You are on page 1of 1

NOTES

CN 01 CONSTRUCTION STAGES
FIRST PHASE - EXTENSION OF FOUNDATION AND ADDITION / REPLACEMENT OF BOLTS 1. PLANT DATUM H.P.P. EL.+100.000 CORRESPONDS TO EL.+15.550 METERS ABOVE THE LOW LOW WATER SPRING (LLWS).
1. ALL THE ADJOINING STRUCTURES / FACILITIES SHALL BE PROPERLY PROTECTED BEFORE STARTING THE 2. ALL DIMENSIONS ARE IN MILLIMETERS (UNLESS INDICATED OTHERWISE).
TN DEMOLITION WORK. EXISTING EQUIPMENT (IF ANY) SHALL BE REMOVED / DISMANTLED FROM POSITION.
EXISTING PLATFORM / PIPE SUPPORT (IF ANY) ABOVE PEDESTAL SHALL BE REMOVED / DISMANTLED.
3. ALL ELEVATIONS AND COORDINATES ARE IN METERS (UNLESS INDICATED OTHERWISE).
49° 01
4. DIMENSIONS AND DETAILS TO BE CROSS VERIFIED AND CONFIRMED FROM SITE.
2. EXISTING BOLTS, AFTER REMOVAL OF GROUT SHALL BE CUT AND FLUSHED WITH EXISTING TOC. 5. PRIOR TO THE EXECUTION OF WORKS DESCRIBED IN THIS DRAWING, THE SUB-CONTRACTOR HAS TO PREPARE A
EXISTING / DEMOLITION RECONSTRUCTION / MODIFICATION 3. EXISTING PAVING SHALL BE DEMOLISHED. EXISTING REINFORCEMENT BARS FOR PAVING SHALL BE METHOD STATEMENT OF DESCRIBED WORKS AND TAKE APPROVAL FROM CONTRACTOR / OWNER REPRESENTATIVES AT
STAGES 1 TO 5 STAGES 6 TO 23 TEMPORARILY BENT UPWARDS DURING SOIL EXCAVATION AND TREATED WITH CORROSION INHIBITOR SITE.
PUMP FOUNDATION PLAN PUMP FOUNDATION PLAN (AAA03AB21). 6. BEFORE STARTING THE DEMOLITION ACTIVITIES, SITE SHALL BE INSPECTED BY SUBCONTRACTOR AND CONTRACTOR’S
(SCALE 1:25) (SCALE 1:25) 4. EXISTING SUB-GRADE / SUB-BASE & SOIL SHALL BE EXCAVATED (ABA02AD01). REPRESENTATIVE TO IDENTIFY AND MARK ANY POSSIBLE ADDITIONAL ITEMS NOT SHOWN IN THE DRAWING TO BE
OLD VENDER DRAWING NOT AVAILABLE (****) BEFORE STARTING FOUNDATION CONSTRUCTION ACTIVITIES, SUBCONTRACTOR DEMOLISHED OR RELOCATED. PRIOR APPROVAL BY CONTRACTOR REPRESENTATIVE IS NECESSARY BEFORE
5. ANY UNDERGROUND UTILITIES IF FOUND DURING EXCAVATION SHALL BE TEMPORARILY SUPPORTED OR
TO VERIFY ON SITE THAT, GIVEN COORDINATES & TOG LEVELS IS IN ACCORDANCE TO RE-ROUTED AS PER INSTRUCTIONS FROM ENGINEER IN CHARGE. DEMOLITION OF THESE ITEMS.
EXISTING DISCHARGE LINE. 7. DURING PAVING DEMOLITION EXISTING SURROUNDING FOUNDATIONS SHALL BE PRESERVED.
RECONSTRUCTION (FOUNDATION ENLARGEMENT SIDE).
6. AS THE NEW BOLTS ARE LOCATED (SEE PLAN VIEW) NEAR THE REINFORCEMENT OF EXISTING 8. THE NEW REINFORCEMENT TO BE EMBEDDED USING EPOXY RESIN CAN BE LOCALLY ADJUSTED IN CASE IT CLASHES
OF FOUNDATION
WITH EXISTING REINFORCEMENT.

X=5968.274
FOUNDATION, THE FOUNDATION SHALL BE FIRST DEMOLISHED ADEQUATELY WITHOUT DAMAGING THE
EXISTING REINFORCEMENT (ADA08AB02). 9. ANY DAMAGE TO THE EXISTING FOUNDATION DONE BY SUBCONTRACTOR DURING EQUIPMENT DISMANTLING SHALL BE
RECONSTRUCTED BY SUBCONTRACTOR.

(****)
200x137x885 DEEP EXISTING 7. ADDITIONAL REBAR SHALL BE ADDED BY CHEMICAL ANCHORING (ADA10BC01, ADA10AA02).
FOUNDATION TO BE DEMOLISHED OF FOUNDATION 200x250x885 DEEP CUT OUT TO BE 8. BEFORE POURING THE NEW CONCRETE, DEMOLISHED PART OF THE 10. ACCORDING TO SITE INSPECTION SURVEY, FOUNDATION IS IN GOOD CONDITION. NDT TEST IS DEEMED NOT NECESSARY.
ALONG WITH EXISTING BOLTS EXISTING REINFORCEMENT BARS TO BE 1220
X=5968.274 PRESERVED AND TREATED WITH POURED WITH CONCRETE. (TYP.) 11. ISOLATION JOINT IN CONCRETE SLAB ON GRADE SHALL BE FORMED WITH AN APPROVED BITUMEN IMPREGNATED
= = SURFACE SHALL BE TREATED WITH BONDING AGENT (ADA08AB02).
SURFACE PREPARATION 1220 CORROSION INHIBITOR FOR DETAIL REFER DETAIL ''A2/B2" FIBERBOARD. THE UPPER 20MM SHALL BE SEALED WITH AN APPROVED BITUMINOUS SEALANT RESISTANT TO
160 900 160

112.5
BY CHIPPING 9. CREATE POCKET FOR NEW ANCHOR BOLTS (ADA09BA01).

100
625 180 765 275 675 60 HYDROCARBONS, APPLIED STRICTLY IN ACCORDANCE WITH THE MANUFACTURER'S INSTRUCTIONS. THE JOINT FILLER
60 10. NEW PORTION OF FOUNDATION SHALL BE POURED WITH CONCRETE (ADA08AB02). SHALL BE FIXED FIRMLY TO THE FIRST PLACED CONCRETE BEFORE THE ADJOINING CONCRETE IS PLACED. THE

25
88
137

137
11. BITUMEN PAINT SHALL BE APPLIED ON THE EXTENDED NEW PORTION OF CONCRETE MUST BE THOROUGHLY COMPACTED ON BOTH SIDES OF THE EXPANSION JOINT. THE LOCATION OF

200
EXPANSION JOINTS SHALL BE AS SHOWN ON THE DRAWINGS WHERE REQUIRED BY DESIGN.

250
THE CONCRETE THAT IS EXPOSED.

265
12. ALL DIMENSIONS / COORDINATES / ELEVATIONS ARE BASED ON LASER SCAN DATA AND TO BE VERIFIED AT SITE BEFORE

280
12. EXCAVATED SIDES SHALL BE BACKFILLED AND COMPACTED (ACA05AM01)

165
350

665
200 200 OF EXISTING DISCHARGE OF NEW DISCHARGE
13. EXISTING REINFORCEMENT BARS FOR PAVING SHALL BE REPLACED IN THE ORIGINAL CONSTRUCTION ACTIVITIES.
Y=90441.477 200 TO BE ADOPTED BY PIPING
NEW GROUT TO BE POURED IN POSITION BEFORE POURING OF A NEW PAVING SHALL BE RESTORED (AEA08AG01) 13. BOF ELEVATION SHOWN IN THE DRAWING IS TENTATIVE DEPENDING ON DESIGN VERIFICATIONS. SITE TO ENSURE THAT,
Y=90441.477

255

825
860

(TYP.) ACTUAL DEPTH OF FOUNDATION SHALL BE EQUAL OR DEEPER THAN SPECIFIED ELEVATION TO PROCEED WITH GIVEN
255

SECOND PHASE DURING SKID


RECONSTRUCTION (ANCHOR BOLTS REPLACEMENT SIDE).

1000

1000
LEVELING MODIFICATIONS WORK. IN CASE OF SHALLOW FOUNDING DEPTH, SUBCONTRACTOR TO INFORM & TAKE CONCURRENCE
14. EXISTING FOUNDATION SHALL BE DEMOLISHED AT NEW BOLTS LOCATION, BY ADEQUATE METHOD TO FROM CIVIL DESIGN ENGINEER BEFORE PROCEEDING WITH GIVEN MODIFICATION.

(TYP.)
100

(TYP.)
PRESERVE EXISTING REINFORCEMENT, AS PER NEW BOLTS EMBEDMENT LENGTH REQUIREMENT

100
200
215 14. IN CASE OF HINDRANCE DUE TO SMALL PAVING SUPPORTS, SWITCH & INSTRUMENT SUPPORTS etc. CONSTRUCTION
215 PLUS 50MM. THE EXISTING CORRODED BOLTS SHALL BE CUT-OFF AND FLUSHED WITH EXISTING TOC. SUBCONTRACTOR CAN SUITABLY CHECK & DEMOLISH THESE PEDESTALS/SUPPORTS AFTER CONSULTING

1435

3375 (EXISTING FOUNDATION DIMENSION)


1 1 15. EXISTING REINFORCEMENT BARS SHALL BE PRESERVED AND TREATED WITH CORROSION INHIBITOR. CONTRACTOR'S RESPECTIVE DISCIPLINE ENGINEER AT SITE.
1 1
OF FOUNDATION

OF FOUNDATION
16. ADDITIONAL REBARS SHALL BE ADDED BY CHEMICAL ANCHORING (ADA10BC01, ADA10AA02). 15. CONSTRUCTION SUBCONTRACTOR TO SUITABLY DEVELOP THE REINFORCEMENT BBS FOR REQUIRED REBARS
1050

_ _ _ _
6 NOS. 17 DIA ANCHOR EXISTING BOLTS SECOND PHASE - NEW SKID INSTALLATION CONSIDERING SITE FEASIBILITY & CONCRETE CLEAR COVER AS SPECIFIED IN CONCRETE WORK GENERAL NOTE
(TYP.)

DRAWING 4239-AA-DX-00000005."
200

TO BE CUT AND FLUSHED WITH TOC. (CLV1)


(TYP.)

100
(ANCHOR BOLTS REPLACEMENT SIDE)
100

3400 (NEW SKID)


17. CONCRETE SURFACE SHALL BE TREATED WITH BONDING AGENT (ADA08AB02).

1000

1000
Y=90440.042 Y=90440.042
3375

3600
OF NEW SKID 18. NEW ANCHOR BOLTS/ POCKETS SHALL BE PLACED AT PROPOSED LOCATIONS AND

= =
==

250x200x350 DEEP EXISTING (****) FORMWORK SHALL BE PUT IN PLACE.


FOUNDATION TO BE DEMOLISHED
ALONG WITH EXISTING BOLTS 19. NEW PORTION OF FOUNDATION SHALL BE POURED WITH CONCRETE WITH APPROVED
MIX DESIGN TO AVOID SHRINKING (ADA08AB02).
200

200
20. EXCAVATED SIDES SHALL BE BACKFILLED AND COMPACTED (ACA05AM01)
1050

215x200x350 DEEP EXISTING 250 250


FOUNDATION TO BE DEMOLISHED 21. EXISTING REINFORCEMENT BARS FOR PAVING SHALL BE REPLACED IN THE ORIGINAL
ALONG WITH EXISTING BOLTS 215x200x350 DEEP CUT OUT TO BE POSITION BEFORE POURING OF A NEW PAVING. PAVING SHALL BE RESTORED (AEA08AG01)
POURED WITH CONCRETE. (TYP.) REFERENCE DRAWINGS:
900

250x200x350 DEEP CUT OUT TO BE

1000
(FOUNDATION ENLARGEMENT SIDE )
EXISTING GROUT TO BE FOR DETAIL REFER DETAIL ''A1/B1" POURED WITH CONCRETE. 4239-AA-DX-00000005 STANDARD DRAWING - CONCRETE GENERAL NOTES

2
1330

_
REMOVED AS PER DRAWING 22. INSTALLATION IN POCKET OF ANCHOR BOLTS (ADA11EB01).

100
NO. 4239-AA-DC-21U10RD030 1220x500x885 DEEP CUT OUT TO BOTH SIDE 4239-GG-VD-LG0362263P533001 GENERAL ARRANGEMENT DRAWING FOR FUEL OIL BLENDING (HGO) PUMP 63P533B
BE POURED WITH CONCRETE. 23. NEW GROUT SHALL BE POURED FOR SKID LEVELING (ADA12AB01). 4239-AA-DC-21U10RD030 REMOVAL OF EXISTING GROUT AND TOP OF FOUNDATION CHIPPING - AREA - OFFSITE
610

4239-AA-DA-2100N003 FOUNDATION LAYOUT CONSTRUCTION PLAN AREA 5 OFFSITE (PART-B)


388
25

200 200

500
100
1315
SURFACE PREPARATION 970 (NEW SKID)
2260 100X100X350 125 125 LEGEND

100
112.5
BY CHIPPING POCKET = = 4#14 @200 INDICATES MODIFICATION

X=5967.824
1220x388x885 DEEP EXISTING NEW REBARS
450

525

525
FOUNDATION TO BE DEMOLISHED 10 NOS. 20 DIA NEW ANCHOR BOLTS

2_
12 DIA NEW
ALONG WITH EXISTING BOLTS BY VENDOR 1050
REBAR CONCRETE CHIPPING
OF NEW SKID
TO BE ADOPTED BY PIPING
OF NEW DISCHARGE
ABBREVIATIONS
CLV1 : REDUCTION OF ANCHOR BOLT ORIGINAL DIAMETER LESS THAN 2.00mm,
NO DAMAGE OF ANCHOR BOLTS AND NUT'S THREAD
CLV2 : REDUCTION OF ANCHOR BOLT ORIGINAL DIAMETER MORE THAN 2.00mm,
DAMAGE OF ANCHOR BOLTS AND NUT'S THREAD
CLV3 : ANY OTHER DAMAGE OF ANCHOR BOLTS AND NUT'S THREAD OR BENDING OF
EXISTING ANCHOR BOLTS

EXISTING / DEMOLITION RECONSTRUCTION / MODIFICATION RECONSTRUCTION / MODIFICATION


STAGES 1 TO 5 STAGES 6 TO 23
STAGES 6 TO 23
SECTION SECTION 2
SECTION 1 1
(SCALE 1:25) -
(SCALE 1:25) - (SCALE 1:25) -
(**) SUB-CONTRACTOR TO INFORM CONTRACTOR IN CASE (**) SUB-CONTRACTOR TO INFORM CONTRACTOR IN CASE
(**) SUB-CONTRACTOR TO INFORM CONTRACTOR IN CASE OF HIGHER PAVING THICKNESS.
OF HIGHER PAVING THICKNESS. OF HIGHER PAVING THICKNESS.
(***) FROM 3D MODEL (***) FROM 3D MODEL
(***) FROM 3D MODEL
(****) BEFORE STARTING FOUNDATION CONSTRUCTION ACTIVITIES, SUBCONTRACTOR
(****) BEFORE STARTING FOUNDATION CONSTRUCTION ACTIVITIES, SUBCONTRACTOR
TO VERIFY ON SITE THAT, GIVEN COORDINATES & TOG LEVELS IS IN ACCORDANCE TO
TO VERIFY ON SITE THAT, GIVEN COORDINATES & TOG LEVELS IS IN ACCORDANCE TO
EXISTING DISCHARGE LINE.
EXISTING DISCHARGE LINE.

JUST BEFORE POURING GROUTING CONCRETE SURFACE TO BE TREATED


EXISTING BOLTS TO BE CUT AND 1220 1220 WITH EPOXY BONDING AGENT LIKE
FLUSHED WITH TOC. CONCRETE SURFACE TO BE 500
P=80

215 845 160 NITOBOND EP OR EQUIVALENT


P=75

EXISTING GROUT TO BE REMOVED TREATED WITH EPOXY BONDING AGENT 30 THK. NEW GROUT TO BE POURED IN M20 NEW ANCHOR BOLTS 200 200 110
180 765 275 AS PER DRAWING NO. LIKE NITOBOND EP OR EQUIVALENT 160 900 160 30 THK. NEW GROUT TO BE POURED IN
SECOND PHASE DURING SKID LEVELING
40

SUPPLIED BY VENDOR (TYP.)


4239-AA-DC-21U10RD030 SECOND PHASE DURING SKID LEVELING
EL.+99.550 (***) EL.+99.540 (****)

75
EL.+99.510 (TOC) EL.+99.510 (TOC) EL.+99.540 (****) EL.+99.510 (TOC)
(TOG) (TOG) (TOG)
350
425

415
385

350
415

P=115
75

EL.+99.125 (***)TOP OF EXISTING PAVING EL.+99.125 (***)TOP OF EXISTING PAVING


100
150 (**)

150 (**)
925

915

150 (**)

685
100

915
75
500

350

350
100
EL.+98.625 (BOF) EL.+98.625 (BOF) 1
1 (TYP.) EL.+98.625 (BOF)
(REFER NOTE 13) (REFER NOTE 13) (REFER NOTE 13)
PAVING TO BE RESTORED 535
0.3MM THICK POLYTHENE 500(TYP.)

75
215x200x350 DEEP EXISTING FOUNDATION 50 THK EXISTING 20THK. ISOLATION JOINT (TYP.) (TYP.)
SHEET (TYP.) NEW POLYTHENE SHEET
TO BE DEMOLISHED LEAN CONCRETE (TYP.) 3#14@100 (TYP) (SEE NOTE 11) 50 THK. EXISTING
50 THK LEAN CONCRETE (TYP) M20 NEW ANCHOR BOLTS EXCAVATED SIDES TO BE BACKFILLED
ANCHOR BOLT POCKET TO BE CREATED BY EXISTING REINFORCEMENT BARS TO BE ADDITIONAL REBARS AND COMPACTED TO 95% MDD LEAN CONCRETE
215x200x350 DEEP CUT OUT SUPPLIED BY VENDOR
150MM DIA X 350MM DEEP CORE CUTTING PRESERVED AND TREATED WITH 100x100x350 TO BE POURED WITH EMBEDDED IN CONCRETE WITH
TO BE POURED WITH EXISTING REINFORCEMENT
NEW PORTION OF FOUNDATION TO BE
NON-SHRINK GROUT HIT-HY-500R-V4 EPOXY RESIN PRICE CODE
AND INTERNAL CONCRETE CHIPPING INTO CORROSION INHIBITOR CONCRETE (TYP.) POURED WITH CONCRETE
WITH DRILL BIT OF NOMINAL
8#14
EXISTING FOUNDATION ADDITIONAL REBAR DIA 14 OR 16 mm (TYP.) PRICE CODES DESCRIPTION OF WORK
AAA03AB21 DEMOLITION OF REINFORCED PAVING CONCRETE
AAA03AD03 CHIPPING OF EXISTING RC WORK
ABA02AD01 LIMITED SECTION EXCAVATIONS BY HAND
ACA05AM01 BACKFILLING
AEA10AB01 SUPPLY, CUTTING, MACHINING AND INSTALLATION OF WIRE WELDED MESH
ADA08AA01 LEAN CONCRETE
ADA08AB02 CONCRETE FOR FOUNDATION
AEA08AG01 CONCRETE FOR PAVING

DETAIL DETAIL SECTION SECTION 3 ADA09AA01 STRAIGHT FORMWORK FOR CONCRETE FOUNDATIONS
A1 B1 2
(SCALE 1:10) - ADA09BA01 ANCHOR BOLT BOXES
(SCALE 1:10) - (SCALE 1:10) - (SCALE 1:10) -
ADA10AA02 SUPPLY AND INSTALLATION OF REBAR
SECTION FOR STAGES 6 TO 23
SECTION FOR STAGES 6 TO 23 CONCRETE SURFACE TO BE TREATED ADA10BC01 FIXING STEEL REBAR HILTI DRILL INTO EXISTING CONCRETE
(AS PER SHOWN EXISTING (IN CASE OF DIFFERENT EXISTING
WITH EPOXY BONDING AGENT LIKE
REINFORCEMENT ARRANGEMENT / CASE 1) REINFORCEMENT ARRANGEMENT / CASE 2) ADA11EB01 INSTALLATION IN EXISTING BOXES OF ANCHOR BOLTS
NITOBOND EP OR EQUIVALENT
M20 NEW ANCHOR BOLTS ADA12AB01 NON-SHRINK GROUT
290 125 250
SUPPLIED BY VENDOR ADA16AA01 THREE COATS OF OXIDIZED BITUMINOUS PAINT
(TYP.) 200
P=75

30 THK. NEW GROUT TO BE POURED IN


SECOND PHASE DURING SKID LEVELING
ADA16AB01 POLYETHYLENE SHEET
KEY PLAN (OFFSITE- AREA 5)
CN
75

CONCRETE FOR FOUNDATION QUANTITY

.
49 Gr
44.1°
DRAWING LIMIT
X = 5656.210 DRAWING LIMIT
ROAD 1

290

Y = 90094.700
290

Y = 90430.820
75

TN
2#14@100 125 MATERIAL TOTAL QUANTITY [Cu. M]

TRACK 8
PW
215 125 215 125

FOR CONT. REFER DWG. NO. 4239-XX-DE-41000001


ADDITIONAL REBARS
2#14@100
200

0.121
350

FOUNDATION CONCRETE PW
52 TK 61 I X = 5722.955 X = 5722.955 52 TK 63 J 52 TK 63 H X = 5722.955 52 TK 61 H

ADDITIONAL REBARS

Y = 90472.045
ROAD 16

ROAD 14
01

Y = 90142.100

Y = 90235.050

Y = 90281.750

Y = 90350.565
52 P 549
NEW POWER STATION
(SOLAR TURBINE SITE)

72 TK 581 X = 5759.811

1_ 1 2_ 2 PAVING CONCRETE QUANTITY 01


200

200
100

100

52 TK 63 K X = 5784.250 X = 5784.250 52 TK 63 I 52 TK 63 G X = 5784.250 52 TK 61 G

_ _ 20 THK. ISOLATION JOINT


75

X = 5807.330 ROAD 3

MATERIAL TOTAL QUANTITY [Cu. M] BASIN 4 SOUTH BASIN 4 NORTH


S/S D

215 52 P 511A/ B 01 X = 5850.630


Y = 90430.670
52 TK 01 F

X = 5837.410
52 TK 01 E

CONCRETE FOR PAVING 0.515


52 P 512A/ B
52 P 513A/ B
52 TK 01 D 52 TK 01 C
X = 5850.630 X = 5850.630

FOR CONT. REFER DWG. NO. 4239-XX-DE-21000001


EMBEDDED WITH HILTI
ROAD 5

TRACK 2
X = 5854.610

EMBEDDED WITH HILTI

FOR CONT. REFER DWG. NO. 4239-XX-DE-41000001

Y = 90598.810

Y = 90630.310
01 BASIN 1
01 52 P 508 A/B/C 56 P 505

HIT-RE-500- V4 EPOXY RESIN


51 P 531A/ B
685

52 P 509 A/ B 52 P 510A/ B
56 P 501A/B/C

HIT-RE-500- V4 EPOXY RESIN

Y = 90142.100

Y = 90142.100
52 TK 61 M 52 TK 61 L 01
X = 5885.000
X = 5890.250

WITH DRILL BIT OF NOMINAL


52 TK 02 D 52 TK 02 C

ROAD 4
ROAD 12
56 P 506

ROAD 8
52 TK 57 I 52 TK 59 H 01

WITH DRILL BIT OF NOMINAL

Y = 90478.415

Y = 90508.715
TRACK 8
52 TK 57 K 52 TK 59 F 56 P 507

DEMOLITION OF REINFORCED PAVING


01
52 TK 57 P X = 5711.525 52 TK 57 M X = 5711.525 X = 5711.525

DIA. 18mm (TYP.)

ROAD 18
X = 5916.540

EMBEDDED WITH HILTI


56 P 502A/ B

DIA. 18mm (TYP.)


X = 5921.910 56 P 503A/ B

TRACK 6
56 P 504

Y = 90360.325
51 TK 01 D
51 TK 01 C

Y = 90227.225

Y = 90258.935

Y = 90303.935
52 TK 61 K 52 TK 61 J BASIN 1
BASIN 2

HIT-RE-500- V4 EPOXY RESIN


CONCRETE QUANTITY 52 TK 57 N X = 5959.175 52 TK 57 L X = 5959.175 X = 5959.175 52 TK 59 E

TRACK 4
WITH DRILL BIT OF NOMINAL 63 P 533 S/S 15
A
3650 S/S B

2#14@100 ADDITIONAL REBARS


B

3#14@100 ADDITIONAL REBARS

Y = 90000.000
EXISTING S/S

Y = 90668.520
C 3700
52 TK 57 J 72 P 545 72 TK 580 X = 5975.984
52 TK 57 H 52 TK 59 G A 3360
B 2450
72 P 544 2450 01

DIA 18mm (TYP.)


X = 5980.174

Y = 90442.297

Y = 90465.040
BASIN 5 SOUTH BASIN 5 NORTH BASIN 5 NORTH
01

EXISTING REINFORCEMENT EXISTING REINFORCEMENT MATERIAL TOTAL QUANTITY [Cu. M] FOR CONT. REFER DWG. NO. 4239-XX-DE-41000002
50 P 534 A/B/C
50 P 539 A 01
ROAD 7
X = 6000.000

S/S C
X = 6019.150
FOR CONT. REFER DWG. NO. 4239-XX-DE-21000002

Y = 90094.640
FOR CONT. REFER

Y = 90430.820
50 P 539 B
01 TRACK 9 DWG. NO. 4239-XX-DE-21000001

Y = 90616.479
PAVING CONCRETE 0.515
50 P 539 C
50 P 539 D/E

PAVING TO BE RESTORED
50 TK 01 L X = 6055.925 50 TK 01 J X = 6055.925 50 TK 01 H X = 6055.925

NEW POLYTHENE SHEET 63P533B

Y = 90142.100

Y = 90252.275

Y = 90345.875
75

1 EXCAVATED SIDES TO BE BACKFILLED DEMOLITION OF REINFORCED 50 TK 01 K X = 6110.925 50 TK 01 I X = 6110.925 50 TK 01 G X = 6110.925


X = 6099.388

1 AND COMPACTED TO 95% MDD

FOR CONT. REFER DWG. NO. 4239-XX-DE-21000001


Y = 90094.790
NEW PORTION OF FOUNDATION TO BE
FOUNDATION CONCRETE QUANTITY X = 6152.160

FOR CONT. REFER DWG. NO. 4239-XX-DE-41000002


BASIN 6 SOUTH BASIN 6 NORTH

ROAD 11

500(TYP.)

Y = 90208.000
01
52 P 504 A/ B
52 TK 51 F

300 POURED WITH CONCRETE MATERIAL TOTAL QUANTITY [Cu. M]


HORTON
SPHERE
X = 6178.900

AVENUE B
52 TK 51 G 52 TK 51 E
X = 6197.500

(TYP.) FOUNDATION CONCRETE 0.121

ROAD 12
Y = 90375.825
Y = 90353.295
8#12

Y = 90332.000
DETAIL DETAIL EMBEDDED IN CONCRETE WITH

Y = 90430.820
A1 B1 ADDITIONAL REBARS 01

Y = 90392.023
FGL EL. 99.350

(SCALE 1:10) - (SCALE 1:10) -


HIT-HY-500R-V4 EPOXY RESIN
WITH DRILL BIT OF NOMINAL 4#12 @ 200 GROUT QUANTITY FOR CONT. REFER
DWG. NO. 4239-XX-DE-41000002

DIA 14 OR 16 mm (TYP.) ADDITIONAL REBARS MATERIAL TOTAL QUANTITY [Cu. M]


(AS PER SHOWN EXISTING (IN CASE OF DIFFERENT EXISTING 8#12 50 THK. NEW LEAN CONCRETE GROUT 0.299
am
REINFORCEMENT ARRANGEMENT / CASE 1) REINFORCEMENT ARRANGEMENT / CASE 2) ADDITIONAL REBAR N.Nik

FIXING STEEL REBARS 02 17.Nov.2022 IFC - ISSUE FOR CONSTRUCTION N.NIKAM K.Pachgade A.Frigerio

3_ 3_ INTO EXISTING CONCRETE REBARS FOR FOUNDATION QUANTITY 01

00
30.Sept.2022

27.JULY.2022
IFA - ISSUE FOR APPROVAL

IFA - ISSUE FOR APPROVAL


S.PATIL

A.Sawant
K.Pachgade

V.Rama Rao
A.Frigerio

A.Frigerio
MATERIAL TOTAL QUANTITY [NOS.] MATERIAL TOTAL QUANTITY [Kg.] Issue Date Reason for Issue - Revision Description Prepared Checked Approved
60 200 EXISTING REINFORCEMENT EXISTING REINFORCEMENT 9 (FOR DETAILS -A1, SECTION-1) 7.405 (FOR DETAILS -A1, SECTION-1)
REBARS REBARS
Digital signature
60 200 REBARS 6 (FOR DETAILS -B1, SECTION-2) REBARS 5.663 (FOR DETAILS -B1, SECTION-2)
AUTHORIZED FOR CONSTRUCTION
REBARS 12 (FOR DETAILS -A2) REBARS 11.034 (FOR DETAILS -A2)
REBARS 8 (FOR DETAILS -B2, SECTION-3) REBARS 8.324 (FOR DETAILS -B2, SECTION-3) DATE INITIAL SIGNATURE
REBARS 12 (FOR DETAILS -A3) REBARS 13.705 (FOR DETAILS -A3) 17.Nov.2022 O.OJU (Civil Dep.DL)
250

250

2#14@100 ADDITIONAL REBARS 12 (FOR DETAILS -B3, SECTION-4) REBARS 12.922 (FOR DETAILS -B3, SECTION-4)
REBARS TECNIMONT IDENTIFICATION CODE
REHABILITATION OF
325

325

Job-EC-Type-N°
CONDITION OF EXISTING FOUNDATION
PORT HARCOURT 4239-AA-DC-21U62RN018
EMBEDDED WITH HILTI EMBEDDED WITH HILTI PHASE DESCRIPTION CONCLUSION REFINERY PROJECT
125

125

DOC. CLASS. ISSUE


HIT-RE-500- V4 EPOXY RESIN HIT-RE-500- V4 EPOXY RESIN (Port Harcourt - Nigeria) 1 02
WITH DRILL BIT OF NOMINAL WITH DRILL BIT OF NOMINAL BEFORE CHIPPING 1. SURFACE DETERIORATION AND DISCOLORATION OF CONCRETE SURFACE DUE TO THE EXISTING FOUNDATION IS DEEMED ACCEPTABLE
DIA. 18mm (TYP.) DIA. 18mm (TYP.) OF EXISTING GROUT EXPOSURE TO ENVIRONMENTAL FACTORS AND OIL SPILLS OBSERVED. THROUGH COSMETIC REPAIR, ACCORDING TO CLIENT IDENTIFICATION CODE

2. SLIGHT DAMAGE ON THE CONCRETE FOUNDATION OBSERVED. PROJECT SPECIFICATION 4239-AA-SG-00000007. PORT HARCOURT
REFINING COMPANY
LIMITED (PHRC)
3
_ 3
_ AFTER CHIPPING
OF EXISTING GROUT (****) (****) TITLE
CONCRETE DRAWING
AFTER DEMOLITION
ACTIVITIES SHOWN IN THIS (****) (****) ANCHOR BOLT REPLACEMENT FOR
DRAWING
NOTE :- (****) MEANT FOR : "TO BE FILLED BY CONTRACTOR'S REPRESENTATIVE"
FOUNDATION PUMP 63P533B - OFFSITE- AREA 5 SCALE
1:25 / 1:10
ORIG. SIZE
A0

You might also like