You are on page 1of 9

IPA18-337-E

PROCEEDINGS, INDONESIAN PETROLEUM ASSOCIATION


Forty-Second Annual Convention & Exhibition, May 2018

DO-IT-YOURSELF GRAVEL PACK APPLICATION IN TARAKAN, INDONESIA

Alexis Ariwibowo*
Muchammad Rizal Alfaqih*

ABSTRACT successfully overcome sand problem in Tarakan.


Whereas the absence of sand control or using a
Sandstone formations in the Mamburungan Field of stand alone sand screen would result in decreasing
Tarakan Island, North Kalimantan have a history of production lifetime as shown in the other wells in
sand production especially from shallow gas Table 1 without gravel pack.
reservoirs. Gravel packs using third party services
have been proven to extend production lifetime and Unfortunately, the location of Tarakan island itself
increase cumulative production. However, the makes most of the potential gas formations
remote location of Tarakan Island and cost of the uneconomically viable to produce due to high
gravel pack job has limited application with third- gravel pack cost. This high gravel pack cost is
party services which must be mobilized from far mainly caused by high mobilization and
away. The Operator, PT. Medco E&P Indonesia, has demobilization cost to and from Tarakan island,
developed its own gravel pack, nicknamed Do-It- which could be more than the cost to perform the
Yourself or DIYGP, based on techniques and gravel pack services itself. This paper will describe
procedures which rely mostly locally-manufactured how designing, manufacturing, and installing
tools in order to reduce cost and so extend gravel pack using mostly local resources can be the
application of gravel packs to previously solution for a more cost efficient way to produce
uneconomic candidates. So far the DIYGP has been gas reservoirs, without taking away the quality and
applied per design in just one well with a cost technical advantage of a service provided gravel
reduction of over 90% compared to third party jobs. pack. The designed DIYGP will be installed in
And, after five (5) months with cumulative well M-9.
production of 17.7 MMscf, the well continues to
produce sand-free. Payout time for the DIYGP for DESIGN OF GRAVEL PACK
this particular well is one and a half (1.5) months.
However, testing indicates a significant positive Gravel and Screen Design
skin, and efforts are underway to improve the
technique and extend it to other candidates. Gravel and screen design is made based on sand
sieve analysis of sand produced from wells which
INTRODUCTION produce from formations above 1,000 meters. The
results of the sieve anlaysis are shown in Table 2.
Sandstone formations in Tarakan Island, Based on the table, the 50% value on the
especially shallow gas formations that are above cumulative mass distribution plot (D50) is
1,000 meters have a history of producing sand. The approximately 180 µm with uniformity coefficient
effects could be sand piling in the wellbore, choke D40/D90 of 4.62. In this design, gravel pack sand
abrasion, flow line leaks, separator fill-up, etc. size is calculated in the range of 5 to 6 times the
Attempts to overcome these problems by applying D50 and also keeping in mind the design used in
sand control have been done over the years with gravel pack well H-3. Therefore, 16/40 sand size
various results and include things like stand-alone and 404 µm screen slot width was determined to
screens, gravel packs, and surface sand handling be used in gravel pack well M-9.
with no downhole sand control. A summary of
selected adjacent and reference wells that have Gravel used in this DIYGP sourced from Juwata
produced in similar gas reservoirs and the various natural sand in Tarakan. The natural sand was
sand control techniques is displayed in Table 1. As sized using a 16/40 mesh sieve screen. While sand
shown in Table 1, sand control using gravel pack screen was purchased from one of the gravel pack
in well H-3 has been historically proven to supplier.

* Medco E&P Indonesia


Tool Configuration Design single trip, two (2) run installation process is a slight
disadvantage. However, since the daily rate cost for
Normally a gravel pack tool configuration would this DIYGP installation in M-9 is relatively low, the
consist of a screen, blank pipe, and gravel pack additional operation time cost was less significant
packer complete with a multi-position working tool. compare to the overall cost saving made using
The multi-position working tool is essential in gravel DIYGP.
placement due to its ability to alter the circulating
path during placement and pumping of gravel. Since Installation and Gravel Placement Procedure
a multi-position working tool was unavailable, and
could not be manufactured locally, the DIYGP tool Prior to setting the seal packer and gravel in place, a
configuration was modified to accommodate its cement plug is set approximately 9-meters below
function, without jeopardizing the quality and perforation interval. The cement plug acts as a
functionality of the whole gravel pack configuration. landing base for the gravel pack screen and it enables
seal packer to be set in place.
DIYGP tool configuration for M-9 can be seen in Installation and gravel placement procedure are
Figure 1, consist of seal-bore packer, screen, blank described as follow:
pipe, float valve, and mule shoe. In addition to the
gravel pack tools assembly, Figure 2 shows the  RIH with a drill pipe string and DIYGP tool
seal bore & seal stinger assembly which was made configuration, which consist of mule shoe, float
and installed on top of cross over (inside blank valve, crossover complete with seal bore, blank
pipe). This seal bore & seal stinger assembly is pipe, screen, and seal packer, using a packer
critical to ensure the gravel slurry could flow from setting tool to top of cement
the work string to the annulus of the screen.
Without this assembly, gravel would fill up inside  Set the seal packer and gravel pack assembly by
the screen, instead of behind the screen, and the rotating setting tool clockwise until torque
whole gravel pack would have failed. The function 1,000-ftlb. Ensure using tally that the screen is
of the seal bore & seal stinger assembly replaced in front of perforation. Once seal packer is set,
the multi-position working tool which is normally pick-up test by over pull 6,000-lb
used in gravel pack job services.
 Release packer setting tool and POOH setting
The seal packer and seal bore & seal stinger tool
assembly were designed and manufactured locally
in a vessel specialized machinery workshop.  RIH seal stinger to top of seal bore, circulate and
Sketch drawings complete with dimensions were record circulating pressure
discussed in advance with manufacturer to assess
the visibility of the work. During the  Sting in seal stinger to seal bore, circulate and
manufacturing process, which took approximately record circulating pressure (there should be an
2 weeks, company representative was assigned to increase in circulating pressure)
supervise the process.
 Mix gravel slurry with concentration of 1 – 1.5
The seal packer is designed complete with setting ppg gravel, or 1 – 1.5 lb of gravel per gallon
tool, and once the seal packer is set complete with slurry* with formula as follow:
the gravel pack configuration, the setting tool can 10-bbl FW + 0.25-ppb Caustic soda + 40-ppb
be retrieved. The seal stinger is then run to latch Bentonite gel + 11-sack Natural 16/40 sand (@
into the seal bore to create a seal between the 5-gal, 62.7-lb)
inside of the tubing string and the tubing annulus
inside the screen. This will prevent sand building * - The range of gravel slurry concentration was
up inside the screen, and divert the flow path to go based on previous experience at H-3 which had
through the float valve, mule shoe, and annulus of a premature screen out above 2 ppg.
the screen.
 Pump gravel slurry and displace with tubing
By using DIYGP, installation would require two (2)
volume with pumping schedule as follow:
runs. The first run is to set gravel pack screen and
Slurry volume : 12-bbl
seal packer assembly, and the second run is to run the
Displace volume : 9.6-bbl
seal stinger for gravel placement. Compared to a
Surface line volume : 1-bbl
service-provided gravel pack, which is done in a

 
Total pumping volume : 22.6-bbl Installation of completion string and testing result
Flow path of gravel slurry could be seen in confirms that dry gas was be produced without any
Figure 3. sand problem to occur. Well M-9 has been
producing with no evidence of sand production and
RESULT the gas was being produced for 177 days until the
wellhead pressure declines to equal gas system
Gravel Pack Tool Installation pressure. Although the well has successfully
produce Gas without sand problem, there are
For well M-9, the base cement for landing the gravel improvements to be made as pressure survey test
pack tools is at 652.6 meter KB, and the perforation show that the gravel pack has a permeability of
interval is from 642 to 643 meter KB. Therefore, the only 11 mD and skin factor of 36. These are the
gravel pack tool configuration was installed as parameters that should be addressed in next
shown in Table 3. Once the gravel pack tool was in DIYGP design.
place, the seal packer was set with 1,000 ft.lb right-
hand torque, and a pick-up test was conducted with Cost wise, significant savings were made during
overpull 15,000 lb., then the packer setting tool was the whole gravel pack design, manufacture, and
released and the work string was pulled out of the installation process. This DIYGP method of
hole. All indication and parameters showed the performing simple gravel pack with locally
gravel pack tool was set according to design. designed and manufactured key downhole
equipment reduced cost by more than 90 %
Gravel Placement compare to previous third party gravel pack jobs.
This cost reduction was mainly due to the absence
The seal stinger assembly was run until top of blank
of mobilization & demobilization cost, service cost
pipe for a circulation test. The circulation test was
and a significant reduction in gravel pack tools and
conducted to record initial circulating pressure prior
consumable materials.
to sting in and after sting in into seal bore. This step
was necessary to ensure the seal stinger was working
There are three (3) additional well candidates for
properly and the integrity of the circulation path
DIYGP application, which are currently on
through the float valve and screen annulus. The
subsurface review. Based on the lessons learned
recorded circulation pressure are shown below:
during DIYGP installation in M-9, there are two
Sting out position : 200-psi (2) main improvements to be done in future job.
Sting in position : 240-psi (shows circulation First is to use a well-rounded ceramic sand, and
path through float valve adds 40-psi pressure drop) second is to use fresh water as gravel carrier fluid.
By using fresh water as a carrier fluid, gravel
After ensuring the gravel pack tools were in pumping concentration would have to be 1-ppg.
position, the gravel slurry was mixed with using a
company-owned cementing unit and with CONCLUSIONS and RECOMMENDATIONS
parameters:
1. The DIYGP using local resources for design
 Slurry volume : 12 bbl and manufacturing of key equipment and
 Slurry density : 9.8 ppg consumable materials reduced cost by over
 Excess : 18 % 90% compared to previous third party jobs.
 Gravel concentration : 1.4 ppg
2. Well M-9 has produced for five (5) months
The gravel slurry volume of 13 bbl was pumped with sand free since the DIYGP with total
pump pressure 300-psi, continued by 8 bbl production of 17.7 MMscf which gives a
displacement volume until achieving a gravel pack payout of one and a half (1.5) months.
pressure at 1,000-psi, with the pressure limited by the
potential for hydraulic fracturing. After re- 3. DIYGP is currently being considered for three
confirming the pack pressure to 1,000-ps, the string (3) other wells in the Hakebabo and Sesanip
was pulled out of the seal stinger and excess gravel field. Based on lessons learned, the DIYGP
slurry was reversed out inside string. Post job can be improved by using well-rounded
calculation estimates that gravel placement achieved ceramic sand and use clear fresh water as
92.2 % of total gravel volume with top of gravel carrier fluid for the gravel.
behind screen at 637 meter KB.

 
ACKNOWLEDGMENTS http://gekengineering.com/Downloads/Free_Downl
oads/Sand_Control_Overview.pdf
The author would like to thank PT. Medco E&P
Indonesia, SKK Migas, and Direktorat Jenderal Halliburton. 2004. Design of Service for Gravel Pack
Migas for their permission to publish this paper. Service HKB-03
We also acknowledge the valuable contribution of
members of Tarakan Asset field operation and Halliburton. 2008. Design of Service for Gravel Pack
engineering. Last but not least, the authors would Service Mengatal 2008-1
like to show their appreciation for the support of
Medco’s Drilling and Completions Department Purwaka, Edi. 2013. Work Over and Well
and the Workover & Well Services Department. Completion.

REFERENCES TRACS International training material. February


2009. Completion Design
George E. King Engineering. 14 March 2009. Sand
Petrowiki. 2017. Gravel Pack Design.
Control Method.
http://petrowiki.org/Gravel_pack_design

 
TABLE 1

SUMMARY OF SELECTED ADJACENT AND REFERENCE WELLS THAT HAS PRODUCED IN


SIMILAR GAS RESERVOIRS IN THE MAMBURNGAN AND HAKEBABO FIELD, TARAKAN,
KALIMANTAN

Well Formation Oil / Gas Sand Control Lifetime

M-10 700MZ Gas Stand alone screen 135 days

M-17 700MZ Gas None 99 days

H-3 745MZ Gas Gravel pack

H-4 790MZ Gas Stand alone screen +/- 7 days

TABLE 2

(A) TABLE AND (B) GRAPHIC FOR SIEVE ANALYSIS OF PRODUCED SAND IN
FORMATIONS ABOVE 1000 METER FROM [NAME] FIELD

Grain
Sieve No Size Weight Weight Cum. Weight
(mesh) (μm) (gram) (%) (%)
50 300 130.61 43.54 43.54
60 250 6.95 2.32 45.85
70 212 7.23 2.41 48.26
80 180 4.98 1.66 49.92
100 125 92.18 30.73 80.65
170 90 14.79 4.93 85.58
230 63 38.79 12.93 98.51
270 53 2.36 0.79 99.30
>270 40 2.11 0.70 100.00
TOTAL 300 100
(a)

SIEVE ANALYSIS
100
CUMMULATIVE WEIGHT (%)

80

60

40

20

0
400  300  200  100  0 
GRAIN SIZE (µm)
(b)

 
TABLE 3

GRAVEL PACK TOOL CONFIGURATION FOR DIYGP IN WELL M-9.

Top Lower Depth Depth


Description Connection Connection Length (m) (mKB) (mKB)
(mKB) (mKB) Top Bottom
Upper Seal Packer - BTC 0.225 634.4 634.62
Lower Seal Packer BTC 4" NUE 0.875 634.62 635.50
Screen GP 4" NUE 4" NUE 9.970 635.50 645.47
Blank Pipe 4" NUE 4" NUE 6.065 645.47 651.53
Cross Over 4" NUE 3-1/2" EUE 0.120 651.53 651.65
Float Valve 3-1/2" EUE 3-1/2" EUE 0.275 651.65 651.93
Mule Shoe 3-1/2" EUE - 0.675 651.93 652.60

 
 Description
Seal Pac ker

Screen Gravel Pack

Blank Pipe

Cross Over (with seal bore)

Float Valve

Mule Shoe

Figure 1 - Designed gravel pack tool configuration

 
 Description
Seal Stinger (connect to work
string and latch to seal bore)

Blank Pipe

Seal Bore

Cross Over
Figure 2 - Designed seal bore & seal stinger assembly

 
Gravel slurry flow path:
1. Inside Work string  
2. Through seal stinger and seal bore 
3. Through float valve and mule shoe 
4. Enter annulus between gravel pack screen 
and production casing 
5. Carrier fluid will flow through inside screen, 
and gravel will be filtered and remain in 
annulus 
6. Carrier fluid flow between inside seal 
packer and work string up to surface 
through annulus work string 

Pumping gravel slurry should always be in sting


in position

Figure 3 - Flow path of gravel slurry during gravel placement

You might also like