Nil General cleaning, dusting blowering and necessary maintenace carried Routine Maintenace as per
out as per routine. schedule.
General cleaning, dusting blowering and necessary maintenace carried Routine Maintenace as per
23 200KVA Auxilliary transformers 8/31/2022 Nil
out as per routine. schedule.