METHODOLOGY
TLRB

The following procedures describe how the samples collected from Drilling Operation
to Laboratory Testing. The mode of transportation has explained as well from the drilling
site in Tagum-Libuganon River Basin to Antipolo laboratory.

Drilling Operation
1. Gather all equipment;
2. Check all equipment if all functions properly then report back to field head and
inventory head;
3. Receive the order to proceed to the site from field head with location and orders
and instructions from field head and project manager;
4. Travel to site location with help of logistics team;
5. Contact field head and project head to ask for permission to proceed with the
location for their approval;
6. Unload the rig from transportation vehicle and move all required equipment
and accessories on to the targeted site;
7. Set up the tripod and the machine while installing side pump and flexible hose for
the water supply;
8. Report to field head that set up is complete and ready to proceed with the drilling;
9. Check in with project engineer and update a status on the on-going drilling operation;
10. Extract samples and immediately report to project engineer for the progress;
11. Take a picture of samples while in a core box;
12. Pack the samples in a proper container and label them accordingly with location
and borehole number and store them in a secure and safe location;
13. Take a picture in the rig with a clear and clean photo;
14. Record the progress in a log book of date and time of start to finish;
15. Have the logistics team pick up the samples and sign over the necessary documents
to turn over the samples; and
16. Logistic team delivers the samples and turn over the samples to the laboratory head
and sign documents for the turn over the samples.
SOLAR SURVEYING
CORPORATION
ENGINEERS-SURVEYORS-CONTRACTORS-CONSULTANTS
1449 A.H Lacson Street., Sta. Cruz
Manila Tel. No. (02) 8 732-26-89, (02)
8807-18-44
Mobile No. 639985965761,639992284338

Transportation of Borehole Samples

The samples from Tagum will be delivered to Antipolo laboratory one time each week.
They are sealed with a meter of stretch wrap and placed on a corebox. When the settings are
done, the samples will be carried by a Hino Truck.
The mode of transportations by land and sea will take 2 days before the samples will
arrive to the laboratory. There are more than of 30 borehole samples can be distributed in a
single trip.

Laboratory Testing
1. Receive samples from logistics team and have them signed for record book
2. Laboratory technicians will prepare for grading and liquid limit
3. Grading:
 Weigh the sample
 Put it in the oven and dry sample. 115 deg Celsius minimum of 4 hours
 Weigh again and dry the sample
 Wet wash the sample
 Put it in the oven again
 Weigh the sample
 Proceed to sieving
4. Conducting testing of grading liquid limit and plastic limit
Reporting
SOLAR SURVEYING
CORPORATION
ENGINEERS-SURVEYORS-CONTRACTORS-CONSULTANTS
1449 A.H Lacson Street., Sta. Cruz
Manila Tel. No. (02) 8 732-26-89, (02)
8807-18-44
Mobile No. 639985965761,639992284338

You might also like