DESIGN, MANUFACTURING, SUPPLY, INSTALLATION,

CONSTRUCTION & COMMISSIONING OF BQPS RLNG SPUR


PIPELINE PROJECT

DOCUMENT TITLE:
DATA SHEET FOR METERING SKIDS

Doc. #: 15-501-EP-DS-001

Rev. 1

CLIENT: K-Electric

1 21-Dec-20 Re-Issued for Construction AK IUR MSK


1B 22-Oct-20 Issued for Approval AK IUR MSK
1A 13-Oct-20 Issued for Review AK IUR MSK
Rev. Date Description Prepared By Checked By Approved By

GASCO Engineering Private Limited


501, Amber Estate Building, Shahra-e-Faisal, Karachi, pakistan
Email: info@gascoengineering.com.pk : T: +92 21 3432 0635-36 & 3432 0770 - 71
Document. No. 15-501-EP-DS-001
Rev.1
DATA SHEET FOR RLNG METERING SKID Date: 22-Oct-2020
Made by: AK
Client: K-Electric Limited PFD No 15-501-PFD-001
Project: RLNG SPUR PIPELINE P&ID No. 15-501-PID-002
Plant: Bin Qasim Power Station-I No. Req. 1

1 Process Conditions Requirements Remarks

2 Designation RLNG Metering Skid

3 Type Ultrasonic

4 Fluid Hydrocarbon

5 Phase Vapor

6 Design Flow Rate (MMSCFD) 250 (2 x 100%) Note-1


One (01) Operating One (01)
7 Operating Philosphy Standby

8 Operating Flow (MMSCFD) (Max./Nor./Min.) 250/ 150 / 09

9 HC Liquid Nil

10 Water Liquid Nil

11 Inlet pressure @ metering Pressure (barg) (Max/Min) 90 / 66

12 Allowable pressure drop accros metering (bar) 0.7

13 Design Pressure (barg) 100

14 Inlet Gas Temperature (oC) 5-38

15 Design Temperature (oC) 0oC / 60oC

16 Mol. Weight 19.34

17 Compressibility (z) 0.684

18 Cp/Cv 2.052

19 Viscosity (Cp) 0.0145

20 Line Size (Inlet/Outlet) 14"/14"

21 Metallurgy Carbon steel

22 Rating & Facing 600#RF

23 Inlet Gas Composition (Range) (Mol %)


24 Nitrogen 0.7 0.2
25 Methane (CH4) 81.52 99.7
26 Ethane (C2H6) 13.39 0.1
27 Propane (C3H8) 3.7 0
28 i-Butane (i-C4H10) 0.7 0
29 Total 100 100
30
Notes:
1. Vendor to Provide (2 X 100%) flow metering run including Ultrasonic type flow meter.
2. Vendor to refer flow metering specification given (15-501-EI-SP-002) to develop metering skid package.
.