Notes and comments regarding processed water installation and

water skids

This document contains confidential, proprietary information of Varian Transmittal Date Reply due
Medical Systems. It may not be copied or reproduced without prior
written permission from Varian Medical Systems. #27 2.3.23 n/a

Installer to have full understanding of:

• RFE requirements (Associated Punch list items & ‘attachment 7-appendix 6’ of BID)
• Water skids installation and pre-installation requirements
• Specific requirements associated with each loop
• High specification of water quality including its testing/sampling to ensure levels are met
• Implementing a water quality management plan (WQMP)
• Criticality of cryogenic compressors and relation to loop 3
• BMS installation to be completed & operational

Associated documentation:

• Full set of Varian mechanical drawings


• Full set of construction set mechanical design drawings
• Varian document PB CTB 00026_00 WQMP
• Water skids associated drawings and interfaces (incl’ attachment 7 appendix 6):
o Technics IOM document
o Technics 100174GA document
o Modbus provisional list for BMS connections
o Document 100163 Electrical loads
o Responsibility matrix

Alternative cable manufacturers for interlinking Belden cabling:

1DB_20115_en

Datasheet-1041239-lapp-32453

Belden has an approved distributor in Almaty:

ITC Electronics. Office 626 Gogolya str, 86. 50016 Almaty.

+7 (727) 2797117 http://www.itc-electronics.com

Varian Confidential
Installation process and requirements:

Below is an outline schedule of works required Pre and Post RFE & regarding the water loops and
skids installation.

Critical points are:

• System is resilient and dynamically & chemically flushed


• BMS & electrical installation completed
• WQMP in place
• Note duration timelines are advisable and to be confirmed by BDCT

Item Owner Duration TBC


Pre RFE:
Processed water loops installation mechanically completed BDCT
Certificated and tested BDCT
Temp pumps installed + water available BDCT 2 weeks
Flushing & chemical clean completed (similar to - BSRIA 2-3 weeks
BG29 standards) BDCT
Water sampling BDCT 2 weeks
SR4 completed as far as practically possible with exception TBA
of skids access area BDCT
Skids delivered to site Varian + BDCT 1 day
Water skids fixed in place – fully protected Varian + BDCT 1 week
SR4 completed (construction) BDCT BDCT TBC
Mechanical/electrical/BMS/CA installation completed BDCT BDCT TBC

Varian Checklist:
WQMP confirmed BDCT
BMS system functioning BDCT + Varian
Power and control electrical connections completed BDCT + Varian
Permanent Mechanical connections completed BDCT + Varian
CA connections completed BDCT
Strainers and filters checked BDCT + Varian
Water sampling criteria met BDCT + Varian

Commissioning at RFE:
Fill with D.I water BDCT BDCT TBC
System start-up/checks BDCT + Varian >1 week
Commissioning Varian 1-2 weeks
Water sampling as per BID requirements BDCT + Varian 1 week
Balancing for SR3/8 cabinets BDCT + Varian 1-2 weeks
Monitoring and report Varian On going

Note: The water skids are not protected from external elements and must be located in SR4
immediately and/or protected during installation from any adverse weather. (See below)

Varian Confidential
Skids delivery

Generic skid dimensions

Varian Confidential
SR4 when skids delivered:

SR4 prior to skids commissioning:

Varian Confidential
Highlighted BID references (full BID compliance required):

Water quality primary loops:

Varian Confidential
Specific parameters for loop 1B: Loop 1A:

Loop 2:

Varian Confidential
Varian Confidential
Secondary system:

8.2.3 Chilled water systems

8.2.4 Mechanical interfaces

Varian Confidential