Name: Bokhari Syed Asad Abbas ID: 22212463

Fill out the blanks in the table

Expected Immediate Early Late Critical


Activity Time Predecessors Finish Finish Slack Path?

A 5 Days -- 1-Sep 5-Sep 0  

B 3 Days A 2-Sep 5-Sep 0  

C 4 Days A 5-Sep 9-Sep 0  

D 6 Days C 7-Sep 13-Sep 0  

E 4 Days B, C 11-Sep 15-Sep 0  

F 1 Day D 16-Sep 17-Sep 2.5  

G 5 Days D, E, F 17-Sep 22-Sep 0  

Show the critical path

1-Sep 5-Sep 10-Sep 14-Sep 17-Sep


 
 
 
 

 
 

 
Draw a network diagram for the activities

Requirements Collection Report Design


Star 1 Sep 2022 ID: A Star 5 Sep 2022 ID: C
Finish 5 Sep 2022 Dur 5-Days Finish 9 Sep 2022 Dur 4-Days
Res: Res:

Screen Design Database Design Progamming


Star 2 Sep 2022 ID: B Star 7 Sep 2022 ID: D Star 16 Sep 2022 ID: F
Finish 5 Sep 2022 Dur 3-Days Finish 13 Sep 2022 Dur 6-Days Finish 17 Sep 2022 Dur 1-Day
Res: Res: Res:

User Documentation Testing


Star 11 Sep 2022 ID: E Star 17 Sep 2022 ID: G
Finish 15 Sep 2022 Dur 4- Finish 22 Sep 2022 Dur 5-
Days Days
Res: Res:

Installation
Star 22 Sep 2022 ID: G
Finish 22 Sep 2022 Dur 1-Day
Res: