INTRODUCTION
To conduct routine inspection, test and servicing of equipment in order to detect and eliminate impending problems which
Objective :
could cause breakdown or disruption of services.
Need : To understand system operation and the functionality of every system component.
Interest : To have detail of system schematic diagram and complete operation manual.
TRAINING AIDS / EQUIPMENT : Proper tools, Operation Manual and Electrical Single line drawing.
1. Check starter panel and Measure supply voltage and load Amps – single phase 230-240 To ensure all electrical components are free from
control panel volts using multi meter and Amp meter. dust and lose cable connection will cause arching
(monthly). Check cable terminals and connectors. Retightened all cable and tripping.
connection using proper screw driver. Sensor in good condition and reading correct
Check contactors, timer switch and relays. Cleaned all dust using parameters.
portable blowers.
Check indicator light and replace all fused bulb if necessary.
Check all temperature sensors reading through BCS system. (Off
coil, supply duct, air flow switch and pocket thermometer for
chilled water supply / return pipe together with pressure gauge.
Page 1
STANDARD OPERATING PROCEDURE
2. Check and service Observed motor running sound and measure vibration level by To ensure the plant room system is running in
blower motor & fan using basic visual check. correct parameters.
blade (monthly). Visual check the motor pulley condition together with pulley belts. To record all data value for future reference.
Visual check the motor supply cable and terminal cable insulation To ensure the machine is running with acceptable
condition. noise and vibration level. ( 60-75 db)
Visual check the fan blade physical condition. Observed fan blade
alignment and vibration level. Clean all dust at fan blade.
3. Check and service Visual check cooling coil condition. Flush thru the coil with cold To ensure maximum heat transfer and to avoid
cooling coil (monthly). water. energy losses.
If the cooling is found to be chocked, chemical cleaning has to be To ensure cooling coil structure material does not
organized. (normal cooling coil chemical cleaning schedule will be damage.
once for every 6 month depend on the coil condition )
Make good of cooling coil fins by using fins comb. This will
maintain the air flow efficiency at all time.
Clean and service cooling coil drain pan. Clear all algae and flush
thru drain pan pipe line.
4. Check and clean fresh Check fresh air filter and wash if necessary depend on the filter Avoid cooling coil from dirty and stuck the coil.
air filter (monthly). condition. (Only apply to washable filter).
5. Check and clean drain Clean drain pan from dirt and algae. Flush thru drain pipeline and Avoid drain pan and drain pipeline from chock.
pan tray and drain provide drain pan tablet.
pipeline (monthly).
Page 2
STANDARD OPERATING PROCEDURE
6. Check motorize valve Clean and service motorize valve, cable terminal and valve gear To ensure motorize valve in good condition.
(monthly). motor.
Note :
a) Observe all safety precaution.
b) Wear PPE (ear plug/muff) if necessary for hearing protection.
c) Ensure enough portable fire extinguisher located in the plant room.