You are on page 1of 4

IE Comments Location Concessionaire Compliances IE Reply Concessionaire Compliances

06.09.2022
Horizontal Alignment
The drawings are not satisfying as per 513140.656, Clause 9.1.5 of IRC:73 is only for As per codal We have provided AutoCAD file also
IRC:73 clause 9.1.5 “Short curves give 513286.4065, aesthetics and appearance, it is not provisions, Short to IE and it was discussed that
appearance of kinks, particularly for 514058.4145, safety / geometry requirement. We have curves give alignment cannot be modified further.
small 514270.6555 tried to fulfill this requirement in the appearance of kinks,
deflection angle and should be avoided. whole stretch except 4 locations particularly for small
The curves should be sufficiently long mentioned by you. Please note that, at deflection angle and
and have suitable transition to provide all location mentioned in letter, curve should be Avoided.
pleasing appearance. Curve length should radius is provided more than 2000m and However, decision
be at least 150 meters for a deflection practically straight. It will not give any has to be taken by
angle of 5 degrees and this should be bad appearance because of very mild Authority as the
increased by 30 meters for each one radius. If length of curve is increased, matter related to
degree decrease in the deflection angle. ROW will go outside the ROW constraints.
For deflection angle less than one degree, acquired ROW at Locations mentioned
no curve is required to be designed” by IE. There is only one location where
These locations are as below which radius is very sharp (60 m) and It is not
requires modifications and resubmission:- feasible to increase the curve length due
to ROW constraints and buildings. So
this requirement can be relaxed at these
few locations due to site constraints and
considering very mild radius. This is
relaxed in DPR alignment also.
The drawings are not satisfying as per 504470.1585, We agree that broken back Curves are Decision has to be We have provided AutoCAD file also
IRC:73 clause 9.1.7 “Curve in the same 506946.5555, not desirable and tried to avoid in the taken by Authority as to IE and it was discussed that
direction separated by short tangents, 513647.3675, whole stretch except few locations as the matter related to alignment cannot be modified further.
known as broken-back curves, should be 514270.6555 mentioned DPR Alignment is also ROW constraints.
avoided as far as possible in the interest showing broken back curve at these
of aesthetics and safety and replaced by a locations and land is also acquired like
single curve. If this is not feasible, a that. It is not feasible to avoid this and
tangent length corresponding to 10 convert it into single curve due to ROW
seconds travel time must at least be constraint in built up area.
ensured between the two curves”. These
locations are as below which requires
modifications and resubmission
Vertical Alignment
The drawings are not satisfying as per 504736.9904, Please note that probably Engineer is ok ok
IRC:SP:84 clause 2.9.5 “The safe 505900.25, checking as per case (i) given in IRC:73
stopping sight distance and desirable 508840.8277, 10.4.1.There are two equation’ given in
minimum sight distance for divided 511608 IRC code for calculation of length of
carriageway for various design speed are summit curve. locations mentioned in
given in Table 2.7. The desirable values letter( sn 2 to 5), equation (ii) is
of sight distances shall be adopted applicable i.e., L<S and we have
throughout unless specified in schedule. checked SSD / ISD at all location and
A minimum of safe stopping sight found all are ok as per IRC 73 .
distance shall be available throughout SSD / ISD is achieved at all locations.
these locations are as below which
requires modifications and resubmission.
Gradient
Gradient to be provided as per clause 504736 (a) Ruling gradient as per IRC:
2.9.4.2 of IRC:SP:99. SP: 99 is 2.5% and limiting
gradient is 3.0% for plain
terrain. We have adopted 3.0%
which is also permitted as per
IRC: SP: 99.
(b) Also, note that in DPR also
gradient of 3.3% is adopted. In
our case it is mild (3.0%).
(c) This cannot be changed as
minor bridge at chainage
504782 is to be retained.

Design FRL Vs CA FRL with OGL to be This is an elevated road project and not Design FRL to be (a) Nowhere in Schedule-B
provided as mentioned in 4.11 of a conventional highway project. maintained as per (clause-4.11), it is mentioned
schedule-B Nowhere in schedules/bid documents, it clause 4.11 of to maintain minimum FRL as
and same has to be maintained. is mentioned that DPR FRL is to be Schedule-B. per DPR P&P. In our case,
followed. FRL is designed on the basis this is an elevated road project
of 5.5 m clearance pier cap depth and and not a conventional
Structure depth. Our structural system is highway project.
different from DPR structural system. (b) Please note in comparison
So there is no point of comparing the table made by IE, for chainage
total height with DPR. So, we request 509000 to 510000, existing
you to kindly approve the P&P of levels in DPR seems to be
expressway ch 503200 to 515000. wrong. We can see from our
profile that there is a existing
flyover at site which is not
reflected in DPR levels/ P&P.
There is no point comparing
the total height with DPR.
(c) The girder system adopted in
the Detailed project report
(DPR) differs from the girder
system adopted by the
concessionaire. e.g in DPR
conventional I girder was
proposed in which 9 nos of
girder with depth of 2225mm,
whereas concessionaire has
adopted flanged to flange 21
nos of girder with depth of
1450mm.

Chainage Av. Diff. Av. Diff. Diff.


From To CA Design (Design
(FRL- (FRL- – CA)
GL) GL)
504+000 505+00 6.158 6.002 -0.156
0
506+000 507+00 10.188 9.012 -1.176
0
507+000 508+00 10.313 10.098 -0.215
0
509+000 510+00 9.511 7.040 -2.472
0
510+000 511+00 10.480 10.191 -0.289
0
511+000 512+00 11.515 11.028 -0.486
0

You might also like