PMC for Construction of Greenfield Port

at Ramayapatnam, SPSR Nellore District,


Andhra Pradesh

Weekly Progress Report No.25


(16th July 2022 to 22nd July 2022)

Report Submitted on 23rd July 2022

Prepared for: Andhra Pradesh Maritime Board

Document: 60638578_RPT_2022_07_04_WPR_025_R01
60638578_RPT_2022_07_04_WPR_025_R01

Quality information
Prepared by Checked by Approved by
Pradeep Kumar J
Sravan Muvva
M Harikrishna Sudhakar Rao Kandula
Lakshmipathy K
Polavarapu Venkata Avinash

Revision History
Authorized
Revision Revision date Details Name Position
R1 23-07-2022 Land Details
Correspondence Letters

Distribution List
# Hard Copies PDF Required Association / Company Name

Prepared for: Andhra Pradesh Maritime Board


PMC for Construction of Greenfield Port at Page 2 of 27
Ramayapatnam
0609779471.docx
60638578_RPT_2022_07_04_WPR_025_R01

Employer: Contractor:

Andhra Pradesh Maritime Board NECL-ARIPL JV


Plot No. 379,
Kakinada – 533 001
Road No. 10, Jublilee Hills,
Andhra Pradesh, India
Hyderabad - 500033

Employer’s Representative:

AECOM India Private Limited,

3rd Floor, Building No.8A,


DLF Cyber City, DLF Phase II,
Gurgaon 122 002,
Haryana, India
T: +91 124 4830100

CIN : U74210KA2005PTC037770

aecom.com

© 2018 AECOM India Private Limited. All Rights Reserved

This document has been prepared by AECOM India Private Limited (“AECOM”) for sole use of our client (the “Client”) in accordance
with generally accepted consultancy principles, the budget for fees and the terms of reference agreed between AECOM and the Client.
Any information provided by third parties and referred to herein has not been checked or verified by AECOM, unless otherwise
expressly stated in the document. No third party may rely upon this document without the prior and express written agreement of
AECOM

Prepared for: Andhra Pradesh Maritime Board


PMC for Construction of Greenfield Port at Page 3 of 27
Ramayapatnam
0609779471.docx
60638578_RPT_2022_07_04_WPR_025_R01

CONTENTS
LIST OF FIGURES............................................................................................
LIST OF TABLES..............................................................................................
GENERAL INFORMATION...............................................................................
STATUS OF LAND..........................................................................................
Day 1 : 16th JULY 2022 – SATURDAY.........................................................
1.1 CONSTRUCTION ACTIVITY....................................................................................................
1.1.1 PORT ACCESS ROAD WORK........................................................................................ 13
1.1.2 INTERNAL ACCESS ROAD WORK IN SITE...................................................................13
1.1.3 WORK IN CHIMAKURTHI................................................................................................ 13
1.1.4 SITE ESTABLISHMENT ACTIVITY..................................................................................13
Day 2 : 18th JULY 2022 – MONDAY.............................................................
2.1 SAFETY, HEALTH AND ENVIRONMENT................................................................................
2.2 BREAKWATER.........................................................................................................................
2.3 CONSTRUCTION ACTIVITY....................................................................................................
2.3.1 PORT ACCESS ROAD WORK........................................................................................ 14
2.3.2 INTERNAL ACCESS ROAD WORK IN SITE...................................................................15
2.3.3 SITE ESTABLISHMENT................................................................................................... 15
Day 3 : 19th JULY 2022 – TUESDAY............................................................
3.1 CONSTRUCTION ACTIVITY....................................................................................................
3.1.1 PORT ACCESS ROAD WORK........................................................................................ 16
3.1.2 INTERNAL ACCESS ROAD WORK.................................................................................16
3.1.3 SITE ESTABLISHMENT ACTIVITY..................................................................................16
Day 4 : 20th JULY 2022 – WEDNESDAY......................................................
4.1 BHOOMI PUJA.........................................................................................................................
4.2 BREAKWATER.........................................................................................................................
4.2.1 SOUTH BREAKWATER................................................................................................... 18
Day 5 : 21st JULY 2022 – THURSDAY..........................................................
5.1 BREAKWATER.........................................................................................................................
5.2 CONSTRUCTION ACTIVITY....................................................................................................
5.2.1 SITE ESTABLISHMENT ACTIVITY..................................................................................19
Day 6 : 22nd JULY 2022 – FRIDAY...............................................................
6.1 BREAKWATER.........................................................................................................................
6.2 CONSTRUCTION ACTIVITY....................................................................................................
6.2.1 INTERNAL ACCESS ROAD............................................................................................. 19
6.2.2 SITE ESTABLISHMENT ACTIVITY..................................................................................19
Appendix A MACHINERY UTILISED..............................................................
Appendix B SITE VISIT AND MEETINGS......................................................
Prepared for: Andhra Pradesh Maritime Board
PMC for Construction of Greenfield Port at Page 4 of 27
Ramayapatnam
0609779471.docx
60638578_RPT_2022_07_04_WPR_025_R01

Appendix C MACHINERY DEPLOYED..........................................................


Appendix D CONTRACTOR’S MANPOWER.................................................
Appendix E PMC’s MANPOWER....................................................................
Appendix F CORRESPONDENCE LETTERS................................................

Prepared for: Andhra Pradesh Maritime Board


PMC for Construction of Greenfield Port at Page 5 of 27
Ramayapatnam
0609779471.docx
60638578_RPT_2022_07_04_WPR_025_R01

LIST OF FIGURES

Figure 1 Seaport’s map of Andhra Pradesh........................................................................................... 8


Figure 2 Port Limits................................................................................................................................ 8
Figure 3 Ramayapatnam Port Layout – Phase I....................................................................................9
Figure 4 Map showing physical status of road as on 15th July 2022.....................................................12
Figure 5 Pylon granite fixing in progress..............................................................................................13
Figure 6 Arial view of Helipad after painting of H mark........................................................................14
Figure 7 Sign board being installed as a measure of safety................................................................14
Figure 8 CM meeting stage work is in progress...................................................................................15
Figure 9 Pylon work in progress.......................................................................................................... 15
Figure 10 Bhoomi Pooja Name Board.................................................................................................16
Figure 11 The Hon’ble Chief Minister of Andhra Pradesh offering prayer near seashore....................17
Figure 12 The Hon’ble Chief Minister of Andhra Pradesh Opening Pylon of Ramayapatnam Port......17
Figure 13 The Hon’ble Chief Minister of Andhra Pradesh receiving Vessel prototype as a token of gift
............................................................................................................................................................. 18
Figure 14 Core material being dumped in SBW on the occasion of Bhoomi Pooja.............................18
Figure 15 Core Material Dumping at South Breakwater......................................................................19
Figure 16 Floor Concrete for Site Establishment.................................................................................20
Figure 17 Bankers Visit........................................................................................................................ 22

Prepared for: Andhra Pradesh Maritime Board


PMC for Construction of Greenfield Port at Page 6 of 27
Ramayapatnam
0609779471.docx
60638578_RPT_2022_07_04_WPR_025_R01

LIST OF TABLES

Table 1 Port Limits................................................................................................................................. 8


Table 2 Land details in core area......................................................................................................... 10
Table 3 Land details in external road connectivity area.......................................................................11
Table 4 Land details in External Rail connectivity area........................................................................11
Table 5 Machinery utilised by the contractor for this week..................................................................21
Table 6 Machinery available for project as on 15th July 2022...............................................................23
Table 7 Contractor's Manpower........................................................................................................... 24
Table 8 PMC Manpower...................................................................................................................... 25

Prepared for: Andhra Pradesh Maritime Board


PMC for Construction of Greenfield Port at Page 7 of 27
Ramayapatnam
0609779471.docx
60638578_RPT_2022_07_04_WPR_025_R01

GENERAL INFORMATION

The Ramayapatnam port will be developed newly from greenfield layout which is in the
eastern coastal village in SPSR Nellore district of Andhra Pradesh, India. Proposed port will be
located on Bay of Bengal coastline at 93 km North of existing Krishnapatnam Port. Geographical
coordinates of proposed project location are 15° 02’ 55” N and 80° 02’ 50” E.

Figure 1 Seaport’s map of Andhra Pradesh Figure 2 Port Limits

Table 1 Port Limits

North Boundary South Boundary East Boundary West Boundary


Port Limits
Point A Point B Point C Point C
Latitude 15° 10’ 44” N 15° 10’ 44” N 14° 44’ 34” N 14° 44’ 34” N
Longitude 80° 04’ 40” E 80° 17’ 57” E 80° 18’ 06” E 80° 06’ 53” E

Prepared for: Andhra Pradesh Maritime Board


PMC for Construction of Greenfield Port at Page 8 of 27
Ramayapatnam
0609779471.docx
60638578_RPT_2022_07_04_WPR_025_R01

Figure 3 Ramayapatnam Port Layout – Phase I

Prepared for: Andhra Pradesh Maritime Board


PMC for Construction of Greenfield Port at Ramayapatnam Page 9 of 27
0609779471.docx
60638578_RPT_2022_07_04_WPR_025_R01

STATUS OF LAND

LAND DETAILS IN CORE AREA


Table 2 Land details in core area

Land
Bal to
SL Core Land Acquired / Land in
be Remark
no Area Requisitioned Land in possession
acquired
possession

1. Bal of 5.62 acres to be taken in


Patta
1 82.23 82.23 0.00 76.61 possession due to title owners
Land
dispute
1. 220 Acres - proposal received by
Govt. for ex-gratia of Rs. 8.06
Crores for eligible occupants
2. 43 Acres of Gramakantam lands,
to be vacated after R & R for 775
PDFs
a) Enumeration and estimation of
household structures valuations
has been completed in
Gramakantam - 40 Crs (Approx.)
b) 23 acres of land identified for
R&R of Mondivaripalem and
Avulavaripalem villages. (PLC
Meeting to be conducted for
Govt submitting proposal to R& R
2 296.78 0.00 296.78 0.00
Land commissioner - Not conducted due
to EC)
c) 39 acres of land is identified for
Karlapalem village R & R. and
pending at Gram Sabha approval
for willingness.
3. 7.5 Acres land proposals sent to
CCLA for advance possession
(Roads, Culverts & water bodies)
4. 12 acres is under POT, notice
issued
5. 14.28 acres (anadeenam land)
proposals under preparation for
submitting regular alianation to
CCLA
1. 43.46 acres - DD stage at District
2. 20.76 acres - PN published
3. 92.5 acres - Claims accepted by
Dotted
3 196.72 0.00 196.72 0.00 DLSC, PN has to be published
Land
(stopped due to EC)
4. 40.00 acres - Pending appeals
with CCLA
Assigned
4 61.00 61.00 0.00 61.00 Completed
Land

Total in Acre 636.73 143.23 493.50 137.61  


Prepared for: Andhra Pradesh Maritime Board
PMC for Construction of Greenfield Port at Page 10 of 27
Ramayapatnam
0609779471.docx
60638578_RPT_2022_07_04_WPR_025_R01

LAND DETAILS IN EXTERNAL ROAD CONNECTIVITY AREA

Table 3 Land details in external road connectivity area


External Land Land in
Land Bal to be
S. No Road Requisiti possessi Remark
Acquired acquired
Area oned on
2.26 acres to be taken in
Patta
1 89.00 89.00 0.00 86.74 possession due to title owners
Land
dispute
Govt Proposals with CCLA (6.12 ACRES)
2 10.58 0.00 10.58 0.00
Land & Collector (4.46 acres)
1. 10.01 acres - claims accepted
Dotted
3 18.57 0.00 18.57 0.00 2. 7.71 acres - claims rejected
Land
3. 0.85 acres - proposals at DLSC
Assigned
4 4.53 4.53 0.00 4.53 Completed
Land
File is under process - RoFR
Forest certificate from Collector, Nellore
5 11.37 0.00 11.37 0.00
Land & authentication done by PCCF,
and Maps sent to DFO Giddalur
Total in Acre 134.05 93.53 40.52 91.27  

LAND DETAILS IN EXTERNAL RAIL CONNECTIVITY AREA

Table 4 Land details in External Rail connectivity area


External Bal to
Land Land Land in
S.No. Rail be Remark
Requisitioned Acquired possession
area acquired
Patta
1 18.58 18.58 0.00 18.58  
Land
1. 18.5 acres land alianation
proposals submitted to CCLA
Govt
2 25.08 0.00 25.08 0.00 2. 6.58 acres of land alianation
Land
proposals under preparation at
tahsildar Gudlur
Dotted
3 2.21 0.00 2.21 0.00 Proposal with Collector
Land
File is under process - RoFR
Forest certificate from Collector, Nellore
4 33.73 0.00 33.73 0.00
Land & authentication done by PCCF,
and Maps sent to DFO Giddalur
Total in Acre 79.60 18.58 61.02 18.58  

LAND ACQUISITION

 8.6 Acre of aqua land along with 26.3 Acre of Dry land in Avulavaripalem and 16.74 Acres in
Mondivaripalem has been acquired by the revenue department on 8 th July 2022

 Employer have handed over the land to an extent of 267.19 Acre

Prepared for: Andhra Pradesh Maritime Board


PMC for Construction of Greenfield Port at Page 11 of 27
Ramayapatnam
0609779471.docx
60638578_RPT_2022_07_04_WPR_025_R01

Figure 4 Map showing physical status of road as on 15th July 2022

Prepared for: Andhra Pradesh Maritime Board


PMC for Construction of Greenfield Port at Ramayapatnam Page 12 of 27
0609779471.docx
60638578_RPT_2022_07_04_WPR_025_R01

Day 1 : 16th JULY 2022 – SATURDAY

1.1 CONSTRUCTION ACTIVITY

1.1.1 PORT ACCESS ROAD WORK


 Levelling in progress in Car parking area from Ch 5+300 to 5+600

1.1.2 INTERNAL ACCESS ROAD WORK IN SITE


 Aquaculture pond bund removal, sand filling and dozing in progress
 Moorum being filled at the backside of staff mess, Qty = 868 Cu.m Approx

1.1.3 WORK IN CHIMAKURTHI


 Approach road is being prepared from canal crossing to Mudhucon dump yard
 Rock segregation is in progress

1.1.4 SITE ESTABLISHMENT ACTIVITY


 Moorum being filled in VIP accommodating area
 Pylon
o Granite flooring and plastering work in progress
o 20 Nos of SS pipe arrived to be placed around the name board
 Helipad : Painting work completed
 Staff Building 2 : Roof truss fixing in progress
 Labour Building 6 : Column casting work in progress

Figure 5 Pylon granite fixing in progress

Prepared for: Andhra Pradesh Maritime Board


PMC for Construction of Greenfield Port at Page 13 of 27
Ramayapatnam
0609779471.docx
60638578_RPT_2022_07_04_WPR_025_R01

Figure 6 Arial view of Helipad after painting of H mark

Day 2 : 18th JULY 2022 – MONDAY

2.1 SAFETY, HEALTH AND ENVIRONMENT


 Sign boards being installed at various locations to guide the vehicle movement form NH to site

Figure 7 Sign board being installed as a measure of safety

2.2 BREAKWATER
 10 loads of core material received at site
 In SBW, as a part of Bathymetry survey sounding were taken from land for a width of 200 m from
Ch 0+000 to Ch 0+030 in 10 m x 10 m grid

Prepared for: Andhra Pradesh Maritime Board


PMC for Construction of Greenfield Port at Page 14 of 27
Ramayapatnam
0609779471.docx
60638578_RPT_2022_07_04_WPR_025_R01

2.3 CONSTRUCTION ACTIVITY

2.3.1 PORT ACCESS ROAD WORK


 Moorum filling in Bus parking area in progress from Ch 5+100 to Ch 5+500, Qty = 252 Cu.m
Approx

2.3.2 INTERNAL ACCESS ROAD WORK IN SITE


 VIP car parking area being extended by filling Moorum, Qty = 448 Cu.m Approx
 Aquaculture pond bund removal and sand levelling in progress
 Moorum being filled behind office in Mondivaripalem, Qty = 262 Cu.m Approx

2.3.3 SITE ESTABLISHMENT


 CM meeting stage erection in progress
 Barricades and plantation being provided in both sides from Helipad to Pylon
 Pylon : Granite flooring in progress
 Aquaculture pond bund removal, sand levelling in progress
 Moorum being filled of Qty = 448 Cu.m
o At back side of staff mess
o Connecting all labour building and labour mess

Figure 8 CM meeting stage work is in progress

Prepared for: Andhra Pradesh Maritime Board


PMC for Construction of Greenfield Port at Page 15 of 27
Ramayapatnam
0609779471.docx
60638578_RPT_2022_07_04_WPR_025_R01

Figure 9 Pylon work in progress

Day 3 : 19th JULY 2022 – TUESDAY

3.1 CONSTRUCTION ACTIVITY

3.1.1 PORT ACCESS ROAD WORK


 Helipad to SBW approach road extension work in extension work in progress

3.1.2 INTERNAL ACCESS ROAD WORK


 Public parking area cleaning, Moorum filling and grading in progress, Moorum Qty = 1,218 Cu.m

3.1.3 SITE ESTABLISHMENT ACTIVITY


 Pylon Fixing of Granite stone, SS logo, SS Name plates
 CM meeting stage works completed
 Aquaculture pond bund removal followed by sand levelling in progress in both day and night shift

Prepared for: Andhra Pradesh Maritime Board


PMC for Construction of Greenfield Port at Page 16 of 27
Ramayapatnam
0609779471.docx
60638578_RPT_2022_07_04_WPR_025_R01

Figure 10 Bhoomi Pooja Name Board

Prepared for: Andhra Pradesh Maritime Board


PMC for Construction of Greenfield Port at Page 17 of 27
Ramayapatnam
0609779471.docx
60638578_RPT_2022_07_04_WPR_025_R01

Day 4 : 20th JULY 2022 – WEDNESDAY

4.1 BHOOMI PUJA


 Chief Minister Y.S. Jagan Mohan Reddy performed “Bhoomi Puja” and initiated the construction
works by throwing a piece of rock into the breakwater work to spur port-lead industrial growth in
the region

Figure 11 The Hon’ble Chief Minister of Andhra Pradesh offering prayer near seashore

Figure 12 The Hon’ble Chief Minister of Andhra Pradesh Opening Pylon of Ramayapatnam Port

Prepared for: Andhra Pradesh Maritime Board


PMC for Construction of Greenfield Port at Page 18 of 27
Ramayapatnam
0609779471.docx
60638578_RPT_2022_07_04_WPR_025_R01

Figure 13 The Hon’ble Chief Minister of Andhra Pradesh receiving Vessel prototype as a token of gift

4.2 BREAKWATER

4.2.1 SOUTH BREAKWATER


 3 trips of core material being laid, Qty = 71.17 MT

Figure 14 Core material being dumped in SBW on the occasion of Bhoomi Pooja

Day 5 : 21st JULY 2022 – THURSDAY

5.1 BREAKWATER

5.2 CONSTRUCTION ACTIVITY


 Moorum filling in storwe and workshop area, Qty = 966 Cu.m Approx
 Moorum filling in NBW approach road, Qty = 70 Cu.m Approx
 2 trips of core material being laid at North Breakwater, Qty = 52.29 MT
Prepared for: Andhra Pradesh Maritime Board
PMC for Construction of Greenfield Port at Page 19 of 27
Ramayapatnam
0609779471.docx
60638578_RPT_2022_07_04_WPR_025_R01

 4 trips of core material being laid at South Breakwater, Qty = 92.58 MT


 Total 6 Trips of Core Material, Qty = 144.87 MT

Figure 15 Core Material Dumping at South Breakwater

5.2.1 SITE ESTABLISHMENT ACTIVITY


 Aquaculture pond bund removal, sand filling and dozing in progress
 Staff building 2 : Fixing of roof sheet started and in progress

Day 6 : 22nd JULY 2022 – FRIDAY

6.1 BREAKWATER
 In SBW, as a part of Bathymetry survey sounding were taken from land for a width of 200 m from
Ch 0+030 to Ch 0+050 in 10 m x 10 m grid

6.2 CONSTRUCTION ACTIVITY


 3 trips of core material being laid at North Breakwater, Qty = 59.91 MT
 5 trips of core material being laid at South Breakwater, Qty = 125.44 MT
 Total 8 Trips of Core Material, Qty = 185.35 MT

6.2.1 INTERNAL ACCESS ROAD


 Aquaculture pond bund removal and sand dozing in site establishment area in RHS of Old
Moorum Road

6.2.2 SITE ESTABLISHMENT ACTIVITY


 Staff building 6 : Flooring concrete work in progress
 Aquaculture pond bund removal, sand filling and dozing in progress

Prepared for: Andhra Pradesh Maritime Board


PMC for Construction of Greenfield Port at Page 20 of 27
Ramayapatnam
0609779471.docx
60638578_RPT_2022_07_04_WPR_025_R01

Figure 16 Floor Concrete for Site Establishment

Prepared for: Andhra Pradesh Maritime Board


PMC for Construction of Greenfield Port at Page 21 of 27
Ramayapatnam
0609779471.docx
60638578_RPT_2022_07_04_WPR_025_R01

Appendix A MACHINERY UTILISED

Table 5 Machinery utilised by the contractor for this week

19 July

21 July
16 July

18 July

20 July

22 July
2022

2022

2022

2022

2022

2022
S.No. Type of Machinery Brand and Model Description Location

Sat Mon Tue Wed Thu Fri


1 Excavator Kobelco SK380XDLC Road/Site Establishment 2 2 2 1 2 2
2 Excavator Kobelco SK220XDLC Road/Site Establishment 2 2 2   2 2
3 Tractor Dozer John Deere 5310 Road/Site Establishment 2 2 2   1 1
4 Backhoe loader JCB 3DX Road/Site Establishment 3 3 3   3 3
5 Roller L&T 1900 Road/Site Establishment 1 1 1   1 1
6 Grader SDLG G9138H Road/Site Establishment 1 1 1   1 1
7 Tractor Tanker 4 KL Road/Site Establishment 6 6 6   2 2
Bharath Benz 3528C 8X4 BSVI
8 12-wheel dumper Road/Site Establishment 24 24 24 3 6 8
Eicher Pro 6035T 8X4 BSVI
9 Chain mounted Dozer BEML D50 Road/Site Establishment 1 1 1   1 1
10 SLM Ajax Agro 2000 Site Establishment 1 1 1   1 1
11 Backhoe loader L&T Case Site Establishment 1 1 1   1 1
12 Tanker 4 KL Site Establishment 1 1 1   1 1
13 Excavator Kobelco SK380XDLC Quarry 2          
Bharath Benz 3528C 8X4 BSVI
14 12-wheel dumper Quarry 2          
Eicher Pro 6035T 8X4 BSVI
15 Tractor Dozer John Deere 5310 Quarry 1          
Total 50 45 45 4 22 24

Prepared for: Andhra Pradesh Maritime Board


PMC for Construction of Greenfield Port at Ramayapatnam Page 22 of 27
0609779471.docx
60638578_RPT_2022_07_04_WPR_025_R01

Appendix B SITE VISIT AND MEETINGS

 Bankers of State Bank of India and Union Bank of India members are visited site on 21-07-2022

Figure 17 Bankers Visit

Prepared for: Andhra Pradesh Maritime Board


PMC for Construction of Greenfield Port at Page 23 of 27
Ramayapatnam
0609779471.docx
60638578_RPT_2022_07_04_WPR_025_R01

Appendix C MACHINERY DEPLOYED

Table 6 Machinery available for project as on 15th July 2022


S.No. Location Type Brand & Model Count Remarks

1 Sri Srinivasa Stone Excavator Kobelco SK380XDLC 2

2 Crusher, Chimakurthi Excavator Kobelco SK220XDLC 1

3 Excavator Kobelco SK380XDLC 2

4 Excavator Kobelco SK220XDLC 1

12 Wheel Bharat Benz 3528C 8X4


5 30
dumpers BSVI Own

12 Wheel Eicher Pro 6035 T L CBC BS


6 30
dumpers VI

7 Grader SDLG G9138H 1

8 Roller L&T 1190 1

9 Excavator Kobelco SK850LC 1

Backhoe
10 JCB 3DX 2
Site loader

Tractor
11 John Deere 5310 2
Dozer

Tractor
12 with 4 KL 2
Tanker
Outsourced
13 Tanker 4KL 1

14 SLM Ajax Agro 2000 1

15 Fuel Tank 20 KL 1

Backhoe
16 L&T Case 1
loader

17 Dozer BMEL D50 1

Prepared for: Andhra Pradesh Maritime Board


PMC for Construction of Greenfield Port at Page 24 of 27
Ramayapatnam
0609779471.docx
60638578_RPT_2022_07_04_WPR_025_R01

Appendix D CONTRACTOR’S MANPOWER

Table 7 Contractor's Manpower

16 July 2022

18 July 2022

20 July 2022
19 July 2022

21 July 2022

22 July 2022
S.No. Location Designation

Mo Tu We Th
Sat Fri
n e d u
1 Deputy General Manager - Civil 1 1 1 1 1 1
Assistant General Manager -
2 1 1 1 1 1 1
Civil
3 General Manager - Mech 1 1 1 1 1 1
4 Senior Manager - Mech 1 1 1 1 1 1
5 Mechanical Engineer 2 2 2 2 2 2
6 Liasioning Department 2 2 2 2 2 2
7 QC Engineer 1 1 1 1 1 1
8 SHE Deputy Manager 1 1 1 1 1 1
9 Overall Surveyor 2 2 2 2 2 2
10 Planning Engineer 1 1 1 1 1 1
  First Aider 1 1 1 1 1 1
11 Admin/HR Department 3 3 3 3 3 3
12 Stores Department 1 1 2 2 2 2
  Accounts Department 1 1 1 1 1 1
13 Aurobindo Helpers 8 8 8 8 8 8
14 Electrical 1 1 3 3 3 3
  Heavy Machine Mechanic 1 1 1 1 1 1
  Welder 1 1 1 1 1 1
15 Engineer 2 2 2 2 2 2
16 Supervisor 2 2 2 2 2 2
Site
17 Labour 50 50 50     36
Establishment
Superstructure Installation
18 12 12 12   12 12
Team
19 Engineer 2 2 2 2 2 2
20 Supervisor 2 2 2 2 2 2
21 Foreman 2 2 2 2 2 2
Road
22 Vehicle In-charge 1 1 1 1 1 1
23 Heavy Machinery Operator 49 44 44 3 21 23
24 Flag Man 4 4 4 4 4 4
Security
25 Guards 10 10 10 10 10 10
Personnel
16 16 12
Total 161 61 91
6 4 9

Prepared for: Andhra Pradesh Maritime Board


PMC for Construction of Greenfield Port at Page 25 of 27
Ramayapatnam
0609779471.docx
60638578_RPT_2022_07_04_WPR_025_R01

Appendix E PMC’s MANPOWER

Table 8 PMC Manpower

S.No. Location Designation No of Persons

1 Project Manager 1
2 Vijayawada Contracts and Procurement Specialist 1
3 Engineer I 1
4 Technical Director 1
5 Resident Engineer 1
6 Assistant Manager – Contract Management 1
7 SHE Specialist 1
8 Senior Quality Assurance Specialist 1
Kavali
9 Engineer III 1
10 Quantity Surveyor III 2
11 Engineer II 1
12 Document Controller 1
13 Supporting staff 1
Total 14

Prepared for: Andhra Pradesh Maritime Board


PMC for Construction of Greenfield Port at Page 26 of 27
Ramayapatnam
0609779471.docx
60638578_RPT_2022_07_04_WPR_025_R01

Appendix F CORRESPONDENCE LETTERS

End of the document

Prepared for: Andhra Pradesh Maritime Board


PMC for Construction of Greenfield Port at Page 27 of 27
Ramayapatnam
0609779471.docx