10 Pek,Cor Beton Mutu F’c = 21,7 Mpa Volume = 0.05 X 4.05 X 4.00 = 0.85 m3
11, Pek. Pembesian Kolom Volume = 0.12 X 2.00 X 4.05 X 9.00 = 8.75
m2
Pek. Pembesian Besi Ulir / Tul Utama
a.Jumlah Tulangan = 4.00 bh
b.Panjang Tulangan = 4.55
m
c. Bengkokan + Sambungan 10% = 0.46 m
d. Jumlah Tiang = 9.00 bh
e. Total Panjang tul.pokok = 180.18 m
f. BJ besi Dia 13.00 = 1.042 kg/m
g. Berat Tulang Pokok =exf
= 187.73 kg
12, Pek. Pembesian Besi Polos / Tul Sengkang a.Jumlah Tulangan = 27.00
bh b.Panjang Tulangan =
0.28 m
c. Bengkokan + Sambungan 10% = 0.03 m
d. Jumlah Tiang = 9.00 bh
e. Total Panjang tul.pokok = 74.84 m
f. BJ besi Dia 8.00 = 0.395 kg/m
g. Berat Tulang Pokok =exf
= 29.53 kg
13, Pek. Cor Beton Mutu F'c = 14.5 Mpa Volume= 0.01 x 4.05 x 9.00
= 0.52 m3
14,
PEKERJAAN LANTAI - 2
15, Kolom Kp. Uk - 120 x 120 cm. Elev + 4.000 Dimensi = 0.40 x 0.40 = 0.16 m2
T. Beton = 4.00 m
P. Besi = 4.30 m
Selimut = 0.03 m
Jumlah = 25.00
bh
Tul Utama = 12.00 D 16.00
Tul Bagi = 8.00 - 0.15
16, Pek. Pembesian Bakesting Volume = 0.40 x 4.00 x 4.00 x 25.00 = 160.00 m2
17, Pek. Pembesian Besi Ulir / Tul Utama a. Jumlah Tulangan = 12.00 bh
b. Panjang Tulangan = 4.30 m
c. Bengkokan+Sambungan 10% = 0.43 m
d. Jumlah Tiang = 25.00 bh
e. Total Panjang Tul. Pokok = 1,419.00 m
f. BJ Besi Dia. 16.00 = 1.578 kg/m'
g. Berat Tulang Pokok = e x f = 2,239.52 kg
18, Pek. Pembesian Besi Polos / Tul Sengkang a. Jumlah Tulangan 26.67 = 27.00 bh
b. Panjang Tulangan = 1.40 m
c. Bengkokan+Sambungan 10% = 0.14 m
d. Jumlah Tiang = 25.00 bh
e. Total Panjang Tul. Pokok = 1,039.50 m
f. BJ Besi Dia. 8.00 = 0.395 kg/m'
g. Berat Tulang Pokok = e x f = 410.15 kg
19 Pek. Cor Beton Mutu F’c = 21.7 Mpa Volume = 0.16 x 4.00 x 25.00 = 16.00 m3
20 Kolom Kp. uk - 120x120 cm. Elev + 4.000 Dimensi = 0.12 x 0.12 = 0.01 m2
T. Beton = 4.00 m
P. Besi = 4.20 m
Selimut = 0.03 m
Jumlah = 23.00
bh
Tul Utama = 4.00 D 13.00
Tul Bagi = 8.00 - 0.15
= 18,90 m2
22, Pek. Pembesian Besi Ulir / Tul Utama a. Jumlah Tulangan = 4.00 bh
b. Panjang Tulangan = 4.20 m
c. Bengkokan+Sambungan 10% = 0.42 m
d. Jumlah Tiang = 23.00 bh
e. Total Panjang Tul. Pokok = 425.04 m
f. BJ Besi Dia. 13.00 = 1.042 kg/m'
g. Berat Tulang Pokok = e x f = 442.84 kg
23 Pek. Pembesian Besi Polos / Tul Sengkang a. Jumlah Tulangan 26.67 = 27.00 bh
b. Panjang Tulangan = 0.28 m
c. Bengkokan+Sambungan 10% = 0.03 m
d. Jumlah Tiang = 23.00 bh
e. Total Panjang Tul. Pokok = 191.27 m f. BJ
Besi Dia. 8.00
= 0.395 kg/m'
g. Berat Tulang Pokok = e x f
= 75.47 kg
24 Pek. Cor Beton Mutu F.c = 14.5 Mpa Volume= 0.01x 4.00x 23.00= 1.32 m3
28 Pek. Cor Beton Mutu f’c = 21,7 Mpa Volume = 0,16 x 2,05 x 25,00
= 8,20 m3