Construction Daily Report

Project Address Job Type Job # Prepared By Date


Garage 123 Main St. Construction build 123 Luc Godard 12/3/2021
Weather Conditions
Sunny, clear, mid-70s

Work
Task Status
Paint exterior Doing
Remove vegetation near foundation Done

Crew
Type Name Hours
Painter Joe Smith 8
Painter Sam Jones 8
Landscaper Frank Lesser 4

Equipment
Type Status Hours
Paint blower In Use 8
Brushes, rollers In Use 8
Pick, shovel, wheelbarrow In Use 4

Materials
Type Used Remaining
Paint Yes 3 gallons
Tarp Yes 30 sq. ft.

Delivered
Type Scheduled Actual
Paint 8:00 AM 8:30 AM

Delays
Type Description Time
Paint delivery Paint came half an hour after expected Half-hour lost

Other Events
Type Description Time
N/A

Meetings
Type Time Attendees Summary
Daily Standup 8:00 AM Foreman, paint and landscape crews Rain expected next day, rescheduling painting
Safety Inspection
Yes No Incident

Visitors
Name Purpose Title
N/A

Company Signature Date

Client Signature Date