Project: Repairs and Repainting at The Anchorage and The Anchorpoint, MCST 2304
Contractor: SKK
1. We refer to the above inspection. The following are the list of minor outstanding works and/or defects
observed during the joint inspection.
2. Reference layout
Pg 1 / 8
Disclaimer: The observations are made at date and time of inspection. VBF cannot be responsible for alterations made to the contents of this document without its express
consent. This document is confidential and may be privileged. If you are not the intended recipient, please notify the sender immediately. There shall not be any
reproductions in any form of this document for any purpose, or disclosure of its contents to any other person.
3. Observations as below:
Pg 2 / 8
Disclaimer: The observations are made at date and time of inspection. VBF cannot be responsible for alterations made to the contents of this document without its express
consent. This document is confidential and may be privileged. If you are not the intended recipient, please notify the sender immediately. There shall not be any
reproductions in any form of this document for any purpose, or disclosure of its contents to any other person.
S/N 2 17/03/2020 10:48 25/06/2020 10:25
Pg 3 / 8
Disclaimer: The observations are made at date and time of inspection. VBF cannot be responsible for alterations made to the contents of this document without its express
consent. This document is confidential and may be privileged. If you are not the intended recipient, please notify the sender immediately. There shall not be any
reproductions in any form of this document for any purpose, or disclosure of its contents to any other person.
S/N 3 17/03/2020 10:48 25/06/2020 10:25
Element External
plastered
surfaces
Pg 4 / 8
Disclaimer: The observations are made at date and time of inspection. VBF cannot be responsible for alterations made to the contents of this document without its express
consent. This document is confidential and may be privileged. If you are not the intended recipient, please notify the sender immediately. There shall not be any
reproductions in any form of this document for any purpose, or disclosure of its contents to any other person.
S/N 4 17/03/2020 10:48 25/06/2020 10:25
Element Road
demarcations
Description To improve: to
straighten, neat
termination
Pg 5 / 8
Disclaimer: The observations are made at date and time of inspection. VBF cannot be responsible for alterations made to the contents of this document without its express
consent. This document is confidential and may be privileged. If you are not the intended recipient, please notify the sender immediately. There shall not be any
reproductions in any form of this document for any purpose, or disclosure of its contents to any other person.
S/N 5 17/03/2020 10:48 27/08/2020 09:48
Element External
plastered
surfaces
Description To improve: to
provide
reinforcement
mesh and
redecorate over
accordingly
Pg 6 / 8
Disclaimer: The observations are made at date and time of inspection. VBF cannot be responsible for alterations made to the contents of this document without its express
consent. This document is confidential and may be privileged. If you are not the intended recipient, please notify the sender immediately. There shall not be any
reproductions in any form of this document for any purpose, or disclosure of its contents to any other person.
S/N 6 17/03/2020 10:48 10/06/2020 13:15
Element External
plastered
surfaces
Description To prepare
surface and
repaint with
correct paint
system/ 1 more
FC: outstanding
works
Element External
plastered
surfaces
Pg 7 / 8
Disclaimer: The observations are made at date and time of inspection. VBF cannot be responsible for alterations made to the contents of this document without its express
consent. This document is confidential and may be privileged. If you are not the intended recipient, please notify the sender immediately. There shall not be any
reproductions in any form of this document for any purpose, or disclosure of its contents to any other person.
S/N 8 17/03/2020 10:48 25/06/2020 10:25
Element External
plastered
surfaces
Description Leakage
4. Acknowledgement
Before
After
5. End of report.
Pg 8 / 8
Disclaimer: The observations are made at date and time of inspection. VBF cannot be responsible for alterations made to the contents of this document without its express
consent. This document is confidential and may be privileged. If you are not the intended recipient, please notify the sender immediately. There shall not be any
reproductions in any form of this document for any purpose, or disclosure of its contents to any other person.