You are on page 1of 2

ENERGY AUDIT QUESTIONNAIRE

END USER CONTRACT/P.O. NO.


CUSTOMER LOCATION
SITE DATE
EAC PERSONNEL

YES NO
1.0 Motors, Belts, Drives
1.1 Are standard efficiency motors installed?
Are motors running during periods when the equipment or process they are
1.2
driving is idle?
Does the facility utilize DC generator sets to provide variable speed control
1.3
of equipment?
1.4 Does the facility utilize Eddy Current drives for variable speed control?
1.5 Are motors installed that operate continuously at part load?

2.0 Pumps/Fans
2.1 Are pumps or fans installed that are not sized correctly for the task?
2.2 Does the facility have a cooling tower(s)?
2.3 Are pumps or fans being throttled in order to control the flow rate?
2.4 Is bypass control being utilized to vary the flow out of the pump?

3.0 Compressed Air System


Are large compressors serving minimal system needs during off-hours such
3.1 as maintaining the minimum pressure requirements for a Dry Fire
Suppression System?
Does the facility have centrifugal screw compressors that operate at less
3.2
than full load capacity for more than 70 percent of the time?
3.3 Is throttle control used to modulate the compressor output capacity?
3.4 Is turn valve control used?
3.5 Is poppet valve control used?
Does the facility have more than one compressor feeding into a common
3.6 header? Are these compressors operating at less than full output (cfm)
capacity?
3.7 Are compressors operating at zero capacity for extended periods of time?
3.8 Is the discharge pressure of the compressors higher than 110 psig?
Is high-pressure air being used for tasks that do not require high-pressure
3.9
air?
3.10 Does the compressed air system have significant air leaks?
3.11 Does the facility have rotary vane air compressors?
3.12 Does the facility have desiccant air dryers?
3.13 Is the compressor cooling water discharged to the sewer?
Is the pressure drop across auxiliary equipment such as dryers, oil
3.14
separators, or filters excessive?
4.15 Is compressed air the best utility for the given application?
4.16 Does the facility utilize any air nozzles?
3.17 Have the air nozzles been designed for maximum efficiency?
Is the Air Compressor on a Regular Maintenance Schedule? Review
3.18 maintenance logs to verify if the following is being done on a scheduled
basis.
ENERGY AUDIT QUESTIONNAIRE
END USER Therma South, Inc. CONTRACT/P.O. NO.
CUSTOMER Therma South, Inc. LOCATION Brgy. Binugao, Toril, Davao City,
Davao del Sur (TSI Plant)
SITE Brgy. Binugao, Toril, Davao City, Davao DATE 12/6/2021
del Sur
EAC PERSONNEL

Fuel Company Name


Fuel Type Fuel Delivery Units (liters, tons, etc)
Fuel Use (entire facility, area,
Fuel cost / unit
equipment, etc.)
Year 2020-2021 No. of Months 12 First Month April, 2020

Month/Year Monthly Fuel Consumption(L)


Total Cost (Pesos/Liters)
Fuel Delivered Unit 1&2 (Station)
1.April, 2020 164,143.70 (April, 2020) 32.96
2.May, 2020 329,084.20 (May, 2020) 27.17
3. 240,258.80 (June, 2020) 23.66
4. 0 (July, 2020) 23.66
5. August, 2020 0 (August, 2020) 23.67
6. 9,108.10 (September, 2020) 23.67
7. 0 (October, 2020) 23.67
8. 0 (November, 2020) 23.67
9. 102,792.80 (December, 2020) 27.28
10. January, 2021 134,417.71 (January, 2021) 23.67
11. 0 (February, 2021) 24.78
12. 79,419.40 (March, 2021) 24.78
Total 1,059,224.71

You might also like