You are on page 1of 13

Section 16

ELECTRICAL CONSTRUCTION CHECKOUT AND TESTING

GENERAL Certified and calibrated Measuring and Test


Equipment (or Instruments) are requirements to
Certain construction tests and checkouts are required satisfy ISO9000 (International Organization for
to be performed before the electrical portions of any Standardization) or NRC (Nuclear Regulatory
systems or equipment can be turned over for startup. Commission) requirements.
Adequate assurances have to be demonstrated that
construction is complete and the systems or Calibration of Measuring and Test Equipment
equipment are ready for startup and operation.
Only Measuring and Test Equipment (M&TE)
The amount and extent of construction testing varies utilized to perform electrical tests that are required to
from project to project. Each project will clearly be formally documented and/or verified need to be
define the area of responsibility of each organization initally “calibrated” by either offsite certified testing
involved in the construction, startup and operation of agencies or laboratories or by qualified on-site
systems or equipment. personnel utilizing approved national certification
testing standards and/or programs. M&TE used for
Each person involved in construction checkout and “informational readings or checks” need not be
testing is required to review and understand the calibrated. For the measuring and test equipment or
following procedures and activities. instruments that are calibrated they must:

• Safety Tagging Procedure - A clearance • Be calibrated to an established national testing


procedure designed to protect construction standard and/or by a calibrated testing device or
personnel. instrument.
• Be provided with certification documentation
• Turnover Procedures and Documentation - identifying test used. Manufacturer name,
Construction is usually responsible for turning make, model, and/or serial number. The
over completed systems to startup or operations. certification needs to contain test date and
The required flow of information and unique recertification test date (expiration date of
procedural requirements should be fully certification).
understood. • The M&TE needs to have a certification
“sticker” with date tested and expiration date
• Craft Personnel Organization - Lines of visibly attached to the instrument.
communication between the testing • The certification documentation must be
supervisors/engineers and crafts people should controlled, updated, (as recertifications or
be clearly understood as should craft work repairs are performed) maintained, and available
assignments and jurisdictions. for independent audit, review, inspection, or
compliance by inspecting agencies or
TEST EQUIPMENT individuals (e.g. QA - Quality Assurance
auditors).
The great diversity in electrical equipment and • Certified M&TE must be suitably controlled,
associated circuits requires a large variety of testing maintained, and recalibrated.
apparatus. Tests can be made easily and accurately
only with well maintained test equipment, so it is Damaged, lost, or M&TE failing re-calibration
essential all testing apparatus be used carefully and checks may require the issuance of non-conformance
kept in good condition. Test equipment found to be reports or reinspection of electrical components.
in improper condition or out of calibration must not The Field Engineer should be apprised of the
be used and shall be repaired and/or re-calibrated. requirements for their use on each project.

Rev. 0 Electrical Handbook 16-1


 Bechtel Corporation 1997. 11/26/97
Section 16
ELECTRICAL CONSTRUCTION CHECKOUT AND TESTING

Note: For nuclear plants the use and control of • Megger (Hand Crank or Battery Operated) -
M&TE is a federal requirement and is significantly Used to measure insulation condition of
more stringent than for most non-nuclear industrial conductors, motors, transformers, etc., when
facilities though for these facilities it is just as making a one-minute insulation test.
significantly important and should not be
discounted. • Digital Multimeter - Measures AC and DC
voltages, currents, and DC resistance’s.
Certification of M&TE Procedures
• High-Potential DC Tester - Used for proof-
Use of M&TE in nuclear facilities comprise testing the insulation of conductors, motors,
significantly more than just using electrical testing transformers, etc., by measuring leakage current
equipment. When work is performed in these as a function of voltage. The test is based on the
facilities a specific “procedural specification” will theory that the electrical stress in the insulation
address in more detail these requirements. Non- increases with the applied voltage.
nuclear facilities may also have a specific procedure
relative to use and control of M&TE. • “Hot Stick” - Voltage Probe used to indicate
high voltage on exposed bus-work and
Relative to M&TE measuring equipment requiring terminals.
calibration in industrial facilities they typically
include: • Ground/Earth Ground Resistance Tester -
Used to measure earth resistance’s for electrical
• Multimeters grounding systems.
• AC DC Clamp-on Ammeters
• Meggers • Motor Rotation Tester - Used to determine the
• Measuring or recording instruments (e.g. rotation direction of a motor before connecting
pressure guages, test guages, pyrometer) the motor to the electrical source.
• Torque Wrenches (inch or foot pounds)
• Hi-Pot • Inch Pound and Foot Pound Torque
Wrenches - Used for torquing bolts and screws.
Typical test equipment used or required to support Bus Bars, termination bolts/lugs, supports or
most industrial projects (either by construction craft hangers.
or by start-up personnel) are:
• Light Meter - used to measure lumination
• AC Clamp-On Ammeter - Used to measure AC levels.
current.
Specialty test equipment that may be required to
• DC Clamp-On Ammeter - Used to measure DC support a project or start-up work activities include:
current.
• Dew Point Detector - Used to determine the
• Megger (Motor Driven) - Used to measure the temperature at which water vapor condenses.
polarization index (P.I.), a measure of the Typically required when filling transformers
absorption effect of good insulation compared to with oil.
that of moist or contaminated insulation of cable
and equipment. The P.I. is a ratio of the ten • GFCI Tester - Determines the condition of
(10)-minute insulation resistance value divided ground fault current interrupters by measuring
by the one (1)-minute value. the amount of ground current required to trip
the interrupter.

Rev. 0 Electrical Handbook 16-2


 Bechtel Corporation 1997. 11/26/97
Section 16
ELECTRICAL CONSTRUCTION CHECKOUT AND TESTING

• Hydrometer - Used to check the specific gravity should be selected and connected to give deflections
of battery electrolyte to determine battery cell on the accurate part of the scale.
charge condition.
INSULATION TESTING
• Infrared Pyrometer - Senses infrared radiation
emitted from the small local area at which it is The standard tool for insulation testing is the
pointed and determines the area temperature. megohmmeter (megger). They are essentially a
Used for checking potential troublespots such as voltage/current generator with a built-in high range
loose electrical connections and failing bearings. resistance meter allowing megohms to be read
directly. The generator produces high DC voltage
• Cable Tracer - Impresses a signal on a cable to which causes a small current flow through and over
identify, locate, and trace a cable. the insulation surface. The resistance values are
then read on the display of the meter. What really
• Camera - Provides a permanent record of matters are trends in these readings over a period of
equipment condition. Equipment damage can time, and the location and importance of the
be photographed for future reference. A digital equipment being tested.
camera is recommend to facilitate transfer of
photographs electronically. There are three basic insulation test methods
employed to help diagnose problems.
• Metal Detector - Used to locate buried metallic
objects such as conduit, cable, and pipe. 1. Short-time or spot-reading tests.
2. Time-resistance (absorption) tests.
• Oscilloscope - Used to analyze power network 3. Step or multi-voltage tests.
waveforms and check electronic/solid-state
circuits. When conducting a Short-Time/Spot-Reading test,
the megohmmeter is connected to the insulation to
• Phase Sequence Tester - Checks the phase be tested and is operated for a short time (60 seconds
rotation or sequence of energized power circuits. is usually recommended). As the capacitance
“charges”, the resistance reading will increase and
• Psychrometer - Used to determine air humidity one reading is taken at a point on the curve of
when making insulation resistance tests. increasing resistance values. For example, 30
seconds is typically less than the 60 second reading
• Recording Meters/Data Loggers - Used for of a test operation. Temperature, humidity and
permanent records of voltage, current, power, insulation condition will affect readings when
temperature, etc., for analytical study. performing spot tests. If the apparatus being tested
has short wiring runs, this test is ideal. However,
• Tachometer - Determines the rpm of rotating most equipment being tested is capacitive so doing
machines. spot readings, without prior testing, can only be used
as a rough guide to insulation condition.
• Thermometer - Used to measure temperature
when making insulation resistance tests. A Time-Resistance test is typically independent of
the effects of temperature and can often give
conclusive information without the availability of
• Vibration Analyzer - Detects excessive
past test results. It is based on the absorption effect
vibration and locates imbalance on rotating
of good insulation compared to that of moist or
components.
contaminated insulation. Successive readings are
taken at specific times and the ratio between the
Accuracy of tests depends primarily on selection of
readings is noted. A 30 second versus 60 second test
proper test instruments. Instruments for each test

Rev. 0 Electrical Handbook 16-3


 Bechtel Corporation 1997. 11/26/97
Section 16
ELECTRICAL CONSTRUCTION CHECKOUT AND TESTING

will work, although a 1,2, 5 and 10 minute test gives Whether it be a single piece of apparatus or multiple
the best evaluation. It will take longer to charge the items comprising a system, there are definite
capacitance of good insulation, and values will procedures to follow before applying power. If new
continually increase due to absorption current. If the wiring in raceways or cable tray has been installed it
insulation contains moisture or contaminates, the should be checked thoroughly and tested for shorts
absorption effect is masked by high leakage current and grounds. Many times, cables and wires are
and the resulting values, over time, will remain damaged during installation. Damage may not show
fairly constant. Another benefit of this test is the up until load is applied or the cables approach
values obtained are independent of the size of the maximum current carrying capacity.
equipment. The increase in resistance for clean, dry
insulation occurs in the same manner whether a Megohmmeter testing of newly installed wiring is a
motor is large or small (very small equipment common practice. Usually a high voltage
without much insulation volume may reach megohmmeter is used which will provide a voltage
maximum very quickly, flattening the absorption potential somewhat higher than the voltage rating of
ratio, but not actually meaning there is a problem). the wire. Megohmmeter testing of medium and high
voltage cables, however, is not considered a
Step-Voltage tests require the use of multi-voltage satisfactory method of determining whether cable
megohmmeter allowing the application of two or insulation has been damaged. A high voltage
more voltages in steps, like 250, 500 and 1000 volts. megohmmeter will only revel severely damaged
It is only necessary to keep the test voltage constant insulation which will probably fail as soon as full
between steps for about 60 seconds. The short voltage is applied.
period between steps will not affect resistance trends,
however, the time period between steps should be the Wire/cable pulling is involved when installing power
same for a given piece of equipment. Reductions of cables in raceways and cable tray. If, it is an
insulation resistance is looked for as each voltage extended run and several conductors are pulled at the
increase is made. If the readings become lower it is same time, considerable force is required. This not
a sign of an insulation weakness. Although other only stresses insulation, it could crack protective
test step ratios can be used, applied voltages should outer layers and result in cuts or tears through
preferably be in the ration of 1 to 5 or greater. It has several layers of insulation if there are burrs or sharp
been determined that a change of 25 percent in the edges in the raceway. Conductors in multiple
insulation resistance value, at a 1:5 voltage ratio, is conductor cables can break or be reduced in cross
usually due to the presence of excessive moisture or sectional area by too much pull. This effectively
other contaminates. reduces the current carrying capacity of the cable,
could produce internal arcing between ends of
The benefit of the Step-Voltage test is effects of broken strands and other progressive deterioration
aging or mechanical damage in clean, dry insulation conditions. These could cause failures months or
may not be revealed at lower stress. Applying years after the cables are installed.
voltage in increase steps produces electrical stresses
that simulate or exceed those found in actual service. Newly installed cables should be subjected to a
Local weak spots then begin to influence overall nondestructive test at higher than normal use values.
resistance, and resistance values begin to drop as The test is generally performed using DC high
electrical stress increases. Even though the voltage cable testing equipment. The advantage in
megohmmeter’s highest voltage does not stress the pretesting cables is that any damaged cable can be
insulation beyond its rating, multi-voltage test will repaired/replaced without a service interruption. A
often reveal problems. cable failure in a raceway with several cables can be
disastrous. Frequently all cables have to replaced
POWER AND DISTRIBUTION CABLE TESTING because of arc damage from the one which failed.

Rev. 0 Electrical Handbook 16-4


 Bechtel Corporation 1997. 11/26/97
Section 16
ELECTRICAL CONSTRUCTION CHECKOUT AND TESTING

Cable testing provides assurance that the cables were


not damaged during installation. If there is any Recommended DC Dielectric Test Voltages for
indication cables have been damaged during New Installations
shipment, or confidence in the cable manufacturer so
dictates, cables should be tested upon jobsite receipt
to provide assurance cables are suitable for XHHW
installation. RHH THHN
SIZE RHW USE THWN
“Megger” Insulation Resistance Test
14 4800 ---- 3200
Low-voltage non-shielded cables can be tested using 12 4800 4800 3200
a megger. Hand held ohmmeters generally have 10 4800 4800 3200
outputs from several volts to 24 volts. They are 8-2 4800 5600 3200
excellent for detecting direct “shorts” such as bolted 1-4/0 6400 6400 4000
faults and low resistance measurements in the 250-500 8000 8000 4800
kilohm range. A megger measures resistance in the 550-1000 9600 9600 5600
megohm range using higher voltages than an 1100-2000 11200 11200 6400
ohmmeter. Manual, battery operated or motor-
driven meggers are available for a range of fixed DC
voltages. Typical fixed DC voltages are 500, 1000,
2500, and 5000 volts. Recommended AC Dielectric Test Voltages for
New Installations
Applied DC potential may be 500 or 1000 volts DC
with the insulation resistance reading taken at one
(1) minute. A megohmmeter reading of less than 50 XHHW
megohms may be used for deciding when to RHH THHN
investigate the cable installation, and readings less SIZE RHW USE THWN
than two (2) megohms will most likely indicate
damaged insulation. Readings of two (2) to 50 14 2400 ---- 1600
megohms are usually associated with long circuit 12 2400 2400 1600
lengths, moisture, or contamination. In most cases a 10 2400 2400 1600
two (2) to 50 megohm reading does not indicated the 8-2 2800 2800 1600
insulation quality, therefore two (2) to 50 megohms 1-4/0 3200 3200 2000
should not be specified as a pass/fail value. 250-500 4000 4000 2400
Insulation resistance readings should be made and 550-1000 4800 4800 2800
interpreted by experienced personnel to determine 1100-2000 5600 5600 3200
the condition of the cable’s insulation.
Alternating current new installation test voltages are
“Hi-Pot” - High Voltage Potential Test 80% of the factory test voltage. Direct current
voltages are two times the alternating current new
High potential tests are “go no-go” tests. The cable installation test voltage. Test duration should not
is required to withstand the specified voltage for the exceed five (5) minutes.
specified time duration. These tests will normally
reveal gross imperfections due to improper field For medium voltage, shielded cables.
handling, such as excessive bending or air gaps With any High Voltage Direct Current (HVDC)
between the insulation and shield interfaces. testing it is highly recommended that IEEE Standard
400 be understood and that there is concurrence of
For low voltage, non-shielded cables.

Rev. 0 Electrical Handbook 16-5


 Bechtel Corporation 1997. 11/26/97
Section 16
ELECTRICAL CONSTRUCTION CHECKOUT AND TESTING

the manufacturers of the cables, terminals and For more sophisticated evaluations, it is important to
splices prior to the performance of any proposed recognize the components of DC “leakage” current.
testing. IEEE Standard 400 tests are “go no-go” The output current of the test set into the cable is not
tests. The system is required to withstand the the true leakage current. The output current is the
specified voltage for the specified time duration. sum of three currents; geometric capacitance,
absorption, and true leakage current. The absolute
value of output current is not of primary importance.
This value is virtually impossible to predict and is
Field Test Voltages for Shielded Power Cable dependent upon the previously mentioned factors
Systems 5 kV to 35 kV which can affect the resultant output current from a
few microamperes to hundreds of microamperes.

System System Acceptance Maintenance It is the shape of the total current curve (it) with
Voltage BIL Test Voltage Test Voltage respect to time that indicates the condition of the
(kV rms) (kV) (kV dc) (kV dc) dielectric. A drop-off of current with respect to time
∅ to ∅ ) (crest)
(∅ (cond-gnd) (cond-gnd) is an indication of sound insulation. A rising current
is and indication of questionable condition or
5 75 28 23 pending failure. A flat curve is generally due to test
8 95 36 29 conditions.
15 110 56 46
25 150 75 61 The output current variation with respect to time of
28 170 85 68 voltage application is generally considered more
35 200 100 75 indicative than the absolute value. The
characteristic shapes of the time-leakage current
curve and probable causes are outlined below.
Acceptance test voltage duration is normally 15
minutes. • A rising leakage curve at a steady voltage may
be indicative of faulty insulation. However,
Maintenance test voltage duration is normally not other leakage paths (over porcelain surfaces and
less than five (5) minutes or more than 15 minutes. through insulating fluids) can contribute to such
a result.
Cable insulation can, without damage, sustain
application of DC potential equal to the system basic • A falling leakage curve is indicative of good
impulse insulation level for very long periods. In insulation characteristics, especially if at similar
contrast, most cable insulation will sustain levels for all phases.
degradation from AC overpotential, proportional to a
high power of overvoltage to time (and frequency) of • A flat leakage curve at low value is generally
the application. Hence it is desirable to utilize direct indicative of acceptable insulation. Flatness
current for any testing that will be repetitive. While may be influenced by circuit length, cable
manufacturers use alternating current for the geometry, and possible presence of moisture or
original factory test, it is almost universal practice to contaminants over terminal surfaces.
employ direct current for any subsequent testing.
• A flat leakage curve at high value may indicate
any of the following conditions
1. Presence of moisture
Time-Leakage Test 2. Contaminants over terminal surfaces or
other creepage surfaces

Rev. 0 Electrical Handbook 16-6


 Bechtel Corporation 1997. 11/26/97
Section 16
ELECTRICAL CONSTRUCTION CHECKOUT AND TESTING

3. Surface leakage greater than volume Fall of Potential Method


leakage
4. Moist laminated insulation This involves the passing of alternating current in
5. Condition of insulating fluids known magnitude throughout the grounding
6. Air Ionization losses (corona) from electrode (or grounding network/grid) under test and
projections. an auxiliary current electrode, and measuring the
influence of this current in terms of voltage between
• Dissimilar leakage curves are indicative of the electrode under test and a second auxiliary
nonuniformity or circuit insulation. The potential electrode.
characteristics curve of each phase should be
analyzed to determine the cause of dissimilarity.
Air ionization losses from projections may affect
one phase more than the others, dependent upon
corona shielding (such as terminals),
temperature and humidity transients, air
movement, and the like.

Generally speaking, the increase of current with test


voltage is approximately linear for sound insulation.
Care should be exercised to prevent terminal corona
and minimize terminal surface leakage as these can
mask test results.

GROUND RESISTANCE TESTING

This section discusses commonly used methods of


measuring ground resistance. The ohmic value
measured is called resistance; however, there is a
reactive component that should be taken into account
when the ohmic value of ground under test is less
than 0.5 ohms, as in the case of large substation
grids. This reactive component has little effect on
grounds with an impedance higher than one (1)
ohm.

Ground resistance can be measured by commercially For a large grounding network, both current and
available, self-contained instruments, which give potential electrodes should be placed as far from the
readings directly in ohms. These instruments are grounding network under test as practical
small in size and very easy to use because they (depending on the geography of the surroundings),
require no external power source. It is recommended so that they are outside the influence of the ground to
the test instrument manufacturers’ instructions be be tested. A distance of 750 to 1000 feet or more
followed when setting up the test equipment and from the grounding network is recommended for
taking measurements. grounding mats with dimensions in the order of 300
feet x 300 feet. This is required to obtain
The four most commonly used methods of measurements of adequate accuracy. The potential
testing/measuring ground resistance are: electrode, for large grounding networks (low-
resistance grounds), should be driven in at a number

Rev. 0 Electrical Handbook 16-7


 Bechtel Corporation 1997. 11/26/97
Section 16
ELECTRICAL CONSTRUCTION CHECKOUT AND TESTING

of points. Resistance readings are then plotted for


each point as a function of distance from the
grounding network, and a curve is drawn. The value
in ohms at which the plotted curve appears to level
off is taken as the resistance of the grounding
network under test. When it is found that the curve
is not leveling off, the current electrode should be
moved farther from the grounding electrode under
test. However, for a high-resistance ground, there is
no preferred placement of electrodes, and the most
practical placement of electrodes should be chosen.

The resistance between the ground network Two-Point Method


(electrode) under test and the auxiliary electrodes
should be measured. The resistance measured The two-point method is usually used to determine
should be no more than 500 ohms for increased the resistance of a single grounding rod where it is
accuracy in the measurement of low-resistance necessary to know only that a given grounding
ground network. In order to obtain the lowest electrode’s resistance to earth is below a stipulated
possible auxiliary electrode resistance, locate the value. In this method the total resistance of the
electrodes in moist locations, such as drainage unknown and an auxiliary grounding rod, usually an
ditches or ponds, or drive two or more rods spaced existing know object which is well grounded
three (3) or four (4) feet apart, or where practicable, (metallic water pipe with no insulating joints), is
use long rods driven to considerable depths. measured. Since the auxiliary ground resistance is
considered negligible, the resistance measured by the
After checking the auxiliary electrodes’ resistance, meter will be that of the grounding electrode under
connect test probes to the instrument. Reverse test.
connections at the instrument and take another
reading. The difference in both readings should be This method is subject to large errors for low-
less than 15%, otherwise auxiliary electrodes should resistance grounding networks but is very useful and
be moved farther away from the ground network adequate where a “go no-go” type of test is required.
(electrode) under test.

This method should be used for large substations, ELECTRICAL TESTING OF INSULATION OF
industrial plants, and generating stations where ROTATING APPARATUS
grounding network resistance is usually less than one
(1) ohm. For a small ground mat or single-rod- Electrical tests should discover existing weaknesses
driven electrode, the influence of the ground to be or faults in the insulation system and give some
tested is assumed to be negligible at about 100 to 125 indication of the expected service life expectancy and
feet, so the current electrode can be placed at about reliability.
that distance from the ground rod under test. To
measure earth resistance of a single-rod-driven
electrode or small ground mat, the potential WARNING
electrode can be placed midway between the current
electrode and the ground electrode under test. Do not make electrical insulation tests on motors
or generators unless they have been electrically
Readings with the circuit connected as per the isolated and will remain so during the test.
accompanying illustration are taken. Failure to do so before testing begins can result in

Rev. 0 Electrical Handbook 16-8


 Bechtel Corporation 1997. 11/26/97
Section 16
ELECTRICAL CONSTRUCTION CHECKOUT AND TESTING

serious injury or death by electric shock, and energized system, the difference between the total
damage to equipment. leakage and the constant steady state value
(conduction component) is due to a phenomenon
called dielectric absorption.
The following tests and testing principles should be
considered in planning diagnostic tests: Dielectric absorption tests, as described in IEEE No.
43, are more significant than one-minute insulation
Insulation Tests at Low Voltage resistance tests, (particularly on higher voltage
windings) because the slope of the time-resistance
The simplest and most easily made insulation characteristic gives further information about the
resistance test is the megohmmeter measurement. condition of the insulation with respect to moisture
This is a low voltage, direct current measurement of and contamination. This slope is expressed as the
leakage relative to surface contamination and ratio of ten to one-minute insulation resistance and is
moisture content of the insulation. It is important to called the polarization index. The ratio which is
understand the limitations of these tests. non-dimensional, aids in making comparisons
between insulations of machines of different size. It
• Megohmmeter tests will not usually reveal also allows comparison on measurements on the
complete but clean, dry ruptures in the ground same machine taken at different times.
wall insulation.
Dielectric absorption measurements can be made at
• When applied to high voltage insulating voltages as low as 500 volts, but higher voltages are
systems, megohmmeter tests do not offer any recommended, particularly on high voltage stator
proof of the physical integrity of insulation or its windings.
ability to withstand high voltage tests or even
service potential. A polarization index of 2.0 or more is normal for
asphalt , bitumen, and varnish impregnated
• Megohmmeter measurements are commonly windings. Modern impregnated insulation systems
made to determine insulation condition with will produce higher index values. This index applies
regard to contamination before overvoltage tests only to a stator winding and could be considerably
are made. When testing a stator winding, it is different if the measurements were made with parts
preferable to test one phase at a time, to ground external to the windings such as leads, cables, or
with the other two phases grounded as this protective equipment included in the test circuit.
procedure allows a comparison between phases
and also tests the insulation between phases and A polarization index of less than 1.0 indicates time-
between phase and ground. dependent leakage. The causes should be
investigated and corrected before the machine is
Dielectric Absorption Testing either tested or placed in service.

Dielectric absorption tests are a measurement of Over-Potential Tests


insulation resistance against time. The time period
will usually be until resistance stabilizes, or as much Low voltage insulation resistance and dielectric
as ten minutes. absorption test do not produce electrical stresses of
sufficient magnitude to expose faults which might
Insulation leakage is not constant. It starts at a lead to in-service failure. Power factor (or tangent
relatively high value and decreases until it reaches a delta) measurements which are an effective tool used
stable value. This stable value is called the by the manufacturer in insulation development and
conduction component, and is established by the quality control, are not effective in assessing either
direct current resistivity of the material. On an the condition of insulation or suitability for

Rev. 0 Electrical Handbook 16-9


 Bechtel Corporation 1997. 11/26/97
Section 16
ELECTRICAL CONSTRUCTION CHECKOUT AND TESTING

continued operation. Electric strength has been failures. There are many methods of drying out
demonstrated to be the most effective criterion for transformer insulation in the field; all of them
determining the condition of an insulation system require considerable equipment and one to four
which has been subjected to long use and aging weeks of drying time, depending on the size of
conditions. transformer and the degree of wetness. Consult the
manufacturer for directions if a transformer requires
Over-potential testing requires experience testing drying before energization.
personnel and should only be performed by a
manufacturers’ representative, personnel from a Oil Tests
motor repair organization or by a electric testing
organization. Test all oil in each shipping container (drums, tank
truck, or railroad car). The dielectric strength,
power factor, water content, interfacial tension and
TRANSFORMER TESTING neutralization number should be determined. If tests
cannot be made at site, certified test reports from the
The following tests should be made before a supplier should be available for tests made on
transformer is energized. The results of these tests samples taken from each shipping container,
should become part of the permanent record of the showing that the oil meets specifications.
transformer. They will allow for comparison with
future maintenance test comparison checks. It is recommended that the dielectric strength of oil
from each container be checked in the field prior to
It is best practice to have the transformer tests done installation to assure the oil has not been
by a manufacturers’ representative, who are fully contaminated in transit.
knowledgeable of the equipment being tested and the
proper testing techniques and procedures. Most of the desirable properties of insulating oil are
affected by impurities, particularly water. It is
Insulation-Resistance Test important to avoid contamination when obtaining
samples. All equipment used in taking samples
A megohmmeter insulation-resistance test, made in should be clean and dry. Sample containers should
the field and compared with measurements made at be amber glass bottles of at least 16 fluid ounce
the factory will indicate if a transformer is capacity. The bottles should be cleaned with a
sufficiently dry to energize. Insulation-resistance suitable solvent and dried. No rubber gaskets or
measurements are made on each winding with all stoppers should be used because the rubber will
other windings grounded. No windings with dissolve and contaminate the sample.
external bushings should be left floating during the
insulation-resistance measurements. Normally- A sample thief which permits taking the sample
grounded windings must have the ground removed from the bottom should be used when taking samples
to measure insulation-resistance to the other from drums. The thief should be cleaned with an
grounded windings. If it is not practical to remove appropriate solvent and dried before each use.
the ground, as in the case of solidly grounded Samples from each drum should be tested for
neutrals, the insulation resistance of the winding dielectric breakdown strength. Where large numbers
cannot be measured; treat it as part of the grounded of drums are to be tested for a single transformer it is
circuit. permissible to mix samples from as many as five
drums and test the composite. If the breakdown
If field measurements of insulation resistance values meet the 30 kV minimum all the drums
indicate a wet transformer, dry it out before represented in the composite may be used. If the
energizing. Moisture is the greatest enemy of breakdown value of the composite does not meet the
insulation and the cause of many transformer

Rev. 0 Electrical Handbook 16-10


 Bechtel Corporation 1997. 11/26/97
Section 16
ELECTRICAL CONSTRUCTION CHECKOUT AND TESTING

30 kV minimum, each drum must be tested to find 1/1000 inch). Factory tests are made using accurate
the offending oil. instruments, with the motor resting on a resilient
support. Large motors are bolted to the test floor
For sampling from a tank car, truck or large tank, a bedplate.
thief employing a bottom valve may be used. The
thief should be solvent cleaned and thoroughly dried Factory balancing is precise, a half-key is used to
before each use. compensate for the unbalance of the shaft extension
keyway if the motor is shipped without half of the
When taking an oil sample from electrical coupling mounted. Balancing checks are always
equipment it should be drawn from the sampling made after the coupling installation at the factory.
valve at the bottom of the tank. Two or three quarts The coupling, as delivered by the supplier, is seldom
of oil should be drawn off and disposed of before the precision balanced. Motor manufacturers must
sample is taken to assure the sample is representative compensate for the added coupling weight. An
of the whole. Disposal of oil shall be in accordance unbalanced condition places excess strain on
with environmental requirements. bearings and if allowed to progress can result in very
bad machine performance.
The dielectric breakdown test measures the stress
which an insulating liquid can withstand without Excessive vibration, if not transmitted from some
failing. The measurement is made by applying a other source, is always a symptom of something
voltage between two electrodes immersed in the wrong. Some driven apparatus is designed to vibrate
liquid, and under prescribed conditions. This test violently; stokers, screen separators, ball-mills, rock
also serves as an indication of the presence of crushers, etc. transmit vibrations to the driving
contaminants, particularly moisture and conducting motor. Many of these are belted applications and the
particulate. Dielectric testing is performed as vibrations are damped by the belt drive, but some are
described in ASTM Procedures. ASTM D-877 direct drive. In these situations greater attention
specifies a test cup equipped with one inch diameter must be directed at assuring that vibration does not
vertical disc electrodes spaced 0.100 inch apart be damage the driving motor. Motors react to
used. conditions of vibration even when not directly
coupled to the apparatus producing the vibration.
ASTM D-1816 specifies a test cup equipped with a
spherical electrodes spaced 0.04 inch or 0.08 inch Effects of Vibration
apart. This cup includes a stirrer and is sensitive to
small amounts of contaminants. It is primarily Excessive vibration is a serious condition requiring
suitable for use with new oils. A portable dielectric immediate correction. There are many negative
strength tester may be used and tests can be made in effects of vibrations, direct and indirect:
the field.
• It imposes unnecessary forces and stresses on
The dielectric strength of the oil must be at least 30 equipment. Standard motors are not designed or
kV. warranted for use where there is excessive
vibration.
VIBRATION TESTING
• The effect on foundations can be so severe as to
Vibration is readily detectable, even without cause them to shift and cause misalignment.
instruments. A simple vibration check is to stand a Concrete can be deteriorated by the powdering
coin on edge on a running machine. On a well of the bonding materials. Weight combined
balanced machine the coin will not fall over. New with torsional forces can cause foundations to
motors, depending on type and speed, will have been shift, producing cracks and changes in
balanced to operate within 0.5 to 2.5 mils (one mil = elevation. These are conditions that may remain

Rev. 0 Electrical Handbook 16-11


 Bechtel Corporation 1997. 11/26/97
Section 16
ELECTRICAL CONSTRUCTION CHECKOUT AND TESTING

hidden until cracks appear and misalignment accelerated and decelerated through their known
occurs. critical speed as rapidly as possible. Prolonged
operation at critical speed can damage a machine by
• Vibration frequently creates objectionable noise. breaking a shaft and destroying bearings, and other
components.
• When several units of rotating equipment are
operating simultaneously they produce a variety The techniques of measurement have advanced from
of vibration frequencies. Since drive motors and simple vibrometers requiring much analysis of their
coupled equipment constitute a system, there are output, through oscillographic and light beam
many variable frequencies which can combine to devices, to today’s electronic measuring equipment.
set up vibrations no inherent in the operation of Some high speed apparatus is manufactured with
any of the machines. built-in sensors which are connected to recording
devices to monitor vibration.
• Ambient noise and physical vibration often
result from cyclic variations in the vibratory Most vibration measurements are obtained by using
forces in a resonant system. portable electronic equipment. Electronic pick-ups,
hand-held probes or proximity sensors are used to
Vibration Analysis Checks feed electrical signals into the analyzer. The
electrical impulses produced by even minute
Vibration is an oscillating motion. One of the amounts of vibration are amplified and read directly
factors needed to evaluate the extent of motion is the from meters on the vibration analyzer. Use of
distance traveled, or the excursions occurring at each modern equipment results in accurate measurement
cycle. The amplitude of motion is usually expressed of amplitudes, indicates phase angles of
in mils peak-to-peak. A one mil excursion in one displacement, and, if an oscilloscope is used, visually
direction is actually two mils peak-to-peak display the wave form. An experienced person with
amplitude. proper instruments can very quickly locate the source
of vibration without resorting to complex
Frequency is the rate at which oscillations occur. mathematical calculations.
The unit of measurement is cycles per second (cps)
or cycles per minute (cpm). Frequency does not While this basic procedure is easily learned, there is
always indicate true revolutions per minute, it can a real skill involved in correcting vibration. The
contain a number of harmonics. field engineer will be responsible for taking readings
and helping to determine the source of vibrations.
Velocity and acceleration are two other vibration Manufacturers’ representatives and vibration experts
parameters that may enter into calculations to will be required to correct the vibrations.
accurately evaluate the effect of vibration. A
vibrating body or a rotating mass, such as a motor, ELECTRICAL EQUIPMENT TESTING
moves with a given amplitude and frequency. The
speed at which it moves (velocity) is expressed in Electrical equipment is furnished with Instruction
inches per second (ips) and is directly related to Manuals which provide instructions on what and
displacement. Any change in velocity affects how to test prior to energization of the equipment.
vibration. These tests are safety related to determine no short
circuits or ground faults exist in the equipment.
Acceleration of deceleration of massive rotors in
turbines and large motors accompanied is always Components of electrical equipment is tested
accompanied by some vibration. At critical speeds individually and collectively at the factory prior to
oscillations can cause flexing and bending of the shipment. Further testing is not required in the field
supporting shaft. For this reason machines are unless there are signs of shipping damage.

Rev. 0 Electrical Handbook 16-12


 Bechtel Corporation 1997. 11/26/97
Section 16
ELECTRICAL CONSTRUCTION CHECKOUT AND TESTING

Any testing required beyond those required by the


inspection manual should be done by the
manufacturer’s representative.

Rev. 0 Electrical Handbook 16-13


 Bechtel Corporation 1997. 11/26/97

You might also like