At the beginning of first week internship in the company called Sidama National
regional state water, mine and energy bureau were mainly about submitting and
inscribeing internship entrance letter sent from Hawassa university.
In the following days of the internship, I get a detailed and elaborated explanation of
the company’s vision, objective and a general explanation about the wondogenet
water supply project which I mainly participated in by the company assigned
supervisor Mr.Tesfahun Bayu, who is an office engineer.
These are:-
General steps of planning of water supply scheme
1) Demand analysis.
Population projection
Water demand analysis
2) Source investigation
Surface
Ground
3)Scheme design
Intake structure, Treatment units, Transmission mains, Distribution lines, pump
and generator, Ancillary buildings
4) preparing specifications 5) scheme construction and supervision
6) scheme operation and maintenance
Population projection
Pn= Pp (1 + r) n
Where:- Pn = population at the target year. Pp= present population
Source selection
Ground:- must be adequate to cover the maximum day mater demand for stage 1
The project's source is a ground water source(deep well), so the next thing I learned is about
basic pump design preoaration.
Basic pump design preparation.
Calculation of velocity
o The calculated velocity must be between 1 and 2 m/sec to avoid incrustation and
corrosion bursting of pipe. V = Q/A
Finally:-
Discharge (l/sec)
Benefit I gained
Challenges
Transportation problem
All the workers are always busy since the project is huge and vast. Due to this reason they
did not give enough time for the interns to treat efficiently.