Professional Documents
Culture Documents
4239 AA DC 21U62RN018 IS02 - Checkprint
4239 AA DC 21U62RN018 IS02 - Checkprint
CN 01 CONSTRUCTION STAGES
FIRST PHASE - EXTENSION OF FOUNDATION AND ADDITION / REPLACEMENT OF BOLTS 1. PLANT DATUM H.P.P. EL.+100.000 CORRESPONDS TO EL.+15.550 METERS ABOVE THE LOW LOW WATER SPRING (LLWS).
1. ALL THE ADJOINING STRUCTURES / FACILITIES SHALL BE PROPERLY PROTECTED BEFORE STARTING THE 2. ALL DIMENSIONS ARE IN MILLIMETERS (UNLESS INDICATED OTHERWISE).
TN DEMOLITION WORK. EXISTING EQUIPMENT (IF ANY) SHALL BE REMOVED / DISMANTLED FROM POSITION.
EXISTING PLATFORM / PIPE SUPPORT (IF ANY) ABOVE PEDESTAL SHALL BE REMOVED / DISMANTLED.
3. ALL ELEVATIONS AND COORDINATES ARE IN METERS (UNLESS INDICATED OTHERWISE).
49° 01
4. DIMENSIONS AND DETAILS TO BE CROSS VERIFIED AND CONFIRMED FROM SITE.
2. EXISTING BOLTS, AFTER REMOVAL OF GROUT SHALL BE CUT AND FLUSHED WITH EXISTING TOC. 5. PRIOR TO THE EXECUTION OF WORKS DESCRIBED IN THIS DRAWING, THE SUB-CONTRACTOR HAS TO PREPARE A
EXISTING / DEMOLITION RECONSTRUCTION / MODIFICATION 3. EXISTING PAVING SHALL BE DEMOLISHED. EXISTING REINFORCEMENT BARS FOR PAVING SHALL BE METHOD STATEMENT OF DESCRIBED WORKS AND TAKE APPROVAL FROM CONTRACTOR / OWNER REPRESENTATIVES AT
STAGES 1 TO 5 STAGES 6 TO 23 TEMPORARILY BENT UPWARDS DURING SOIL EXCAVATION AND TREATED WITH CORROSION INHIBITOR SITE.
PUMP FOUNDATION PLAN PUMP FOUNDATION PLAN (AAA03AB21). 6. BEFORE STARTING THE DEMOLITION ACTIVITIES, SITE SHALL BE INSPECTED BY SUBCONTRACTOR AND CONTRACTOR’S
(SCALE 1:25) (SCALE 1:25) 4. EXISTING SUB-GRADE / SUB-BASE & SOIL SHALL BE EXCAVATED (ABA02AD01). REPRESENTATIVE TO IDENTIFY AND MARK ANY POSSIBLE ADDITIONAL ITEMS NOT SHOWN IN THE DRAWING TO BE
OLD VENDER DRAWING NOT AVAILABLE (****) BEFORE STARTING FOUNDATION CONSTRUCTION ACTIVITIES, SUBCONTRACTOR DEMOLISHED OR RELOCATED. PRIOR APPROVAL BY CONTRACTOR REPRESENTATIVE IS NECESSARY BEFORE
5. ANY UNDERGROUND UTILITIES IF FOUND DURING EXCAVATION SHALL BE TEMPORARILY SUPPORTED OR
TO VERIFY ON SITE THAT, GIVEN COORDINATES & TOG LEVELS IS IN ACCORDANCE TO RE-ROUTED AS PER INSTRUCTIONS FROM ENGINEER IN CHARGE. DEMOLITION OF THESE ITEMS.
EXISTING DISCHARGE LINE. 7. DURING PAVING DEMOLITION EXISTING SURROUNDING FOUNDATIONS SHALL BE PRESERVED.
RECONSTRUCTION (FOUNDATION ENLARGEMENT SIDE).
6. AS THE NEW BOLTS ARE LOCATED (SEE PLAN VIEW) NEAR THE REINFORCEMENT OF EXISTING 8. THE NEW REINFORCEMENT TO BE EMBEDDED USING EPOXY RESIN CAN BE LOCALLY ADJUSTED IN CASE IT CLASHES
OF FOUNDATION
WITH EXISTING REINFORCEMENT.
X=5968.274
FOUNDATION, THE FOUNDATION SHALL BE FIRST DEMOLISHED ADEQUATELY WITHOUT DAMAGING THE
EXISTING REINFORCEMENT (ADA08AB02). 9. ANY DAMAGE TO THE EXISTING FOUNDATION DONE BY SUBCONTRACTOR DURING EQUIPMENT DISMANTLING SHALL BE
RECONSTRUCTED BY SUBCONTRACTOR.
(****)
200x137x885 DEEP EXISTING 7. ADDITIONAL REBAR SHALL BE ADDED BY CHEMICAL ANCHORING (ADA10BC01, ADA10AA02).
FOUNDATION TO BE DEMOLISHED OF FOUNDATION 200x250x885 DEEP CUT OUT TO BE 8. BEFORE POURING THE NEW CONCRETE, DEMOLISHED PART OF THE 10. ACCORDING TO SITE INSPECTION SURVEY, FOUNDATION IS IN GOOD CONDITION. NDT TEST IS DEEMED NOT NECESSARY.
ALONG WITH EXISTING BOLTS EXISTING REINFORCEMENT BARS TO BE 1220
X=5968.274 PRESERVED AND TREATED WITH POURED WITH CONCRETE. (TYP.) 11. ISOLATION JOINT IN CONCRETE SLAB ON GRADE SHALL BE FORMED WITH AN APPROVED BITUMEN IMPREGNATED
= = SURFACE SHALL BE TREATED WITH BONDING AGENT (ADA08AB02).
SURFACE PREPARATION 1220 CORROSION INHIBITOR FOR DETAIL REFER DETAIL ''A2/B2" FIBERBOARD. THE UPPER 20MM SHALL BE SEALED WITH AN APPROVED BITUMINOUS SEALANT RESISTANT TO
160 900 160
112.5
BY CHIPPING 9. CREATE POCKET FOR NEW ANCHOR BOLTS (ADA09BA01).
100
625 180 765 275 675 60 HYDROCARBONS, APPLIED STRICTLY IN ACCORDANCE WITH THE MANUFACTURER'S INSTRUCTIONS. THE JOINT FILLER
60 10. NEW PORTION OF FOUNDATION SHALL BE POURED WITH CONCRETE (ADA08AB02). SHALL BE FIXED FIRMLY TO THE FIRST PLACED CONCRETE BEFORE THE ADJOINING CONCRETE IS PLACED. THE
25
88
137
137
11. BITUMEN PAINT SHALL BE APPLIED ON THE EXTENDED NEW PORTION OF CONCRETE MUST BE THOROUGHLY COMPACTED ON BOTH SIDES OF THE EXPANSION JOINT. THE LOCATION OF
200
EXPANSION JOINTS SHALL BE AS SHOWN ON THE DRAWINGS WHERE REQUIRED BY DESIGN.
250
THE CONCRETE THAT IS EXPOSED.
265
12. ALL DIMENSIONS / COORDINATES / ELEVATIONS ARE BASED ON LASER SCAN DATA AND TO BE VERIFIED AT SITE BEFORE
280
12. EXCAVATED SIDES SHALL BE BACKFILLED AND COMPACTED (ACA05AM01)
165
350
665
200 200 OF EXISTING DISCHARGE OF NEW DISCHARGE
13. EXISTING REINFORCEMENT BARS FOR PAVING SHALL BE REPLACED IN THE ORIGINAL CONSTRUCTION ACTIVITIES.
Y=90441.477 200 TO BE ADOPTED BY PIPING
NEW GROUT TO BE POURED IN POSITION BEFORE POURING OF A NEW PAVING SHALL BE RESTORED (AEA08AG01) 13. BOF ELEVATION SHOWN IN THE DRAWING IS TENTATIVE DEPENDING ON DESIGN VERIFICATIONS. SITE TO ENSURE THAT,
Y=90441.477
255
825
860
(TYP.) ACTUAL DEPTH OF FOUNDATION SHALL BE EQUAL OR DEEPER THAN SPECIFIED ELEVATION TO PROCEED WITH GIVEN
255
1000
1000
LEVELING MODIFICATIONS WORK. IN CASE OF SHALLOW FOUNDING DEPTH, SUBCONTRACTOR TO INFORM & TAKE CONCURRENCE
14. EXISTING FOUNDATION SHALL BE DEMOLISHED AT NEW BOLTS LOCATION, BY ADEQUATE METHOD TO FROM CIVIL DESIGN ENGINEER BEFORE PROCEEDING WITH GIVEN MODIFICATION.
(TYP.)
100
(TYP.)
PRESERVE EXISTING REINFORCEMENT, AS PER NEW BOLTS EMBEDMENT LENGTH REQUIREMENT
100
200
215 14. IN CASE OF HINDRANCE DUE TO SMALL PAVING SUPPORTS, SWITCH & INSTRUMENT SUPPORTS etc. CONSTRUCTION
215 PLUS 50MM. THE EXISTING CORRODED BOLTS SHALL BE CUT-OFF AND FLUSHED WITH EXISTING TOC. SUBCONTRACTOR CAN SUITABLY CHECK & DEMOLISH THESE PEDESTALS/SUPPORTS AFTER CONSULTING
1435
OF FOUNDATION
16. ADDITIONAL REBARS SHALL BE ADDED BY CHEMICAL ANCHORING (ADA10BC01, ADA10AA02). 15. CONSTRUCTION SUBCONTRACTOR TO SUITABLY DEVELOP THE REINFORCEMENT BBS FOR REQUIRED REBARS
1050
_ _ _ _
6 NOS. 17 DIA ANCHOR EXISTING BOLTS SECOND PHASE - NEW SKID INSTALLATION CONSIDERING SITE FEASIBILITY & CONCRETE CLEAR COVER AS SPECIFIED IN CONCRETE WORK GENERAL NOTE
(TYP.)
DRAWING 4239-AA-DX-00000005."
200
100
(ANCHOR BOLTS REPLACEMENT SIDE)
100
1000
1000
Y=90440.042 Y=90440.042
3375
3600
OF NEW SKID 18. NEW ANCHOR BOLTS/ POCKETS SHALL BE PLACED AT PROPOSED LOCATIONS AND
= =
==
200
20. EXCAVATED SIDES SHALL BE BACKFILLED AND COMPACTED (ACA05AM01)
1050
1000
(FOUNDATION ENLARGEMENT SIDE )
EXISTING GROUT TO BE FOR DETAIL REFER DETAIL ''A1/B1" POURED WITH CONCRETE. 4239-AA-DX-00000005 STANDARD DRAWING - CONCRETE GENERAL NOTES
2
1330
_
REMOVED AS PER DRAWING 22. INSTALLATION IN POCKET OF ANCHOR BOLTS (ADA11EB01).
100
NO. 4239-AA-DC-21U10RD030 1220x500x885 DEEP CUT OUT TO BOTH SIDE 4239-GG-VD-LG0362263P533001 GENERAL ARRANGEMENT DRAWING FOR FUEL OIL BLENDING (HGO) PUMP 63P533B
BE POURED WITH CONCRETE. 23. NEW GROUT SHALL BE POURED FOR SKID LEVELING (ADA12AB01). 4239-AA-DC-21U10RD030 REMOVAL OF EXISTING GROUT AND TOP OF FOUNDATION CHIPPING - AREA - OFFSITE
610
200 200
500
100
1315
SURFACE PREPARATION 970 (NEW SKID)
2260 100X100X350 125 125 LEGEND
100
112.5
BY CHIPPING POCKET = = 4#14 @200 INDICATES MODIFICATION
X=5967.824
1220x388x885 DEEP EXISTING NEW REBARS
450
525
525
FOUNDATION TO BE DEMOLISHED 10 NOS. 20 DIA NEW ANCHOR BOLTS
2_
12 DIA NEW
ALONG WITH EXISTING BOLTS BY VENDOR 1050
REBAR CONCRETE CHIPPING
OF NEW SKID
TO BE ADOPTED BY PIPING
OF NEW DISCHARGE
ABBREVIATIONS
CLV1 : REDUCTION OF ANCHOR BOLT ORIGINAL DIAMETER LESS THAN 2.00mm,
NO DAMAGE OF ANCHOR BOLTS AND NUT'S THREAD
CLV2 : REDUCTION OF ANCHOR BOLT ORIGINAL DIAMETER MORE THAN 2.00mm,
DAMAGE OF ANCHOR BOLTS AND NUT'S THREAD
CLV3 : ANY OTHER DAMAGE OF ANCHOR BOLTS AND NUT'S THREAD OR BENDING OF
EXISTING ANCHOR BOLTS
EXISTING GROUT TO BE REMOVED TREATED WITH EPOXY BONDING AGENT 30 THK. NEW GROUT TO BE POURED IN M20 NEW ANCHOR BOLTS 200 200 110
180 765 275 AS PER DRAWING NO. LIKE NITOBOND EP OR EQUIVALENT 160 900 160 30 THK. NEW GROUT TO BE POURED IN
SECOND PHASE DURING SKID LEVELING
40
75
EL.+99.510 (TOC) EL.+99.510 (TOC) EL.+99.540 (****) EL.+99.510 (TOC)
(TOG) (TOG) (TOG)
350
425
415
385
350
415
P=115
75
150 (**)
925
915
150 (**)
685
100
915
75
500
350
350
100
EL.+98.625 (BOF) EL.+98.625 (BOF) 1
1 (TYP.) EL.+98.625 (BOF)
(REFER NOTE 13) (REFER NOTE 13) (REFER NOTE 13)
PAVING TO BE RESTORED 535
0.3MM THICK POLYTHENE 500(TYP.)
75
215x200x350 DEEP EXISTING FOUNDATION 50 THK EXISTING 20THK. ISOLATION JOINT (TYP.) (TYP.)
SHEET (TYP.) NEW POLYTHENE SHEET
TO BE DEMOLISHED LEAN CONCRETE (TYP.) 3#14@100 (TYP) (SEE NOTE 11) 50 THK. EXISTING
50 THK LEAN CONCRETE (TYP) M20 NEW ANCHOR BOLTS EXCAVATED SIDES TO BE BACKFILLED
ANCHOR BOLT POCKET TO BE CREATED BY EXISTING REINFORCEMENT BARS TO BE ADDITIONAL REBARS AND COMPACTED TO 95% MDD LEAN CONCRETE
215x200x350 DEEP CUT OUT SUPPLIED BY VENDOR
150MM DIA X 350MM DEEP CORE CUTTING PRESERVED AND TREATED WITH 100x100x350 TO BE POURED WITH EMBEDDED IN CONCRETE WITH
TO BE POURED WITH EXISTING REINFORCEMENT
NEW PORTION OF FOUNDATION TO BE
NON-SHRINK GROUT HIT-HY-500R-V4 EPOXY RESIN PRICE CODE
AND INTERNAL CONCRETE CHIPPING INTO CORROSION INHIBITOR CONCRETE (TYP.) POURED WITH CONCRETE
WITH DRILL BIT OF NOMINAL
8#14
EXISTING FOUNDATION ADDITIONAL REBAR DIA 14 OR 16 mm (TYP.) PRICE CODES DESCRIPTION OF WORK
AAA03AB21 DEMOLITION OF REINFORCED PAVING CONCRETE
AAA03AD03 CHIPPING OF EXISTING RC WORK
ABA02AD01 LIMITED SECTION EXCAVATIONS BY HAND
ACA05AM01 BACKFILLING
AEA10AB01 SUPPLY, CUTTING, MACHINING AND INSTALLATION OF WIRE WELDED MESH
ADA08AA01 LEAN CONCRETE
ADA08AB02 CONCRETE FOR FOUNDATION
AEA08AG01 CONCRETE FOR PAVING
DETAIL DETAIL SECTION SECTION 3 ADA09AA01 STRAIGHT FORMWORK FOR CONCRETE FOUNDATIONS
A1 B1 2
(SCALE 1:10) - ADA09BA01 ANCHOR BOLT BOXES
(SCALE 1:10) - (SCALE 1:10) - (SCALE 1:10) -
ADA10AA02 SUPPLY AND INSTALLATION OF REBAR
SECTION FOR STAGES 6 TO 23
SECTION FOR STAGES 6 TO 23 CONCRETE SURFACE TO BE TREATED ADA10BC01 FIXING STEEL REBAR HILTI DRILL INTO EXISTING CONCRETE
(AS PER SHOWN EXISTING (IN CASE OF DIFFERENT EXISTING
WITH EPOXY BONDING AGENT LIKE
REINFORCEMENT ARRANGEMENT / CASE 1) REINFORCEMENT ARRANGEMENT / CASE 2) ADA11EB01 INSTALLATION IN EXISTING BOXES OF ANCHOR BOLTS
NITOBOND EP OR EQUIVALENT
M20 NEW ANCHOR BOLTS ADA12AB01 NON-SHRINK GROUT
290 125 250
SUPPLIED BY VENDOR ADA16AA01 THREE COATS OF OXIDIZED BITUMINOUS PAINT
(TYP.) 200
P=75
.
49 Gr
44.1°
DRAWING LIMIT
X = 5656.210 DRAWING LIMIT
ROAD 1
290
Y = 90094.700
290
Y = 90430.820
75
TN
2#14@100 125 MATERIAL TOTAL QUANTITY [Cu. M]
TRACK 8
PW
215 125 215 125
0.121
350
FOUNDATION CONCRETE PW
52 TK 61 I X = 5722.955 X = 5722.955 52 TK 63 J 52 TK 63 H X = 5722.955 52 TK 61 H
ADDITIONAL REBARS
Y = 90472.045
ROAD 16
ROAD 14
01
Y = 90142.100
Y = 90235.050
Y = 90281.750
Y = 90350.565
52 P 549
NEW POWER STATION
(SOLAR TURBINE SITE)
72 TK 581 X = 5759.811
200
100
100
X = 5807.330 ROAD 3
X = 5837.410
52 TK 01 E
TRACK 2
X = 5854.610
Y = 90598.810
Y = 90630.310
01 BASIN 1
01 52 P 508 A/B/C 56 P 505
52 P 509 A/ B 52 P 510A/ B
56 P 501A/B/C
Y = 90142.100
Y = 90142.100
52 TK 61 M 52 TK 61 L 01
X = 5885.000
X = 5890.250
ROAD 4
ROAD 12
56 P 506
ROAD 8
52 TK 57 I 52 TK 59 H 01
Y = 90478.415
Y = 90508.715
TRACK 8
52 TK 57 K 52 TK 59 F 56 P 507
ROAD 18
X = 5916.540
TRACK 6
56 P 504
Y = 90360.325
51 TK 01 D
51 TK 01 C
Y = 90227.225
Y = 90258.935
Y = 90303.935
52 TK 61 K 52 TK 61 J BASIN 1
BASIN 2
TRACK 4
WITH DRILL BIT OF NOMINAL 63 P 533 S/S 15
A
3650 S/S B
Y = 90000.000
EXISTING S/S
Y = 90668.520
C 3700
52 TK 57 J 72 P 545 72 TK 580 X = 5975.984
52 TK 57 H 52 TK 59 G A 3360
B 2450
72 P 544 2450 01
Y = 90442.297
Y = 90465.040
BASIN 5 SOUTH BASIN 5 NORTH BASIN 5 NORTH
01
EXISTING REINFORCEMENT EXISTING REINFORCEMENT MATERIAL TOTAL QUANTITY [Cu. M] FOR CONT. REFER DWG. NO. 4239-XX-DE-41000002
50 P 534 A/B/C
50 P 539 A 01
ROAD 7
X = 6000.000
S/S C
X = 6019.150
FOR CONT. REFER DWG. NO. 4239-XX-DE-21000002
Y = 90094.640
FOR CONT. REFER
Y = 90430.820
50 P 539 B
01 TRACK 9 DWG. NO. 4239-XX-DE-21000001
Y = 90616.479
PAVING CONCRETE 0.515
50 P 539 C
50 P 539 D/E
PAVING TO BE RESTORED
50 TK 01 L X = 6055.925 50 TK 01 J X = 6055.925 50 TK 01 H X = 6055.925
Y = 90142.100
Y = 90252.275
Y = 90345.875
75
ROAD 11
500(TYP.)
Y = 90208.000
01
52 P 504 A/ B
52 TK 51 F
AVENUE B
52 TK 51 G 52 TK 51 E
X = 6197.500
ROAD 12
Y = 90375.825
Y = 90353.295
8#12
Y = 90332.000
DETAIL DETAIL EMBEDDED IN CONCRETE WITH
Y = 90430.820
A1 B1 ADDITIONAL REBARS 01
Y = 90392.023
FGL EL. 99.350
FIXING STEEL REBARS 02 17.Nov.2022 IFC - ISSUE FOR CONSTRUCTION N.NIKAM K.Pachgade A.Frigerio
00
30.Sept.2022
27.JULY.2022
IFA - ISSUE FOR APPROVAL
A.Sawant
K.Pachgade
V.Rama Rao
A.Frigerio
A.Frigerio
MATERIAL TOTAL QUANTITY [NOS.] MATERIAL TOTAL QUANTITY [Kg.] Issue Date Reason for Issue - Revision Description Prepared Checked Approved
60 200 EXISTING REINFORCEMENT EXISTING REINFORCEMENT 9 (FOR DETAILS -A1, SECTION-1) 7.405 (FOR DETAILS -A1, SECTION-1)
REBARS REBARS
Digital signature
60 200 REBARS 6 (FOR DETAILS -B1, SECTION-2) REBARS 5.663 (FOR DETAILS -B1, SECTION-2)
AUTHORIZED FOR CONSTRUCTION
REBARS 12 (FOR DETAILS -A2) REBARS 11.034 (FOR DETAILS -A2)
REBARS 8 (FOR DETAILS -B2, SECTION-3) REBARS 8.324 (FOR DETAILS -B2, SECTION-3) DATE INITIAL SIGNATURE
REBARS 12 (FOR DETAILS -A3) REBARS 13.705 (FOR DETAILS -A3) 17.Nov.2022 O.OJU (Civil Dep.DL)
250
250
2#14@100 ADDITIONAL REBARS 12 (FOR DETAILS -B3, SECTION-4) REBARS 12.922 (FOR DETAILS -B3, SECTION-4)
REBARS TECNIMONT IDENTIFICATION CODE
REHABILITATION OF
325
325
Job-EC-Type-N°
CONDITION OF EXISTING FOUNDATION
PORT HARCOURT 4239-AA-DC-21U62RN018
EMBEDDED WITH HILTI EMBEDDED WITH HILTI PHASE DESCRIPTION CONCLUSION REFINERY PROJECT
125
125
2. SLIGHT DAMAGE ON THE CONCRETE FOUNDATION OBSERVED. PROJECT SPECIFICATION 4239-AA-SG-00000007. PORT HARCOURT
REFINING COMPANY
LIMITED (PHRC)
3
_ 3
_ AFTER CHIPPING
OF EXISTING GROUT (****) (****) TITLE
CONCRETE DRAWING
AFTER DEMOLITION
ACTIVITIES SHOWN IN THIS (****) (****) ANCHOR BOLT REPLACEMENT FOR
DRAWING
NOTE :- (****) MEANT FOR : "TO BE FILLED BY CONTRACTOR'S REPRESENTATIVE"
FOUNDATION PUMP 63P533B - OFFSITE- AREA 5 SCALE
1:25 / 1:10
ORIG. SIZE
A0