You are on page 1of 2

AP-52908 WMS REAL VALUES DATA VALIDATION

202
Framework: C2C:G:G-091 Owner Org. code: SGRE ON CRO IN Classification: Restricted
Author: Masilamani, Padmanaban (SGRE ON CRO IN PR
Date: 2020-07-07 Page: 1 of 2
SPM POE)

Project: Client: Date:


Location: Drawing:

Installation Monitor
Parameter Remarks
Status /Recording

COMMUNICATION OK
Commissioning procedures reviewed

Operation and maintenance information

System Completeness

Location of Control Equipments (accessible)

Control panel environmental conditions as per


manufacturer’s guidelines
Ensure that cables in the control room, Racks, to the
cameras are to be properly arranged and dressed.
Ensure that all NSMs, Cameras & Monitors are
properly tagged.
Ensure that all the cables from Camera to the
Network Switch are properly terminated and
clearly tagged.
Ensure that distribution of cameras to Network
Switch is to be done as per approved drawing.
Camera Location by each camera is to be clearly
indicated on the monitor during viewing.
Focusing of the camera to be adjusted by proper
positioning to obtain optimum result/image
Ensure that the camera Enclosure power supply
installed properly
Ensure that Power supply outlets for CCTV system to
be fed by UPS (Optional).
Check the NSMs are connected to the security
network LAN.

Observation: Mention Numeral value for (*) Asterisk marked items

Signature
AYANA/AYANA
Contractor SG-Projects SG-Quality Representative
AP-52908 WMS REAL VALUES DATA VALIDATION
202
Framework: C2C:G:G-091 Owner Org. code: SGRE ON CRO IN Classification: Restricted
Author: Masilamani, Padmanaban (SGRE ON CRO IN PR
Date: 2020-07-07 Page: 2 of 2
SPM POE)

MAJOR CHANGES COMPARED TO LAST REVISION


Date: Change description:
yyyy-mm-dd Initial version
© Siemens Gamesa Renewable Energy, S.A., 2019, All Rights Reserved