You are on page 1of 1

Zamil Process Equipment Company Ltd

Vendor Document Review Sheet

A Approved

B Approved as Noted, Work May Proceed, Re-Submission not required

C Reviewed With comments. Resubmission required, Work may proceed

D Not Approved. Correct & Resubmit.

E For Infromation only

ZAMIL Job No.: ZS-PE-0494-01 to 18; 31 to 36 & 49 to 52 Equipment Name: SCRAPPER LAUNCHER / RECIEVER
Equipment Tag No.: End User: Saudi Arabian Oil Company
Project Name: FIELD GAS COMPRESSION-HARADH (SOUTH) Client: SAIPEM
Sub Vendor: GD Engineering CELEROS Flow Technology PO No.: 12470
Document No.: WPS No.: 2347/131, Rev. 5 & PQR No.: 2019; 2019 S1 & 2019 S2 Document Description: WPS & PQR
ASME B31.8, Ed.2018 &
Construction Code: ASME SEC VIII DIV.1, Ed. 2021 (QOC)
PWHT: NO

Design Data MDMT (°C): -2.2°F (-19°C) Impact: NO (WELD OVERLAY)


Base Material: ASTM A694 F65 Service: SOUR
Other:
02-SAMSS-009 SAES-W-012 ASME SEC II Part A
Reference
02-SAMSS-012 ASME SEC II Part C
Documents:

ZPEC Comments
Document number: WPS # WPS 2347/131, Rev. 5
PQR # PQR 2019, 2019 S1 & 2019 S2

All comments by ZPEC, SAIPEM and ARAMCO CSD are incorporated / Clarified.

Date: 06th December, 2023


Mohammad Mushtaq
Document Reviewed by:
ZPEC-QA/QC
Signature
APPROVAL OF THE PROCEDURE(S) SHALL NOT BE CONSTRUED AS AUTHORITY FOR DEVIATION FROM LISTED SPECIFICATIONS OR REQUIREMENTS OF THE RELEVANT CODES, STANDARDS AND SPECIFICATIONS AND SHALL NOT RELIEVE
THE CONTRACTOR, FABRICATOR OR VENDOR FROM CORRECTING ANY DEVIATIONS.