TRANSCO HSE INSPECTION CHECKLIST Issue Date XX/XX/XX


FOR CONSTRUCTION SITES Approved By
HSEQ Manager

HSE INSPECTION INFORMATION


MAIN CONTRACTOR Toshiba DATE 17/07/2007
CONSULTANT Fitchner CONTRACT NO. N 3968
TITLE OF CONTRACT New 400 kV Grid Station at Qidfa
LOCATION Qidfa
INSPECTED BY Paul Roberts INSPECTION REF. PAR/001/07

Please Note: The inspection is undertaken over the items listed in the sections below. Every effort was made to ascertain compliance but not all
areas were applicable at the time of inspection or available due to constraints. Therefore, although comprehensive, the inspection is not a
guarantee of 100% compliance to HSE standards or regulations.

SUMMARY
Upon first entering the site, the site looked tidy and busy with no immediate housekeeping issues. The gateman just let me enter the site without
any challenge though. Walking around the site, it looked and was found to be tidy, PPE was being worn by 99% of the people working. The
scaffolding on the 400 kV GIS room was Scaftaged and appropriate. The workers were using their PPE and generally, compliance was good.

A few items need to be addressed and they are listed below. There is enough HSE staff on the site for this site to be in perfect compliance to the
Toshiba HSE Plan. Toshiba Management must support their Line Management on site in implementing the HSE Plan successfully. HSE Staff
should meet on a regular basis with Line Management to plan for good organized HSE.

CORRECTIVE ACTIONS
No Non-conformance Action Required T/Date Action By C/Date
1 Stores area housekeeping The hazardous material must be stored separately 16/08/07 Toshiba
needs attention especially for and appropriately with adequate signs and fire
the chemicals and hazardous precautions. See check sheet below for details.
materials stored in that area.
2 Security The Security man must control access to the site 07/08/07 Toshiba
and not juts let anybody on. Even Transco staff.

3 Subcontractor was allowed to Toshiba must enforce checks on mobile cranes and 14/08/07 Toshiba
bring a mobile crane on to the their equipment before being allowed on to the site,
site with every sling damaged. even for their subcontractor staff. Record to be
kept.
4 Scaffolding on the back side of All Scaffolding must conform to the Scaftag system. 07/08/07 Toshiba
the 132kV GIS building is poor.

5 Waste area is not appropriate. The Waste needs to be segregated into Hazardous 07/08/07 Toshiba
Also plenty bits of wood with Waste and Non Hazardous Waste. See photos.
nails sticking out around the Clear wood with nails. They should be removed or
site. knocked down.
6 Labour Camp facilities are poor. Toshiba should enforce their subcontractor to 30/08/07 Toshiba
provide adequate welfare facilities for their staff

7 EM evacuation procedure The site evacuation procedure must be tested at 07/08/07 Toshiba
least once every three months. This must be done
immediatelty.

1- JOB SITE GENERAL C NC COMMENTS


 Posters and safety Signs/warnings? √
 Safety meetings held periodically? √
 First aid kit available and adequately stocked? √
 Job related safety training? DNC
 Accident reporting procedure established? √
 Substance abuse policy in place? DNC
 Injury records being kept? DNC
 Emergency telephone numbers posted? √
 Traffic routes identified? √

2- HOUSEKEEPING & SANITATION C NC COMMENTS


 General neatness of work area(s)? √
 Regular disposal of waste and trash? √
 Procedures to handle hazardous waste? √ N/C No 5

This Document is the property of TRANSCO, and cannot be used nor given to outside party without prior authorization
Rev : X Page 2 of 6
TRANSCO HSE INSPECTION CHECKLIST Issue Date XX/XX/XX
FOR CONSTRUCTION SITES Approved By
HSEQ Manager

 Passageways and walkways clear? √


 Adequate lighting? √
 Waste containers provided and used? √ N/C No 5
 Sanitary facilities adequate and clean? √ Labour Camp was very poor N/C No 6
 Adequate potable water supply? √
 Adequate drinking cups? DNC
 Nails, boards, debris removed √ Plenty of nails sticking out of planks of wood N/C No 5
 Eye flushing facilities available? √
 Emergency showers available? N/A

3- CONSTRUCTION AREA - ACCESS C NC COMMENTS


 Warning signs in place? √
 Open ditches protected √
 Drop-offs protected? N/A
 Ladders lowered? N/A
 Hazard lights utilized? N/A
 Equipment secured? N/A
 Utility ditches flagged or barricaded? √

4- HAZARD COMMUNICATION C NC COMMENTS


 Written program? √
 Employees trained? √
 MSDS’s on file and available? √ N/C No 1
 Control and disposal measure(s) established? √ N/C No 1
 Material properly stored and labeled? √ N/C No 1
 Log of all chemicals on site available? √ N/C No 1
 Labels legible? √

5- FIRE PREVENTION C NC COMMENTS


 Adequate number/type of fire extinguisher(s) available? √
 Fire prevention/extinguisher training accomplished? DNC
 Fire extinguisher inspections done periodically? √
 Phone number of fire department posted? √
 Fire extinguisher(s) provided on proper equipment? √
 Are flammable liquids labeled? √ N/C No 1
 Are flammable liquids properly stored? √ N/C No 1
 Fire alarm available/fire evacuation plan established? √ N/C No 1
 Fuel supplies protected against accidental impact? DNC
 Fire training given to appropriate personnel? √ No drill done on the site N/C No 7
 Is equipment shut down prior to refueling? DNC
 Is equipment properly grounded to fuel trucks before refueling? DNC
 “No smoking” signs posted and enforced? √ N/C No 1
 Hydrants clear, access to public thoroughfare open? DNC

6- FLAMMABLE LIQUIDS/MATERIALS C NC COMMENTS


 Empty containers removed? √ N/C No 1
 Only approved containers being used? √
 Containers stored in approved and appropriate areas? √ N/C No 1
 Outside storage diked for containment? √ N/C No 1
Storage tanks properly grounded, bunded and pressure relief

provided? √ N/C No 1
This Document is the property of TRANSCO, and cannot be used nor given to outside party without prior authorization
Rev : X Page 3 of 6
TRANSCO HSE INSPECTION CHECKLIST Issue Date XX/XX/XX
FOR CONSTRUCTION SITES Approved By
HSEQ Manager

 Cylinders stored/secured in upright position? √

7- ELECTRICAL C NC COMMENTS
 Electrical devices have been inspected and tested? √
 Electrical equipment properly maintained? √
 Equipment properly grounded? √
 Assured equipment grounding program established? DNC
 GFCI used and tested where required? √
 Fuses provided? √
 Electrical dangers posted? √ Signs should be erected.
 Proper fire extinguisher(s) provided? √
 Are terminal boxes equipped with required covers (cover used)? DNC
 Are circuits labeled in terminal boxes? DNC

8- PERSONAL PROTECTIVE EQUIPMENT C NC COMMENTS


 Hazard evaluation accomplished and certified? √
 Protective equipment adequate for exposure? √
 Employees issued PPE where needed? √
 Is PPE being used? √
 Employees trained in the use of PPE? √
 Is inspection being done periodically before/after use? DNC
 Adequate maintenance and sanitary storage available? √
 Adequate fall protection provided? √
 Eye protection? √
 Face protection (glasses, goggles, shields)? √
 Hearing protection? N/A
 Respirators and masks? N/A
 Respirators used? N/A
 Head protection? √
 Hand and foot protection? √
 Physicals accomplished as required? DNC

9- HAND TOOLS C NC COMMENTS


 Proper tool used for the job? √
 Handles free of cracks and attached to tool properly? √
 Inspections and maintenance done prior to use? DNC
 Neatly stored, safely carried? √

10- POWER TOOLS C NC COMMENTS


 Good housekeeping where tools are used? √
 Inspections and proper maintenance accomplished? √
 Tools grounded properly or double insulated? √
 Guards in place and used correctly? √
Damaged or malfunctioning tools tagged out until repaired or
 DNC
replaced?
 Local laws and ordinance compliance? DNC
 All operators qualified? DNC
 Tools protected from unauthorized use? DNC
 Competent instruction and supervision? DNC
 Cords included in electrical inspection? DNC

This Document is the property of TRANSCO, and cannot be used nor given to outside party without prior authorization
Rev : X Page 4 of 6
TRANSCO HSE INSPECTION CHECKLIST Issue Date XX/XX/XX
FOR CONSTRUCTION SITES Approved By
HSEQ Manager

11- LADDERS C NC COMMENTS


 Ladders inspected and in good condition? √
 Ladders used properly for type of exposure? √
 Ladders secured to prevent slipping, sliding, falling? √
 Do side rails extend 36” above top of landing? DNC
 Are ladders spliced? DNC
 Rungs or cleats not over 12” on center? DNC
 Proper maintenance and storage? DNC
 Are ladders painted? √
 Do fixed ladders in excess of 20 feet have fall protection? N/A
 Are aluminum ladders of sufficient strength for the task? DNC

12- SCAFFOLDS C NC COMMENTS


 Erection properly supervised? DNC Already up
 All structural members free from defects and meet safety factor? √ N/C No 4
 Are all connections secured? √ N/C No 4
 Are scaffolds erected on solid footing? √ N/C No 4
 Is scaffold tied to structure? √
 Are working areas free of dirt, debris, ice, grease, etc.? √ N/C No 4
 Are workers protected from falling objects? √ N/C No 4
 Is scaffold plumb and square, with cross-bracing? √ N/C No 4
 Are guard rails, intermediate rails, and toe boards in place? √ N/C No 4
 Are ropes and cables in good condition? √
 Fall protection available and in use? √

13- EXCAVATION AND SHORING C NC COMMENTS


Are holes, trenches, and cuts over 1.5 meter deep shored, sloped

or trench boxes used? √
 Operation supervised by competent person? √
 Spoil banks at least 1 meter from edges of cut? √
Ladders placed to ensure no greater than 25 feet of lateral travel
 N/A
by worker?
 Ladder properly secured? N/A
 Are adjacent structures properly shored? N/A
 Is shoring and sheathing correct for soil and depth? N/A
 Are roads and sidewalks supported and protected? √
 Excavation barricaded and lighting provided? √
 Are equipment ramps adequate? √
 Have underground utility installations been identified? √
Registered professional engineers design/approval
 DNC
accomplished?
 Confined space permit required, plan established? N/A
 Are daily inspections completed by a competent person? DNC

15- HOISTS, CRANES & DERRICKS C NC COMMENTS


 Are annual inspections completed? √ N/C No 3
 Are operators properly tested & physical exams current? √ N/C No 3
 Are daily inspections completed by operators? √ N/C No 3
 Outriggers used? √
 Cranes operating under Overhead Transmission Lines? N/A
 Hoists designed by a competent professional engineer? √
 Proper loading for capacity at lifting radius? N/A
This Document is the property of TRANSCO, and cannot be used nor given to outside party without prior authorization
Rev : X Page 5 of 6
TRANSCO HSE INSPECTION CHECKLIST Issue Date XX/XX/XX
FOR CONSTRUCTION SITES Approved By
HSEQ Manager

 Operation in accordance with manufacturer’s instruction? N/A


 Competent person inspecting crane? √ N/C No 3
 Equipment properly lubricated and maintained? √ N/C No 3
 Load testing accomplished?
 Signalmen where needed? √
 Alarms working and audible? DNC

20- HANDLING/STORAGE OF MATERIALS C NC COMMENTS


Chemicals need better storage and segregation N/C No
 Materials properly stored or stacked? √
1
 Are shelves, racks, and overhead storage load rated? √
 Are passageways clear? √ Needs to be kept clear N/C No 1
 Sufficient employees to do the job? √
 Lifting correctly? DNC
 Materials protected from weather? √
 Employees protected from falling into hoppers and bins? N/A
 Is dust protection used? √
Correct type of fire extinguisher(s) and other fire protection
 √ Needs better fire protection as made of wood N/C No 1
available?
 Traffic controlled through the storage area? N/A
 Rigging inspected prior to use? N/A
 Competent person responsible? √

This Document is the property of TRANSCO, and cannot be used nor given to outside party without prior authorization
Rev : X Page 6 of 6
TRANSCO HSE INSPECTION CHECKLIST Issue Date XX/XX/XX
FOR CONSTRUCTION SITES Approved By
HSEQ Manager