CAESARS PALACE LUXURY VILLA FIT OUT

BLUEWATERS ISLAND
DUBAI, UNITED ARAB EMIRATES

SITE MANPOWER HISTOGRAM

FOR

MEP INSTALLATION

Name Position Date Signature

Prepared by Shinos M Bavu Project Manager 30/AUG/2022

Verified by Shanavas Operations Manager 30/AUG/2022

Main Contractor
Approval

Consultant’s
Approval
SITE MAN POWER HISTOGRAM
Month 1 Month 2 Month 3 Month 4 Month 5 Month 6

TECHNICIANS 6 10 16 16 2 5

HELPERS 3 5 8 8 2 3

TOTAL 9 15 24 24 4 8

24 24

16 16
15

10
9
8 8 8

6
5 5
4
3 3
2 2

MONTH 1 MONTH 2 MONTH 3 MONTH 4 MONTH 5 MONTH 6

TECHNICIANS HELPERS TOTAL

Includes subcontractors and suppliers for special systems (Fire, ELV,IT)