Professional Documents
Culture Documents
02
OPEN SHED Revision No.
Environment Checklist
General Information
Company Name: EBS GPG ARIA FZE Project Name:
Conducted By: Date:
Location: Plot No. 2M-11A, 13A & 13B Phase I – Hamriyah Free Zone, Sharjah - UAE
Poor: Absence of major control measures (high risk), work to be stopped and risk assessment to be reviewed immediately.
Fair: Some minor controls are missing (medium risk), additional control measures to be implemented.
Good: All required controls are in place (low risk), only monitoring is required.
Description
Proper oil/chemicals leakage & spill control in places (tanks Properly and well controlled
bunding, dripping trays, oil spill response materials).
Allocation of designated area for washing concrete mixers & NA
pumps.
Proper collection & disposal of waste water & sewage water. Well collected &disposed
Do noise and vibrations comply with the country's standards? Total compliance to standards
Proper management of noise generated from the project, by Adequate management of noise
installing noise enclosure measures (e.g. silencers, & work
scheduling).
Dust and/or fumes control measures have been implemented. Measures are implemented
Are there any odor sources? Are adequate odor control Adequately controlled
measures taken?
Is there a possibility that the project will adversely affect the All necessary measures taken
local landscape? Are necessary measures taken?
Is the stability of the existing topographic conditions Well stabled
adequately considered for alteration of topographic features,
such as cut and fill operations?
Adequate lighting arrangements provided for required areas. Lighting is provided
Is there a proper reporting system for environmental incident Sufficient and proper reporting
e.g. spill etc.and is the procedure communicated to all system in place
workforce/staffs?
Other Comments: SITE ENIVRONMENT NEEDS TO BE IMPROVED ON AND WASTES COLLECTION
IMPLEMENTATION NEED TO PUT INPLACE.
Approved By:
Position Name Date Signature
HSE Representative