You are on page 1of 6

ZXDU88 S402 (V5.

0R01M01)
Quick Installation & Commissioning Guide
Document number/version:
DC Power System SJ-20110329120423-001/ 2011-06-28 R1.1 /6

Precautions Installing Fixing Plates Between Racks Installing Busbars Between Racks
Remove watches, hand chains, rings or other conductive objects before the operation. Wear
special gloves for protection.
Never install the equipment where there is a risk of liquid or objects falling onto the top of the Install two fixing plates between two adjacent racks.
equipment! Otherwise, short circuit may occur and damage the equipment! To prevent The table below lists the busbars between racks.
equipment damages, no heavy objects should be placed on the top of the cabinet.
(1) Batteries used in the equipment should be of the same type. Old and new batteries must
Busbar Description
not be used together. (2) Battery packs should not be short circuited in any way during the
operation.
Use insulated tools for electrical connection. Full insulate connection terminals and 整流柜(RECR) Negative busbar between RECRs
unnecessarily exposed metal parts.
(1) The cross-sectional area of cables should match the load. (2) When using cables in non-
standard colors, choose those in black and mark them with heat-shrinkable tubes or 整流柜(RECR) Positive busbar between RECRs
insulating tapes in the corresponding colors to avoid confusion. If the local regulations have
different requirements for the cable colors, follow the local regulations.
+

整流柜 直流柜
Negative busbar between RECR and DCDR
ZXDP12 D252 ZXDU88 S402 ZXDP03 T601 RECR DCDR
(DCDR) (RECR) (ACDR)

Installing the Racks 直流柜 Positive busbar between RECR and DCDR
DCDR + 整流柜
RECR

1. Prepare four M12×100 expansion


bolts for each cabinet. Negative busbar between DCDRs
直流柜(DCDR)
2. Drill the holes (70 mm deep) with the
same dimensions as the cabinet holes at
the bottom.
Positive busbar between DCDRs
3. Install the M12×100 expansion bolts 直流柜(DCDR)
into the holes (leave 30 mm of the bolt +
above the ground).
4. Remove the feet of the ZXDP12 D252
DCDR.
5. Mount the cabinet on the floor and The procedures to connect the busbars between two adjacent racks are
into the expansion bolts. similar. The following section takes the procedure to connect the
busbars between DCDR and RECR as an example.
6. Insert metal plates at the bottom to
limit the vertical inclination of the cabinet
to 5°. Result:
Operation steps:
7. Fasten the four bolts to fix the DCDR The image below shows the two adjacent cabinets with the busbars installed.
in position. 1. Install the positive busbar (+) between DCDR and RECR.
8. Repeat the step 4 through 7 to install 2. Install the negative busbar (-) between DCDR and RECR.
the ZXDU88 S402 RECR and the ZXDP03
Nut T601 ACDR.
Spring washer
Flat washer
Unit: mm
+ +
Installed expansion bolt

ZXDP12 D252 ZXDU88 S402 ZXDP03 T601


418

(DCDR) (RECR) (ACDR)


_ _
Installation Installation Installation
hole hole hole
676 124 476 124 676 ZXDP12 D252 ZXDU88 S402
(DCDR) (RECR)
Cabinet front Cabinet front Cabinet front ZXDP12 D252 ZXDU88 S402
Space Requirement for the (DCDR) (RECR)
Cabinet Placement
L1

Back Front Dampproof Sunproof No stacking 直流柜 整流柜


ZXDU L4
DCDR RECR ACDR DCDR+ RECR
(Front) (Front) (Front) L4
L2 L3 DCDR
(Side) RECR
Dimensions (H × W × D): 直流柜 整流柜
ACDR: 2000 mm × 800 mm × 600 mm DCDR RECR
DCDR: 2000 mm × 800 mm × 600 mm
Top space (L1) ≥ 100 mm RECR: 2000 mm × 600 mm × 600 mm
Back space (L2) ≥ 1000 mm
Front space (L3) ≥ 1000 mm
Side space (L4) ≥ 100 mm

ZTE Corporation Address: No. 55, Hi-tech Road South, Shenzhen, P.R.China Area code:518057 Website: http://ensupport.zte.com.cn Email:800@zte.com.cn
ZXDU88 S402 (V5.0R01M01)
DC Power System Quick Installation & Commissioning Guide http://www.zte.com.cn /6
Preparations Before Electrical Connections
The equipment has high leakage current, thus it must be properly grounded before
power-on. Its grounding cable should be connected to the nearest grounding terminal, Connecting DC Input Cables to
and the cable length cannot be greater than 30 m.
Unplugging the CSU and Rectifiers No operation with power-on! Turn off all the breakers & switches and remove all ZXDP03 T601 Cabinet
the DC output fuses and battery fuses before connecting cables.
The ACMU needs DC power from ZXDP12 D252 (DCDR).
To avoid damages that might be caused to the Centralized Supervision Unit (CSU) and The live (L) and neutral (N) cables cannot be connected reversely! The positive and
rectifiers by operation errors during the electrical connections, unplug the already negative cables cannot be connected reversely!
installed CSU and rectifiers 50 mm out of the RECR to cut off the electrical connection of
these modules with the system.
Connecting Grounding Cables
Unplugging the Rectifiers Slots Configuration
(hot-pluggable) _ +
Connect the grounding cables to the nearest
CSU
Communication grounding point. The PE cable length cannot ZXDP12 D252 ZXDP03 T601
box exceed 30 m. The grounding cable should be (DCDR) (ACDR)
1 PE busbar Working ground laid as short and straight as possible. Front View
busbar Back View
2
Handle
3 1. Connect a grounding cable between ACDR Color code
DC output (+):Black
ground busbar and DCDR grounding bolt. DC output (-): Blue
_ +
2. Connect a grounding cable between ACDR
ground busbar and RECR grounding bolt.
Screw
20 ZXDP03 T601 ZXDU88 ZXDP12 D252 3. Connect a grounding cable between ACDR
(ACDR) (RECR) (DCDR) ground busbar and grounding busbar of 1. Connect a cable between the negative terminal of DC output (DCDR) and negative
Back View Back View Back View the installation site. terminal of DC input (ACDR).
4. Connect the working ground cable 2. Connect a cable between the positive terminal of DC output (DCDR) and positive
Operation Steps: between DCDR and the grounding terminal of DC input (ACDR).
PE PE busbar of the installation site.
1. Remove the screws from the
Switch
flanges. Color code
PE: Yellow green
Connecting AC Input Cables to
Handle 2. Hold the handles and slowly pull the
rectifier out until it cannot be pulled out
further.
GND: Black
ZXDU88 S402 RECR
Protection ground busbar of the
3. Push the switch upwards to unlock it. installation site

4. Hold the handles and pull the Do not reverse the live wires and neutral
rectifier 50 mm out of the RECR slowly. wire.
Connecting AC Input Cables to Make sure that the AC input power is cut
off during the operation to connect the AC
Unplugging the CSU ZXDP03 T601 Cabinet PE busbar input cables.
AC input 1

(hot-pluggable) L1
PE L3 L2
L2 Do not reverse the live wires and L1
Operation Steps: L3
neutral wire. ZXDU88 S402
1. Press the lock of the Communication box. Make sure that the AC input power is
(RECR)
cut off during the operation to Back View
2. Open the Communication box.
connect the AC input cables.
3. Remove the four screws from the flanges
AC input 2

L3
on both sides of the CSU. L2 AC input 1
4. Carefully pull the CSU 50 mm out of the L1
L3 L2 L1 ZXDP03 T601 Color code
RECR. (ACDR) L1: Yellow
Back View L2: Green
N
L3: Red
PE: Yellow green
Color code
Neutral busbar L1: Yellow
L2: Green 1. Select a 250 A breaker in the front of the ACDR to power
ZXDP03 T601 ZXDU88 S402 ZXDP12 D252 L3: Red the RECR.
(ACDR) (RECR) (DCDR)
2. Turn off the corresponding AC output breaker of the
N: Blue
Back View Back View Back View
ACDR.
L3 L2 L1 3. Remove the top cover of the RECR.
AC input 2
4. Connect the PE cable between the PE busbar of the ACDR
1. Turn off the AC input breaker of the AC distribution box that powers ZXDP03 T601 and the PE terminal of the RECR.
ZXDP03 T601
(ACDR). (ACDR) 5. Connect the AC input live wires (L1/L2/L3) between the
2. Turn off the AC input switch of ZXDP03 T601. Front View breaker of the ACDR and the live connection terminals of
3. Remove the protection plate at the back of ZXDP03 T601 to show the AC input the RECR.
connection terminals.
Cabinet MCCB/Terminals
4. Connect the neutral wire (N) of the AC input 1 to the neutral busbar of ZXDP03 T601.
ZXDP03 T601 3P MCCBs: 100 A - 250 A 250A/3P MCCBs are used
5. Connect the live wires (L1/L2/L3) of the AC input 1 to the connection terminals of (ACDR) 1P MCBs: 16 A - 32 A to power RECRs
ZXDP03 T601.
ZXDU88 S402 1*UIK35 terminal (PE)
6. Repeat step 4 and 5 to connect the neutral wire and the live wires of the AC input 2. -
(RECR) 3*M8 bolts (L1/L2/L3)

ZTE Corporation Address: No. 55, Hi-tech Road South, Shenzhen, P.R.China Area code:518057 Website: http://ensupport.zte.com.cn Email:800@zte.com.cn
ZXDU88 S402 (V5.0R01M01)
DC Power System Quick Installation & Commissioning Guide http://www.zte.com.cn /6

Connecting Battery Temperature Connecting Output Relay Cables


Connecting DC Output Cables
Cables
-48V Load The load current MUST NOT exceed the capacity
2 3 The ZXDU88 S402 RECR provides eight output relays. User can connect
1
_ of the breakers to avoid tripping of breakers and the output relay cables at the front or back.
+ shutdown of loads.
Connection at the Back
Tighten any loose detection cable after DC
Relay sampling cables
ZXDP12 D252 output cable connection.
(DCDR)
Front View
Remove the corresponding fuse before connecting

A1

A3

A5

A7
A2

A4

A6

A8
Remove the paper Paste the sensor to
Working ground cover of the sensor
busbar
the cable. the side of a battery

Color code Clean surface where to paste the sensor


DC output (+):Black and make sure that the battery temperature
ZXDP12 D252 DC output (-): Blue sensor and cable are properly installed.
(DCDR)
Back View 1. Turn off the loads.
Connect cable to the BACK
2. Remove the DC output fuses. Paste the sensor between battery temperature port
adjacent battery cells
3. Connect the positive cable of a load to the Battery Temperature (female)
working ground busbar (+/GND). Temperature sensor
4. Connect the negative cable of a load to one of

R2COM

R1COM

R4COM

R3COM

R6COM

R5COM

R8COM

R7COM
the fuses.

R2NO

R1NO
R2NC

R1NC

R4NO

R3NO

R6NO

R5NO

R8NO

R7NO
R4NC

R3NC

R6NC

R5NC

R8NC

R7NC
5. Label with the load name and polarity.

B_T1 1
6
+12V1 2
B_T3 7
3
+12V1 8
B_T2 4
9
+12V1 5
NO: Normally Open

6
5
4
3
2
1

6
5
4
3
2
1

6
5
4
3
2
1

6
5
4
3
2
1
Battery cell Battery cell NC: Normally Closed
Classification Fuse DC Voltage Remark
16*400A X8 X9 X10 X11
Larger capacity -48V The DC output configuration can be changed Output relay Output relay Output relay Output relay
250 A - 630 A
according to the user's requirements.
Smaller capacity < 250 A -48V Connecting Environment Sensor Connection at the Front
Cables ENV INFO

RS422/RS485
The interfaces at the front
The CSU in the ZXDU88 S402 RECR collects the following environment

RS232_1
Connecting Battery Cables

RS232_2
of the ZXDU88 S402 RECR
parameters: temperature, smog, flood, door status, entrance control and glass are optional.
broken. User can connect the corresponding cables at the front or back.
Connection at the Back OUT-RELAY
The negative cable
Battery Pack 1 is the first cable to
_ be connected
+

R8COM

R7COM

R6COM

R5COM

R4COM

R3COM

R2COM

R1COM
R8NO

R7NO

R6NO

R5NO

R4NO

R3NO

R2NO

R1NO
R8NC

R7NC

R6NC

R5NC

R4NC

R3NC

R2NC

R1NC
NO: Normally Open
NC: Normally Closed

13
25
12
24
11
23
10
22

21

20

19

18

17

16

15

14
9

1
BACK
Working ground
busbar
WATER
2 SMOKE

1 DOOR1

3 DOOR2

GLASS
AGND

2 AGND

2 AGND

AGND

AGND
1 TEMP

ZXDP12 D252 ZXDP12 D252 Color code


2 +12V

1 +12V

+12V

1 +12V

+12V
BATT (+): Red
VF

(DCDR) (DCDR)
BATT (-): Blue
4
3
2
1

4
3
2
1
Back View Front View

Connect the negative cable first to X20 X21 X22 X23 X24 X25
ensure safety. Env temp Smog Flood Door status Entrance ctrl Glass broken

Do not connect positive and negative


cables in reverse.
Connection at the Front
Tighten any loose detection cable after
battery cable connection. ENV INFO
RS422/RS485

RS232_1 The interfaces at the front


RS232_2

of the ZXDU88 S402 RECR


1. Install the batteries. are optional.
2. Remove the battery fuses.
OUT-RELAY
3. Connect the negative cable to the battery fuse.
4. Connect the positive cable to the working ground busbar (GND).
WATER

DOOR2

DOOR1
GLASS
AGND

AGND
TEMP

+12V
SMOG

AGND
AGND

AGND
+12V

+12V

+12V

+12V
VF

5. Install the connecting plates between the battery cells.


6. Label with battery number and polarity. For example, mark battery 1 (+) on the
13
25
12
24
11
23
10
22

21

20

19

18

17

16

15

14
9

positive cable and battery 1 (-) on the negative cable.

Battery Pack Fuse


Battery pack 1 1*1000A
Battery pack 2 1*1000A

ZTE Corporation Address: No. 55, Hi-tech Road South, Shenzhen, P.R.China Area code:518057 Website: http://ensupport.zte.com.cn Email:800@zte.com.cn
ZXDU88 S402 (V5.0R01M01)
DC Power System Quick Installation & Commissioning Guide http://www.zte.com.cn /6

Connecting Background Connecting CAN Bus


Preparations Before Commissioning:
Monitoring Cables Performing Electrical Check
The ZXDU88 S402 RECR provides two RS232 interfaces for background There are two CAN interfaces at the back of a ZXDU88 S402 RECR. One is X2 on the Perform electrical check before system startup, to avoid equipment damages
monitoring at the front and at the back. BACK board at the upper part of the RECR and the other is at the lower part of the RECR. caused by cable connection errors.
Two background monitoring systems can be connected at the same time. 1. Open the back doors of the rectifier racks.

Connection at the Back


2. Connect a communication cable between each two adjacent ZXDU88 S402 RECRs. (If
there is only one RECR, proceed to step 3.) 17.1 Checking for Short Circuit
3. Insert a DB9 connector with a matching resistor into each remaining idle CAN interface. 1. Turn off all breakers and switches, and Short Circuit Test:
Connecting CAN Bus of One RECR remove all the fuses. Turn the knob of a multimeter to
2. Check the following cables for short circuit: and put the two probes on the fixing
bolts of the connection terminals. An
BACK AC input cables alarm sound given by the multimeter
DC output cables indicates that there is a short circuit!
Locate any short circuit and
CAN eliminate it before proceeding to the
BACK
GND_2

RXD_2
next step.
TXD_2

AC input 1

5 GND1

2 RXD1
RING

3 TXD1
DCD
DSR
DTR
CTS

RTS

Install the matching resistors at


both ends of the CAN bus. L3 L2 L1
Warning:
5
9
4
8
3
7
2
6
1

9
4
8

6
1
DB9 connector with Perform the short circuit check
Background a matching resistor with power-off. Check with
monitoring X3 (male) X4 (male) L1
power-on will damage the
system RS232 RS232 L3 L2 multimeter!
ZXDU88 S402 AC input 2
(RECR1)
Back View
Connection at the Front CAN
ENV INFO
RS422/RS485

RS232_1
RS232_2

DB9 connector with CAN interface


The interfaces at the front a matching resistor
of the ZXDU88 S402 RECR
OUT-RELAY are optional. Cables to Be Checked Qualified
Connecting CAN Bus of Two RECRs AC input cables (L/N/PE) YES □
Load cables (positive and negative cables of each load) YES □
GND_2

RXD_2

RECR1 refers to the RECR


TXD_2

5 GND1

2 RXD1
RING

3 TXD1
DCD
DSR
DTR
CTS

RTS

CAN CAN with the CSU installed.


Background BACK
Install a DB9 connector with
5
9
4
8
3
7
2
6
1

9
4
8

6
1

monitoring
system a matching resistor at each
end of the CAN bus.

RS232_2 RS232_1
DB9 connector with
a matching resistor

ZXDU88 S402 ZXDU88 S402


(RECR1) (RECR2)
Connecting RS485 Cables Between Back View Back View

Racks CAN CAN

DB9 connector with CAN interface


a matching resistor

Communication interfaces
of DCDR
RS485 interfaces at the
back of RECR
Operation steps:
Communication interfaces of ACDR 1. Prepare two RS485 communication cables.
2. Connect an RS485 cable between an
RS485 interface at the back of RECR and
an RS485 interface at the back of ACDR.
3. Connect an RS485 cable between the other
RS485 interface at the back of RECR and
ZXDP03 T601 ZXDU88 S402 ZXDP12 D252 an RS485 interface at the back of DCDR.
(ACDR) (RECR) (DCDR) DB9 connector with 4. Install a DB9 connector with a matching resistor
Back View Back View Back View a matching resistor
at each end of the RS485 bus.

ZTE Corporation Address: No. 55, Hi-tech Road South, Shenzhen, P.R.China Area code:518057 Website: http://ensupport.zte.com.cn Email:800@zte.com.cn
ZXDU88 S402 (V5.0R01M01)
DC Power System Quick Installation & Commissioning Guide http://www.zte.com.cn /6
System Commissioning: System Commissioning:
17.2 Checking AC Input Voltage
Checking the Rectifiers Connecting Batteries to the
1. Turn off the AC input breaker in the cabinet.
2. Turn on the AC input breaker of the power distribution box that
System and Starting the CSU
powers the system.
3. Turn the knob of a multimeter to the AC voltage scale. Installing the Rectifiers Slots Configuration Installing the CSU (hot-pluggable)
Operation Steps:
4. Refer to the table below to measure the voltage between AC input
cables at the AC input connection terminals. 1. Install the CSU.
Communication
CSU
box i. Press the lock of the Communication box
AC input 1 Neutral busbar 1
to open it.
(N)
2
ii. Insert the CSU into the slot of the RECR.
L1 PE busbar
L2
L3 (PE) Switch 3
iii. Install the screws to fix the CSU in proper
position.
Then the CSU is automatically turned on.
L1
L3 L2 2. Install the battery fuses.
20
AC input 2
Status Indication:
After CSU self-detection and
initialization, the LCD displays the
Turn the knob to the AC voltage scale. main menu interface, which means
Example: Measure the phase voltage of L-N. the CSU is working properly.
Maintenance Suggestion
Check Item Criteria Maintenance Suggestion
If the power indicator is not glowing
Phase voltage: Each phase voltage should If the AC input phase voltages are not (power-on failure), re-install the CSU.
Switch
L1-N, L2-N, L3- be w ithin the range of 80 V w ithin this range, the rectifiers cannot be
N to 300 V, and the phase started. Please start the generator for Screw
voltage is approximately pow er supply. Msg Alm Para OAM
equal to each other. R
Rec Qry Time Ver
Neutral-to- ≤10 V If the neutral-to-ground voltage ≈the DO NOT install a faulty rectifier in the ZXDU88 S402
ground voltage: phase voltage, it indicates that the system. Make sure that no obstacle is blocked in the Main Menu Interface

N-PE air vent of the rectifiers for good heat dissipation.


neutral cable and the phase cable are
reversely connected. Reconnect the
cables. Operation Steps:
Check the neutral-to-ground voltage of 1. Turn on the AC input breaker.
the pow er distribution in the equipment 2. Install rectifier 1 into slot 1. System Commissioning:
room and the pow er supply conditions. It
is suggested that users should improve
i. Push the switch to the unlock position. Starting the Rectifiers
the grounding quality of the site. ii. Push the rectifier 1 into the the rectifier slot 1 with an even force until the
rectifier is in position.
iii. Push the switch to the locked position.
iv. Push the rectifier again until its flanges are flat against the RECR.
17.3 Checking Battery Voltage v. Install the screws to fix the rectifier 1. 15 16 17 18 19 20
1. Turn the knob of a multimeter to the DC voltage scale.
3. Turn on the corresponding rectifier breaker.
2. Refer to the table below to measure the terminal voltage of each battery
4. Check the indicators whether the rectifier is
pack (the battery breakers should be removed).
working properly 8 9 10 11 12 13 14

Battery fuse Working ground 5. Turn off the corresponding breaker. ON


holders busbar (+)
Caution:
If the measured value is 6. Repeat steps 2-5 to check the rectifiers in slots
negative, it indicates that 2-20.
OFF
Black probe the positive and negative Indicators 1 2 3 4 5 6 7
battery cables are Status Indication: The PWR and RUN
reversely connected. indicators are glowing and the ALM and FAU
Red probe PWR Indicator Description
Reconnect the cables! are not, which indicates that the rectifier is
RUN PWR Pow er working properly (the rectifier will perform
ALM output power control according to the input
RUN Running voltage). Operation Steps:
Turn the knob to the DC voltage scale. FAU
ALM Alarm 1. Turn on the rectifier breakers.
Example: Measure the voltage of the battery pack 1.
2. Monitor all the rectifiers whether all of them are started properly.
FAU Fault
Check Item Test Points Check Criterion
Voltage of battery Red probe: BAT1(+) The voltage of each battery pack should be The following should be met for normal rectifier operation
pack 1 Black probe: BAT1(-) a positive value and not low er than 43.2V AC input (wire voltage): 380 VAC ± 25%
(this parameter is for reference only).
Voltage of battery Red probe: BAT2(+)
pack 2 Black probe: BAT2(-)

ZTE Corporation Address: No. 55, Hi-tech Road South, Shenzhen, P.R.China Area code:518057 Website: http://ensupport.zte.com.cn Email:800@zte.com.cn
ZXDU88 S402 (V5.0R01M01)
DC Power System Quick Installation & Commissioning Guide http://www.zte.com.cn /6
System Commissioning:
Setting Parameters in the CSU,
21.3 Setting SMR Parameters (in the CSU) 21.5 Setting Parameters (in the ACMU)
SMR Default Actual Description and Requirements System Default Actual Description and Requirements
Parameter Parameter
ACMU and DCMU Addr. Set Mode Auto Manual Set the parameter to Manual. Buzzer Switch Enabled To enable or disable the buzzer to give a sound in
Device Addr. 1 Set Device Addr. of the rectifiers according to the the case of an alarm.
The section below describes the setting requirement for the important rectifier slots number.
parameters. Please set these parameters correctly. Wrong settings will affect Device Addr.-1# 1 Device address number, which is established
The Device Addr. of the rectifiers shall be in order
the effective management of the CSU, ACMU and DCMU to the system and through COM1.
and different from each other. Wrong setting will
cause alarm errors. For the devices monitored by the same CSU, the
cause communication failure.
Record the modified parameter values in the table below for the future use. address of each device should be unique;
Users can set the parameters of an SMR by: otherwise a communication error will occur.
Accessing the menu path: Qry Para in the CSU.
21.1 Setting System Time (in the CSU)
Pressing the QUY button, which is on the front panel of a rectifier.
Set the date and time to local date and time.
System Time System Time System Time Press the QUY
SMR 01 SMR 01
21.6 Setting Parameters (in the DCMU)
Ent
Ent System Default Actual Description and Requirements
Msg Alm Para OAM Ent Ent button for 5 Password:0000
2011-03-23 2011-03-23 2011-03-23 seconds Parameter
R Msg Alm Para OAM Msg Alm Para OAM
Rec Qry Time Ver 11:43:25 11:43:25 11:43:25 Buzzer Switch Enabled To enable or disable the buzzer to give a sound in the
case of an alarm.
SMR Para SMR Para SMR Para
System Time
/
System Time System Time Ent Ent Device Addr.-1# 1 Device address number, which is established through
/ 1 DC-H Shut Volt. 6 6
2011-03-23 2011-03-23 2011-03-23
Addr. Set Mode Addr. Set Mode COM1.
60.0 V Auto
11:43:25 11:43:25 11:45:25
Auto For the devices monitored by the same CSU, the
address of each device should be unique; otherwise a
communication error will occur.
SMR Para

/ : modify value 6 Addr. Set Mode


Setting System Parameters and Battery Management
21.2 Parameters (in the CSU)
Ent: save Manual
System Commissioning:
Connecting Loads to the System
System
Parameter
Default Actual Description and Requirements
21.4 Setting Alarm Attribute (in the CSU) Operation Steps:
Buzzer Switch Enabled To enable or disable the buzzer to give a sound in the
Refer to ZXDU88 S402 CSU (V1.11) Alarm List for the default level (grade) and
case of an alarm. output relay of the alarms.
1. Make sure that the power switches of the loads themselves are off.

If necessary, set the alarm attribute (grade and output relay) through the following 2. Install the corresponding DC output fuses.
ACDP Qty. 5 Configure it according to the actual configuration.
SMR Qty. 10 Configure it according to the actual configuration. menu path: Para 3.Alm. Attr. 3. Use a multimeter to check the DC power supply for the loads.
DCDP Qty. 5 Configure it according to the actual configuration. En Para Red probe (+): touching the GND connection terminals of the loads
Msg Alm Para OAM t Ent
1. System Para
Batt. Cap. 1000 Ah Set the parameters according to the system Password:0000 Black probe (-): touching the -48 V connection terminals of the loads
R 2. Batt. Manage
configuration. If a battery pack is not configured, set Rec Qry Time Ver 3. Alm. Attr. 4. After the above check is passed, turn on the power switches of the loads themselves.
the corresponding battery capacity to 0. Wrong
battery capacity setting will cause the monitoring unit
Para Alm. Attr.
to fail to mange the batteries. Ent
1. System Para DC Load Test Criteria:
Battery Default Actual Description and Requirements 2. Batt. Manage
1 Common Alarm
Grade: Mask Positive value; 42V DC to 58V DC
Management 3. Alm. Attr. Relay: A1 DC INPUT
Parameter _ Maintenance Suggestion:
Red probe +
Chg.Curr.Coeff 0.125 Use the default value or set the parameter according If a measured value is negative, it
Alm. Attr. Alm. Attr. Alm. Attr. Alm. Attr.
to the user’s requirement. The maximum charge Ent indicates that the positive and negative
9 AC.Power OFF
current depends on Chg.Curr.Coeff. Maximum charge Grade: Major
9 AC.Power OFF 9 AC.Power OFF 9 AC.Power OFF
cables of the corresponding load are
Grade: Major Grade: Major Grade: Major
current = Chg.Curr.Coeff × Battery capacity (C). Relay: A2 Relay: A2 Relay: A2 Relay: A2 reversely connected. Correct the
connection!
Para System Para
Ent Ent 1. Sys. Para. Ent
Msg Alm Para OAM Black probe

Rec Qry Time Ver


R
Password:0000
2. Batt. Manage
3. Alm. Attr.
1 1 Language
English 21.5 Setting Input Relays (in the CSU)
Input relays can be set through the following menu path: Para → 4. In-Relay.
Turn the knob to the DC voltage scale.
Para
System Para Ent System Para System Para Ent Ent 1. System Para
Msg Alm Para OAM Example: Measure the voltage of a DC load.
Password:0000
4 Buzzer Switch 4 Buzzer Switch 4 Buzzer Switch R 2. Batt. Manage
Rec Qry Time Ver 3. Alm. Attr.
Enabled Enabled Enabled
Ent/Esc

Para In-Relay-1#
Ent State: Close
2. Batt. Manage
3. Alm. Attr. Grade: Mask
4. In-Relay Name: In-Relay-1#

In-Relay-1#
State: Close
Grade: Mask
Name: In-Relay-1#

ZTE Corporation Address: No. 55, Hi-tech Road South, Shenzhen, P.R.China Area code:518057 Website: http://ensupport.zte.com.cn Email:800@zte.com.cn

You might also like