PRAN Industrial Park

Bagpara, Palash, Narsingdi


BOQ of 11 KV-3x93 meter line Underground project

S/L Name of Item Qty Unit Price/Unit-TK Total Price-TK


1 11KV Ht Channel 6 Feet Hot Deep Galvanized 12 Set 4700 56,400
2 11KV Disc Insulator 36 Pcs 750 27,000
3 Poll Band Clamp Hot Deep Galvanized all Size 60 Pcs 280 16,800
4 Tension clamp Hot Deep Galvanized 18 Set 1200 21,600
5 Cable Termination Kit (18 pcs) 6 Set 5500 33,000
6 Cable Stand 6 Set 2200 13,200
7 Gay Set Complete Hot Deep Galvanized 4 Set 3500 14,000
8 Barrage Angle 24 Pcs 1700 40,800
9 Nut & Bolt 10/11/12 Hot Deep Galvanized 24 Pcs 150 3,600
10 Nut & Bolt 3/4 inch 100 Pcs 60 6,000
11 Poll Band Cable Clamp 13/14/15/16 18 Pair 500 9,000
12 3x300 RM Cable Laying 300 Meter 310 93,000
13 Overhead line Service work 1 Set 65000 65,000
Totall 399,400

S/L Name of Item Qty Unit Price/Unit-TK Total Price-TK


1 11KV Armoured Cable-Cu-3x95 RM-1 RUN 93 Meter 6372 592,596
2 11KV Armoured Cable-Cu-3x150 RM-2 RUN 186 Meter 9000 1,674,000
Total 2,266,596
Grand Total Cost: 2,665,996
Notes: All Prices are considered with present market price. It may change anytime.