Professional Documents
Culture Documents
▪ PART 1: Energy Sale & Purchase between EDL & TNB- Set out the issues that
are relevant to EDL & TNB relating to the sale by EDL and its purchase by TNB of
the LTM energy
▪ PART 2: Wheeling Charge between EDL and EGAT- Set out the issues that are
relevant only to EDL & EGAT relating to the wheeling obligations of EGAT
35,000
30,683
Installed Capacity (MW)
30,000
25,000
21,151 23,595
20,000
16,651
17,173
15,000 13,055
13,273
10,000 10,577
6,437 6,393
Voltage Thailand
EDC EVN CSG Myanmar Total
Level EGAT PEA
22/35 kV 1 7 3 1 6 18
115 kV 1 1 5 7
230 kV 2 2 4
500 kV 3 3
Total 2 9 4 1 10 6 32
Remarks:
22/35kV – Import
115kV – Exchange
230kV – Purely Export
500kV – Purely Export
Legend : 115 kV
230 kV
500 kV
Physical Flow 2018-2019
275/230kV HVAC
115 kV HVAC 300 kV HVDC and Plentong -
300 MW Woodlands
TNL, PT-NK KNE-Gurun
PX-BKN
Note:
•Between Lao PDR-Thailand: without Power Flow Control (without ACE)
•Between Thailand-Malaysia: Controlled by Pole Control of HVDC
•Between Malaysia-Singapore: AGC setting of Area Control Error (ACE)
LTM-PIP Commercial Arrangement for Phase 1
Part2:
Existing Wheeling
Energy Flow
Agreements Charge
Energy
Purchase
Transit Thailand and
Wheeling
Agreement
(EPWA)
Existing
Agreement Part 1:
Energy
Purchase
Buyer Malaysia
10
LTM- PIP 2.0 – Timelines and Activities
11
Lesson Learn of LTM PIP
• The LTM-PIP is the first and successful venture of multilateral energy trading in
ASEAN where Malaysia purchases electricity power up to 100MW from Lao PDR via
existing Thailand’s transmission grid.
• A tripartite agreement known as the Energy Purchase and Wheeling Agreement (EPWA)
was signed among EDL, EGAT and TNB on 27 September 2017 during the 35th ASEAN
Ministers on Energy Meeting in Manila, Philippines. This EPWA governs the sale, transit
and purchase of electrical energy up to 100 MW. This agreement is for a period of 2 years
from 1 January 2018 until 31 December 2019.
• As of September 2019, there were 24.93 GWh energy has been transacted via the LTM-
PIP
• During 36th ASEAN Ministers on Energy Meeting in October 2018, all parties agreed
to continue the implementation of LTM-PIP with a new extension term and proposal
to increase the capacity up to 300MW with committed energy.
• All the parties intend to extend the term of EPWA for additional 2 years. Following
this, Supplementary Agreement to EPWA is proposed to reflect this extension
together with necessary amendments to EPWA.
• Series of meetings have been conducted from March – July 2019 among Lao PDR,
Thailand and Malaysia to discuss technical & commercial aspect LTM-PIP 2.0 and
the proposed Supplementary Agreement to EPWA. 12
The way forward
13
Conclusion
14
ຂອບໃຈ
Thank you for your attention