Professional Documents
Culture Documents
FOR THE
CARTAGENA REFINERY
EXPANSION PROJECT
© CBI Americas Ltd. 2008. All rights reserved. Contains confidential information proprietary to CB&I, or its affiliates, clients or
suppliers and may not to be used, reproduced or disclosed without CB&I's prior written permission.
CB&I CONTRACT NO. 166000
Prepared by: Process - CB&I
Document No: 190-RP-PR35-0001
© CBI Americas Ltd. 2008. All rights reserved. Contains confidential information proprietary to CB&I, or its affiliates, clients or
suppliers and may not to be used, reproduced or disclosed without CB&I's prior written permission.
Document No.:
190-RP-PR35-0001
SUPERVISORY OPERATING MANUAL Revision: C
UNIT NO.: 190
Date: 23-Aug-10
EARLY WORKS
Page: 3 of 25
TABLE OF CONTENTS
1 GENERAL OVERVIEW........................................................................................................4
1.1 Preface............................................................................................................................................ 4
1.2 Raw Water Pond System................................................................................................................. 5
1.3 Crude Oil Line Relocation................................................................................................................ 5
1.4 Light Fuel Oil Line Relocation......................................................................................................... 6
1.5 Site Dewatering system................................................................................................................... 6
2 RAW WATER POND SYSTEM...........................................................................................6
2.1 Process description.......................................................................................................................... 6
2.2 Process system overview................................................................................................................ 6
2.3 Operating variables and control philosophy.....................................................................................8
2.4 Product specifications and emissions summary..............................................................................9
2.5 Battery Limit conditions.................................................................................................................... 9
2.6 Safety............................................................................................................................................. 10
2.7 Start-up preparation....................................................................................................................... 11
2.8 Start-up procedures...................................................................................................................... 11
2.9 Special procedures........................................................................................................................ 12
2.10 Operating requirements................................................................................................................. 13
2.11 Analytical procedures..................................................................................................................... 14
3 CRUDE OIL LINE RELOCATION......................................................................................14
3.1 Process description........................................................................................................................ 14
3.2 Process system Overview.............................................................................................................. 15
3.3 Operating Variables and control Philosophy..................................................................................15
3.4 Products specifications and emissions summary...........................................................................17
3.5 Battery Limit conditions.................................................................................................................. 17
3.6 Safety............................................................................................................................................. 17
3.7 Start-up preparation....................................................................................................................... 18
3.8 Start-up procedures....................................................................................................................... 18
3.9 Special procedures........................................................................................................................ 18
3.10 Operating requirements................................................................................................................. 18
3.11 Analytical procedures..................................................................................................................... 19
4 FUEL OIL LINE RELOCATION..........................................................................................19
4.1 Process description........................................................................................................................ 19
4.2 Process system Overview.............................................................................................................. 19
4.3 Operating Variables and control Philosophy..................................................................................19
4.4 Products specifications and emissions summary...........................................................................20
4.5 Battery Limit conditions.................................................................................................................. 20
4.6 Safety............................................................................................................................................. 20
4.7 Start-up preparation....................................................................................................................... 21
4.8 Start-up procedures....................................................................................................................... 21
4.9 Special procedures........................................................................................................................ 21
© CBI Americas Ltd. 2008. All rights reserved. Contains confidential information proprietary to CB&I, or its affiliates, clients or
suppliers and may not to be used, reproduced or disclosed without CB&I's prior written permission.
Document No.:
190-RP-PR35-0001
SUPERVISORY OPERATING MANUAL Revision: C
UNIT NO.: 190
Date: 23-Aug-10
EARLY WORKS
Page: 4 of 25
© CBI Americas Ltd. 2008. All rights reserved. Contains confidential information proprietary to CB&I, or its affiliates, clients or
suppliers and may not to be used, reproduced or disclosed without CB&I's prior written permission.
Document No.:
190-RP-PR35-0001
SUPERVISORY OPERATING MANUAL Revision: C
UNIT NO.: 190
Date: 23-Aug-10
EARLY WORKS
Page: 5 of 25
1 GENERAL OVERVIEW
1.1 Preface
Supervisory Operating Procedures are intended only as a guide and reference for
personnel connected with the operation and maintenance of the facilities built for unit
190 early works. As such, this manual does not cover each and every step to be taken
in the ordinary operation of the unit. This document provides basic information and
hence is not practical to cover all possible contingencies or emergency situations.
Therefore, some of the procedures and operating conditions stated herein may require
further detailed explanation to meet unusual or emergency conditions.
This Supervisory Operating Manual is the property of CB&I, including all patentable
features and / or confidential information, and its use is conditioned upon the user’s
agreement not to reproduce this information, in whole or in part, nor the material
described therein and not to use the information for any purpose other than for the
operation and maintenance of the unit, without the written permission of CB&I.
The facilities built as early works effort in order to facilitate the construction of the new process
units were:
Raw Water Pond system
Crude Oil Line Relocation
Fuel Oil Line Relocation
Site Dewatering system
© CBI Americas Ltd. 2008. All rights reserved. Contains confidential information proprietary to CB&I, or its affiliates, clients or
suppliers and may not to be used, reproduced or disclosed without CB&I's prior written permission.
Document No.:
190-RP-PR35-0001
SUPERVISORY OPERATING MANUAL Revision: C
UNIT NO.: 190
Date: 23-Aug-10
EARLY WORKS
Page: 6 of 25
● To Receive, aerate and settle the raw water supplied to Existing plants and new
facilities at Cartagena Refinery.
● To supply the existing refinery with 2300 gpm of raw water for the existing water
treatment plant.
● To provide normally 3488 GPM and a maximum of 4500 GPM of Raw water for
new Unit 131 when new water pumps 190-EWO-P-001 A/B will be connected to
this Pond.
The relocated pipeline tie-in to the existing Pipeline at the following plant coordinates:
a) on the South side at S2791, E4326 and b) on the North side at S3012, E3212.
REFICAR has advised that the pipeline currently transport Crude oil and Fuel oil at a
rate of 144,000 BPD and 120,000 BPD respectively. For the new refinery operation this
pipeline is dedicated for crude oil transport only.
© CBI Americas Ltd. 2008. All rights reserved. Contains confidential information proprietary to CB&I, or its affiliates, clients or
suppliers and may not to be used, reproduced or disclosed without CB&I's prior written permission.
Document No.:
190-RP-PR35-0001
SUPERVISORY OPERATING MANUAL Revision: C
UNIT NO.: 190
Date: 23-Aug-10
EARLY WORKS
Page: 7 of 25
© CBI Americas Ltd. 2008. All rights reserved. Contains confidential information proprietary to CB&I, or its affiliates, clients or
suppliers and may not to be used, reproduced or disclosed without CB&I's prior written permission.
Document No.:
190-RP-PR35-0001
SUPERVISORY OPERATING MANUAL Revision: C
UNIT NO.: 190
Date: 23-Aug-10
EARLY WORKS
Page: 8 of 25
The level between the two cells is equalized through the gravity line connection and by
adjusting the flows to each cell.
Effective Storage Capacity
Raw Water supply to existing Refinery is a Gravity flow system, because of this the
normal Water Level inside new pond is set to 53 ft elevation (Ground level in pond
Area is of 36 Ft). The maximum water level is at a 54 ft elevation and the minimum
level to guarantee 2300 gpm, is at 43 ft elevation. Under these conditions the existing
refinery will be guaranteed an effective minimum flow rate of 2300 gpm.
The New unit 131 will receive raw water supplied by pumps 190-EWO-P-001 A/B (131-
UWT-P-100 A/B) located alongside this Pond and will receive raw water at a minimum
elevation of 40 ft.
The effective water storage of the New Raw water Pond for both the existing refinery
and new unit 131 is 12,800,000 gallons.
New Raw water Pond will provide 38.5 hours of raw water supply at a rate of 5520
GPM for existing and new Refinery, approximately 80% of the total raw water storage.
The rest of water storage required to guarantee 48 Hours of operation in new refinery
will be provided by the Filtered water tank located in unit 131.
Gravity Line to Existing refinery supply system.
A 30” gravity line is installed and connected to existing 14”, 18” and 12” inches raw
water supply lines to existing refinery raw water plant. This line will is sized to minimize
head loss and to guarantee 2300 gpm flow to existing Refinery at the minimum water
level of 43 Ft. (Referred to Refinery elevation zero reference point)
Supply to Unit 131.
Connections and valves to the suction of new pumps 190-EWO-P-001 A/B (131-UWT-
P-100 A/B) are provided. Two Horizontal centrifugal pumps (one operating and one
spare) are installed to supply raw water to Unit 131 water Clarifiers. Pumps are
designed for maximum expected flow of 4620 GPM (when condensate recovery is 60
% of normal condensate recovery). And shall have stable operation at the normal raw
water requirements of 3500 GPM
Supply to existing fire water pond
A 14” CS line located at the end of the 24” HDPE pipe supply raw water to the existing
fire water pond. Also a bypass line with a valve is connected from the 14” CS line to
the 30” gravity line that supply water to the existing refinery.
Chlorination systems.
(PID 190- DG-PR05-0056)
© CBI Americas Ltd. 2008. All rights reserved. Contains confidential information proprietary to CB&I, or its affiliates, clients or
suppliers and may not to be used, reproduced or disclosed without CB&I's prior written permission.
Document No.:
190-RP-PR35-0001
SUPERVISORY OPERATING MANUAL Revision: C
UNIT NO.: 190
Date: 23-Aug-10
EARLY WORKS
Page: 9 of 25
Two independent chlorinator systems are provided for disinfection of the raw water
and oxidation of organic matters. This provides liquid chlorine injection using water
ejectors that inject chlorinated water to the main raw water lines.
Chlorination System for RW to the Existing Refinery:
Chlorination for existing raw water units is provided by Chlorinator 190-EWO-X-002,
this system is conformed by a chlorinator shelter containing the following equipment:
4 liquid chlorine Ton Cylinder ( 2000 lb each)
Chlorine Meter and Vacuum controller with a maximum capacity of 500 lb/day
Chlorine ejector
Chlorinator booster pumps 190-EWO-P-002 A/B
Chlorine analyzer.
Water is taken from 30” gravity line by a 3” CS line, at a rate of 25 GPM and
pressurized in pumps 190-EWO-P-002 A/B to a minimum pressure of 55 psig and
passed through the Chlorine ejector. Liquid chlorine is vaporized and measured in
chlorine Vacuum controller and mixed with raw water in the ejector and send to the 30”
gravity line through the injection quill SP-009. The normal amount of chlorine required
is 150 lb/day required to guarantee 5 mg/ L of chlorine in 2300 gpm of raw water after
the mixing quill.
Chlorination System for RW to the New Refinery (Unit 131):
A new Chlorination System (131-UWT-SK-001A) is defined for the RW being received
by Unit 131, which is to be designed, procured and provided on a skid by Siemens,
and constructed by CB&I, under the scope of Unit 131
© CBI Americas Ltd. 2008. All rights reserved. Contains confidential information proprietary to CB&I, or its affiliates, clients or
suppliers and may not to be used, reproduced or disclosed without CB&I's prior written permission.
Document No.:
190-RP-PR35-0001
SUPERVISORY OPERATING MANUAL Revision: C
UNIT NO.: 190
Date: 23-Aug-10
EARLY WORKS
Page: 10 of 25
CaCO3
Calcium Hardness mg/L 54 62 70
CaCO3
Total Alkalinity mg/L 52 73 95
CaCO3
Organic Matter mg/L 4.1 6.3 30
Ammonium mg/L 0.01 0.12 0.56
Nitrites mg/L 0.02 0.03 0.05
Nitrates mg/L 1.1 2.6 5.3
Fluorides mg/L 0.23 0.23 0.23
Iron mg/L 0.02 0.09 0.31
Manganese mg/L 0.03 0.06 0.12
Sodium mg/L 19 23 32
Potassium mg/L 2.7 3 3.2
Suspended Solids mg/L 25
Total Solids (Dissolved + mg/L 114 215 385
Suspended)
Conductivity μS/cm 244 306 553
Coliformes Totals NMP/100 ml 23 358 1700
E. coli UFC/100 mL 1 14 99
© CBI Americas Ltd. 2008. All rights reserved. Contains confidential information proprietary to CB&I, or its affiliates, clients or
suppliers and may not to be used, reproduced or disclosed without CB&I's prior written permission.
Document No.:
190-RP-PR35-0001
SUPERVISORY OPERATING MANUAL Revision: C
UNIT NO.: 190
Date: 23-Aug-10
EARLY WORKS
Page: 11 of 25
2.6 Safety
Main safety Risks associated with raw water pond are related to:
Drowning: The possibility of a person falling into the pond and subsequent
drowning should be prevented. No authorized personnel should be allowed to
walk on pond walls. It is responsibility of the owner to assure procedures are
followed for accessing the raw water pond premises. Also during maintenance
of the cells ponds refinery blinding and isolation procedures must be followed.
The 24“ nd 30” inches outlet lines have spacers to install blinds. All inlet valves
should be securely closed. Worker should not be allowed to work by
themselves in pond premises, they should be accompanied.
Adequate safety lines and escape ladders should be used when working inside
the Cells. Cleaning of cells should be done only with inlet and outlet lines
blocked to each cell.
Falling: Due to the slope of the pond walls and the Polyethylene lining inside
the pond, the possibilities of slipping and falling are high. Caution should be
exercised while walking or working on the Pond walls and piping systems.
High pressure streams: While the normal pressure of pond inlet line is only 30
Psig, this pressure may rise to 157 psig in case of abnormal conditions in
municipal pipelines. The release of high volume, high pressure water on the
proximity of the external pond walls should be immediately stopped, since it
could damage the pond walls and integrity of the system.
Sudden flow stops: Because of the use of HDPE underground pipes, the
sudden flow stops should be prevented, since they could produce pipe
breakage and result in big emergency situation due to the possibility of eroding
pond walls and affec the integrity of the system. A minimum of five (5) minutes
should be established during the process of opening or closing inlet or outlet
pond valves.
Chlorine exposure: chlorine detectors and alarms have been provided in
chlorination areas. Proper safety kit should be located close to chlorinator area
and in case of leakage; evacuation should be done immediately for all
personnel without protection.
© CBI Americas Ltd. 2008. All rights reserved. Contains confidential information proprietary to CB&I, or its affiliates, clients or
suppliers and may not to be used, reproduced or disclosed without CB&I's prior written permission.
Document No.:
190-RP-PR35-0001
SUPERVISORY OPERATING MANUAL Revision: C
UNIT NO.: 190
Date: 23-Aug-10
EARLY WORKS
Page: 12 of 25
© CBI Americas Ltd. 2008. All rights reserved. Contains confidential information proprietary to CB&I, or its affiliates, clients or
suppliers and may not to be used, reproduced or disclosed without CB&I's prior written permission.
Document No.:
190-RP-PR35-0001
SUPERVISORY OPERATING MANUAL Revision: C
UNIT NO.: 190
Date: 23-Aug-10
EARLY WORKS
Page: 13 of 25
d. Continue circulation to the new 30” Line and the existing 12”, 14” and 18” lines
using the bypass line in order to eliminate any remaining air in the system and
guarantee siphoning effects.
e. Remove air from the 30” outlet nozzle by venting and after the pond is ready,
slowly start opening 30” valve on pond outlet and start closing the bypass
f. Confirm that flow is normal by checking existing raw water pumps operation.
g. Check with Refinery Operations to confirm flows and levels are sustainabilie
based on actual operation.
h. Once Cell No 1 is in operation, Cell No 2 could be commissioned. This filling
could be accelerated by pumping (using portable diesel pumps) to empty the existing
ponds. It is not recommended to drain existing ponds to the water treatment Unit,
because the new pond and existing ponds will try to equalize levels. The Use of
portable diesel pumps is recommended (500 GPM)
i. Once Cell No 2 is filled it should be aligned to the 30” line flow.
j. Civil engineers will check Cell No 2 permeability, stability and let the system
settle down.
k. Align cell No 2 by slowly opening outlet valves and adjusting pond inlet flows and
levels.
l. Once stable operation of the new RW system is confirmed, formal approval
should be obtained from Refinery Operation prior to emptying and demolishing of the
old ponds and the related piping system.
© CBI Americas Ltd. 2008. All rights reserved. Contains confidential information proprietary to CB&I, or its affiliates, clients or
suppliers and may not to be used, reproduced or disclosed without CB&I's prior written permission.
Document No.:
190-RP-PR35-0001
SUPERVISORY OPERATING MANUAL Revision: C
UNIT NO.: 190
Date: 23-Aug-10
EARLY WORKS
Page: 14 of 25
Chlorination.
Chlorination is adjusted manually, reading the chlorine analyzer data and adjusting the
vacuum controller based on the chlorine meter reader (Rotameter)
Follow the chlorine injection package manufacturer manuals for complete information
about the chlorine operation.
Follow all safety measures recommended by the Chlorine Institute and chlorine
manufactures while operating the chlorinator system.
Raw Water Flow: Inlet water system requires 30 psig pressures at municipal raw
water headers of 40” and 48” inches. Under these conditions the following flow are
obtained
Normal operating flow “ 5800 GPM
Maximum operating Flow 7300 GPM
Ultimate operating Flow 11000 GPM
The ultimate capacity is obtained with all inlet valves fully open and meter filters clean,
Two cells operating and two 20 “ lines from municipal raw water main headers in
operation.
The above mentioned flows are distributed to existing refinery and new refinery as
follows:
Existing Refinery : 2300 GPM normal , 2800 GPM maximum
Unit 131 : 3500 GPM Normal, 4500 GPM maximum
Pond Levels: In order to guarantee Pond storage capacity the following levels should
be controlled:
Maximum Operating level: 54 Ft Elevation
Normal operating level for 12.8 MM Gallons capacity: 53 FT Elevation
Minimum Operating Level for gravity flow: 43 Ft Elevation
Pond Bottom Elevation 36 Ft Elevation
© CBI Americas Ltd. 2008. All rights reserved. Contains confidential information proprietary to CB&I, or its affiliates, clients or
suppliers and may not to be used, reproduced or disclosed without CB&I's prior written permission.
Document No.:
190-RP-PR35-0001
SUPERVISORY OPERATING MANUAL Revision: C
UNIT NO.: 190
Date: 23-Aug-10
EARLY WORKS
Page: 15 of 25
Pond levels are indicated in the field and DCS by Level meter and Transmitter LT-
1003 A /B. Level is maintained by manually adjusting valves to inlet pond raw water
distributor nozzles.
For water level Elevations below 43 FT gravity flow rate of 2300 GPM can not be
guaranteed.
Chlorination dosing: for successful elimination of bacteria growth in raw water pipes
and oxidizing organic matters, the following chlorine addition should be used:
Normal Maximum
Chlorination is adjusted manually, reading the chlorine analyzer data and adjusting the
vacuum controller based on the chlorine meter reader (Rotameter)
Follow the chlorine injection package manufacturer manuals for complete information
about the chlorine operation.
© CBI Americas Ltd. 2008. All rights reserved. Contains confidential information proprietary to CB&I, or its affiliates, clients or
suppliers and may not to be used, reproduced or disclosed without CB&I's prior written permission.
Document No.:
190-RP-PR35-0001
SUPERVISORY OPERATING MANUAL Revision: C
UNIT NO.: 190
Date: 23-Aug-10
EARLY WORKS
Page: 16 of 25
pipe sleeves. The new route is 4,400 ft long, with a total of 18 bends (90 and 45
Degree bends).
The relocated pipeline tie-in to the existing Pipeline at the following plant coordinates:
a) on the South side at S2791, E4326 and b) on the North side at S3012, E3212.
REFICAR has advised that the pipeline currently transports Crude oil and Fuel oil at a
rate of 144,000 BPD and 120,000 BPD respectively. For the new refinery operation
this pipeline is dedicated for crude oil transport only.
© CBI Americas Ltd. 2008. All rights reserved. Contains confidential information proprietary to CB&I, or its affiliates, clients or
suppliers and may not to be used, reproduced or disclosed without CB&I's prior written permission.
Document No.:
190-RP-PR35-0001
SUPERVISORY OPERATING MANUAL Revision: C
UNIT NO.: 190
Date: 23-Aug-10
EARLY WORKS
Page: 17 of 25
Operating Pressures
Operating pressures at Cartagena refinery are relative to the product transported and
flow rates.
Operating pressures measured at Pig receiver are as follows:
Normal operating pressure handling crude oil: 50 psig
Normal Operating Pressures handling fuel oil: 90 psig (Sending product to TNP
Tanks)
Safety Valve GI-2-PSV -100 Located at pig Receiver is set to 175 Psig. VIT is
considering modifying this set pressure in order to manage 168000 BPD crude oil
rates and 120000 BPD fuel oil rates to TNP
Maximum operating pressure is observed when accidentally blocking valves at pig
receiver or downstream at crude or fuel oil tanks inlets. In these cases it is expected
the pipeline will reach a maximum operating pressure consistent with discharge
pressure of the pumps located in Covenas, unless safety relief valve discharge is
properly routed to the Relief tank (Outlet Valve Blocked)
Maximum operating pressure handling Crude Oil: 1350 psig
Maximum Operating Pressures handling Fuel Oil: 1350 psig
Operating Temperatures
Normal Inlet Temperature 90 F
Minimum Inlet Temperature 73 F
Maximum Inlet Temperature 110 F
© CBI Americas Ltd. 2008. All rights reserved. Contains confidential information proprietary to CB&I, or its affiliates, clients or
suppliers and may not to be used, reproduced or disclosed without CB&I's prior written permission.
Document No.:
190-RP-PR35-0001
SUPERVISORY OPERATING MANUAL Revision: C
UNIT NO.: 190
Date: 23-Aug-10
EARLY WORKS
Page: 18 of 25
Control Philosophy
Pipeline is managed by Covenas operations. Refinery Operator controls the Pig
receiving station and the Crude and Fuel Oil allocation to Tankage.
The section installed by CB&I is integral part of the total pipeline and is not
independently controlled
3.6 Safety
Main safety Risks associated with Crude and Fuel Oil Pipeline are:
Overpressure: Pipe line could be over-pressured by downstream blockage,
pig blockage, or sudden flow stop. The PSV for the pipeline protection due to
overpressure is located at the covenas pump discharge. In case of
overpressure, the measured pressured could be in excess of 1000 psig.
Leakage: Pipeline leaks can be the result of internal or external corrosion as
well as mechanical damage. Corrosion monitoring is required to prevent leaks.
Fire: In case of pipeline leaks a fire could develop provided an ignition source
is close to the leak. In area were pipeline is crossing close to process units
extra-thickness was considered to prevent leakage. Barriers were also
providing in places near the Refinery roads to prevent mechanical damage...
Sudden flow stops: Because of the length of the pipeline (in excess of 120
KM) and the high flow rates, sudden flow stops should be prevented, since
such stops could result in dangerous emergency situation due to the possibility
of pipeline breakage, liquid release and subsequent fire. Protection for this risk
is considered part of the pipeline operational protection system installed by the
pipeline operator Ecopetrol. In general operating procedures should be in place
to avoid sudden flow stops
© CBI Americas Ltd. 2008. All rights reserved. Contains confidential information proprietary to CB&I, or its affiliates, clients or
suppliers and may not to be used, reproduced or disclosed without CB&I's prior written permission.
Document No.:
190-RP-PR35-0001
SUPERVISORY OPERATING MANUAL Revision: C
UNIT NO.: 190
Date: 23-Aug-10
EARLY WORKS
Page: 19 of 25
© CBI Americas Ltd. 2008. All rights reserved. Contains confidential information proprietary to CB&I, or its affiliates, clients or
suppliers and may not to be used, reproduced or disclosed without CB&I's prior written permission.
Document No.:
190-RP-PR35-0001
SUPERVISORY OPERATING MANUAL Revision: C
UNIT NO.: 190
Date: 23-Aug-10
EARLY WORKS
Page: 20 of 25
Transported Fuel Oil by Covenas – Cartagena Pipeline with the following conditions:
Light Fuel OIL
Normal Flow rate BPSD 108000
Maximum Flow rate BPSD 120000
API 7.2
Viscosity Cp @ T 98
Flow Temperature 90
Density lb/Ft3 @ T 62.72
© CBI Americas Ltd. 2008. All rights reserved. Contains confidential information proprietary to CB&I, or its affiliates, clients or
suppliers and may not to be used, reproduced or disclosed without CB&I's prior written permission.
Document No.:
190-RP-PR35-0001
SUPERVISORY OPERATING MANUAL Revision: C
UNIT NO.: 190
Date: 23-Aug-10
EARLY WORKS
Page: 21 of 25
Operating Pressures
Operating pressures for the light Fuel oil lines are:
Normal operating pressure: 90 psig
Maximum Operating Pressures: 175 psig
Safety Valve GI-2-PSV -100 Located at pig Receiver is set to 175 Psig. VIT is
considering modifying this set pressure in order to manage 168000 BPD Crude oil
rates and 120000 BPD fuel Oil rates to TNP
Operating Temperatures
Normal Inlet Temperature 90 F
Minimum Inlet Temperature 73 F
Maximum Inlet Temperature 110 F
Control Philosophy
Fuel oil operation is controlled by Refinery tank farm operations.
The section installed By CB&I is integral part of the fuel oil handling system and
because of this, no separate control philosophy is discussed here.
4.6 Safety
Main safety Risks associated with Fuel Oil Pipeline are:
Overpressure: Pipe line could be over-pressured by downstream blockage, or
sudden flow stop. This pipeline is protected by Safety Valve GI-2-PSV -100,
located at the pig Receiver set at 175 Psig.
© CBI Americas Ltd. 2008. All rights reserved. Contains confidential information proprietary to CB&I, or its affiliates, clients or
suppliers and may not to be used, reproduced or disclosed without CB&I's prior written permission.
Document No.:
190-RP-PR35-0001
SUPERVISORY OPERATING MANUAL Revision: C
UNIT NO.: 190
Date: 23-Aug-10
EARLY WORKS
Page: 22 of 25
© CBI Americas Ltd. 2008. All rights reserved. Contains confidential information proprietary to CB&I, or its affiliates, clients or
suppliers and may not to be used, reproduced or disclosed without CB&I's prior written permission.
Document No.:
190-RP-PR35-0001
SUPERVISORY OPERATING MANUAL Revision: C
UNIT NO.: 190
Date: 23-Aug-10
EARLY WORKS
Page: 23 of 25
© CBI Americas Ltd. 2008. All rights reserved. Contains confidential information proprietary to CB&I, or its affiliates, clients or
suppliers and may not to be used, reproduced or disclosed without CB&I's prior written permission.
Document No.:
190-RP-PR35-0001
SUPERVISORY OPERATING MANUAL Revision: C
UNIT NO.: 190
Date: 23-Aug-10
EARLY WORKS
Page: 24 of 25
Underground Water 10 29 86 95 73
5.6 Safety
Safety
Main safety Risks associated with Dewatering system are:
• Falling: 190-EWO-TK-002 (Sump Tank) is an underground open bottom tank;
precaution should be taken in working close to tank to avoid falls.
• H2S exposure: When working inside the sump tank precautions and adequate
ventilations is required because of the possibility of H2S or other obnoxious gases
presence, as well as lack of sufficient oxygen.
• Electrical shocks: maintenance of electrical system in raw water pond should
be done in accordance to the refinery practices in order to prevent electric shock.
Proper isolation procedures must be following.
© CBI Americas Ltd. 2008. All rights reserved. Contains confidential information proprietary to CB&I, or its affiliates, clients or
suppliers and may not to be used, reproduced or disclosed without CB&I's prior written permission.
Document No.:
190-RP-PR35-0001
SUPERVISORY OPERATING MANUAL Revision: C
UNIT NO.: 190
Date: 23-Aug-10
EARLY WORKS
Page: 25 of 25
6 APPENDIX
190-DG-PR05-0050 REV 0
190-DG-PR05-0051 Rev 2
190-DG-PR05-0052 Rev 3
190-DG-PR05-0053 Rev 0
190-DG-PR05-0054 Rev 0
190-DG-PR05-0056 Rev 0
6.5 Heat and Material Balance
166000-190-CL-PR31-0001 Rev B
6.6 Alarm Summary (to be provided later)
© CBI Americas Ltd. 2008. All rights reserved. Contains confidential information proprietary to CB&I, or its affiliates, clients or
suppliers and may not to be used, reproduced or disclosed without CB&I's prior written permission.