Section A- MCQ .
4) If during the installation of a pile a large volume of soil is displaced laterally and
upward is called as:
a) Displacement pile
b) Replacement pile
c) Shaft
d) none of the above
8) The joints between the beams and columns are rigidly joined together by welding
the steel or pouring the concrete in situ, and lateral resistance is provided by the
rigid joints. This system in High rise is called as :
a) Shear wall
b) Rigid frame
c) Framed tube structure
d) none of the above
9) This type of high rise is reasonably efficient from 38 - 300 metres (125 - 1,000
feet) in height. Which type?
a) Shear wall
b) Rigid frame
c) Framed tube structure
d) none of the above
11)Piles are also used to resist horizontal loads as in the case of foundation for
retaining walls, bridges,abutments and wharves. These piles are called as :
a) laterally loaded piles.
b) Gravitational piles
c) Batter piles
d) none of the above
Section B-
1) Draw a detailed plan and section of an 3 pile End bearing pile of 200mm diameter with
Reinforcement details.
3) Explain the importance of Seismic Resistant construction and design considerations for
a load bearing structure.
4) Explain in detail the classification of Pile foundation wrt construction method and
materials used.
5) Explain with neat sketches and appropriate dimensions details of the following-
6) Explain in detail how building react to ground motion during earthquake with proper
sketches.
7) Explain in detail the seismic effect on different building components of load bearing
structure.
10) Explain the different structural system for high rise building.
14) Explain in detail the different methods of basement waterproofing also suggest which
method is best for site with high water table.
15) Explain in detail different water drain systems used for basement with proper sketches.