You are on page 1of 1

Doc No:

Rev No:
PPM CHECKLIST: ACDB PANEL
Date:
Page 1 of 1

Plant Name :250 MW ISTS-1, BAP, RJ


Equipment ID :
Equipment Name : ACDB Panel
Location :
Date :
Frequency :

Sr.
Maintenance Checklist points Frequency Status
No.
1 Check the panel Earthing. Monthly

2 Check for vermin proofing. Take corrective action if necessary. Monthly

3 Check the indication Lamp working Monthly

4 Visual Inspection of Metering and Indication system for proper operation Quarterly
5 Clean the Panel thoroughly. Quarterly
6 Check the insulators for any cracks / tracking / burns or any damages. Half Yearly
Check for tightness of AC / DC control lines. Check all control cable
7 Half Yearly
terminations at various points for proper termination & tightness.
8 Check all the joints for tightness. Half Yearly

9 Inspect all wires for wear & cuts. Replace if necessary. Half Yearly
10 Check the control circuit connections & tightness of each panel. Half Yearly
Check for mechanical damage, distortion of structure & mechanism in
11 Yearly
general.
12 Perform Maintenance activity on MCCB & Contactor Yearly

Observations/Suggestions:

Spares Replaced / Required Quantity

PPM Carried Out By: Engineer Site In-Charge


MTPL O&M MTPL (MTPL)