Professional Documents
Culture Documents
PMF-007-INT-004 - 02 Construction Management Plan
PMF-007-INT-004 - 02 Construction Management Plan
Date: dd/mm/yyyy
Version: 1/2/3, etc. <FOR THE PROJECT; NOT FOR THE TEMPLATE>
617920369.docx
Construction Management Plan
Document Control
Document Information
Document History
Approval
Distribution
Name Position
<as identified in Section 11.2> Business Unit Construction Director
<as identified in Section 11.2> NWC Project Manager
<as identified in Section 11.2> Cluster Engineering Manager
<as identified in Section 11.2> Cluster Risk Section Head
<as identified in Section 11.2> Cluster Value Engineering Section Head
<as identified in Section 11.2> Cluster Contracts Administration Section Head
<as identified in Section 11.2> Cluster Cost Control Section Head
<as identified in Section 11.2> Cluster Scheduling Section Head
<as identified in Section 11.2> Cluster Document Control Section Head
<as identified in Section 11.2> Contracts Administration Specialist
<as identified in Section 11.2> Cluster Senior Cost Estimation Engineer
<as identified in Section 11.2> Supervising Consultant <if/when applicable>
617920369.docx 2 of 11
Construction Management Plan
Table of Contents
1 Introduction..............................................................................................................................................5
1.1 Purpose of this Construction Management Plan..............................................................................5
1.2 Site Layout Diagram(s) for this Project.............................................................................................5
2 The Construction Team.............................................................................................................................5
3 Integration Management for this Project.................................................................................................5
3.1 Responsibility for monitoring and controlling of construction work................................................5
3.2 Change Management.......................................................................................................................5
4 Scope Management for this Project.........................................................................................................6
4.1 Construction Work Breakdown Structure (WBS)..............................................................................6
4.2 Formal process for acceptance and handover..................................................................................6
4.3 Controlling the scope........................................................................................................................6
5 Schedule Management for this Construction Project...............................................................................6
5.1 Development of the construction schedule......................................................................................6
5.2 Controlling the construction schedule..............................................................................................6
5.3 Monitoring of progress against the construction schedule..............................................................6
6 Cost Management for this Construction Project.......................................................................................6
6.1 Cost estimating.................................................................................................................................6
6.2 Controlling the construction cost.....................................................................................................7
7 Quality Management for this Construction Project..................................................................................7
7.1 Quality planning of the construction................................................................................................7
7.2 Assuring the quality of construction.................................................................................................7
7.3 Controlling the quality of construction.............................................................................................7
8 Human Resource Management for this Construction Project..................................................................7
8.1 Construction resource planning........................................................................................................7
8.2 Acquisition of the construction team...............................................................................................7
8.3 Special training requirements for this construction project.............................................................8
8.4 Management of the construction team............................................................................................8
9 Communications Management for this Construction Project...................................................................8
9.1 Communications planning................................................................................................................8
9.2 Distribution of information...............................................................................................................8
9.3 Performance reporting.....................................................................................................................8
9.4 Management of stakeholders...........................................................................................................8
617920369.docx 3 of 11
Construction Management Plan
617920369.docx 4 of 11
Construction Management Plan
1 Introduction
1.1 Purpose of this Construction Management Plan
The purpose of this Construction Management Plan (CMP) is to guide the construction team in the
performance of its duties, which are the construction and handover of the project to meet the required
specifications within the approved parameters of the contract budget and time schedule.
The CMP is intended to be concise, clear and consistent with all other contract documentation and terms of
engagement by Second-parties with National Water Company (NWC). The emphasis is upon identifying
policies, strategies and the lines of communication and key interfaces between the various parties involved
in the construction and handover phases of the project.
This CMP was initially prepared by the Contractor’s Project Manager upon his appointment to the project
and describes the general procedures to be adopted by the construction team. It comprises a set of ground
rules for the construction team.
This CMP is not a static document and it is anticipated that changes and amendments will be required in
accordance with the procedures described in the NWC Project Management Plan. Consequently, an
electronic master format will be used to facilitate its distribution and partial update, whenever required.
The Contractor’s Project Manager is the only person authorized to co-ordinate and implement revisions.
This CMP must be updated, as a minimum, at each interim time when there is an approved change
request.
A read-only copy of this CMP, including all pages updated under formal revision, is made available for
access via the Project Site in NWC’s SharePoint system (CONNECT).
<INSERT A HYPERLINK HERE TO THE CONNECT FOLDER CONTAINING THE UP-TO-DATE CMP>
This CMP is to be read in conjunction with the NWC Project Manager’s Project Management Plan (PMP),
reference <Project ID>_PMP.
1.2 Site Layout Diagram(s) for this Project
<INSERT DIAGRAM(S) HERE OR, IF THE DIAGRAM(S) ARE LARGER FORMAT SUCH AS A3 SIZE, THEN ADD THE DIAGRAM(S) AS AN
APPENDIX>
A construction team directory is included as Appendix 15.1 to this CMP, giving full contact details of the
named construction team members, as shown in the above organization chart.
3 Integration Management for this Project
3.1 Responsibility for Monitoring And Controlling Of Construction Work
Refer to Section 6 of the NWC Project Management Plan.
3.2 Change Management
Refer to Section 6 of the NWC Project Management Plan.
3.2.1 Formal Variation Orders
A table of approved change requests is included as Appendix 15.2 to this CMP.
3.2.2 Updated Plans and Schedules
617920369.docx 5 of 11
Construction Management Plan
For all approved change requests, the CMP and the construction schedule shall be updated and re-issued
by the Contractor to record and reflect the change.
The project’s risk and value registers must be reviewed as part of each change request impact analysis, and
must also be updated accordingly for each approved change request. Any modification of the risk and value
actions assigned to the Contractor, as a result of approved change requests, must also be documented in
updates to this CMP.
4 Scope Management for this Project
4.1 Construction Work Breakdown Structure (WBS)
The Construction WBS for this project is included as Appendix 15.3 to this CMP.
The master is held within the Primavera database, under the control of the Cluster Scheduling Section
Head.
The Consultant/Contractor may not make any structural changes to the WBS unless authorized to do so
through an approved Change Request.
4.2 Formal Process For Acceptance And Handover
Refer to Section 7 of the NWC Project Management Plan.
4.3 Controlling The Scope
Ad hoc scope changes will not be allowed at any time during the project’s construction and handover
phases.
4.3.1 Formal Scope Changes
Refer to Section 7 of the NWC Project Management Plan.
4.3.2 Records of Acceptance and Handover
Refer to Section 7 of the NWC Project Management Plan.
5 Schedule Management for this Construction Project
5.1 Development of The Construction Schedule
Refer to Section 8 of the NWC Project Management Plan.
5.2 Controlling the Construction Schedule
Refer to Section 8 of the NWC Project Management Plan.
5.3 Monitoring of Progress Against The Construction Schedule
Progress against the schedule will be monitored at two levels; site level and Cluster level.
5.3.1 Site-Level Progress Monitoring
Refer to Section 8 of the NWC Project Management Plan.
5.3.2 Cluster-Level Validation of Progress Reports
Refer to Section 8 of the NWC Project Management Plan.
6 Cost Management for this Construction Project
6.1 Cost Estimating
Refer to Section 9 of the NWC Project Management Plan.
All project cost estimates will be performed using the standard NWC methodology
617920369.docx 6 of 11
Construction Management Plan
Class 2 cost estimates (design-based rates and quantities) for change requests during construction.
The NWC-agreed methods of measurement and preambles must be used as far as practicable, and the
NWC cost estimate format must be used to build-up and record the estimate.
All cost estimate records shall be submitted to the Project Document Controller for retention in the project
file.
6.2 Controlling the construction cost
6.2.1 Build to the target budget
Refer to Section 9 of the NWC Project Management Plan.
7 Quality Management for this Construction Project
7.1 Quality planning of the construction
Refer to Section 10 of the NWC Project Management Plan.
7.1.1 Internal sources of quality requirements
Refer to Section 10 of the NWC Project Management Plan.
7.1.2 External sources of quality requirements
Refer to Section 10 of the NWC Project Management Plan.
7.2 Assuring the quality of construction
Refer to Section 10 of the NWC Project Management Plan.
7.2.1 Design reviews
Any designs produced by the Contractor must be subjected to formal design reviews, identifying
deliverables under review, scope and purpose of the review, planned date of the review and who shall
participate in the review.
All such reviews must be recorded using checklists and submitted to the Project Document Controller for
logging into the project file.
All change requests arising from such reviews, and at any other time by the project team members or
stakeholders, must also be submitted to the Project Document Controller for logging into the project file
and for impact assessment through the Change Management process (see Section 6 of the NWC Project
Management Plan).
7.3 Controlling the quality of construction
Refer to Section 10 of the NWC Project Management Plan.
7.3.1 Design acceptance
Refer to Section 10 of the NWC Project Management Plan.
7.3.2 Construction work acceptance
Refer to Section 10 of the NWC Project Management Plan.
8 Human Resource Management for this Construction Project
8.1 Construction resource planning
Refer to the ‘Construction Team’ section of this CMP (Section 2). This section includes the Contractor’s
organization chart for the project.
617920369.docx 7 of 11
Construction Management Plan
617920369.docx 8 of 11
Construction Management Plan
617920369.docx 9 of 11
Construction Management Plan
617920369.docx 10 of 11
Construction Management Plan
617920369.docx 11 of 11