Professional Documents
Culture Documents
Grouping - Line Efficiency Finnal
Grouping - Line Efficiency Finnal
This sector shows the division of the 7 workstations. The members conducted
line balancing to distribute the task evenly over the work station so that idle time to
man of machine can be minimized. The assigned tasks of every workstation is shown on
the table 10 below.
Operation Cycle Time
Number of
Activity Operation Predecessor Cycle Time per
Operators
(Min) Operator
Measuring and
A --- 12.34 1 39.93
Tracing
B Cutting A 42.13 4 32.375
Shaping and
C B 52.25 3 35.167
Pre-sanding
D Drilling C 11.81 3 35.167
E Assembly D 53.10 4 32.375
F Sanding E 6.77 3 35.167
G Finishing F 20.40 1 39.93
Quality Control
H G 8.97 4 32.375
Inspection
I Packaging H 13.31 3 35.167
221.08
Table 10. Precedence Table for Line Balancing
Time
Operation Idle Time
Workstation Operator Remaining Eligible Task
Assigned (Min.)
(Min.)
I & IV 1 40.91 A,G A,G -
0.98 0.98
II,III,IV, & V 2, 3, & 4 40.91 C, D, F & I C, D, F & I -
5.743 5.743
VII 5, 6, 7, & 8 40.91 B,E & H B,E,G, & H -
8.535 8.535
Table 11. Production Line Balancing
Activity Operation Workstation Number of Idle Time
Assignment Operators (Min.)
A Measuring and I 1 0.98
Tracing
B Cutting VII 4 8.535
C Shaping and Pre- II 3 5.743
sanding
D Drilling III 3 5.743
E Assembly VII 4 8.535
F Sanding IV 3 5.743
G Finishing VI 1 0.98
H Quality Control VII 4 8.535
Inspection
I Packaging V 3 5.743
Table 12. Summary of Production Line Balancing
3 1
3
1 3 3
4