Client: Project Title: Contractor:

EOM Media Liveability Assets


PMC: Doc. Title: Doc. No: 14-371600-
Checklist (CL) – for Installation Testing and 4800000496-BEI-FPR-ITPCL-
Commissioning of Fire Fighting System 000001
Rev.
Date : 03 November, 2022
02

ITP Ref No.: 14-371600-4800000496-BEI-FPR-ITP-000001_02


S/N Acceptance Criteria References Yes No N/A Remarks
A Checks for documents
1 Is Shop drawing(s) approved? NEOM Specs Sec
210500, Clause
2 Is Material submittal(s) approved? 1.5
3 Is Materials delivery inspection approved?
4 Is Relevant material Test Certificates available?
B Checks for Material delivered
1 Any Physical damage found?
2 Storage location of material OKAY?
NEOM Specs Section
3
Is the material conforming to the approved material 210500 Clause 1.5
submittal?
4 Material acceptance test required?
5 Material acceptance test done?
c Checks for Pre-execution Prerequisites
NEOM Specs
1 Is the area of work ready and no obstruction Section 210500
Clause 1.8
2 Coordination with other trades initiated?
4 Survey marking required?
5 Survey Marking done?
D Checks for Execution /Installations
1 Installation of Hangers and Supports
2 Anchor okay?
3 Alignment okay? NEOM Spec. Sec
4 Route as per approved drawing? 210500 clause 3.1

5 Dimensions and sloping okay?


6 Final Installation of Hangers and Supports Accepted?
2 Pipe Installation and Couplings
1 Supports okay? NEOM Spec. Sec
2 Alignment okay? 210500 Clause 3.4
3 Route as per approved drawing?
4 Final Installation of Piping System Accepted?
3 Fusion Welding
1 Welding machine okay?
2 Welder Certified? NEOM Spec. Sec
210500,
3 Welding Procedure Approved? Clause 1.16
4 Welding setup okay?
5 Welding parameters corrects?
6 General Welding Accepted?
4 Placement of Warning Tapes
1 Tape approved? NEOM Specs
Section 210500
2 Placement, okay? Clause 3.7
5 Installation of Valves, Gauges, Flow Meters, Pneumatics, Etc…
1 Valves installed correctly and as per approved drawing? NEOM Specs
2 Gauges installed correctly and as per approved drawing? 210523
Section 3.1
Flow meters installed correctly and as per approved
3
drawing?
4 Other meters installed correctly and as per approved

QMS-BEC.COR.P.09-CL-FORM-Rev.00 Page 1 of 1
Client: Project Title: Contractor:
EOM Media Liveability Assets
PMC: Doc. Title: Doc. No: 14-371600-
Checklist (CL) – for Installation Testing and 4800000496-BEI-FPR-ITPCL-
Commissioning of Fire Fighting System 000001
Rev.
Date : 03 November, 2022
02

drawing?
Others Pneumatics installed correctly and as per approved
5
drawing?
Inline services installed correctly and as per approved
6
drawing?
6 Installation of Fire Hose Reel Cabinet
1 Installed as per approved shop drawings?
2 Anchored and bolted correctly?
NEOM Specs
3 In and Out pipes connected correctly? 211313
4 Equipment properly aligned? Section 3.1
5 Other requirements /accessories installation acceptable?
6 Final and general Installation acceptable?
7 Installation /Placement of Fire Extinguishers
TesInstalled as per approved shop drawings?t done as per
1
Applicable code? NEOM Specs
2 Anchored and bolted correctly? 210000
Section 3.1,
3 Equipment in good condition?
4 Equipment properly aligned?
5 Other requirements /accessories installation acceptable?
6 Final and general Installation acceptable?
8 Installation of Fire Hydrant
1 Installed as per approved shop drawings? NEOM Specs
210000
2 Anchored and bolted correctly? Section 3.1,
3 Equipment in good condition?
4 Equipment properly aligned?
Other requirements /accessories installation
5
acceptable?
6 Final and general Installation acceptable?
9 Installation of Pump and Skid
1 Installed as per approved shop drawings? NEOM Specs
210523
2 Anchored and bolted correctly? Section 3.1
3 In and Out pipes connected correctly?
4 Equipment properly aligned?
10 Touch-up Painting
1 Touch-up Painting Required? NEOM Specs Sec
017300 clause 3.12
2 Touch-up Panting Done?
3 Touch-up Painting Acceptable?
11 Installation of Labels and Tags
1 Labels Required? NEOM Specs
Section
2 Labels Placed at the appropriate position? 330526.
3 Final Labels Placement Acceptable?
E Checks for Testing
1 Pipe Flushing NEOM Specs
211313
1 Test equipment setup correctly? Section 3.2
2 Test done as per Applicable code?
3 Test Sample acceptable?
QMS-BEC.COR.P.09-CL-FORM-Rev.00 Page 2 of 1
Client: Project Title: Contractor:
EOM Media Liveability Assets
PMC: Doc. Title: Doc. No: 14-371600-
Checklist (CL) – for Installation Testing and 4800000496-BEI-FPR-ITPCL-
Commissioning of Fire Fighting System 000001
Rev.
Date : 03 November, 2022
02

4 Test report acceptable?


2 Hydrostatic Test NEOM Specs
211313
1 Test equipment setup correctly? Section 1.5
2 Test done as per Applicable code?
3 Test Parameters complying with specification?
4 Test report acceptable?
Functional Test For Fire Hydrant and Hose
3
Reel Cabinet
1 Test equipment setup correctly? NEOM Specs
211200
2 Test done as per Applicable code? Clause 3.1
3 Test Parameters complying with specification
4 Test report acceptable
4 Functional Test For Sprinklers
1 Test equipment setup correctly NEOM Specs
210500 Clause
2 Test done as per Applicable code? 3.14 NEOM Specs
3 Test Parameters complying with specification? 211313 Clause
3.11-3.18
4 Test report acceptable

Sub-contractor BEC Site Engineer BEC QA /QC Engineer NEOM ETSD


Name: Name: Name: Name:
Sign: Sign: Sign: Sign:

Date: Date: Date: Date:

QMS-BEC.COR.P.09-CL-FORM-Rev.00 Page 3 of 1