Professional Documents
Culture Documents
People in Control: An International Conference on Human interfaces in Control Rooms, Cockpits and Command Centres
19-21 June 2001, Conference Publication No. 481 0 IEE 2001 19
reference group in order to integrate the method Step 9.8: training.
into industry design practices. Otherwise, the structure of the review method holds
closely to that given in IS0 11064.
20
1
.
Phase A Step 0: HF Programme Management
-A
it-- I
6 -- -
~
Phase B I I
i New designs:all
I
i
i
functions I
I I collect data on existing functions/constraints ~ 1 i I
Phase C
.
!
' -
Does 7
I Step 8: Approve h n c e p t u a l Design
the design meet/
~
-l
no 1i
requirements? I- I
I
... ..~ . ........
~ ~ . .~ . ~~~~~ . ~
......
.. . ~~ ~ 1. .Yes
....
~
I
Step 9: Detailed Design and Build I
d
Phase D
the design meet
requirements?
...
Phase E
gure 1: Human Factors Steps in Control Centre Design (adapted from IS0 11064-Part 1)
21
allocated to the control room that could be done
Step 1: Goals and Requirements. This reviews elsewhere, e.g., changing the videos and acting as a
the process of setting human factors goals and telephone exchange. A proper functional analysis
requirements for the project. The design can identify inappropriate functions and enable
documentation should show that an operational them to be removed from the control room.
experience review, OER, has been conducted to
identify human factors problems from previous or Step 3: Function Allocation. After a list. of
other similar designs. In addition, relevant functions is drawn up, they must be allocated to
regulatory requirements and standards related to either CCR operators or the automated systems.
human factors should have been identified before This allocation is often based on what is possible
the goals and requirements of the project can be for machines to do rather than what is best for the
specified. Our experience relating to this step is CCR operator. This step reviews the basis on
that few goals are set for HF aspects of the design which this allocation is made to ensure the
and where they are not concrete enough to be operators’ needs and abilities are taken into account
measurable and not collated into a single document. in this process. When carrying out function
However, manning goals are often set at this stage allocations, we have found that there were many
before actually knowing what the functions and times when systems developers would automate
tasks will be. Our aim with this step is to ensure processes that operators would prefer to retain
that HF goals are set early in the project and that control over in order to maintain a good overview
these goals are measurable so that later in the of the process. Conversely, tasks like generating
design process the design can be tested to see if it reports that could be automated are often
meets the goals and works as it was intended. overlooked when the systems are being designed.
Phase B. Analysis and Definition
Step 4: Define Task Requirements. A list of CCR
Our experience of control room design shows that tasks that have been assigned to the CCR operators
there is insufficient analysis of the human and will be the result of Step 3. These must be analysed
organisational aspects of control room work. A to determine what the operators needs, in terms of
typical problem is the presentation of alarms. It is information, equipment, knowledge skills, etc., to
possible to alarm many process variables and carry them out. Often considering what is needed
frequently the “we can so we will” design in the control room is non-systematic, for example,
philosophy is applied. This has resulted in brainstorming exercises, with things added as the
operators being overwhelmed by an avalanche of design progresses. This step reviews whether the
alarms in abnormal situations and unable to identify CCR operators needs have been properly analysed
the key problem from the myriad alarms presented. and documented. By examining key tasks from
By careful analysis of the information needs of different operating conditions and considering all
operators, the alarm systems can be designed to equipment and information needed to carry out
convey the key information that enables the those tasks designers can ensure that the finished
operators to rapidly identify the initiating problem CCR meets those needs. The application of task
and respond appropriately. When applying the analysis at this stage has, in.our experience, shown
method in new designs the central control room to be of enormous advantage. We have repeatedly
(CCR) operators have been extremely positive to found key items or key information that has been
these analyses. missed is highlighted in this process. It also allows
the optimum layout for equipment and displays and
Step 2: Functional Description. For a new control controls to be found by lmking them sequentially
centre design, this phase will initially involve a within tasks and processes.
detailed analysis of the functions of the control
centre. For an upgrade, an analysis of the changes Step 5: Job and Work Organisation. Individual
in functions of the control centre’may be enough, tasks must be combined to make jobs. This step
assuming that a previous analysis has identified the reviews the process of job design to ensure that
overall control centre functions. This step reviews individual operators have an optimal workload
how the list of functions appropriate for the scope across all operational modes. This step can only be
of the project was arrived at. Often the list of done at a very high level in the early stages of the
functions for the control room is not documented in project nevertheless a time line analysis at this stage
a systematic way. This results in functions being often demonstrates that the workloads of the
missed out in the planning stages. Our experience operators is unrealistic and poorly balanced across
is that it is not unusual to have extra workstations the shift and across operators. This allows a
added into the design at the final stages because a realistic staffing level to be considered early in the
function has been forgotten, resulting a less than design process. Our experience is that once the
optimal layout. Also sometimes functions are design is finished it becomes apparent that at
22
certain times, e.g., process start up, more operators should be verified before proceeding to the detailed
are needed in the CCR. This means that space design phase. Our experience is that
requirements and layout have to be reconsidered in
order to accommodate these people. Phase D. Detailed Design
The detailed design phase is an iterative process
Step 6: Verification and Validation (V&V) of
that begins with identifying clear and detailed
Phase B. An intermediate V&V is performed to
design requirements for systems, and ends with a
check and approve as a whole the allocations and
working control room.
assignments made in the preceding steps of Phase
B. The step reviews this checking process to ensure
Step 9: Detailed Design Requirements. This step
a safe, functional control centre will result, and to
reviews the process of developing the detailed
ensure any conflicts between these preliminary
design specifications to ensure that the correct
design steps are resolved before carrying out the
human factors input has been identified for the
conceptual design. Out experience is that V & V is
following detailed design areas:
not usually carried out until the end of the project,
when the control room is complete. By this time, 1. Control Suite Arrangement;
any changes that are recommended are very costly 2. Control Room Layout;
to implement and it is difficult to mitigate design
flaws. Like the design process the V&V process 3. Workstations Layout and Dimensions;
should be iterative and check the design before 4. Design of Displays and Controls;
proceeding to the conceptual design. 5. Environmental Design;
Phase C. Conceptual Design 6. Operational and Managerial Requirements;
7. Training; and
Step 7: Conceptual Design Framework for the
Control Centre. In the conceptual design, issues 8. Procedures.
such as equipment selection, layout, traffic patterns, It is our experience that most of these areas are well
information flow, and space allocation are typically covered by standards and guidelines, with the
addressed. In both upgrades and new designs, notable exceptions of the last three, and that this
models should be built to provide a tool for part of the design process is generally well done.
verification and validation, e.g., mock-ups, 3-D IS0 11064-1 does not include steps for Training
CAD, or Virtual Reality (VR) models. This step and Procedures but we felt that these issues should
integrates the results of previous steps and produces be included in the method. This was partly because
one or several design concepts and preliminary they are covered by NPD regulations but also
specifications. The review examines this process to because of our experience of what type of errors
ensure that human factors issues are fully occur in control room work. An example is that in
considered, Our experience is that a conceptual some companies, alarm systems are now being
layout is already developed long before the analyses improved by the use of suppression techniques.
of Phase 2 have been performed. Therefore, there However, the CCR operators are not given training
has to be many compromises made and it is usually in the suppression logic so they fail to understand
the case that the operators must fit the design rather what the alarms signify. It is, therefore important
than the design being human centred. to identify new skills that the operators need to
operate the process safely.
Step 8: Conceptual Design Approval. A formal
review of the conceptual design is an opportunity Step 10: Verification of the Detailed Design.
for checking the proposed design before starting This step is intended to verify that the design
detailed design. It also allows the project team to conforms to human factors principles. Throughout
agree a common way forward for the design. the detailed design phase, verifications are
Thirdly, it lets management see the proposals and recommended to ensure that the human factors
decide whether to support them before committing requirements are met. These evaluations should
major resources. Fourthly, it reduces the risk that consist primarily of guidelines and standards-based
the project team must make expensive changes later reviews. Deviations are easier to correct early in
in the project. the design process than later on. However, once the
final design is chosen, scenario-based reviews must
The design team then, in co-operation with future be conducted to ensure that the control centre’s
control centre users, -validates the design using crew performance meets the acceptance criteria. At
techniques such as walk-throughs, talk-throughs, this stage, correcting deviations or problems in the
and link analysis. Problems identified at the design becomes more costly, and trade-offs will
conceptual design stage are generally easy and probably need to be made. The usual method for a
relatively inexpensive to remedy. Any changes final in the Norwegian sector is the use of a CRIOP
23
analysis[ 11. However, the limitations of the CRIOP companies and projects that are inspected by the
method are widely know and the method is NPD .
currently being updated. It was not within the
scope of this method to duplicate that work. ACKNOWLEDGEMENTS
Phase E. Operational Feedback The authors wish to acknowledge and thank the
members of IFE human factors staff Angie Sebok,
Step 11: Operational Feedback. Even though the Dolores Morisseau, Lars Age Seim and Jan Skriver,
design is implemented, the consideration of how who were joint authors of the project report to the
human factors issues affect control room NPD.
performance and working environment should not
end here. Government regulations require that
operational experience is systematically collected,
REFERENCES
analysed and used in improving safety and work
environment. This step reviews the topics that Green, M., Collier, S.G. (2000) A Method
should be covered to provide the basis for human for Reviewing Human Factors in Control
factors improvements, as well as suggestions on Centre Design. Halden, report no.
methods that may be applied. Operational IFE/HFUF-OO/xxxx (confidential).
experience provides useful feedback to designers
[Publicly available from the NPD at
regarding the successes and problem areas of the
design, and will offer necessary input to future http://npd.nolWebdesWnetblastJpages/standa
design projects. Currently there are few systematic rd.html?query=Webside.idWebside=13209]
methods for collecting this type of information
during the control room's lifetime. Data, when
collected, comes from retrospective 'methods such Intemational Standards Organisation ( 1999)
as alarm lists and incident reports. However, few Ergonomic Design of Control Centres -
companies have systematic methods for identifying
Part I : Principles for the Design of Control
the causes of human error in incidents and '
accidents, so this data is relatively poor. In future Centres. Geneva: IS0 (Final Draft
when this data is collected, it will form part of the Intemational Standard ISOIFDIS 11064-1).
OER carried out in Step 1.
24