MAINTENANCE SCHEDULE VS PROGRESS REPORT IN RESPECT OF 220kV GRID STATION DMJ

FOR THE MONTH OF AUGUST-22

Sr.No Schedule Date Progress Remarks


SF6 CB along with adjacent isolators, CT junction boxes cleaning, terminal checks, physical
Routine Maintenace as per
1 E2Q1 along with Isolators 8/1/2022 parameters checks and dusting, blowering will be carried out. schedule.

8/2/2022
Emergency shut down on hotspot at D2Q10, UCH Line, nut bolts were melted and jointed, Dropper Emergent work
2 E3Q1 along with Isolators T-connector assembly changed with new one.
SF6 CB along with adjacent isolators, CT junction boxes cleaning, terminal checks, physical
Routine Maintenace as per
3 E1Q1 along with Isolators 8/3/2022 parameters checks and dusting, blowering will be carried out. schedule.

SF6 CB along with adjacent isolators, CT junction boxes cleaning, terminal checks, physical
220KV CB D1Q1 8/4/2022 parameters checks and dusting, blowering will be carried out. Routine Maintenace as per
4 schedule.

SF6 CB along with adjacent isolators, CT junction boxes cleaning, terminal checks, physical
Routine Maintenace as per
5 220KV CB D1Q2 8/5/2022 parameters checks and dusting, blowering will be carried out. schedule.

8/9/2022
Control room AC supply failed due to RCB was not holding, trooble shoot the matter, find one phase Routine Maintenace as per
6 Control Room AC supply fail from DB. of F/Standing as unit was pinched/broken, repair the wire and matter resolved. schedule.

8/10/2022
220V Battery Bank-I Specific Gravity check, voltage reading & general battery terminal cleaning and Routine Maintenace as per
7 220V DC Battery Bank-I dusting job will be carried out. schedule.
Routine Maintenace as per
8 Switch yard bush Cutting 8/11/2022 Switch yard bush cutting job carried out. schedule.

8/12/2022
110V Battery Bank-I Specific Gravity check, voltage reading & general battery terminal cleaning and Routine Maintenace as per
9 110V DC Battery Bank-I dusting job will be carried out. schedule.
Routine Maintenace as per
10 Switch yard De-Watering 8/14/2022 Switch Yard De-Water work carried out, to empty trenches after heavy rain fall. schedule.
SF6 CB along with adjacent isolators, CT junction boxes cleaning, terminal checks, physical
Routine Maintenace as per
11 E1Q1 along with Isolators 8/15/2022 parameters checks and dusting, blowering will be carried out. schedule.

SF6 CB along with adjacent isolators, CT junction boxes cleaning, terminal checks, physical
Routine Maintenace as per
12 E5Q1 along with Isolators 8/16/2022 parameters checks and dusting, blowering will be carried out. schedule.

SF6 CB along with adjacent isolators, CT junction boxes cleaning, terminal checks, physical
Routine Maintenace as per
13 8/17/2022 parameters checks and dusting, blowering will be carried out. schedule.
E6Q1 along with Isolators

1.160MVA T/F T-1 general inspection, fan noise check and LCC cleaning, dusting and blowering will
8/18/2022
be carried out. Routine Maintenace as per
14 160MVA T/F both 2.160MVA T/F T-2 general inspection, fan noise check and LCC cleaning, dusting and blowering will schedule.
be carried out.

SF6 CB along with adjacent isolators, CT junction boxes cleaning, terminal checks, physical
Routine Maintenace as per
15 220KV CB D2Q2 8/19/2022 parameters checks and dusting, blowering will be carried out. schedule.

8/22/2022
Heavy rain fall and flood water escalation, protection and necessary emergent basis work carried Rain/Flood Emergency
16 220KV CB D2Q3 out.
Heavy rain fall and flood water escalation, protection and necessary emergent basis work carried
10/13 MVA Transformer T-3 8/23/2022 out, Restoration of system and envoled in activities related to flood water control and sand bags Rain/Flood Emergency
17
PT1Q11 & PT2Q12 filling etc and other a large number of works for system healthiness.
18 200KVA Auxilliary transformers 8/24/2022 De-Watering from 220/132KV switch yard area trenches and open area work carried out. Rain/Flood Emergency
19 110V DC Battery Bank-II 8/25/2022 De-Watering from 220/132KV switch yard area trenches and open area work carried out. Emergent work
20 220V DC Battery Bank-II 8/26/2022 De-Watering from 220/132KV switch yard area trenches and open area work carried out. Emergent work
Control House Building AC Units 8/29/2022 De-Watering from 220/132KV switch yard area trenches and open area work carried out. Emergent work
21

Routine Maintenace as per


22 8/30/2022 General cleaning, dusting blowering and necessary maintenace carried out as per routine. schedule.
Emergency Diesel Generator
Routine Maintenace as per
23 8/31/2022 General cleaning, dusting blowering and necessary maintenace carried out as per routine.
200KVA Auxilliary transformers schedule.

ASSISTANT MANAGER (M)


220KV G/S DERA MURAD JAMALI