Table of Contents
Introduction of the Organization.....................................................................................................................................5
1.1. Mission..........................................................................................................................................................5
1.2. Organizational Culture:.................................................................................................................................6
1.3. ORGANOGRAM..........................................................................................................................................9
PC - 1................................................................................................................................................................................
1. Name of the project:.............................................................................................................................................10
2. Location................................................................................................................................................................10
3. Authorities responsible for...................................................................................................................................10
i) Sponsoring.......................................................................................................................................................10
ii) Execution.........................................................................................................................................................10
iii) Operation and maintenance.............................................................................................................................10
4. Provision Planning:..............................................................................................................................................10
5. Project objectives:................................................................................................................................................10
6. Description, justification and technical parameters and technology transfer aspects..........................................11
7. Capital cost estimates...........................................................................................................................................12
8. Annual operating and maintenance cost:.............................................................................................................13
9. Demand and supply analysis................................................................................................................................13
10. Financial plan and mode of financing.............................................................................................................14
11. Project benefits and analysis............................................................................................................................14
i) Financial:.........................................................................................................................................................14
ii) Economic:........................................................................................................................................................15
iii) Social benefits with indicators.........................................................................................................................15
iv) Employment generation...................................................................................................................................15
Page 1 of 76
.
Page 2 of 76
.
Naveena Steels intends to construct 132 KV Grid Station (28 MW) to meet their electricity
requirements for this purpose they have invited several EPC companies to bid for this Project. After
several meetings and brainstorming session of Naveena Steel Management it was decided that they
would award the project to M/s Siemens Pakistan as a Turnkey Project. The Contactor shall work in
accordance to highest international standards. The contactor would mobilize its qualified and
experienced consultant from the date of start till completion.
The contactor shall submit all the drawings, documents within respective phases of Engineering,
Procurement & Construction. The Start date of the Project is 1-Jan 2021 and it should be completed
by 26th Oct 2021.
“To lead Pakistan’s steel industry by creating unparalleled value for our customers through
responsible and innovative processes; and adding momentum to the country’s growth and
prosperity”.
Page 3 of 76
.
The Plant is located at Karachi on 50 acres of land. The need of installation for 28 MW Grid station
came into the mind of the management when the Plant Load increased by 5MW. The Organization
follows Functional Matrix. GM Projects chairs all weekly meeting with contactors and Project team
CEO:
Mr. Haris is the CEO who looks after the technical as well as the financial aspects of the company.
Project Manager
Mr. Nadeem is working as the Project Manager for this Project
Manager Civil:
Mr. Suleiman is working as the Manager Civil.
Manager Procurement
Mr. Yahya is looking after the local & International Purchases
Manager Design
Mr. Khalid is the Manager Design who is looking after Mechanical, Civil & Electrical Design
works
Page 4 of 76
.
Manager Electrical
Mr. Khurram is the Manager Electrical who is responsible for overall Electrical works
Commissioning Manager
Mr. Khalil is the Commissioning Manager for this Project
Page 5 of 76
.
1.1. ORGANOGRAM:
Page 6 of 76
.
PC - 1
Page 7 of 76
.
2. Location:
Karachi, Pakistan
ii) Execution:
Siemens Pakistan
4. Provision Planning: -
The main strategic purpose is the progress of current project for the management and quality
The project will cost PKR 400,000,000 for the financial year 2021.
5. Project objectives:
To timely commission the Grid and provide uninterrupted electricity to plant
To Identify bottlenecks and inefficiencies proactively that will help to streamline the processes
more effectively
To create an environment where the team will effectively collaborate and achieve Project
milestones.
Page 8 of 76
.
PKR 2,000,000 is dedicated for the initial installation and hardware expenses
All drawings to be as built when the Project is complete and to be handed over to the Naveena
Steel Electrical team.
The Construction of Grid will help to supply electricity to the Steel plant without any
interruption and the production target can be met. Naveena Steel is the first of its kind in
with the highest quality steel rebar’s. Naveena Steel intends to transform Pakistan’s steel
us a competitive edge over existing set-ups. On ident with its advanced Continuous Casting
Production Process, Naveena Steel is the first of its kind in Pakistan to be powered by this
state-of-the-art equipment producing superior efficiency along with the highest quality steel
rebar’s. Naveena Steel intends to transform Pakistan’s steel industry, investing in cutting-
Page 9 of 76
.
Page 10 of 76
.
Economic:
Schools.
Hospitals.
Page 11 of 76
.
Miscellaneous:
Page 12 of 76
.
Page 13 of 76
.
PROJECT
MANAGEMENT
PLANS
Page 14 of 76
.
will decide what is included or not. For this purpose, WBS and Scope statement is defined.
The project manager will formulate the strategy and measurement documentation for
Page 15 of 76
.
Page 16 of 76
.
Change control policies are made in this process. If there is any change, it must be confirmed
Page 17 of 76
.
Road Map:
The schedule of project is like a way for executing the project. This is a critical phase for any
project to provide status / picture to team members, stake holders and sponsor about project
at any time during the project lifecycle. Project team creates the schedule of a project by
Activities duration to be more than eighty hours (80) and not less than eight (8) hours.
software.
Network diagram and Gant Chart to be used for schedule Precedence Diagramming
Page 18 of 76
.
Change Management Plan should be properly configured to all other management plans so
that it would be consistent with the Project Management Plan. Change can happen
throughout the project life cycle but it depends further either to accept the change or reject it.
Acceptance and rejection of any change strongly depends on the nature of the particular
change. It should be highlighted that what would be the impact of that particular change on
the project objectives and constraints. Like if the change occurs at the end of the project and
it is of greater potential value and impact is higher on project basic objectives and constraints
that would possibly meant to let this change happen means to change the entire project that
shouldn’t be acceptable in any case because this causes failure of the current project that
If the change is of higher potential value that means to must accommodate this change
further to move onwards, then multiple alternatives should be defined against this change so
that the analysis would be implemented properly to accommodate that change in the project.
Change Management Plan has all the information relevant to all the roles and responsibilities,
also the work activities that are included in the project management plan. Once any change is
occurred and implemented then it should be configured to all other sub-management plans to
make the whole project consistent otherwise the things will be messed up and difficult to
manage and stick to the main project goals, objectives and constraints.
Every implemented change effect the execution and controlling stages of the project life
cycle.
Page 19 of 76
.
Page 20 of 76
.
Change Methodology:
Project Manager is the responsible to establish change request log and changes
To determine the all possible alternatives and costs, all change requests should be
The Change Control Board is the mediator authority that analyse the change
Approved change requests effects on the scope and schedule of the project that will
demand and maintain all the approved changes in the request log.
Page 21 of 76
.
given. There is a need to guide about the requirements of the customer to those human
resources that would help in providing the valid product according to the customer needs. In
Staff Management Plan, the Project Manager and the Project Sponsor are involved.
Following are things that need to be considered as important things in Staff Management
Plan:
Staff Expertise
Quality Staff
Staff Quantity
All the things related to the project must be properly communicated to the staff involved in
the project. The purpose of communicating each and everything to the staff is that everybody
would be on the same stage of understanding the things regarding the project what is new,
and what is going on with the project to make the things consistent.
Page 22 of 76
.
The Staff required in using this application to maintain the record of each hospital, their
patients, insurance companies and their billing system i.e. all payments processes must be
Page 23 of 76
.
Management Plan (PMP). The project team members must effectively communicate with the
Project Manager as the Project Manager has to communicate the assessment reports timely to
the higher authorities. CmMP is used to transmute the communication with the help of
CmMP sets a conceptual model according to which the project is communicated. It is the
CmMP in which, the information is distributed among the stakeholders and Project
Page 24 of 76
.
A CMP that illustrates the variations in cost and how to manage them is developed by the
Project Manager. The Project Manager actually signs to develop this plan. It is the
responsibility of the Project Manager to present the Cost Management Plan (CMP) along
with complete Earned Value Calculations of the project to the project sponsor.
At the fourth level of the work breakdown structure (WBS), project control accounts are
going to be managed. The reason to create control accounts is to find and track the cost
performance in respect to the project. The Earned Value (EV) calculations for control
accounts are then used to determine the financial performance. At what point in time the
It is the responsibility of the Project Manager to present to Project Sponsor, the cost
performance index (CPI) and schedule performance index (SPI) on a regular basis as set by
the organization. Any change in these two indices will have an impact and will change
project cost plan. Project status will be changed into GREEN upon a change of 15% in the
ratio. Similarly, a change of 25% in the ratio may change the status into extremely critical. In
such cases, the Project Manager will be required to take necessary action in order to realign
these ratios. However, the project sponsor will approve the change first before the PM takes
Page 25 of 76
.
The cost regarding each project activity is looked for in estimate cost process. This includes
material, labour, equipment and all the other tools which are used in project plan.
Actual value of work will be calculated via CPI in this project. Schedule Performance
Index (SPI) indicates that how many work activities are being closed. This is
Cost Variance (CV) measures the relationship between the earned value and
actual cost.
Page 26 of 76
.
thing should be purchased or make with in the organization. Moroever, quantity of the
The project manager will make sure that specification in all the system to be used are same.
After the completion of the project, RFP would be developed in order to invite insurance
compnaies and hospitals and make them know about the valid claims software in order to
explain its importance for them. All the technical requirements will be mentioned in the
document. Project manager will be responsible for all the peocurements and he will make
sure the timely delivery of all the goods and services required.
Page 27 of 76
.
product, service or result. For the mitigation of risk, risk management plan is made including
qualitative and quantitave risk. Risk indentification is an ongoing porcess and performed
throughout the project. Following are the few techniques that are used in risk identification
process:
SWOT Analysis
Delphi Technique
Brainstorming
Interviewing
Diagramming
Delphi Technique
In this matrix, Risks are identified as per their impacts and categorize in the category of Red,
Green and Yellow lighted risks. Red area means that risks fall in the category of risks that
highly impacts the project and have high rate of occurance. While yellow area shows that
they have medium chance of occurance and impact will aslo be average. And Green area
shows the risks has very low impact and they have a little chance of occurance too.
Page 28 of 76
.
Risk Register:
In risk register, data is entered in the following table and then their qualitative and
quantitative analysis is performed as per their scores. Their criteria for the categorizing is
QUALITATIVE RISKS 15 – 20
QUANTITATIVE RISKS 7 – 14
Page 29 of 76
.
Contingency Plans:
The organization keeps a certain amount in reserve for risks. This contingency reserve is
usually 10% of total cost of the project. The main risk areas for which these contingencies
Hardware failure
Server issue
No system available
Due to the dynamic nature of risk, the organization reviews the processes for risk
identification continuously. The processes are studied iteratively so that if there are chances
of occurrence of new risks, they are identified on time and are dealt with accordingly.
As the risks occur, a close observation is needed so that it can be studied if the impact of risk
is the same as planned or deviated so that it can be noted for future. The responses planned
are implemented as the risks occur and it is seen if the effects of risks were accordingly
mitigated or not. In case of success, the same responses can be kept for similar risks in other
projects whereas; in case of failure new strategies are to be devised for future.
This step not only helps update the project documents but also becomes a part of
Page 30 of 76
.
are written along with all the details of the major modules used in the Valid Claims
Application.
There are two main things defined in the quality management plan.
To verify the processes that used to develop the application that lies in Quality
Assurance Manager.
To validate scope that is defined in scope management plan and in charter. This is the
The roles and responsibilities of Project Sponsor, Project Manager, Quality Managers, and all
the team members are defined in Quality Management Plan. All assigned work activities are
Page 31 of 76
.
Page 32 of 76
.
11.OBS
Page 33 of 76
.
12.EPS
Page 34 of 76
.
13.WBS DICTIONARY
Page 35 of 76
.
1. PROJECT CONSTRAINTS
Page 36 of 76
.
Page 37 of 76
.
Page 38 of 76
.
Page 39 of 76
.
Page 40 of 76
.
6. PRIMAVERA REPORT EV
Page 41 of 76
.
7. PROJECT WEBSITE
Page 42 of 76
.
Page 43 of 76