Answer: A
2. In which sales process is an invoice immediately printed when the sales order is created?
a. Drop shipment
b. Make-to-order
c. Cash sales
d. Rush order
Answer: C
Answer: B
4. You set up partner determination. To which elements do you assign the partner determination
procedure? Note:There are 2 correct answers to this question.
b. Delivery type
c. Account group
Answer: BC
a. Create a periodic billing plan for the bill to party and assign it to the customer master.
b. Create a new billing type and assign it to the applicable sales order ty8pe.
c. Define a factory calendar and assign it to the customer master of the payer.
d. Assign the invoice list type to each applicable billing document type.
Answer: CD
6. Which elements can you use to influence the determination of the shipping point? Note:There are 3
correct answers to this question.
a. Plant
b. Loading group
c. Shipping condition
d. Transportation group
e. Storage condition
Answer: ABC
7. In the SAP organizational structure for sales. which entity represents your strategy to distribute goods
and/or services to your customers?
a. Division
b. Sales organization
c. Sales group
d. Distribution channel
Answer: D
8. How do you establish the interface between SAP SI4HANA Sales and Finance?
Answer: A
9. Where can you set the condition exclusion indicator? Note:There are 2 correct answers to this question.
a. Pricing procedure
b. Condition supplements
c. Condition type
d. Condition record
Answer: CD
10. which lead time can you use in delivery scheduling? Note:There are 2 correct answers to this question.
Answer: CD
11. During an ATP check for a sales order item, the requested quantity is completely confirmed on the
required date even though there is only a partial quantity in stock on that date. What could be the reason
for this?
a. The customer material info record is set to allow partial deliveries and the customer requires a quantity
as close to the requested delivery date as possible.
b. The customer master record is set to allow partial deliveries and the customer requires a quantity as
soon as possible.
c. In the configuration of the scope of check, the Without Replenishment lead Time flag is not set and the
material availability date is further away than today plus the replenishment lead time.
d. In the configuration of the scope of check, the Without Replenishment Lead Time flag is set and the
material availability date is further away than today plus the replenishment lead time.
Answer: C
12. What can you do with the help of the Manage Billing Documents app? Note:There are 2 During an ATP
check for a sales order item correct answers to this question.
Answer: AB
13. Your project uses the new output management in SAP S/4HANA. What must you create to print the
order confirmation immediately after the order is saved?
a. Output message
b. Condition record
d. Transmission medium
Answer: D
14. Which sales document type do you use to supply specified quantities on defined dates?
a. Value contract
b. Master contract
c. Quantity contract
d. Scheduling agreement
Answer: D
15. You have created a sales order in standard SAP S/4 HANA system. Upon saving you recieved a system
message that a business partner of a specific partner system function is missing. Which of the following
partner function causes the problem? There are 2 correct answers to this question.
a. Forwarding agent
b. Payer
c. Contact person
d. Bill-to party
Answer: BD
16. Which organizational units must you set up for billing? Note:There are 2 correct answers to this
question.
a. Sales area
b. Company code
c. Business area
d. Profit center
Answer: AB
17. Which of the following assignments are possible when you set up organizational units for sales?
Note:There are 3 correct answers to this question.
Answer: BCD
18. In a standard SAP S/4HANA system, which elements are a possible source for the partner function in
your sales order? Note:There are 2 correct answers to this question.
b. Preceding delivery
c. Customer hierarchy
Answer: AC
19. Which organizational unit is defined as a physical location that processes and monitors outbound
deliveries and goods issues?
a. Shipping point
b. Storage location
c. Plant
d. Loading point
Answer: A
Answer: B
21. Your project requires the settlement of a condition contract in SAP S/4HANA. Which of the following
settlement types can you use? Note:There are 3 correct answers to this question.
a. Periodic settlement
b. Partial settlement
c. Invoice settlement
d. Final settlement
e. Delta settlement
Answer: BDE
22. Which field from the customer master record determines the route?
a. Incoterms
b. Delivery priority
c. Delivering plant
d. Shipping conditions
Answer: D
23. In SAP S/4HANA which technologies can you use to set up output for a billing document? Note: There
are 2 correct answers to this question.
a. SAP Workflow
d. NAST
Answer: BD
24. Which master data can you use for automatic determination of the delivering plant in a sales order?
Note:There are 3 correct answers to this question.
a. Sold-to party
b. Ship-to party
d. Material master
e. Customer hierarchy
Answer: BCD
25. Your project requires shipment of several sales orders in one outbound delivery. What must the sales
orders have in common? Note:There are 3 correct answers to this question.
a. Picking location
b. Ship-to party
c. Warehouse number
d. Shipping point
e. Route
Answer: BDE
Answer: B
27. You must ensure that a bill of material will explode to generate sub-items in a sales order. What
controls this functionality?
b. The item usage during the item category determination of each sub-item
Answer: D
28. In a delivery-related billing process, how can you force an automatic new price determination during
billing document creation?
Answer: C
29. When you set up a billing document, which copy control parameters are available at header level?
Note: There are 2 correct answers to this question.
c. Pricing type
d. Reference number
Answer: BD
30. Your project requires that a new text element from the business partner master record is automatically
copied into the header information in sales orders. What must you do?
d. Assign the required text type with an appropriate access sequence to the text determination procedure.
Answer: AB
31. A business user grants his customer a special price. This special price should ignore all possible
discounts that may be applicable in a sales order for this customer. What must the business user do?
a. Maintain a maximum condition value in the condition record for the special price.
b. Activate the Condition Update indicator in the condition record of the discounts.
c. Set the Exclusion indicator in the condition record for the special price.
Answer: D
32. Which business partner categories can you use to create customer master records? Note:There are 2
correct answers to this question.
a. Vendor
b. Person
c. Customer
d. Organization
Answer: BD
33. For which master data can you reduce maintenance using the common master data concept?
Note:There are 2 correct answers to this question.
Answer: AB
34. A customer usually prefers complete delivery of a sales order. When creating a particular
order,however,the customer would like to make an except on and allow partial deliveries. How would you
proceed to do this?
a. Deselect the Complete Delivery flag in the customer-material info record.
c. Deselect the Complete Delivery flag in the business partner master record.
Answer: B
a. Delivery type
Answer: D
36. What are the consequences of posting goods issue? Note:There are 3 correct answers to this question.
Answer: ACD
37. You need to trigger free goods determination in a sales document In a standard SAP S/4HANA system,
which elements influence the item category determination of the free goods item (TANN)? Note:There are
2 correct answers to this question.
a. Item usage
Answer: AD
38. You maintain business partners and want to use them as customers in sales documents. Which
assignment is mandatory in customer-vendor integration (CV') to ensure this?
Answer: B
39. You need to create business partners (BP) to record data relevant for BP roles Customer and Fl
Customer. Which organizational elements must you enter to maintain this data?
Answer: C
40. You need to ensure that an incomplete sales document CANNOT be saved. What must you do?
a. Select the Dialog Message for Incompletion flag in the respective schedule line categories.
b. Select the Dialog Message for Incompletion flag in the respective sales document type.
d. Assign an incompleteness procedure to the respective schedule line categories of the document.
Answer: B
41. Your project requires confirmation of sales order quantities for certain materials even if the stock of
those materials is currently below the safe y stock level. Where do you configure this?
Answer: C
42. In SAP Smart Business, the sales process flow can be the starting point for solvingissues. Which features
does the process flow provide in this context? Note:There are 2 correct answers to this question.
a. It is possible to open and solve an issue directly from the process flow.
b. Using artificial intelligence (Al), the system predicts the issue status on a certain date using colours.
c. A wizard is available that uses machine learning to help the user with issue solving.
Answer: AD
Answer: C
44. You want to maintain a freight charge that is determined automatically and should be based on the
gross weight of all order items. How can you achieve this?
Answer: B
45. For sales order items that are to be picked in a warehouse managed by SAP Extended Warehouse
Management (SAP EWM), an outbound delivery is created with reference to the sales order and replicated
to SAP EWM . Which type of SAP EWM document is created as a direct result of this replication?
a. An outbound delivery order is created. This is used for the creation of warehouse tasks to manage the
pick.
b. A series of warehouse tasks is created. These tasks are grouped into an outbound delivery order, which
is used to manage the pick.
c. An EWM outbound delivery is created. This is used for the creation of a warehouse order to manage the
pick.
d. A warehouse order is created. This is used for the creation of warehouse tasks to manage the pick.
Answer: A
46. What can you trigger in the customizing of schedule line categories? Note: There are 2 correct answers
to this question.
a. Transfer of requirements
Answer: AD
47. Which of the following elements can you use to influence the item category determination in a sales
order? Note: There are 2 correct answers to this question.
b. Material type
d. Sales area
Answer: AC
48. When using new output management in SAP S/4HANA,how does the system process a BRF+ decision
table to retrieve the required result?
a. Every condition column is processed in sequence. In each condition column, every row is processed from
top to bottom. If the condition in each condition column cell is met, the field values in the result columns
are returned.
b. Every row is processed in sequence. In each row, every condition column cell is processed from left to
right. If the condition in each condition column cell is met, the field values in the result columns are
returned.
c. Every row is processed in sequence. In each row, every condition column cell is processed from right to
left. If the condition in each condition column cell is met, the field values in the result columns are
returned.
d. Every row is processed in sequence. In each row, every result column cell is processed from left to right.
If the condition in each result column cell is met, the field values in the condition columns are returned.
Answer: B
49. In a standard SAP S/4HANA system, a customer wants to configure output by adding a new field to an
existing form. In which case can the form modification be regarded as simple?
a. The field does NOT yet exist and needs to be added to the database.
b. The field exists in the communication structure, but its format needs to be changed before it can be
integrated into the form
c. The field is NOT recognized in the processing program and needs to be added to the communication
structure.
d. The field exists in the communication structure and can be integrated in its existing format.
Answer: D
50. Which objects can you use in the standard SAP S/4HANA system to restrict the products to be released
for a value contract? Note:There are 2 correct answers to this question.
b. Product hierarchies
c. Assortment modules
d. Contract profiles
Answer: BC
51. In a customer system, a text item is transferred from a sales order to an outbound delivery. Which
setting enables this?
a. The sales item category for the text item must contain a movement type.
Answer: B
52. Which of the following elements can you use to influence the delivery item category determination?
Note:There are 3 correct answers to this question.
a. Delivery type
b. Plant
d. Loading group
e. Item usage
Answer: ACE
53. What are some features of the Sales Order Fulfilment Monitor app? Note: There are 2 correct answers
to this question.
a. Issues in the process can be resolved directly from the process flow within the app.
b. The app shows cost simulations for all possible order fulfilment scenarios.
Answer: AC
54. What characterizes SAP Smart Business? Note:There are 3 correct answers to this question.
a. It consists of a set of transaction codes for reports that can be linked to unique URLs.
b. It provides a set of SAP Fiori apps for your key business processes based on the SAP S/4HANA Model
Company.
c. It provides an exception-based working model combining analytics with actions to solve issues.
d. It provides key performance indicator (KPI) visualizations with semantic colours and target thresholds.
Answer: CDE
55. A business user needs to display the document flow for a sales process and visualize all relevant
preceding and subsequent documents. Which activities do you suggest? Note:There are 2 correct answers
to this question.
a. Go to the material document and select the icon Display Document Flow.
b. Go to the Manage Sales Orders app on the SAP Fiori launchpad and select a sales order.
c. Go to the sales order and select the icon Display Document Flow.
d. Go to the accounting document and select the icon Display Document Flow.
Answer: BC
56. Which technological concept supports real-time operational reporting on live transactional data?
a. Java layer
57. You need texts for shipping in a sales order. These are usually sourced from the ship-to party, but if they
are not maintained in the ship-to party, they should be sourced from the sold-to party. Which of the
following objects controls this behaviour?
a. Text type
b. Condition table
d. Access sequence
Answer: D
58. A credit memo request was created for a customer's sales order. What must a business user do to
create the respective credit memo? Note:There are 2 correct answers to this question.
b. Create the credit memo with reference to the credit memo request.
Answer: AB
59. You review the standard behaviour of sales document items. Which of the following sales document
items is marked as completely referenced, even if it is only partially referenced?
Answer: A
60. Which features are directly controlled by a billing type? Note:There are 2 correct answers to this
question.
a. Posting block
b. Update pricing
d. Incompletion procedure
Answer: AC
Answer: A
62. What functionality is used to make sales order items available to MRP?
a. Transfer of availability
c. Transfer of requirements
Answer: C
63. Which organizational elements can you configure in Logistics Execution? Note:There are 3 correct
answers to this question.
a. Distribution channel
b. Location
c. Loading point
d. Shipping point
e. Warehouse number
Answer: BCD
64. You want to limit the choice of reasons for reject on in a sales process. What do you need to do?
a. Assign the permitted reasons for rejection to the relevant sales area.
b. Assign the permitted reasons for rejection to the relevant business area.
c. Assign the permitted reasons for rejection to the relevant sales item category.
d. Assign the permitted reasons for rejection to the relevant sales document type.
Answer: D
65. Your project requires an enhancement to the standard sales order processing logic. Which options
should you consider? Note:There are 3 correct answers to this question.
a. User exit
b. Requirement routine
c. Customer exit
e. Customizing (IMG)
Answer: ACD
66. Your project requires a rush order process in which a delivery document is automatically created
immediately after the sales order is saved. In which customizing object do you activate this?
a. Copy control
b. Sales document type
Answer: B
a. Shipping point
b. Status information
c. Texts
d. Picking information
Answer: C
68. Which confirmation strategies can you select when executing backorder processing (BOP)? Note:There
are 3 correct answers to this question.
a. Win
b. Fail
c. Split
d. Lose
e. Fill
Answer: ADE
69. You need to generate a list of conditions for analysis in a standard SAP S/4HANA system. Which activity
does SAP recommend?
Answer: C
70. A customer learns that SAP S/4HANA reporting uses Core Data Services (CDS) views. What are some
advantages of using these? Note:There are 2 correct answers to this question.
a. CDS views can be combined with the analytical engine of embedded BW to provide more advanced
reporting options.
d. CDS views allow for the reuse of existing reporting authorizations due to full ASAP integration.
Answer: AB
71. What do you need to consider when you create a condition record for pricing?
a. You can create condition records for condition types that are selected as manual in the pricing
procedure.
Answer: A
72. Your project requires material determination in a sales order if the ordered material is NOT available.
How do you achieve this?
b. Set up the access sequence to perform a quantity check for the material.
Answer: A
73. A customer orders five different materials. Because these materials are available at different dates and
times, the customer agrees to partial deliveries where necessary. However, they want to minimize the
number of partial deliveries . What should you do to enable partial deliveries for the order, while ensuring
as few deliveries as possible?
b. Set the delivery block until all items are fully confirmed.
Answer: C
74. In complaints processing in a standard SAP S/4HANA system, which documents can only be created with
reference to a billing document? Note:There are 2 correct answers to this question.
b. Invoice cancellation
Answer: AB
75. You use the same text element in a sales order and in the subsequent delivery. What must you
customize to ensure that changes to the sales order text are also visible in the delivery text?
a. Access sequence
b. Text type
Answer: A
76. You maintain a sales order with several items and grant a discount in the sales order. The system should
automatically distribute the discount among the items based on the net value. How do you achieve this?
Answer: C
77. To which of the following elements can you assign an incompleteness procedure? Note:There are 3
correct answers to this question.
a. Partner type
b. Delivery type
c. Billing type
e. Partner function
Answer: BDE
78. What is the purpose of the condition type within the Pricing process?
Answer: D
79. What advantages do a single platform for Online Transact on Processing (OLTP) and Online Analytical
Processing (OLAP) provide? Note:There are 2 correct answers to this question.
Answer: BC
80. Which of the following are characteristics of the down payment process in SAP S/4HANA? Note:There
are 2 correct answers to this question.
Answer: AC