Professional Documents
Culture Documents
TO THE TRAINING
OF SUPERVISORS
FOR LABOUR-BASED ROAD CONSTRUCTION
AND MAINTENANCE
TRAINEES MANUAL/PART 2
II II II I I I I I II I II
46992
Copyright © International Labour Organisation 1981
This book enjoys copyright under PrOtocol 2 of the Universal Copyright Convention.
Purchasers may nevertheless freely photocopy the learning text for trainees for exclusive use wtthin their company or
training institute. However, no portion of this book may be reproduced for resale or mass publication without the
express consent in writing of the 11.0.
No part of thiswork may be stored in a retrieval system ortransmitted in anyform orby any means ortranslated without
the prior authorisation of the Editorial and Translation Branch, International Labour Office, Cl-I-1211 Geneva 22,
Switzerland, to which all enquiries should be addressed. _______
ILO publications can be obtained through major booksellers or ILO local offices in many countries, or direct from ILO
Publications, International Labour Office, CH-1211 Geneva 22, Switzerland. A catalogue or list ofnew publications will
be sent free of charge from the above address.
Printed in Switzerlend
PREFACE
This Guide has been produced for use in the general and
technical training of supervisors for road construction and
maintenance programmes. It is basically in two parts, an
instructors manual and a trainees manual. The former contains
information and advice for instructors on how to plan, design
and implement a training course. The latter provides the detailed
training material for the trainees. In its present form the
trainees manual is incomplete in that it is not country specific.
Thus, such aspects as project organisation and administration,
programme objectives and design standards will vary from country
to country. The instructor, therefore, uses the general modules
presented and adapts them to the specific circumstances of the
country.
I
Acknowledgements
Oontent s
S
SURVEYING AND T-O Nodule learning objectives and content
SETTING OUT: T-1 Survey of proposed alignments
LE-2 Instruments and aide for setting out
LE-3 Setting out of horizontal alignments
LE-4 Setting out of vertical alignments
LE-5 Setting out of cross-sections,
including cuts and fills
LE-6 Hairpin bends
TT-7 Setting out of tasks
LE-8 Nodule summary and checkpoint
C]2ARING: LE-O Nodule learning objectives and content
TE-1 Nature and definition of site clearing
T1-2 Bush clearing
LE-3 Tree and stump removal
LE-4 Grubbing
11-5 Boulder removal
1,T-6 Module summary and checkpoint
EARTHWORKS: L-O Module learning objectives and, content
T-1 Nature, definition and type of earthworks
LE-2 Measuring volumes
LE-3 Excavation
T1-4 Loading, hauling and unloading
12-5 Pill (spreading, compaction, erosion
protection)
LE-6 Nodule summary and checkpoint
Drainage
S
MODULE DRAINAGE M-1O
MODULE CONTENT
LE-l/2
nft /
8uc4uce. wcckr seeçi
cIouJr
t.
we
4 t
-o u(10
9roUv%d waer
S
It is therefore very important to have a good drainage system
which allows for the water to flow off the road and away from it as
quickly as possible. Such a system consists of several components:
- roa surface drainage which makes the water flow off the road
surface;
- side drains and mitre drains which lead the water away;
LE -1/5
- culverts which will lead the water in the side drains under the
road to the other side;
S
RO.AD SURFACE DRAINAGE (O.AMBER)
CL i- xwewenr
roc4 4x*
caber .o I Camber
or t - 7;(
":
>1
rcxia 4oiw'Ian
S
LE - 2/2
S
Exceptions
- c ouck
Mie c.uue..
S
M-1O
LE - 2/3
Construction of camber
The camber is formed by spreading the soil which has been heaped
along the centre-line during the ditching and sloping process towards
the sides of the road. Naturally, the quantity of soil along the
centre-line should be sufficient for the camber to be formed to the
correct angle (7 per cent before compaction/settling, which is
equivalent to approximately 5 per cent when settled).
7', to°e
S
MODULE DRAI NAGE M-lO
SIDE DRAINS
The function of the side drains (or ditches) is to collect the
water from the carriage way and surrounding areas. When they are
excavated the outcoming material serves to form the very important
road surface drain, the camber.
The size of the side ditches must therefore be sufficient to
cope with the run-off water. The outcomning material should be
sufficient to provide a compacted camber of 5 per cent. When a road
with 4 1/2 m formation width is to be provided with a 5 per cent
compacted camber (7 per cent loose) the size of the ditch should be
as shown in figure 6 (area = 0.16 + 0.2 = 0.36 m2).
eCCCLUC4MOV 4cs O
C.L
L
I-lO
L -3/2
Then there axe ditches on bo1h sides of the road the depth of each
side ditch can be reduced to Q.3 in. The soil from the first ditch
can partly serve to raise the elevation of the carriage way.
$r -I-
/
-
, - - -.
-N
-. i::
4.
-. ?)t.t'
LE - 3/3
S
c8
Vch flea 4o cev4re t
Shoue(
The reason for excavating the ditch in this manner and shape is
that it is easier to measure and control than a traditional V-shaped
ditch made in one operation.
The correct width and depth is controlled with a stick which has
been cut to correct length. Each worker who works on drainage should
have his own stick.
N-lO
LE-3/4
Mitre drains
The mitre drains (or off-shoot drains) lead away the water from
the sid.e ditches to lower areas.
12 4O
10 80
8 120 if exceeded
scouring 20 to 50 wherever possible
6 160
will occur onto a boundary
4 2OO
if exceeded
1-2 50 silting
will occur
Remember that these are maximum distances; the quicker the water
is led off the road, the less d.mage (either from scouring or silting)
will occur. lNherever possible, the discharged water from the mitre
drains should be channelled to land boundaries in order to avoid
damage to farm land. The sail coming out when the mitre drain is
excavated should be deposited. on the downhill side of the drain.
Also the mitre drains should have a minimum gradient of 2 per cent.
MODULE DRAINAGE M-lO
S
N-lO
11E - 4/2
1te4 -k an epibaykmev-
dimev1Liov cj' ix
or6.tni ruicerYeV%
Scour checks
Where longitudinal gradients are steep the water gains high
speed. Therefore, if no protective measures are taken, scouring is
likely to occur. The simplest way of dealing with scouring, apart
from reducing the volume of water by leading it off the road at
frequent intervals (mitre drains) is to reduce the velocity of the
water by building scour cheks, in the ditches.
The scour checks hold back the silt carried by the water flow
and provide a series of stretches with gentle gradients interrupted
by small "waterfalls".
Scour checks are usually constructed in natural stone or with
wooden stakes (figure 12). Masonry, or concrete scour checks can
also be constructed (figure ii) but are often uxinecessarily expensive.
H-b
S LE -4/3
12 5
10 10
8 15
6 40
S 4 ) .
not required!
2
S
M-lO
LE -4/4
S
/
\3Je ke &ks
MODULE DR.PJ NAG-E M-lO
.4
LE-5/2
Culvert rin
The rings are usually of concrete and can be manufactured in the
field. The most common diameter is 60 cm (24") but also 90 cm (36")
is frequently used. Smaller diameters than 60 cm are difficult to
maintain and are easily blocked The joints between the rings should
not be cemented but covered with a strip of tarpaper.
Depending on the circumstances, instead of using large diameters
which recluire a high fill over the pipes (overfill), two or more rows
of a smaller dimension can be used. The spacing between the rows
should be at least one diameter of the rings and, one row could be
placed lower than the others to accommodate small flows without
silting.
14
'
ooeFt ci&meer
Oulvet bed
The culvert bed. has to be stable and at the correct level.
Remove stones which might da3rlage the pipes. If the natural material
s not suitable, a bed of gravel should be made.
The bed should be constructed to the correct gradient (igure 13).
A string, spirit level and folding ruler or measure tape can be used
(1VI7) to set out the right gradient.
S________
The purpose of the hea.dwall is to support the road embankment
and. protect it from water damage. Headwalls should always be built
parallel to th? centre-line of the road in order to take the pressure
from the traffic evenly. They can be built in handpacked stones,
masonry or concrete. It is not always necessary to make headwalls
end. instructions to build them should come from the engineer who
also would design them and specify materials.
Eackf ill
The backfill around. the pipes has to be well compacted and
should be made of gravel, sand or other suitable material (not
expanding soils like "black cotton"). The backfill has to be well
compacted, using han.d-rainmners and watering. The minimum compacted
thickness of the layer on top of the pipe, the overfill, .shoald not
be less than three-quarters of the diameter of the pipe.
ents
The gradient of a culvert depends on the terrain situation but
to prevent silting up and erosion the gradient should normally be
kept within 3 and 5 per cent.
M-lO
LE-5/4
12 40 After 40 in every 5 in
10 80 " 80m " lOin
8 120 120 m "
" 15 in
6 160 t?
l6Om " 40m
4 200 Not required
2 240 Not required (max. interval)
DESCRIPTION AD FIJNCTION
The function of water-table drainage is:
to intercept, collect and lead away any flow of subsurface
water in the subgrade of the road;
The design of these will vary from case to case, and it is the
ob of an engineer to design various types of water-table drainage.
LE-6/2
S
16
7. .z.,.
wci.4er' 4nbte.
'7
vI_]O
LE -6 / 3
Frech drains
To diain water pockets French dxains can be constructed.
18
NODULE DRAINACE
SU1V]M.ARY
LE -7 / 2
PRO BLENS
erosion of the road surface along the road and erosion in the
ditches;
erosion of a side cut;
blockage of a culvert.
S MODULE OiICKPOINT
Indicate True (T) or False (F) in the blank.
.nswer br4:
1hy is the drainage system so important?
LE -7/3
0 0
. QUIS FOR
When doing the initial survey for
the road, remember the question
of drainage.
strings between the pegs
Then you set out the ditch and slope, tie
to clearly mark the sides of the ditch.
something in a
Always explain to the workers wh they have to do
particular way, e0g. the camber and
why it is so important that it is
correct.
at the first rains
Remember to observe how the drains work
inadecluacies immediately.
followilig their completion and correct any
FIELD INSTRUCTIONS M-lO
DRPJNAGE
Remember that:
- scour checks will protect the drainage system and the embank-.
ments against erosion;
Method
Oontrol
Before approving the work, ensure that the answer to the following
questions is tye5I:
Tools
For excavation: hoe, forked hoe, mattock, fork, spade, pickaxe and
shovel.
For setting out and control: strings, pegs, measuring tape and
measuring sticks.
FIELD INSTRUCTIONS M-lO
Nethod
- Calculate the volume to be excavated by multiplying the area of
the triangular section by the length to be covered during
the day.
- Set out the width of th.e slope with pegs and strings, i.e. a
string parallel to th,e excavated trench.
C ontrol
- is the surface between the string and the bottom of the slope
straight and without a "hump"?
Tools
S
FIELD INSTRUCTIONS M-lO
CAMBER FORMA.TION
Method
- Calculate the volume to be spread by adding the volumes for the
ditching and sloping over the distance in cluestion.
Control
Before the camber fomation can start:
Tools
SCOUR CHECKS
Scour checks reduce the speed of water in the ditches and thus
reduce the scouring. They should be provided whenever the gradient
of the side drain is greater than 6 per cent. Some soils erode
more easily than others and on such, soils scour checks might be
necessary even at lower gradients. (You can see this when inspect-
ing th.e road after the first rains.)
Method
- When the side drain has been excavated, measure the gradient
with, a dumpy level, abney level or a measuring tape/spirit-
level.
- Find the scour check interval from the learning text table;
the steeper the gradient, the shorter the distance between
the scour checks.
- Deepen and widen the ditch at the place of the scour check
to be able to properly place and secure the boulders or
stakes used to construct the check.
- When stakes are used, they should be driven deep into the
ground and supported with stones on th,e lower side.
Control
- Ensure that the scour checks have been placed at the correct
intervals and that they are properly constructed.
FIELD INSTRUCTIONS M-lO
LAYING CULVERTS
Method
- Set out the position of the culvert lines on the lowest points
in the alignment and on additional places as required.
- Lower the pipes with ropes and place them in the correct
position.
- Cover the joints with tar paper, backfill and compact in thin
layers; add water if necessary to obtain proper compaction; the
layers of backfill should not be thicker than 15 cm.
Control
- Before starting the work on the trench:
- is the outlet or mitre drain ready?
- are the rings on site and undamaged?
- Before laying the rings:
- is the gradient of the bed correct (3-5 per cent)?
- is the bed properly shaped and compacted?
S Before approving the total work:
- is the backfill properly done?
- iS the compaction satisfactory?
- are both inlets and outlets cleared?
Tools
- For excavation: hoes, forked hoes, mattocks, forks, pickaxes
and shovels.
- For lowering rings: strong ropes, car tyres as "cushions".
- For properly placing the rings: wooden stakes (not crowbars).
- For compaction: hand-rainniers.
- For setting out and control: strings, straight-edge board,
spirit-level, tape measure.
S
Module 11
Soil mechanics
S NODULE SOIL IVIECHANICS
MODULE CONTENT
GENERAL
LE-l/2
Road construction
There are many different types of soil and some are not
suitable for road construction. Before starting to build a
road it is therefore important to find out which kinds of soil
there are along the planned alignment. By taking samples of
the soil and examining them, one can find the places which would
cause problems, e.g. areas with black cotton soil or loose sand.
If the road cannot be taken around such areas of difficult
soil, it is sometimes possible to improve the behaviour of the
soil. Some ways of doing this are: (i) mixing it with another
type of soil, (ii) adding chemicals to it, and (iii) providing a
surface layer.
A knowledge of soil mechanics will help you, in judging what
to do in different circumstances.
MODULE SOIL MECHANICS
S
0
1-P
o 0 0 0
-P
00
.z
0
-P 4- rd 0
t
02
-P
0(13
-P
0-P0
P r1 H -P
+O-
' r-I r4 (1)
r4 -1
r0H4
,(1-P
O-PH
J>
HHrd
O.-1c130
H-P'd 02
02
r-4HU r1OH
r4
r4r0r14
(13OC13
rO0(13
02C13H 02
0+ P00 r0 + (I) Q) + P-i P 02
0P
(1)
0-P-P
00202 00202
c13 02P..O
0402.r4
0r1O oo00E-
-IO2 0
002Or-I.PPi
44
0 r-I
r4 rd
0 H (1) .
t/2
02
H
. -P
-P r-1
bU
-1 H H
ci2 C12
0
I -P
0
r1 r4
rd
OH r-4 rI0 (DO S
I -P
C12P 0 0 bJJ r-1
C13r4
HO 0 0 HO02 r4
P-1r1 c,-P
02
H
0 0(0 (1)
jrd -P
02 ((1 r-I
0 02 P.i1 b0 02
P-iO) -Ir-1
0
0 0 OH 00
02 -i r }- rj '
0
(1)
P4
0
-I
H rdH
02
d
13 CD
rd
c-i
02
0102
P 0rd
4c-'o p02-PP
C'J
02
jC\J0-D 0
0 00
1S
r1
02
r-1
C'J 0000 S S
0
H
0'oN o
0o
c13
-I
4
(13 0 C\100 0 0
0 0
r4 02 02
02 Pr4Q)
H O rrJcrd
00r{ -P
(13 0 H (13
p C13O-1 H H
0
CH C12 ti
M-ll
LE-2/4
Jji&.joy
TiE- 2/5
The above tests have shown how you can determine the proportions
of coarse and fine particles and define whether silt or clay is
present. We will now discuSs three tests designed to define the
clay and silt proportions within the fines fraction of the soil.
Moulding. test
Drying test
Fill a matchbox with a moistened sample and allow the sample
to dry out.
S c's do
Figure 4 shows that clay after drying out will have shrunk and
cracked. Silt will not shrink, but tends to crumble after it has
dried.
As we have said before, many soils are mixtures of various
fractions. This means that the results of the tests described
above can only provide indications as to the behaviour which can
be expected from these soils. Laboratory tests will always be
necessary when a detailed soil classification is re uired.
To suminarise the above tests, it can be said that:
Table 2 shows how you can describe different soils after testing.
S
Table 2: Recognition of soils
ci)
----p
-1
H
U) -1 O r-I
rd
',-. ..-
r-{
1r4rd
4
0 F-
cci
H i0 p0-P
l:i
ci)Cl)cl)
r
0 -p
000
Cl)
H Pr°
H ccicci'-
H
0
Cl)
r1
cci
00
MODULE SOIL MECHANICS M-ll
After you have learned this element you should be able to:
S
of the hard. stones will provide a stronger surface. The gravel
will behave better if the stones in the mixture are of various
sizes tiwell graded", so that the voids in between the particles
are filled. Angular-shaped particles are preferable, because
they will "lock" together better than round particles.
Pure clay and silts, mixtures of silt and. clay, and organic
soils are generally unsuitable for surface layers.
The stony particles to be used in a surface layer should not
be bigger than 3 cm in order to obtain a reasonably smooth finish.
Bigger particles should be crushed by hand or by roller.
(2) compaction.
(3) when the right amount (10-25 per cent) of clayey material is
present the stone and sand particles will be glued together
by the cohesive qualities of the clay. Twenty-five per cent.
clay should be the maximum allowed; a lower proportion is
desirable;
(4) the large particles within the soil will form a skeleton.
When a load is applied to the soil, the resulting friction
between the particles will contribute much to its stability.
When a soil does not have the qualities described above the
soil composition can sometimes be improved by adding the missing
components. For example, in dry desert areas, much can be done
to improve the running surface of sand roads if clayey soil is
mixed with the sand. In wet areas with a lot of clayey soil,
the road can be improved by mixing in gravel or even decomposing
rock or other material which contains a substantial proportion of
hard angular particles.
To determine the best mix, the following test can be carried
out:
LE-4/ 3
S
Compaction
Compaction is used to pack the soil particles closer to ether,
so that a more dense and stable soil results.
A volume of soil is composed of three components - solid soil
particles, water and air. Air does not contribute to the strength
and stability of the soil but, on the contrary, reduces its stability
by allowing water movement within the soil. A certain optimum
quantity of water (which is different for each soil type and varies
usually between 8 and 20 per cent) simplifies the compaction and
contributes to the soil's strength and stability, because it lubricates
soils is
The important advantage of cement/lime-stabilised
that they have a high strength in both dry and wet conditions.
The proportion of cement or lime required normally ranges between
of the dry soil. While cement can be
3 and 7 per cent by weight
used to stabilise both plastic (clay containing) and non-plastic
soils, the presence of clay minerals is necessary when lime is
used as the stabiliser.
When the thickness of the layer to be stabilised is known,
the volume per square metre can be calculated. For example, when
a 20 cm layer is to be stabilised, this means a volume of
0.2 x 1 x l=O.2m3 per square metre. The density of the dry soil
can be determined in a laboratory test. For example, if this
density is 1,000 kg/m3 this means that the weight of the layer
per square metre is 200 kg. With a cement proportion of 5 per
cent, this mean that 10 kg per square metre are required (one bag
per 5 square metres).
MODULE SOIL IVIECHANICS M-ll
After you have learned this element you should be able to:
SLThIMY
PRO BLEMS
LE-6/3
MODULE OEIEOKPOINT
Answer briefly:
What is the meaning of the word "well graded" in soil
mechanics?
Remember that:
COIVIPACTI ON
Remember that:
Concrete technology
MODULE CONCRETE TECHNO 10 GY M-12
MODULE CONTENT
LE-3 Aggregate
After you have learned this element you should be able to:
CEMENT D PROPERTIES
Cement is made from a mixture of lime-based material and clayey
material. Cement and water react chemically. This chemical action
causes the water-cement paste to harden and to become a solid mass.
As discussed in LE-1, we make use of this property of cement to bind
aggregate, sand and cement particles together to obtain concrete.
The very fine cement particles also fill the smallest empty spaces,
thereby giving the concrete its density and impermeability. It is
understandable therefore that within certain limits, concrete becomes
stronger when more cement is used.
However, cement is the most costly of the materials required to
make concrete. This implies that in order to minimise the costs of
the concrete, ±he amount of cement used will depend on the purpose
for which the concrete is required.
Concrete used for culvert beds and foundations needs less cement
than concrete used in reinforced bridgedecks. Table 1 shows the
cement proportion (kg/m3) in various types of concrete.
M-12
LE - 2/2
S
Table 1: Cement required for 1 ill5 of finished concrete
mn cm
S
MODULE CONCRETE TECHNDLOG-Y M-l2
LE-3/2
?Ioreover, the
aggregate increases the workability of the mix.
and water
particles have a smaller surface area so tha.t less cement
axe needed to obtain the required strengths.
However, a well graded, well compacted concrete mix with
concrete,
angular aggregate particles also produces an excellent
strong "skeleton".
because the particles "lock" together to form a
If the aggregate contains a large percentage of flat saucer-
shaped particles it should be rejected as far more cement and water
would be reciuired to obtain acceptable results.
Learning
Element
CONCRETE TECI]NOLOGY
LE-4/l
After you have learned this element, you should be able to:
12-4/2
YOU SHOULD REMEMBER THM THE ABOVE TABLE PROVIDES RULES OF THUMB ONLY.
M-12
LE-4/3
S
If a very high quality concrete is required, laboratory tests
must be carried out in order to determine the optimum granulometric
composition of each aggregate, i.e. what are the best proportions pf
particles of different sizes in a particular type of aggregate.
Remember that the volumes of cement and sand can vary with the
degree they are compacted! In addition, the volume of sand varies
with its moisture content. For example, the volume of one kilogramme
of sand increases by 15-50 per cent if the water content is increased
by 3-12 per cent. For these reasons, volumetric proportioning as
shown in table 2 is never used when big quantities of high quality
concrete must be produced. In this case, the materials are weighed
S and. the moisture content is measured, so that the exact quantities of
the different components (gravel, sand, cement and water) can be
determined. For most concrete works carried out on rural roads,
however, the above rules of thumb can be applied.
Water/cement ratio
5 cement ratio between 0.5 and 0.65) but great care should be taken not
to use too much water. The wetter the mix, the weaker the finished
concrete
Remember that the volumes of cement and sand can vary with the
degree they are compactedi In addition, the volume of sand varies
with its moisture content, For example, the volume of one kilogramme
of sand increases by 15-50 per cent if the water content is increased
by 3-12 per cent. For these reasons, volumetric proportioning as
shown in table 2 is never used when big quantities of high quality
concrete must be produced. In this case, the materials are weighed
and. the moistuxe content is measured, so that the exact quantities of
the different components (gravel, sand, cement and water) can be
determined. For most concrete works carried out on rural roads,
however, the above rules of thumb can be applied.
Water/cement ratio
The quantity of water divided by the quantity of cement gives the
water/cement ratio. The water/cement ratio varies between 0.4 and
0.5 for practically all types of concrete. This gives the minimum
amount of water necessary to react with the cement and to make the
mixture workable. To ensure sufficient workability for hand-mixed
and hand-placed concrete sometimes more water is necessary (water!
cement ratio between 0.5 and 0.65) but great care should be taken not
to use too much water. The wetter the mix the weaker the finished
concrete
Table 3:
Table 4:
Length 40 cm
Inside measurements
Width 25 cm volume 40 litres
Height 40 cm 3
H-12
LE -4/5
e3
Mixing
The pixrpose of mixing is to obtain a homogeneous mixture of a
maximum compactness and a suitable workability.
Hand mixing
when mixing is carried out by hand a suitable floor (metal sheets,
boaxds, lean concrete) should be available to ensure that the mixture
is not contaminated with soil. This floor should be sufficiently
large to permit a continuous mixing process. Figure 4 shows a. good
way to mix by hand.
'I-l2
LE -4/6
S
iOCLa fl
Steps
- Add cement and turn over until the batch is uniform in colour.
Mechanical mixing
Mechanical mixing produces a more homogeneous and. better mix.
Never fill the concrete mixer completely.
A large number of different types of cOncrete mixers exist.
Some commonly found. types are:
- charging position;
- mixing position;
- discharging position.
'eGtçr CY
S
M-l2
LE-4/8
2. ruvi
ii-l2
LE - 4/9
add the rest of the predetermined quantity of water and mix for
another 1-2 minutes.
S
M-12
LE - 4/10
add the water and mix wet for another two minutes0
The mixing time varies with the proportions and the total
quantity of the components, the capacity and rotation speed of the
drum and the desired plasticity. Usually 1.5 to 3 minutes is
sufficient to obtain a good mixture. Mixing moxe than 3 minutes does
iot improve the quality of the mixture.
isure that all the tools, platforms and mixers are thoroughly
cleaned after the mixing has teriuins±ed. If the left-over concrete
hardens, the equipment will not be usable the next time.
MODULE OONORTE TECIINOIOGY M-12
TRANSPORT OP OQNORETE
5 drying out, wet sacks can be used to cover the concrete in the
wheelbarrow.
Also ensure that the concrete mixture is not dropped freely from
heights greater than 1.5 metre. This causes segregation as the
coarse particles drop more rapidly than the finer ones. Po± the same
reason, the mixture should not be thrown far with the shovel, but
should be taken as near as possible to where it has to be poured.
Placing of concrete
The concrete should be placed in layers not higher than 30 cm
when compacted by hand and in layers not higher than 60 cm when
compacted by poker vibrator (figure 8).
to U.
S
Pouring in layers is correct whereas pouring in heaps causes
segregation (figure 9).
S
M-12
LE-5/3
Poctth ir &
Pouring irt___
cas
S
5 concrete.
iron rods.
The consolidation can be done by hand with hand-tampers or
. better method is to use the poker vibrator (figure 10).
This is a steel tube, housing a rotating excentric mass driven by
compressed air or a petrol engine.
S
M-l2
LE -514
The vibrator is immersed into the concrete (not further than 2/3
of its length) at distances of ca. 50 cm. When the water wells up to
the surface it is slowly taken out. Do not vibrate longer than
15 seconds in one place and do not place the vibrator closer than
10 cm to the formwork. Too long vibration can cause the particles
to segregate!
Curing of concrete
Curing of concrete is necessary to prevent surface evaporation of
water during the setting and hardening stage. Curing means preventing
evaporation by keeping the exposed surface of the concrete moist for a
period of at least seven days.
covering the surface with wet jute, paper bags, sand, sawdust,
banana or palm leaves or similar materials.
Proper curing will ensure that cracks in the surface layers, caused
by an insufficient binding due to the non-availability of water, will
not occur. Freshly poured concrete should never be exposed to
intensive sunlight.
MODULE CONOPLETE TECHNOLOGY M-l2
After you have learned- this element, you should be able to:
eei molAtas
vcxD1e c?cX4.
c4er
Con
4wo or vce
14-12
LE -6 / 2
The most common diameters for culverts are 60 and. 90 cm. The
length of a pipe can vary between 75 and. 100 cm.
Manufacturing site
When the culvert pipes are to be manufactured. locally, the
manufacturing site should be chosen considering the following:
cement store;
a loading ramp to enable the workers to roll the pipes onto the
Slorry.
The moulds should be cleaned after each stripping and oiled before
they are used again. A mix of two parts diesel with one part used oil
should be appliedwith a brush to the inside of the mould, the hinges,
wedges, etc.
Make sure that the inside mould is carefully centred to ensure
a uniform thickness of the ring (figure 12).
H-12
LE-6/3
S Coredr \1Jron
LE -6/4
The moulds can be taken off the conciete rings aftex' 24 hours if
the rings themselves can be left i.uadistux'bed. Wait at least 24 hours
more before you move the rings.
The rings should be transported standing in a 10-20 cm layer of
sand (ox' similar hockabsorbiflg material).
MODULE CONCRETE TECBIOLOGY M-12
The aggregate should not contain more than 5 per cent impuriti es.
Proper storage and - in some cases - washing before use is necessar y.
Cement should be kept dry as it hardens when it becomes moist.
Water should be used. sparingly. Usually the water/cement ratio,
LE-7/2
PROBIiEMS
NODULE OIOICP0INT
Indicate True (T) or False (P) in the blank:
- one hour
- twenty-four hours
- seven days
- twenty-eight days
I'1-l2
LE - 7/4
Answer briefly:
.Q
I'1-12
LE -7/5
'. 0
S
FIELD INSTRUCTIONS M- 12
Remember that:
(ii) whether the grain sizes of the gravel and sand are correct
(a good distribution of different sizes);
CEMHNT
Remember that:
AGGREGATE
Remember that:
O- -
the aggregate should be stored on a hard, clean surface;
MAI'flJFACTURE OF CONCRETE
Method
- Find out for which purpose the concrete is required. Concrete
for culvert pipes requires a 1:2:4 mixture of cement, sand and
gravel. Concrete for atnictures needs a mixture of 1 measure
of cement, 2 measures of sand and 3 measures of gravel (1:2:3).
For very high quality concrete laboratory tests are necessary
to find out exactly how much gravel and sand of different sizes
is required to produce the best mixture.
- First mix the gravel and sand by turning over the heap several
times.
- Add cement and turn over until the batch is uniform in colour.
the sand;
- Add the rest of the water and mix for two more minutes.
S
FIELD INSTRUCTIONS M-12
Remember that:
1"Iethod
S
PIELD INSTRUCTIONS M-l2
Remember that:
a cement store;
Method
- Clean the moulds and oil them with a mix of 2 parts diesel
and 1 part of used oil.
- Centre the inner mould so that the thickness of the culvert
ring will be uniform.
- Prepare a batch of 1:2:4 or 1:2:3 concrete (see manufacture
of concrete) according to instructions (preferably use gravel
of different sizes).
- Pour the mixture into the mould using a suitable container.
Compact the concrete with a steel bar and by pounding the
rn.oulds lightly with rubber-headed hammers.
FIELD INSTRUCTIONS N-l2
Structures
NODULE S TRUOTURS M-13
MODULE CONTENT
LE-3 Drifts
LE-4 Causeways
LE-5 Bridges
S
MODULE STRUCTURES M-13
After you have learned this element, you should be able to:
S-
-
-
Is local material available?
What are the transport costs for materials not locally available?
re
N
N-l3
LE -1/4
- Bailey bridges;
- Floating bridges;
- Suspension bridges.
M-13
LE-l/6
After you have learned this element you should be able to:
O:kck
- a-
.1:
ftJcer
-
__ Th
- I
WCc&41r
- -
f
'
tc&onr 11TC31
or
Wacnr3
e,c4ion
flJ.
Oukkk eodvt 'a&, (Co,ce& &jemev Jv1ecsAwfl
in c4 5c) <7 944
0
The assembly. and installation of these culverts is not
described here, as the instructions can be easily obtained from
the supplier. The advantages of these steel culverts are their
strength, their flexibility and their easy assembly. However,
steel is a costly material and in many countries the pipes are
not locally manufactured and readily available.
Always make a cost comparison between alternative solutions.
You will find that for rural roads the manufacture of structures
with locally available materials and skills is often cheaper and
preferable.
NODULE S TRUOTUFES
Learning Drifts
Element
After you have learned this element you should be able to:
Alternative 1
This drift consists in principle of a porous dam which retains
the gravel carried by the water of the stream. The top of the dam
is between 15 and 30 centimetres higher than the river bed at the
downstream end.
M-l3
LE - 3/2
ck 4ilei cc&ors
xh 2.y
StYet(vy ec
(1a e -t2jl- onçj
mov )
bion av4L
1vck
ov's
-
ece oç -\jvv,e,r
4ceeMr r
LE - 3/4
£nkLdcLl aedioii
tO-s 20% OV.4
-
Cxos $cIio1
4ct 400 a ue1
. 4hvi&ioike ov
45c47, as/3os' 4
k
L'm '
1VI_13
LE - 3/6
flQ
Cs edion
F(ax too hud
. *
,ñ' 4ES. 4"coss 4cii o (3't) eojn bed
T
.'WA
Z/5 as ohe,p
-covcde. 44 (tt(0r)
-- -- 4ardcore..
/ - Maonrj wa.tt o abion
or con cxek -uLndciov
><o
Longitudinal section
The concrete slab should be carried into the river banks,
well above the maximum flood level recorded. The approaches
should preferably not be steeper than 15 per cent and the
connections between the horizontal stretch and the approaches
should be rounded.
1t2
tO-2.O
'1
Conjac
(eu,.
///
i
Oi( one
(pron.
dthtov
ccwvee e\& coxd 1M
uje O1Do) OOC\ ie
NODULE STRUCTURES N-13
Design
If the culverts are concentrated in the centre of the causeway,
the high speed water jets coming out of these culverts will cause
heavy scour at the sides of the culverts (figure 13A).
kuel
iskaw jjx eue(
A suitable "apron" of concrete or well-graded stones is
therefore absolutely necessary to break the energy of the falling
water0
ro G-tv4'ceA cewc.ec.
or nc*vôvçActted kone)
?civde4 eàe
-
UsecAw wc1rku 1oV
,I'_- #/ -, -
I'I-l3
IiE-4/5
t_l
Ob
Location
The location of a causeway is - as with all, structures -
extremely important. Efforts should be made to locate the most
stable portion of the river bed, so that a better foundation can
be provided to the structure.
M-13
LE-4/6
Construction
F':
-l3
LE - 4/8
After you have learned this element you should be able to:
- bailey bridges.
Poundati on
1ZC)
SpO.v
-- Ow'
f
1 unccMct
4w YiWItAW ck4I4 4 scour
After the piles have been cut off at the same level the tops
have to be soaked in wood preservative before the or crossbeam
is laid.
422.
/
c,cr?.
/
S9X
.
perstracture
Bridges hve to be designed to support different types of
loads:
Vb
v3a\ ctecknt
/1V
r
'__
p - - 's-,
ecMivot1 ekucx4ov
S
]YI-13
S
7.5 cm thick planks of a length equal to the width of the
bridge are often used for the transverse decking. These planks
are spiked to the girders. Between the planks a small space is
left to allow for expansion due to swelling.
An alternative and better transverse decking can be provided
by using 5 x 10 cm planks, laid on edge to make a deck of 10 cm
thick. As each of these planks is laid, it is nailed to the one
next to it, so that we have, in effect, a solid deck of wood 10 cm
thick instead of a number of individual planks. This makes a
very stiff floor and helps to keep down vibration and movement in
the strLlcture. These planks need only be long enough to be
S supported by to girders. Quite often short planks of this size
can be purchased quite cheaply, so that for a similar or lesser
price a transverse decking of 10 cm thickness can be provided
instead of one 7.5 cm.
To protect the deck and give a smooth running surface for the
cars, runninstrips or running planks are provided. Figure 25
shows running strips bolted to a 75 cm thick transverse decking.
Running strips should be bolted, not spiked, to the decking,
because the spikes would soon work themselves loose. lCerbs are
bolted to the decking to prevent vehicles from sliding off into the
water. They also serve to provide a stronger floor, since the
floor planks are prevented from working themselves loose.
S
R2S
S
MODULE S TRUC TUBES
S U'1HARY
LE-6/2
S
Backfills should preferably be made of well-graded gravel
(sometimes rubble may be used) and should be well compacted.
When the function of the road and the traffic density warrant
more sophisticated structures, paved drifts, causeways and bridges
can be considered. Causeways are drifts which have a number of
culverts to receive regular waterfiows. During floods, the water
O passes through and over these structures.
NODUlE CBECICPOINT
Answer briefl :
seepage holes?
kerbs?
girders?
running strips?
S TRUCTURES
LARGE-SIZED CULVERTS
Remember that:
DRIFTS
Remember that:
Construction
- Reehaxinel the water flow so that you obtain a dry working
space.
DRIFTS (contd.)
- After the work on the drift itself has been completed, improve
(especially in sandy soils) the transiti.ons from the road
surface to the drift approaches.
- Dig trenches of one metre wide and one metre deep immediately
next to the drift approaches, across the width of the road.
CAUSEWAYS
Remember that:
Construction
- See FIELD INSTRUCTIONS - DRIFTS.
CAUSEWAYS (contd.)
- Excavate the trench for the apron and place the stones (the
largest at river bed level near the down-stream edge of the
causeway).
FIELD INSTRUCTIONS N-13
BRIDGES
Remember that:
timber used for bridges should be well treated with wood pre--
servative;
Construction
- Set out the centre-line of the bridge and the positions of
the abutments (and. piers).
- Re-channel the water flow so that you have a dry working space.
Construct first one abutment, then the piers (ii' any) and then
the other abutment.
- Excavate the foundation as deep as possible. Try to reach a
hard, solid soil layer or bed-rock. In soft soil, when ground
water is encountered, continue the excavation until no longer
PIELD INSTRUCTIONS M-13
BRIDGES (contd..)
- Lay the girders. Place the tops of the, girders at the same
level using hardwood wedges or mortar. Place suitably sized
pieces of strong plastic or rubber between the timber and
masonry at those places where high wear may be expected.
- Bolt the planks for the running strips to the transverse decking.
Depending on the width of these planks, two or three should
be laid next to each other so that the running strips are wide
enough to be used by vehicles of different sizes.
Gravelling
S
NODULE GRAVTELLING N- 14
earning LE-O/l
Element
Module learning objectives and content
MODULE CONTENT
LE-O Module learning objectives and content
Learning
Nature and definition of gravelling
Element
After you have learned this element you should be able to:
LE- 1/2
1rat ol\.
LB -1/3
After you have learned this element you should be able to:
When to gravel
The basic functions of a gravel layer are (i) to ensure that
the road is assable at all times under all types of weather
conditions and. (ii) to prevent deformation of the road under normal
traffic loads. It follows, therefore, that natural soils which
already possess these required properties do not need an additional
gravel layer. Unfortunately for the road builder, such, soils do
not occur frequently in the places where they are needed so that
gravelling is usually required.
Nethods of gravelling
In principle, the following methods can be used to gravel a
road:
use a mix of labour and equipment;
use labour for all activities, except hauling over
distances longer thai 100 metres.
LE-3/2
IiE-3/3
Selection of quarry
The following aspects need to be considered:
All these people have a specific role to play and have a place
in the organisation. What these functions are and how they relate
to each other can be drawn in an organisation chart (figure 2).
M-14
11E-4/2
S
S
N-14
LE-4/3
S
N-14
Repair of equipment
S
Payment of wages
MODULE GRAVELLING M-14
(e) when the topsoil has been removed, the loading bays (places
where the transport will be loaded) should be prepared. It
is recommended to stockpile, in advance, a volume of gravel
sufficient for two days' gravelling. This allows a good
control of the excavation gang which, ideally, should stay
two days ahead of the loaders;
S (±) turning bays should. be prepared along the road. The distance
in between two turning bays should be a maximum of 100 metres;
so that no time and fuel is wasted during the gravQlling
operation;
finally, the road. to be gravelled should be repaired as
necessary. Pot4ioles s1.ould be filled and. the camber should
be restored where required. A length of road equivalent to
one day's production should be prepared before the first load
is transported.
It is recommended to limit the number of workers carrying out
these preparatory activities to about 25. It is usually
possible to select suitable gang leaders from this first
group of workers. You can do this by carefully observing
individuals who demonstrate a positive attitude towards the
work as well as manmanagement and. leadership abilities.
0P 11flE QJRR
fload
Lae. 4urnin
p\o.cZ equice
eL
M-l4
LE-5/4
LE-5/5
:t:t 5b
dum.in lace and reverse until the have reached the oint where
the gravel should be off-loaded. After dumping, they drive back
to the quarry and. the next vehicle dumps the next load.
However, the use of this method means that the vehicles always
drive over (sections of) earth road, which may cause these sections
to be damaged especially in rainy periods. If it rains, it may
even become impossible to continue graveiling, as the earth road
will become muddy and slippery. Also (if tractors/trailers are
used), reversing can pose considerable problems - in particular,
uphill reversing requires very skilled drivers.
Gravelling away from the quarry does not have such problems
as the vehicles always drive over already graveiled sections.
This method has the additional advantage that the hauling vehicles
frequently pass over the freshly-dumped gravel and compact the layer
thoroughly. The drivers should be instructed to drive in such a
way that the whole width is copacted and. no ruts are formed.
Gravelling away from the quarry means that the greatest number
of workers will be required in the .beginning stages of the
work and that the first workers will have to be laid off very
soon. (The longer the hauling distance, the less workers
are needed for Joading, excavating and spreading - see LE-6,
planning.)
N-14
LE-5/8
S IiE.-5/9
S
MODULE GRAVELLING M-14
Inputs
The inputs required for labour-based gravelling are:
- hand tools;
Table 1 shows how many trips per day can be expected from a
tractor having two trailers, one being hauled, while the other is
loaded. It also indicates the optimal number of tractors for
each hauling distance and the number of workers required. The
output of the workers is estLmated to be 3 in3 per man/day for
excavation, 6 m3 (loose) per man/day for loading, and 12 in3 per
man/day for spreading. The quantity of material transported
per trip is assumed to be 3 m3. The average speed of the
tractor/trailer combination is estimated to be 15 km/hour.
Table 1:
0-1 18 2 36 18 9 63
1-2 12 3 36 18 9 63
2-3 9 4 36 18 9 63
3-4 7 4 28 14 7 49
4-5 6 4 24 12 6 42
5-6 5 4 20 10 5 35
6-7 4 4 16 8 4 28
7-8 3 4 12 6 3 21
This table can be used for planning purposes but the figures
given should be tested in the field and adapted to the local
conditions. Por example, the output per man/day may be higher
if the worker works on piece rate. When the hauling route is in
very good condition, a higher average speed may be possible. With
other types of transport different speeds will be obtained, etc...
By experimenting and studying the works for a period of two/three
days, it should be possible to arrive at realistic figures for a
particular situation.
The workplan
The length of road section gravelied per trip can be calculated
by dividing the quantity of material transported by Ci) the gravelied
width of the road, and (ii) the thickness of the loose gravel
required.
For example, when it is specified that a road should have a
gravelled width of 4 metres and the thickness of the layer of
(loose) gravel should be 0.15 metre, one load of 3 cubic metres
will gravel a length of 3/0.6=5 metres.
Figure 6 shows the location of the quarry. Since this
information is of vital importance, this sketch should always be
attached to the workplan. It is good practice to make the final
sketch on the reverse side of the workplan.
N-14
LE-6 /4
- carry out the build-up and the lay-off of the labour force
in a limited, number of steps;
S
M-14
Table 3
35 xlO 350
42 x 9 378
49. x 7 343
63 x 3 189
28 xl3 364
21 x 17 357
59 1981
'V.)
I S
N NH I
1vI_14
JIE-6/8
f1:
\ A
Ip Th
I
t)
I1
I &
C
IV
'L
II
, %
$ Ili
Ii' N)
t& liii
L I
iti 144tH
M-14
LE-6 /10
S
MODULE GRAVELLI NG- M-14
Daily/weekly report
This report describes how many and which type of people are
working on the different activities, the number and type of
vehicles working, the number of loads transported, the length of
road gravelled and other relevant information. It should be
filled on a daily basis and summarised at the end of the week.
Weekly report
At the end of each week the infoi-ination of the daily report
is added/summarised and additional information on the fuel, oil,
tools and equipment situation is recorded.
M-14
LE-7/2
S
Stores ledger
In this ledger all materials, hand tools, oil, fuel, etc. are
recorded. Every time an item is received, issued or returned
the storekeeper must make an entry in this book. It should
always be possible to:
physically check the balance of usable and unusable items and
compare it with the balance as recorded in the ledger; and
Monthly report'
This report suinmarises the daily/weekly reports and the
information of the work tickets. It should be completed by a
senior supervisor in the presence of the supervisor in charge of
gravelling. All information (progress, kilometrage of vehicles,
fuel consumption, store balance, man/days) should be physically
checked by the senior supervisor before the report is submitted
to the site engineer.
Work tickets
On these forms travel with project vehicles is authorised.
Details of vehicle - services, fuel, oil and lubricant consumption -
should be recorded on these forms as and when they occur.
Muster rolls
It is recouiinended to keep separate muster rolls for the regular
(monthly employed) personnel and the unskilled (daily employed)
labour. It is good practice to keep duplicates of each muster roll,
so that a record is always available on site even at those times
when the original muster rolls are required at headquarters for
preparing and checking of payrolls.
Sample of daily/weekly report and instructions for use
S
Sample of monthly report and £nstructions for use
I
S
Sample of stores ledger and instructions for use
S
Sample of work ticket and instructions for use
M-l4
LE-7/7
S
Sample of muster roll and. LnstructionS for use
5 NODULE RPVELLING M-l4
List of equipmerzt
S
IVIl4
LE-8/3
S
N-14
IE-8/4
LLst of materials
S
M-14
I LE-8/5
S
IE-l4
IiE-8/7
S
M-14
LE-8/8
Tools
Excavating, loading and spreading of gravel are very "tool-
wearing" activities. For this reason it is extremely important
that tools for gravelling are well designed and have a good
quality. Pickaxes should be of the heavy type (weight of head
between 3 and 3..6 kg) and fitted with a handle with an elliptical
cro ss-section.
Oonsumable items
Of these, fuel is certainly the most costly and most frequently
used. Proper handling, storage and recording of fuel consumption
is therefore of utmost importance. Then fuel is kept in drums,
these should be handled gently to avoid leakages and damage of the
drums. Also, take care to leave the drum standing for a few
hours after it has been filled before you use the diesel petrol
to fill vehicles. There is always a danger that the fuel has
mixed with condensed water in. the drum. After leaving the drum
for a while the lighter fuel will be on top of, and separated from,
any water there may be in the container.
Then issuing fuel, keep separate records for each vehicle and
note (i) the date of issue, (ii) the quantity and type of fuel
issued and (iii) the registration number of the vehicle. The
driver should sign for receipt of the fuel. Usually the same
information should be recorded on the work ticket of the vehicle
concerned.
MODULE G-EAVELLING
SUMMARY
The fimctions of a gravel layer are: (i) to provide an
all-weather surface to a road and (ii) to prevent the formation
of ruts and pot-holes by the passing traffic.
The decision of whether or not to gravel a road depends on
the function of the road, the expected traffic density, the nature
of the natural soil and the cost of gravelling.
Different methods of gravelling should be considered before
gravelling is started. bepending on. the hauling distance,
S different methods of hauling may be economical. Depending on
labour availability, cost and motivation, some or most of the
gravelling activities can be carried out with labour-intensive
methods.
There are several simple field tests to determine whether a
particular material is suitable to be used for gravelling. In
case of doubt, have a sample tested in a soils laboratory.
Quarries can be found with the assistance of government
departments responsible for road construction/maintenance, the
local population, the local administration, or by a personal survey
of exposed faces of road ditches or cuts in the area.
MODULE CUE0KPOINT
Indicate True (T) or False (F):
LE-9/3
S
Answer briefly:
Which preparatory activities need to be carried out before
the excavation and hauling of the gravelling can start and
roughly how much time do you estimate to be required for each
of these preparatory activities when a labour force of
20 workers is employed? N,B. Assume quantities of work to
be done whenever required.
S
FIELD INSTRUCTIONS M-l4
Remember that:
- you should find out who owns the land and whether compensation
will have to be paid. If this is the case, inquire about
the regulations in respect of payment of compensation;
S
FIELD INSTRUCTIONS M-14
Remember that:
Remember that:
Routine maintenance and servicing of equipment
Repair of equipment
Payment of wages
Remember that:
Preparatory work
The quarry
- The quarry should be laid out in such a way that the hauling
equipment can enter and leave without being in each other's
way.
Remember that:
you should plan in such a way that the employment and dismissal
of workers can be done in steps. One way to do this is to
start gravelling at the middle hauling distance, to gravel
towards the quarry, to return to the start point and to gravel
away from the quarry until the job is finished (see example
M-l4, IiE-6);
Remember that:
Daily report
Weekly report
Monthly report
Stores ledger
Work tickets
I'Iuster rolls
Maintenance
MAINTENANCE M-15
- describe which tools are necessary and how they are administered.
MODULE CONTE
After you have learned, this element you should be able to:
EU-kt djk'c
I
N-15
LE -1/2
As you can see, there is nowhere the water can go, which means
that it will either be stagnant in the middle of the road if the road
runs through level terrain or move downwards in the longitudinal
direction if the road runs through sloping terrain. Where traffic
has formed ruts, these ruts will act as channels which will be
deepened and widened after every rainfall.
ACTIVITIES
The activities to be carried out thider routine maintenance are:
Learning
Element
Choice of methods for routine maintenance
kiinoS_ dions
t.eoi'e -ad1ii4e
1o4it uevevsss 4 *e e
2..41er (tL&flS
- i r. iwr -
çra.
11ck r -. \.ci. er
Zzi- ____z
kMer Y'LCY1O
M-l5
LE-3/3
Running surface
In those cases where the type of road and the traffic density
justify the use of a motor grader the machine is used to:
remove corrugations;
LE-4/2
Even when a motor grader is used there are many tasks which
can only be undertaken by labour. Examples of such activities
are clearing of culverts, filling and compacting of pot-holes,
repair of masonry work and cutting of grass. Different ways in
which this labour can be organised are described in LE-5 "Routine
maintenance with labour only".
LE-4/3
S
;gç ol4ec& or
woccb cko
M-15
11E-4/4
Ft
'i '1/
I.
4-
- -__1_ I I
___
¶
cevtj'e Une
1
MODULE MAINTENANCE
Learning
Element Routine maintenance with labour only
After you have learned this element you should be able to:
- describe different systems to carry out routine maintenance
and mention some advantages/disadvantages of those systems;
- describe which hand tools are used for routine maintenance.
LE-5/4
0ganisation
Since this system is a contract system where only results
are important, it is not necessary to check how many days or
hours are worked nor whether the contractor carries out the
work himself or is assisted by others. If the road is in
"good order" payments are made whatever the methods used.
Tools
When the tools are issued, the worker should sign. for their
receipt. It iS
good practice to clearly mark the tools so that
they cannot be replaced by other inferior or older ones. It is
essential to have regular (at least once per month) tools
inspections to check the number and condition of the tools.
Such monitoring will help you to anticipate the need for replace-
ment of tools and will enable you to adjust the estimated life
figures given above. The average lifetime of a tool is likely
to vary from area to areas Simple standard forms developed for
this purpose will provide necessary data relevant to other areas
in the country. If such forms are used, ensure that they are
filled in on a regular basisl
If the tools inspection is done on pay-day, the cost of
"lost" tools can be deducted from the salary or contract sum of
the worker. Whenever inspection rounds or payment rounds are
made a number of new tools/light equipment should be carried to
be exchanged for worn or broken ones handed in by the workers.
M-15
LE-5/6
0-ravel
SUMMARY
Routine maintenance is essential to prevent a fast deterior-
ation of the road and to avoid unnecessary damage under normal
weather and traffic conditions.
When major failures occur (landslides, culvert damage, wash-
outs), examine why these have happened befOre repairs are started.
Higher costs are well justified when the cause of the failure
can be found and rectifIed.
Periodic maintenance is necessary after a number of years
to bring the road back to its original state. This type of
maintenance normally involves re-shaping and re-surfacing.
Depending on the type and function of the road and its
average daily traffic, different methods to carry out routine
maintenance can be considered. The use of manual labour for
most of the routine maintenance activities can often be econom-
ical and very effective. If labour-based maintenance methods
are considered the workers should be motivated to continue the
work effectively even in the long run. This means that incentive
systems (rewards for effective work, penalties for poor work)
should be introduced. Which systems can be applied (time off,
extra pay, etc.) depends on the country situation and the local
customs.
N-l5
LE-6/2
MODULE CUEOKPOINT
Indicate True (T) or False (F):
Corrugations are formed after every rain
Answer briefly:
What are the activities to be carried out under routine
maintenance?
S
FIELD INSTRUCTIONS M-15
estimated life
(months, maintenance only)
- hoe 9
- grass slasher 4
- bush knife 9
- shovel 12
S -
-
long-handled shovel
rake
12
12
- pickaxe 36
- hand-rammer 36
- wheelbarrow 24
- sharpening file, pliers, bolts and nuts for wheelbarrows,
grinding wheels, whetstones, claw-hammers, hardwood wedges,
50 per cent spare handles for each type of tool described above.
Remember that:
- when tools are issued the worker should sign for receipt;
MAINTENANCE - GENERAL
Remember that: