Task Status
Paint exterior Doing
Remove vegetation near foundation Done
Crew
Type Name Hours
Painter Joe Smith 8
Painter Sam Jones 8
Landscaper Frank Lesser 4
Equipment
Type Status Hours
Paint blower In Use 8
Brushes, rollers In Use 8
Pick, shovel, wheelbarrow In Use 4
Materials
Type Used Remaining
Paint Yes 3 gallons
Tarp Yes 30 sq. ft.
Delivered
Type Scheduled Actual
Paint 8:00 AM 8:30 AM
Delays
Type Description Time
Paint delivery Paint came half an hour after expected Half-hour lost
Other Events
Type Description Time
N/A
Meetings
Type Time Attendees Summary
Daily Standup 8:00 AM Foreman, paint and landscape crews Rain expected next day, rescheduling painting
Safety Inspection
Yes No Incident
✘
Visitors
Name Purpose Title
N/A