Our ref: TAI2-17
The Permanent Secretary for Infrastructure & Transport
lnisry of Infrastructure and Transport
Nasiivaca House
Sena
Suva
‘Attention: Mr, Mikaele Belen
Dear Sir,
Re: Scheme No. TAI2-17:
(Greetings from Energy Fiji Limited ("EFL"),
kindly note the EFL has revised the quotation for the electricity supply to the following fifteen (15) applicants at Nadolodolo
Vilage, Tawa.
1. Laniana Adi 6. Menani Sakure 11, Asaoli Ratulele
2. Penaia Ratu 7. Viliame tseuige 12) Nacanieli Ware
3. Jovls Dolo 8. Joel Satusalu 13. Kamenileni Sau
4. Salanita Rokoca 9 Dentaci Vinca 44) Wateo Davi Blt
5. Villame Ropate 10. Waisea Duwairast 15. Jovesa Rokovall
EFL wishes to advise that the power supply will be made available under the following terms and conditions:
1.0 Cost of Capital Contribution
“The capital contribution to provide power supply tothe one (1) opplicant is $59,486,53(VIP),
EFL require fll payment to process the scheme further. The concept design for this gid extension and breakdown of costs are
provided in Attachment + and, respectively.
7.0 Formal Easement for Power Line Extension Works
‘The proposed route of the power tine extension requires way-leave clearance and therefore it willbe the responsibility of the
ppiteae to prowae tne Tolownng
4. Well-documented easement rights for the permanant placement of EFL's pover poles, lines and stays; and
i. General unconditional consent forthe cuttng/ trimming of trees fram property owners along the proposed raute,
EFL will only commence work on ths scheme once easement rights are obtained and after receipt of payment.
3.0 Consumer Security Deposit & Meter Connection Fees for Supply Connection
In adlition to the above mentioned cost, the applicant will be required to pay the electricity meter connection fee and a consumer
‘oeurty deposit aqal to two (2) monthe aeeeeted energy consumption charges in accordance wih te Tijat Cunpe\k tat dnd
Consumer Commission Determination before the electrical installation in the applicants’ house i Connected to the supply arid,
4.0 Commencement of Work
EFL will prepare a work schedule for this project, considering precedent project activities and resource availability, once payment
ofthe above stated capital cost s made to EFL,
“ve abowe orter 1s vata Yor a perag of tweive (12) months trom the date ofthis etter. EFL reserves the right to review the quote
‘should there be a change in the proposed design arising from circumstances beyond its contol.
Please contact us on telephone 665 6434 or mobile 9 9242 should vou reaulre any further information relating ta this scheme.
Yours faithfully
WA -
asmuih Patel
hier Executive Orticer
Enclosed: Attachment 1; Preliminary Design with scope of work
Attachment 2; Project Cost for the scheme TA12-17,