You are on page 1of 245

ERKYAH MIXED USE

LUSAIL - QATAR
ARCHITECTURE CONCEPT REPORT
REVISION 00 – NOV. 2019

OWNER / DEVELOPER: 1 LEAD CONSULTANT:


Table of Contents

 ARCHITECTURE ....................................................................................................................................................... 3 - 35

 LANDSCAPE ................................................................................................................................................................... 36 - 47

 INTERIOR DESIGN ........................................................................................................................................ 48 - 71

 STRUCTURE ............................................................................................................................................................. 72 - 100

 ELECTRICAL ....................................................................................................................................................... 101 - 128

 MECHANICAL ................................................................................................................................................... 129 - 226

 UTILITIES ....................................................................................................................................................................... 227 - 245

OWNER / DEVELOPER: 2 LEAD CONSULTANT:


Table of Architecture Contents Appendix (A) PLANS WITH MEP REQUIREMENTS ............................................................ 16
1. Introduction ........................................................................................................................ 4
1.1 General ....................................................................................................................................... 4
6. Classification of Occupations ........................................................................................ 22
1.2 Project description....................................................................................................................... 4
6.1 classification of building occupancy ........................................................................................... 22
Owner ........................................................................................................................................................... 4
6.2 Separate Occupancies .............................................................................................................. 22
Project Site ................................................................................................................................................... 5
Area Statement ............................................................................................................................................ 6 7. Aspects of fire protection ................................................................................................ 23
7.1 Means of Egress ....................................................................................................................... 23
2. Design idea and Used codes............................................................................................. 7
7.2 Occupant Load Calculation........................................................................................................ 26
2.1 Codes & Standards ..................................................................................................................... 7
7.3 Construction Type ..................................................................................................................... 27
2.2 General basis of design .............................................................................................................. 7
7.4 Handicapped Requirements ...................................................................................................... 28
2.3 Goals of design ........................................................................................................................... 7

Appendix (B) ZONING PLANS ............................................................................................ 31


3. External and Internal Finishes .......................................................................................... 8
3.1 Wall Construction ........................................................................................................................ 8
3.2 Internal Finishes .......................................................................................................................... 8
3.3 External Finishes ...................................................................................................................... 10
3.4 Building Thermal & Moisture Protections ................................................................................... 12
3.5 Toilet Fixtures & Accessories .................................................................................................... 12
3.6 Kitchen Equipment .................................................................................................................... 13
3.7 Electro-Mechanical ................................................................................................................... 13
3.8 Design for the Disabled people ................................................................................................ 13

4. Calculation of Toilets ....................................................................................................... 14


4.1 Codes & regulations used ......................................................................................................... 14
4.2 Number of toilets and distribution to the building ....................................................................... 14

5. Car Parking area............................................................................................................... 15


5.1 Car Parking Dimensions............................................................................................................ 15
5.2 Car Parking Rates ..................................................................................................................... 15
5.3 Number of Required Cars Parking to the building ..................................................................... 15
5.4 Number of Available Cars Parking to the building ..................................................................... 15

OWNER / DEVELOPER: 3 LEAD CONSULTANT:


1. Introduction
Owner
1.1 General ARIANE REAL ESTATE
A pioneering Qatar based real estate developer since 2013, Ariane
This section aims to set the design standards and guidelines for the design work to be
Real Estate develops and operates a collection of prime properties
adopted for the preparation of architectural design drawings and specifications for the
throughout Qatar.
building. Also it shall indicate guidelines for the selection of building external and internal
finishing materials, doors, windows, building thermal and moisture protection and other
related works.

Selection Parameters
The selection of materials shall be based on the following parameters:

 Space function requirements

 Aesthetic requirements

 Durability

 Cost & construction method

 Maintenance requirements

 Environmental control (Heat, Light, Sound, etc.)

 Fire and safety requirements

 Availability in the market

 Priority for local Qatari products

1.2 Project description

The Plot will be used for AL ERKYAH MIXED USE building the building consists of:
- Two basements (Parking & Service)
- Ground floor (Retail, Anchors)
- First podium (FEC, Shops and Cinemas)
- Service floor (MEP, Serviced Apartments & Podium LSC)
- Second podium (Service)
- Typical floor plans (12 Floors Serviced Apartment)
- Roof plan

OWNER / DEVELOPER: 4 LEAD CONSULTANT:


Project Site

The Building is located at MARINA DISTRICT, LUSAIL CITY – QATAR


Plot Area = 49759.72 m²

OWNER / DEVELOPER: 5 LEAD CONSULTANT:


Area statement

OWNER / DEVELOPER: 6 LEAD CONSULTANT:


2. Design Idea and Used Codes
2.2 General Basis of design
2.1 Codes & Standards

Building design, materials and safety shall be controlled and complied with the following Design requirements for architectural form
respectable codes and standards: a. Maximum height 18m for Podium , 45m for Towers
b. Maximum Built-up ratio 50%.
 Qatar Fire and Life safety Guidelines, 2015 edition c. Setbacks 5m from all sides. except piazza side 0m
 NFPA - National Fire Protection Association NFPA 101, 2015 edition.

 NFPA - National Fire Protection Association NFPA 5000, 2015 edition 2.3 Goals of Design
 IBC - International Building Code IBC, 2012 edition. a. The design objective is to achieve harmony between the various parts of the project as
 ASTM - American Society for Testing Materials ASTM. well as achieving harmony between the building and the district as a whole through
several axes of design, which are:
 SCDB - Qatari Civil Defense Bureau.
- Efficiency in operating the building and protecting it from accidents through
 ADA - American Disabled Association ADA.
applying codes and regulations governing the design work, and using building
 Other related codes mentioned in the Engineering Design Criteria. materials suitable for urban environment and the exploitation of natural resources
available to provide energy and achieve sustainability.
- Realism by using international standards, which provide modernity with ease in
Standard of Measurements
reviewing and obtaining the necessary approvals and permits. This is through the
The modern metric system, System International (SI), will be applied. All dimensions will be in integration of local requirements and the application of local codes with reference
Millimeters & elevation levels in Meters. to international codes for modern elements not covered by local codes and
regulations.
- Flexibility in design that speeds the completion of construction process with
minimal impact and cost on creativity and innovation.

OWNER / DEVELOPER: 7 LEAD CONSULTANT:


3. External and Internal Finishes
3.1.3 Roof
3.1 Wall Construction
Inverted roofing system consists of the following layers will be used:

3.1.1 External Wall construction a. Concrete screed (slope to drain)


b. Waterproofing membrane
The main external wall construction will be (outside to inside): EIFS system cladding and thermal c. Separation sheets
insulation covering a concrete block.
d. Rigid insulation
e. Separation sheets
3.1.2 Internal Wall Construction f. Pea gravel aggregates
g. 400x400x40mm concrete pavers service walkways
In general, insulated dry walls (16 mm thick gypsum Board on metal studs) will be used for
internal partitions, except for corridors & some services, exit stairs, wet areas and between
unit/unit & unit/corridor 200mm thick CMU walls will be used. The thickness of thermal insulation has been defined to achieve U-value that meets GSAS
requirement (3 Stars).

Wall types will be used to indicate all internal walls in terms of:
1. Fire rating & separation as per the IBC code. 3.2 Internal Finishes
2. Sound transmission class (STC) as per Architectural Graphic Standards -10th Edition
 In addition to architectural and interior design requirements, the room environment,
, based on the following sound isolation criteria:
room temperature, illumination, noise level and sound transmission class shall be kept
 cinema Vs all others. STC 60 at the acceptable levels
 Normal offices, meeting Vs Adjacent offices and similar activities. STC 47
 The selection of material dimension shall be studied carefully. Nominal sizes shall be
 Entertement spacse Vs corridors. STC 47 of first priority. Integration between the finishing material and the adequacy to design
 shops Vs other Toilets STC 47 and to maintenance requirements shall be the most important in selecting the material
dimensions.
 MEP spaces Vs all others. STC 60
 IBC Code Chapter 8 for the interior finishes will be used to control the selection of the
Internal Finishes. In general, the interior finishes shall match the existing.

 For internal finishes, refer to interior design criteria.

OWNER / DEVELOPER: 8 LEAD CONSULTANT:


Flooring: Windows and Glazing:
Flooring will include Marble, granite or porcelain at entrances. Carpet at offices, lounges &
witing areas room areas. Wood for Private offices & meeting rooms. Ceramic tiles at toilets,  Windows will be aluminum to minimize maintenance and to provide a unify appearance
showers, lockers and wet areas and epoxy coat at all service areas. Other special spaces as with the wall finishes.
auditorium , cafeterias …..etc. will be specified by interior designer.  IBC Code, Chapter 12 requirements for Window Openings, Glass, and Glazing (for both
vertical panels & skylights) shall be considered. Glass performance will be considered
Walls: as well in the technical specifications
Walls will have paint, Marble, aluminium cladding, ceramic tiles or wood finishes as  Window openings shall be unified as possible and apply the applicable standards as to
determined by functional use factor. achieve the highest levels of uniformity and reduce the costs.
 Window treatment requirements (draperies, curtains, shutters, etc) shall be provided as
Ceilings: required by the interior design.
Ceiling will be painted plaster, suspended acoustical tiles or gypsum board as determined by  Glazing shall be selected to achieve the best performance for transmittance and
functional use factor. Typical ceiling height for ordinary spaces will be 3000mm but for toilets, reflectance for light and solar energy heat transmittal and shading coefficient in addition
and tea rooms 2600mm. to acoustic requirements.
 Glazing: Double insulated reflective tempered glass outside, clear tempered inside on
Doors: aluminum frames.
The following architectural criteria will be applied:
 Doors shall comply with IBC, NFPA,QCDD.
 Door leaf size dimension shall be selected according to space and code requirements.
 Code fire rating requirements shall be complied strictly to all doors.
 Door hardware shall be complied with the code, and to be selected to suit the use and
the needs of Access Control and zoning. Generally, door hardware shall be stainless
steel, mortise lock, lever handles and heavy duty grade. Access control will be used to
control the main entry & exit doors, Network Operation Center and the Control Room
Area.
 Master key system shall be provided as required.
 Weather proofing devices shall be used for external doors to achieve maximum thermal
efficiency.
 Hollow metal doors for services and areas require fire and security protection.
 For external glazed doors: 24mm thick (6 12 6) Double insulated tinted non reflective
tempered glass outside, clear tempered inside on aluminum frames.
 Glass vision panels, ventilation grills and kick plates shall be provided as required.

OWNER / DEVELOPER: 9 LEAD CONSULTANT:


3.3 Exterior Finishes Exterior Cladding and Materials
1. Marble Cladding.
Curtain wall
Stone Thickness: Approved natural marble slabs to ASTM C503 with finish indicated
Double glazing façade with exterior façade using 2 layers of heat strengthened extra clear on drawings, obtained from one strata of one quarry, free from faults and to the
laminated glass. The glazing shall comprise of (6mm) high performance outer glass + argon shaped, sizes, and patterns shown on the Drawings. Marble slabs to have the
gap (12mm) + (6mm) inner glass. The specified thickness is minimum indicative thickness following minimum properties:
only. The specialist glazing installer/Manufacturer shall confirm the thicknesses by analyzing 1. Density: 175 lbs. /ft3.
Project loads and in-service conditions. The glazing thicknesses shall comply with ASTM E 2. Compression strength: 7540 psi
1300 and the project design wind loads. The insulated glazing units shall be in compliance 3. Water absorption: 0.2 % max
with BSEN 1279 and to achieve required U value and shading coefficient as per GSAS 4. Modulus of rupture: 1015 psi.
requirement (3 Stars). The glazing installer shall submit structural calculations to justify the 5. Abrasion resistance ASTM C241, Ha: 10
proposed thickness. All glazing shall be certified as per BSEN safety standards. The curtain Approved natural marble slabs to ASTM C503 with finish indicated on drawings.
wall system shall be equipped with thermally broken proprietary profiles. It is also necessary to consider the strength of the stone around the fixings. The
An internal EPDM compression gasket assures the system’s total air tightness in the form of breaking load at the fixings will be dependent on the area of the panel, the estimated
vulcanized corners or fitted vulcanized gasket. wind loading and the stones strength.

2. Granite
Approved natural granite slabs to ASTM C615 with finish indicated on drawings,
obtained from one strata of one quarry, free from faults and to the shaped, sizes, and
patterns shown on the Drawings. Granite slabs to have the following minimum
properties:
1. Density: 160 lbs. /ft3
2. Compression strength: 19,000 psi
3. Water absorption: 0.4 % max.
4. Modulus of rupture: 1,500 psi.
5. Abrasion resistance ASTM C241, Ha: 25

Maximum masses per square meter of cladding stones


Stone 20mm thick 40mm thick 50mm thick 75mm thick
Granite, Marbles, Hard Kg Kg Kg Kg
Limestones, Slates and
60 120 * *
Quartzites
Limestones and * * 150 225
Sandstones
Maximum Masses per Square Meter of Stone – BS 8298: 2000

OWNER / DEVELOPER: 10 LEAD CONSULTANT:


The factors that affect the calculation for the thickness are: 3. Metal Cladding
- Stone strength,
Architectural Metal panels shall be capable of withstanding building movements and
- Panel size,
weather exposures based on the following test standards required by the Architect
- Wind loadings,
and/or the local building code.
- Fixing location in the stone,
- Type of fixing.  Wind Load; Wind load testing shall be conducted in accordance with ASTM E 330.
 Air and Water Infiltration Tests; Air Infiltration – shall be tested in accordance with
ASTM E 283.

- Accessories:
o Sealants within the panel system shall be as per manufacturer's standards to
meet performance requirements.
o Internal Flashing: sheet metal flashing which may be required at base or
penetration conditions will be produced in the same material finish as the adjacent
panels.
o Coping: Wall copings will be produced with the same material as the wall panel
system unless otherwise noted. Sheet Metal flashing extensions will be
acceptable in non- viewing areas in accordance with Manufacturer’s
recommended details.
o Furring/Supports.
o Fasteners: Type 304 Stainless Steel or Cadmium plated as recommended for
- Insulation
specific application.
The insulation needs to be non-combustible, rot and vermin proof and non-absorbent. The
o Shims: High impact plastic shims will be used to maintain planar surfaces.
insulation shall have a foil layer to act a vapor control layer or a breather membrane applied to
the outer face to control condensation.

OWNER / DEVELOPER: 11 LEAD CONSULTANT:


- Insulation
The entire building envelope shall be carefully detailed in order to provide continuous insulation,
eliminate thermal bridging, and prevent condensation and trapped moisture within wall and roof
assemblies. The use of spray-in cellulose or cementitious foamed-in-place products are
encouraged as an alternative to Rock-wool to protect air quality.

4. EIFS system
This EIFS system is based on using EPS (Expanded Polystyrene) as the insulation material.
A lightweight system, is comprised of a polystyrene insulation board secured to the exterior wall
with an adhesive or mechanical fasteners, then reinforced with an acrylic plaster and fiberglass
mesh on top, and finished with an acrylic and polymer coat that is both colorfast and crack-
resistant.
Expanded Polystyrene (G-EPS) offers approximately 10% more thermal efficiency and is
especially suited to renovation work as thinner boards can be used 3.4 Building Thermal & Moisture Protections

 The buildings thermal insulation is of a great benefit to reduce air-conditioning loads,


which will affect both direct and running cost.

 Moisture and thermal insulation materials shall be used in all buildings.

 External walls & roofs shall be insulated.

 Under ground structures and roofs shall be completely waterproofed.

 Sound absorption and insulation materials shall be provided as needed.

3.5 Toilet Fixtures & Accessories

 Toilet fixtures & accessories shall be selected according the selection parameters of
the interior designs and color schemes.
 Minimum plumbing fixtures will be calculated in reference to IBC code Table 2902.1

OWNER / DEVELOPER: 12 LEAD CONSULTANT:


3.6 Kitchen Equipment:

 The project contains F&B spaces

 The project contains tea rooms serving the offices

 The selection of tea room equipment for different types shall be studied to achieve
project requirements.

3.7 Electro-Mechanical:

 Close coordination between architectural and electro-mechanical works shall be taken


place through out the whole project.
 Server room raised floor shall have a special coordination between architectural and
electro-mechanical.
 The selection of lighting fixtures, A/C grills and diffusers, drinking fountains, etc.
Dimensions, types, colors, locations of such items shall be coordinated together with
architectural elements to achieve the desired product.

3.8 Design for the disabled people:

 A preliminary study has been made during the conceptual design stage, considering
an easy approach for the handicapped persons in the projects’ buildings.
 Using ramps (slope not steeper than 1:12) and providing special toilets at all public
toilets units.
 All designs shall be reviewed as per the (ADA) standards in the forthcoming phases.

OWNER / DEVELOPER: 13 LEAD CONSULTANT:


Calculated Fixtures:
4. Calculation of Toilets
Basement 1&2

Table 2902.1, IBC 2012 provides the required rates to provide the number of toilets and drinking Male & Female prayer room: 2 WC, 2 Lav., 1 Service Sink and 1 Drinking fountain.
water fountains for all occupations. Stores & services: 2WC, 2Lav, 1 Service Sink and 1 Drinking fountain.

Basement Total WC. =4, Total Lav. =4, Total Service Sink=2, Total Drinking fountain=2

Ground Podium
Hyper market & shops: 9 WC, 5 Lav., 1 Service Sink and 5 Drinking fountain.
Lounge & entrance Tower B: 1 WC, 1 Lav. 1 Service Sink.

Ground Total WC. =10, Total Lav. =6, Total Service Sink=2, Total Drinking fountain=5

First Podium
Food court: 8 WC, 3 Lav., 1 Service Sink and 1 Drinking fountain.
F&B, Shops and mercantile space: 1 WC, 1 Lav. and 1 Service Sink.
FEC: 12 WC, 5 Lav., 1 Service Sink and.
Bowling hall: 3 WC, 2 Lav., and 1 Service Sink.
MGT. Office: 1 WC, 1 Lav. and 1 Service Sink.
Cinema: 11 WC. 5 Lav., 1 Service Sink and 1 Drinking fountain.

First Floor Total WC. =36, Total Lav. =17, Total Service Sink=6, Total Drinking fountain=2

Second Podium
GYM & SPA: 2 WC, 1 Lav., 1 Service Sink.
Swimming pools 28 WC, 7 Lav., 1 Service Sink and 1 Drinking fountain.

Second Floor Total WC. =30 Total Lav. =8, Total Service Sink=1, Total Drinking fountain=1

OWNER / DEVELOPER: 14 LEAD CONSULTANT:


5. Car Parking Area
5.1 Car Parking Dimensions
Typical Parking spaces are to be minimum 2.65m x 5.8m with minimum aisle width for
perpendicular parking to be 6.7m unless otherwise agreed and subject to Authority requirements
and standards.

5.2 Car Parking Rates Piazza Setback


The required parking rate of retail area is 2.75 / 100 Sq. m
The required parking rate of entertainment area is 2.75 / 100 Sq. m
The required parking rate of apartment is 1BR=1 - More = 1.5

Calculated Parking Area for the building:

Required Parking Lots


Usage Location GFA Units Required Total Regulation AREA PARKING
BASEMENT 2 3625 sq. m 85
Retail 19,926 0 548 2.75/100 Sq. m
746 BASEMENT 1 3625 sq. m 75
Entertainment 7,200 0 198 2.75/100 Sq. m TOTAL 160
7250 sq. m
Apartment Tower 0 696 871 871 1BR=1 - More = 1.5
Total 1,617

Available Parking Lots


Note:
Floor Ground Basement 1 Basement 2 Total Parking shortage Number of parking in current design is NOT sufficient
Retail & For optional we can increase number of parking by add Piazza setback in our project which shaded
94 484 0 578 -168
Entertainment in sketch below
Residential 77 0 582 659 -212
Total 171 484 582 1,239 -378

OWNER / DEVELOPER: 15 LEAD CONSULTANT:


Appendix (A)
Plans with MEP Requirements

OWNER / DEVELOPER: 16 LEAD CONSULTANT:


BASEMENT -02 FLOOR PLAN WITH MEP REQUIREMENTS

OWNER / DEVELOPER: 17 LEAD CONSULTANT:


BASEMENT -01 FLOOR PLAN WITH MEP REQUIREMENTS

OWNER / DEVELOPER: 18 LEAD CONSULTANT:


GROUND FLOOR PLAN WITH MEP REQUIREMENTS

OWNER / DEVELOPER: 19 LEAD CONSULTANT:


PODIUM -01 FLOOR PLAN WITH MEP REQUIREMENTS

OWNER / DEVELOPER: 20 LEAD CONSULTANT:


SERVICE FLOOR PLAN WITH MEP REQUIREMENTS

OWNER / DEVELOPER: 21 LEAD CONSULTANT:


6. Classification of Occupations

6.1 Classification of building occupancy

This Building is classified as an “Apartment & Mercantile occupancy” according to Qatari fire
building. The design will apply the life safety requirement and fire resistance according to this
classification With regard to spaces of a special nature (assembly / high hazard).

Table 6.1.14.4.1(a) Required Separation of Occupancies (hours) – Part-2


NFPA-101

Design Criteria:
- Assembly Occupancies > 300<1000 (FEC & Cinema) shall be separated 2 HRs fire rated
with Mercantile Occupancies.
- Assembly Occupancies < 300 (such as bowling hall) shall be separated 2 HRs fire rated with
Mercantile Occupancies.
- Assembly Occupancies > 1000 (such as Swimming pools Area) shall be separated 3 HRs
fire rated with Storage Occupancies.
- Assembly Occupancies > 300<1000 (FEC & Cinema) shall be separated 2 HRs fire rated
Business Occupancy – Revisions B_2015- with Apartment Occupancies.
Qatari fire and Life Safety Guideline - Apartment occupancies shall be separated 2 HRs fire rated with Storage low/ordinary
6.2 Separate Occupancies: Hazard occupancies at basement floor.

The building contains some other occupations such as garage, Cafeterias and assembly zones
such as FEC, Food court and Cinema hall.

Required Separation of Occupancies (hours), will follow Table 6.1.14.4.1 (a) & (b) at NFPA 101,
2015 Edition.

OWNER / DEVELOPER: 22 LEAD CONSULTANT:


7. Aspects of fire protection
7.1 Means of Egress
The means of egress shall comply with the requirements of Chapter 7 of NFPA 101
(Chapter11 of NFPA 5000) including relevant occupancy chapters within NFPA 101 and
NFPA 5000.
Means of Egress Component
The means of egress is the continuous and unobstructed way of travel from any point in
a building or structure to a public way consisting of three separate distinct parts Fig. 7.1.1.A. Minimum clear width (between face of door and stop)
a. Exit Access
b. Exit
c. Exit Discharge

The provisions of Chapter 7 of NFPA101, expresses the way of determining the


design, construction, protection, location and arrangement of exit facilities to provide
safe means of egress for occupants from all occupancies. Means of egress consist of
the vertical and horizontal travel which can be intervening room spaces, doorways,
hallways, corridors, passageways, balconies, ramps, stairs, elevators, enclosures,
lobbies, horizontal exits, courts and yards.
The means of egress shall comply with the requirements of Chapter 7 of NFPA 101,
Chapter 11 of NFPA 5000 and other relevant occupancy Chapters within NFPA
Fig. 7.1.1.B. Minimum clear width with permitted obstructions
In accordance with Chapter 7.2.1.2.1. of NFPA 101, for all doors, projections not more
7.1.1 Door Width than 90 mm at each side of the doorway at a height of not more than 965mm will not
Every door and door assembly shall be designed and constructed so that the egress be considered a reduction in egress width.
travel is obvious and direct. Exit access doors serving a room not exceeding 6.5m 2 in area and not required to be
accessible to persons with
In accordance with QCDD requirements, doors opening in means of egress will be
required to be not less than 915mm in clear width. Where a pair of door is provided, Severe mobility impairments shall not be less than 610mm in door leaf width.
not less than one of the doors shall provide not less than 810mm clear width opening. No door into a means of egress, when fully opened, shall project more than 180mm
The calculation for the capacity of door shall be based on 5mm per person in reference into the required width of an aisle, corridor, passageway or landing.
to the clear width opening of the door.

OWNER / DEVELOPER: 23 LEAD CONSULTANT:


7.1.3 Exit Stairs
Stairs serve multiple functions allowing normal occupant movement among floors of
building, providing egress during emergencies and fires and facilitating rescue and fire
control by fire fighters. The width of stairs shall be in accordance with NFPA 101,
Chapter 7.2.2 as summarized in the table below.

Item Requirements
*Minimum unobstructed width for less 1120 mm
than 2000 people 1140 mm
*Minimum unobstructed width for more
than 2000 people
Fig. 7.1.1.C. Minimum required width Maximum riser height 180 mm
Minimum Riser Height 100 mm
Minimum Tread depth 280 mm
All doors which are located within walls constructed of fire resistant material shall be Minimum Headroom 2030 mm
provided with self-closing devices. Self-closing devices shall comply with the requirements Maximum height between landings 3660 mm
Maximum tread and landing slope 21 mm (1 in 48)
of NFPA 101 Chapter 7.2.1.8
Table 7.1.3: Exit Stair Specifications
Door shall swing in the direction of egress, when serving an occupant load of 50 persons
(*) refers to the total cumulative occupant load assigned to a stair
or more.
The exit door at the point of discharge from a stair shall open outwards, in the direction of
travel. The minimum stair width should be clear of all obstructions except projections not more
than 114 at or below handrail height on each side of the stair (Chapter 7.2.2.2.1.2 of NFPA
The calculation for the width capacity of door shall be based on 5mm per person.
101)
The minimum required unobstructed clearance with door leaf encroaching into a landing
7.1.2 Corridors is shown in Fig. 7.1.1.C the minimum width of stair used in the project is 1150mm.
As per NFPA 101, Assembly Occupancy, Mercantile Occupancy & Business Occupancy, Tread and Landing surfaces shall be as per Chapter
corridor and lobby protection shall not be required in buildings protected throughout by an 7.2.2.3.3 of NFPA 101.
approved, supervised automatic sprinkler system in accordance with Chapter 9.7 of NFPA
Measurement of headroom clearance is shown in Fig.7.1.3 and in accordance with
101.
Chapter 7.2.2.2.1.1 of NFPA 101.
Corridors with a required capacity of more than 50 persons will be required to be of
sufficient width to accommodate the required occupant load but have a width of not less
than 1120mm as per NFPA 101. Corridors with a required capacity of not more than 50
persons will be required to be not less than 915mm width for general public areas unless
specific occupancy chapter requires different corridor width. However, based on
operational constraints corridors in this project may be required to exceed the minimum
width requirements noted above.
The minimum width of corridor used in the project is 1200mm .

Figure 7.1.3: Headroom

OWNER / DEVELOPER: 24 LEAD CONSULTANT:


7.1.4 Ramps
Ramps are permitted as a part of egress and are preferred over stairs under some
circumstances, provided conformity to the following construction requirements is
ensured and QCDD approves.
Every ramp used as a component in a means of egress shall conform to the general
requirements of Chapter 7.1 and to the special requirements of NFPA Chapter 7.2.5.
RAMP SPECIFICATIONS
ITEM REQUIREMENTS
Maximum unobstructed width 1200 mm
Maximum projections at or below Handrail 114 mm
height on each side
Maximum slope 1 in 12 (8.3%)
Maximum cross slope 1 in 48 (2%)
Maximum rise for a single Ramp run 760 mm
Maxim slope of Landings 1 in 48 (2%)
Minimum width of landings in the direction of 1220 mm
travel
Table 7.1.4: Ramp Specifications
Where the rise of the ramp is less than 150mm then the ramp is not
required to have handrails. If the walking surface has a slope that does
not exceed 1in 20, then it shall not be classified as a ramp and therefore Fig. 7.1.5.C: Guard Details
is not required to have handrails.
7.1.5 Handrails and Guardrails
Stairs and ramps shall have handrails on both sides. Handrails shall be as per Chapter
7.2.2.4.1 of NFPA 101.
Guards in accordance with Chapter 7.2.2.4 shall be provided at the open sides of means of
egress that exceed 30in. (760mm) above the floor or the finished ground level below.

Fig. 7.1.5.B: Handrail Details and Measurement


Fig. 7.1.5.A: Wall Bracket detail

OWNER / DEVELOPER: 25 LEAD CONSULTANT:


7.2 Occupant Load Calculation Stairs:

Occupant load factor for each usage as per Qatari fire and life safety guideline: Minimum clear width for escape Stairs needed according to Qatari fire and life safety guide-line
is 1420mm.
 Residential: 18.6 m2/Person

 Storage use 27.9 m2/Person


Residential:
 Assembly: 1.4 m2/Person

 F&B less 9.3 m2/Person


Than 232 m2 Mercantile:
 Business: 9.3 m2/Person

 FEC hall: 4.6 m2/Person

 Mercantile: 2.8 / 5.6 m2/Person Assembly:

 Cinema Fixed seating


Chapter 3; Use and Occupancy
IBC-2018

Travel Distance and Dead End


Travel distance and dead-end for different classifications as per Qatari fire and life safety guide-
line is shown in the following schedule:

Residential:

Table 13.2.3.2 Capacity Factors Table 7.4.1.2 Capacity Factors


Mercantile: NFPA-101, 2018 NFPA-101, HB, 2018

Assembly:

OWNER / DEVELOPER: 26 LEAD CONSULTANT:


7.3 Construction Type
The calculated required escape Exits for each floor regarding the current design:
Construction minimum requirement as per Qatari fire and life safety guideline is limited or Non-
Combustible materials
MIN. WIDTH
TOTAL CAPACITY TOTAL REQUIERED Construction type is defined according to Allowable building height and area that calculated
NUMBER OF
FLOOR Occupant FACTOR (m) For REQUIRED BY DESIGN
Escape EXITS through Table 7.4.1 at NFPA 5000, 2015 edition:
LOAD Escape Exit WIDTH (m) (m) FOR
EACH EXIT
Basement 2 54 0.0056 .30 10 .03
Basement 1 149 0.0056 .89 10 .089
Ground podium 3299 0.0056 18.4 8 2.3
Ground (Hyper market) 1132 0.0056 6.33 4 1.58
First podium(Mercantile & food court) 1288 0.0056 7.2 3 2.4
1ST Floor (Cinema) 800 0.0056 4.48 2 2.2
1ST Floor (FEC) 900 0.0056 5.04 3 1.6
Service floor 212 0.0056 1.18 6 .19
Second Podium (Swimming Pool) 1512 0.0056 8.46 5 1.69
Second Podium (Tower B + Gym1.46) 192 0.0056 1 3 .33
Second Podium (Tower A) 372 0.0056 2 3 .66
Second Podium ( Tower C) 372 0.0056 2 3 .66
Typical apartment floor (Tower B) 166 0.0056 2.2 3 .73
Typical apartment floor (Tower A) 114 0.0056 .63 3 .21
Typical apartment floor (Tower C) 114 0.0056 .63 3 .21

Table 7.4.1 Allowable Building Height and Area – NFPA 5000, 2015
Conclusion:
- The current Design doesn’t cover the needed number of Escape stairs in (cinema zone &
food court) and required escape Exits in (hyper market & Lounge in Tower B). According to table 7.4.1, for buildings protected with an automatic sprinkler system and for
buildings with built-up area exceeding 23000 sq. ft. that considered as un-limited classification
the construction type shall be determined as shown above.

OWNER / DEVELOPER: 27 LEAD CONSULTANT:


Construction Type: I-442 (S)

7.4 Outdoor Handicapped requirements


Ramps
Slope. Ramp runs shall have a running slope not steeper than 1:12
Clear Width. The clear width of a ramp run and, where handrails are provided, the clear width
between handrails shall be 36 inches (915 mm) minimum.
Rise. The rise for any ramp run shall be 30 inches (760 mm) maximum.
Width. The landing clear width shall be at least as wide as the widest ramp run leading to the
landing.
Length. The landing clear length shall be 60 inches (1525 mm) long minimum.
Change in Direction. Ramps that change direction between runs at landings shall have a clear
landing 60 inches (1525 mm) minimum by 60 inches (1525 mm) minimum.

Fire Resistance Ratings for Type I Construction (hr.) – NFPA 5000, 2015

Conclusion:
- Columns supporting more than one floor or columns, shall be 3hr fire resistance ratings for
type I construction. Ramp Landings; Ref. “ADA code, 2010”
- Beams, Girders, Trusses, and Arches supporting more than one floor or columns, shall be
3hr fire resistance ratings for type I construction. Curb Ramps:
- Floor / Ceiling assemblies, shall be 2hr fire resistance ratings for type I construction. Counter Slope. Counter slopes of adjoining gutters and road surfaces immediately adjacent to
- Roof / Ceiling Assemblies, shall be 11/2hr fire resistance ratings for type I construction. the curb ramp shall not be steeper than 1:20.
The adjacent surfaces at transitions at curb ramps to walks, gutters, and streets shall be at the
same level.

OWNER / DEVELOPER: 28 LEAD CONSULTANT:


Landings. Landings shall be provided at the tops of curb ramps. The landing clear length shall
be 36 inches (915 mm) minimum. The landing clear width shall be at least as wide as the curb
ramp, excluding flared sides, leading to the landing.

Landings at the Top of Curb ramps; Ref.


“ADA code, 2010”

Diagonal Curb Ramps.


Diagonal or corner type curb ramps with returned curbs or other well-defined edges shall have
the edges parallel to the direction of pedestrian flow. The bottom of diagonal curb ramps shall
have a clear space 48 inches (1220 mm) minimum outside active traffic lanes of the roadway.
Diagonal curb ramps provided at marked crossings shall provide the 48 inches (1220 mm)
minimum clear space within the markings. Diagonal curb ramps with flared sides shall have a
segment of curb 24 inches (610 mm) long minimum located on each side of the curb ramp and
within the marked crossing.

Diagonal or corner Type curb ramp; Ref. “ADA code,


2010”

OWNER / DEVELOPER: 29 LEAD CONSULTANT:


Appendix (B)
Zoning Plans

OWNER / DEVELOPER: 30 LEAD CONSULTANT:


GROUND PODIUM ZONING

OWNER / DEVELOPER: 31 LEAD CONSULTANT:


FIRST PODIUM ZONING

OWNER / DEVELOPER: 32 LEAD CONSULTANT:


SERVICE FLOOR ZONING

OWNER / DEVELOPER: 33 LEAD CONSULTANT:


SECOND PODIUM ZONING

OWNER / DEVELOPER: 34 LEAD CONSULTANT:


TYPICAL APARTMENT FLOOR ZONING

OWNER / DEVELOPER: 35 LEAD CONSULTANT:


LANDSCAPE

LANDSCAPE
CONCEPT REPORT

OWNER / DEVELOPER: 36 LEAD CONSULTANT:


SITE LOCATION & LANDUSE

OWNER / DEVELOPER: 37 LEAD CONSULTANT:


4
SITE LAYOUT MASTER PLAN 2 9
7 5
GROUND FLOOR 7 2
BLOCK A BLOCK B
LAYOUT
7 1 6 4
1 RETAIL ENTRANCE 8 7
3
5
2 RESIDENTIAL ENTRANCE 7 1
3
3 GATES 1 4
2 2
4 BICYCLE RACK FEUTURE 1
5 5
EXTENSION 7
5 SHADED PARKING
AREAS 5
3
6 VIP PARKING 6 8
3 8 7
7 SERVICE PARKING
4 3
8 OUTDOOR
SITTING AREA 1
2
9 WATER FEATURE
3
PODIUM 2nd - FLOOR FIRST FLOOR PLAN 2
PLAN 4
1
7
1 MAIN SWIMMING POOL 1 PRIVATE GARDENS BLOCK C 4
2 KIDS SWIMMING POOL 2 JOGGING TRACK 7 6
1
3 9
3 KIDS PLAYGROUND 3 SHADED SITTING AREA
4 EXTERNAL SHOWER 4 ARTIFICIAL GRASS
5 SITTING AREA
6 SNACK BAR
7 WOODEN PERGOLA
8 GREEN WALLS

OWNER / DEVELOPER: 38 LEAD CONSULTANT:


GROUND FLOOR LAYOUT
4 5
9
1-HARDSCAPE MATERIALS 2
7
2
BLOCK A BLOCK B
7
7

Dark Gray Light Beige Dark Brown Light Beige


Interlocking Interlocking Granite Granite

5 5
9 1
5 8
3
6
7
Pure Rounded Mica Stone Hardscape Patterns
Pebbles Cladding GROUND FLOOR
LAYOUT
2-SOFTSCAPE PALLET
1 RETAIL ENTRANCE 5
2 RESIDENTIAL
ENTRANCE 2
4
3 GATES
7
4 BICYCLE RACK 4
BLOCK C
9
Delonix Regia Chamaerops Humilis Plumeria Obtusa Cassia Fistula 5 SHADED PARKING 7 6
1
AREAS
3 9
6 VIP PARKING
7 SERVICE PARKING
8 OUTDOOR
SITTING AREA
Phoenix Lantana Camara Pennisetum Nerium Oleander Wedelia Trilobata Washingtonia
9 WATER FEATURE
Dactylifera Setaceum robusta

OWNER / DEVELOPER: 39 LEAD CONSULTANT:


GROUND FLOOR LAYOUT
3-FURNITURE
3-1-Sitting Areas 3-3-Bicycle Racks 3-6-Drop Off

3-2-Planters 3-4-Shades 3-7-External Gates

3-5-Parking Shades

OWNER / DEVELOPER: 40 LEAD CONSULTANT:


GROUND FLOOR LAYOUT
4-LIGHTING FIXTURE
3-9-External Signage

3-8-Recycle Trash Cans

5-WATER FEATURE

OWNER / DEVELOPER: 41 LEAD CONSULTANT:


PODIUM 2nd - FLOOR PLAN
1-HARDSCAPE MATERIALS

BLOCK A BLOCK B

6 4
8
5 1
Granite Flooring Beige Porcelain Brownish Gray Dark Brown
Wooden Texture Porcelain Granite 7
2

7 5

Pure Rounded Light Blue 8


Light Beige Mica Stone
Granite Cladding Pebbles Mosaic Tiles
PODIUM 2nd - FLOOR
PLAN
1 MAIN SWIMMING POOL 5 SITTING AREA

2 KIDS SWIMMING POOL 6 SNACK BAR

3 KIDS PLAYGROUND 7 WOODEN PERGOLA

Dark Blue Red EPDM Yellow EPDM Blue EPDM 4 EXTERNAL SHOWER 8 GREEN WALLS
Mosaic Tiles Rubber Tiles Rubber Tiles Rubber Tiles
BLOCK C
2-SOFTSCAPE PALLET

Plumeria Obtusa Rhapis Excelsa Cycas Revoluta Lantana Camara Cortaderia Selloana Leucophyllum
Frutescens

OWNER / DEVELOPER: 42 LEAD CONSULTANT:


PODIUM 2nd - FLOOR PLAN
3-SWIMMING POOL & EXTERNAL SHOWER AREA

4-KIDS PLAYGROUND

5-SNACK BAR IDEAS 7-TOWEL CENTER IDEAS

OWNER / DEVELOPER: 43 LEAD CONSULTANT:


PODIUM 2nd - FLOOR PLAN
6-FURNITURE

Green Walls

7-PLANTERS IDEAS 8-LIGHTING FIXTURE

Lighting pole Lighting Bollard

OWNER / DEVELOPER: 44 LEAD CONSULTANT:


PODIUM 2nd – POOL SECTION

BLOCK A BLOCK B

BLOCK C

SECTION (A – A)

OWNER / DEVELOPER: 45 LEAD CONSULTANT:


FIRST FLOOR PLAN
1-HARDSCAPE MATERIALS
BLOCK A BLOCK B

1
3

3
1 4
Granite Flooring Beige Porcelain Light Beige Pure Rounded 2
Wooden Texture Granite Pebbles

FIRST FLOOR PLAN


1 PRIVATE GARDENS 3 SHADED SITTING AREA 3
4 1
Natural Rocks Dark Red EPDM Artificial Grass 2 JOGGING TRACK 4 ARTIFICIAL GRASS
Rubber Tiles 2
4-LIGHTING
2-SOFTSCAPE PALLET 3-JOGGING TRACK FIXTURE
3
1
BLOCK C

Dodonaea Atriplex Cycas Revoluta Ruellia Sp.


Viscosa Semibaccata
5-PRIVATE GARDENS 6-FURNITURE & PLANTER

OWNER / DEVELOPER: 46 LEAD CONSULTANT:


SITE LAYOUT RECOMMENDATIONS

THE BELOW STRATEGY WILL BE FOLLOWED TO IMPROVE GSAS SCORE:

1- USE (NATIVE / ADAPTIVE) PLANTS AT LEAST 51 %

2- WATER PRESERVATION BY USE RAIN WATER TANKS & DROPED IRRIGATION SYSTEM

3- USE PARKING SHADES

4- PROVIDE SHADED AREAS IN SITE

5- PROVIDE HANDICAPPED PARKING AND PATHWAY FOR THEM WITH SUITABLE WIDTH AND SLOPE

6- USE LOCAL MATERIALS

OWNER / DEVELOPER: 47 LEAD CONSULTANT:


INTERIOR DESIGN
CONCEPT REPORT

OWNER / DEVELOPER: 48 LEAD CONSULTANT:


THE MALL

OWNER / DEVELOPER: 49 LEAD CONSULTANT:


MALL SPACES
ENTRANCE , ATRIUM & CORRIDOR – ALT 01 ( STRAIGHT LINES - GEOMETRIC – DURABLE )
FLOORING

LIGHT EMPERADOR MARBLE CREMA MAFRIL MARBLE OFF WHITE PAINT OAK WOOD/VENEER STAINLESS HAIRLINE FINISH

OWNER / DEVELOPER: 50 LEAD CONSULTANT:


MALL SPACES
ENTRANCE , ATRIUM & CORRIDOR – ALT 01 ( STRAIGHT LINES - GEOMETRIC – DURABLE )
CEILING

LIGHT EMPERADOR MARBLE CREMA MAFRIL MARBLE OFF WHITE PAINT OAK WOOD/VENEER STAINLESS HAIRLINE FINISH

OWNER / DEVELOPER: 51 LEAD CONSULTANT:


MALL SPACES
ENTRANCE , ATRIUM & CORRIDOR – ALT 02 ( FREE FORMS - FASCINATING – DURABLE )
FLOORING

LIGHT EMPERADOR MARBLE CREMA MAFRIL MARBLE OFF WHITE PAINT OAK WOOD/VENEER POLISHED BRUSHED COPPER

OWNER / DEVELOPER: 52 LEAD CONSULTANT:


MALL SPACES
ENTRANCE , ATRIUM & CORRIDOR – ALT 02 ( FREE FORMS - FASCINATING – DURABLE )
CEILING

LIGHT EMPERADOR MARBLE CREMA MAFRIL MARBLE OFF WHITE PAINT OAK WOOD/VENEER POLISHED BRUSHED COPPER

OWNER / DEVELOPER: 53 LEAD CONSULTANT:


MALL SPACES
FOOD COURT ( FREE FORMS - FASCINATING – DURABLE )

PORCILAIN TILES WOOD EFFECT CREMA MAFRIL MARBLE OFF WHITE PAINT OAK WOOD/VENEER MIXED TYPES FLOOR

OWNER / DEVELOPER: 54 LEAD CONSULTANT:


MALL SPACES
PUBLIC TOILETS ( SIMPLE- DURABLE – HYGIENIC )

PORCELIAN TILES -OFFWHITE PORCELIAN TILES –LIGH GREY PORCELIAN TILES – OFF WHITE PORCELIAN TILES – MARBLE EFFECT GREY WHITE PAINT

OWNER / DEVELOPER: 55 LEAD CONSULTANT:


RESIDENTIAL

OWNER / DEVELOPER: 56 LEAD CONSULTANT:


RESIDENTIAL SPACES
ENTRANCE ( LUXURY - PRIVATE - CALM)

NOVO RUVINIA MARBLE CREMA MAFRIL MARBLE DOUBLE BLACK MARBLE OAK WOOD/VENEER WALL PAPER

OWNER / DEVELOPER: 57 LEAD CONSULTANT:


RESIDENTIAL SPACES
ELEVATOR LOBBY ( LUXURY - PRIVATE – CALM )

DARK EMPERADOR MARBLE CREMA MAFRIL MARBLE DOUBLE BLACK MARBLE WALL PAPER POLISHED BRUSHED BRASS

OWNER / DEVELOPER: 58 LEAD CONSULTANT:


RESIDENTIAL SPACES
CORRIDORS ( LUXURY - PRIVATE – CALM )

PORCELAIN TILES (MARBLE EFFECT) WALL PAPER OAK WOOD/VENEER DOUBLE BLACK MARBLE

OWNER / DEVELOPER: 59 LEAD CONSULTANT:


RESIDENTIAL SPACES
2 BR T01– FURNITURE LAYOUT (SAMPLE)

OWNER / DEVELOPER: 60 LEAD CONSULTANT:


RESIDENTIAL SPACES
3 BR T01– FURNITURE LAYOUT (SAMPLE)

OWNER / DEVELOPER: 61 LEAD CONSULTANT:


RESIDENTIAL SPACES
ONE / TWO / THREE BEDROOM – LIVING AREA ( COOL - PRACTICAL – COZY )

PORCILAIN TILES WOOD EFFECT OFF WHITE PAINT GREY PAINT

OWNER / DEVELOPER: 62 LEAD CONSULTANT:


RESIDENTIAL SPACES
ONE / TWO / THREE BEDROOM – MASTER BEDROOM ( COOL - PRACTICAL – COZY )

PORCILAIN TILES WOOD EFFECT OFF WHITE PAINT LIGHT GREY PAINT WALL PAPER

OWNER / DEVELOPER: 63 LEAD CONSULTANT:


RESIDENTIAL SPACES
ONE / TWO / THREE BEDROOM – DRESSING ( COOL - PRACTICAL – COZY )

PORCILAIN TILES WOOD EFFECT OFF WHITE PAINT OAK WOOD/VENEER WALNUT WOOD/VENEER

OWNER / DEVELOPER: 64 LEAD CONSULTANT:


RESIDENTIAL SPACES
ONE / TWO / THREE BEDROOM – KITCHENS ( COOL - PRACTICAL – COZY )

PORCILAIN TILES WOOD EFFECT MARBLE CLADDING OFF WHITE PAINT

OWNER / DEVELOPER: 65 LEAD CONSULTANT:


RESIDENTIAL SPACES
ONE / TWO / THREE BEDROOM – BATHROOM ( COOL - PRACTICAL – COZY )

PORCILAIN TILES PORCELIAN TILES -OFFWHITE OFF WHITE PAINT LIGHT GREY PAINT

OWNER / DEVELOPER: 66 LEAD CONSULTANT:


RESIDENTIAL SPACES
DOUBLEX – LIVING AREA ( RICH - LUXURY – WARM )

PORCILAIN TILES PORCILAIN TILES -BEIGE OFF WHITE PAINT GREY PAINT

OWNER / DEVELOPER: 67 LEAD CONSULTANT:


RESIDENTIAL SPACES
DOUBLEX – MASTER BEDROOM ( RICH - LUXURY – WARM )

HDF FLOORING OFF WHITE PAINT WALNUT WOOD/VENEER

OWNER / DEVELOPER: 68 LEAD CONSULTANT:


RESIDENTIAL SPACES
DOUBLEX – DRESSING ( RICH - LUXURY – WARM )

HDF FLOORING WALNUT WOOD/VENEER


OFF WHITE PAINT GRAY PAINTED WOOD

OWNER / DEVELOPER: 69 LEAD CONSULTANT:


RESIDENTIAL SPACES
DOUBLEX – KITCHENS ( RICH - LUXURY – WARM )

HDF FLOORING WALNUT WOOD/VENEER OAK WOOD/VENEER


OFF WHITE PAINT

OWNER / DEVELOPER: 70 LEAD CONSULTANT:


RESIDENTIAL SPACES
DOUBLEX – BATHROOM ( RICH - LUXURY – WARM )

CALACATTA MARBLE PORCILAIN TILES WOOD EFFECT GRIGIO SAN MARCO MARBLE OFF WHITE PAINT GRAY PAINTED WOOD

OWNER / DEVELOPER: 71 LEAD CONSULTANT:


ERKYAH MIXED USE
LUSAIL - QATAR
STRUCTURE CONCEPT REPORT
REVISION 00 – NOV. 2019

OWNER / DEVELOPER: 72 LEAD CONSULTANT:


Table of Structure Contents 12.6. MATERIALS ......................................................................................................................................... 87

1. INRODUCTION ............................................................................................................................................. 74 12.7. DEFLECTION ....................................................................................................................................... 87


12.8. MODELLING ASSUMPTIONS .............................................................................................................. 88
2. PROJECT DESCRIPTION ................................................................................................................................ 3
3. DESIGN OBJECTIVE...................................................................................................................................... 74 13. SCHEMATIC STRUCTURAL SYSTEM .............................................................................................. 90

4. DESIGN WORKING LIFE ................................................................................................................................. 3 13.1. FOUNDATION SYSTEM ...................................................................................................................... 90

5. DESIGN METHODS.......................................................................................................................................... 3 13.2. HORIZONTAL SYSTEMS ..................................................................................................................... 90

6. CODES AND STANDARDS .............................................................................................................................. 3 13.3. VERTICAL SYSTEMS .......................................................................................................................... 90

7. STRENGTH OF MATERIALS ......................................................................................................................... 75 13.4. RETAINING WALL ............................................................................................................................... 91

8. LOAD ASSUMPTIONS ................................................................................................................................... 76 13.5. WATER TANK ...................................................................................................................................... 91

8.1. DEAD LOADS AND SUPERIMPOSED DEAD LOADS ......................................................................... 76 14. CONEPTUAL STRUCTURAL PLAN .................................................................................................. 92
8.2. LIVE LOADS ........................................................................................................................................ 76 14.1. EXPANSION JOINTS LOCATION ........................................................................................................ 92

8.3. WIND LOAD ......................................................................................................................................... 77 14.2. ZONES ................................................................................................................................................. 93

8.4. EARTH AND GROUNDWATER PRESSURE ....................................................................................... 77 14.3. BASMENT 01 FLOOR PLAN ................................................................................................................ 94

8.5. SEISMIC LOAD .................................................................................................................................... 77 14.4. GROUND FLOOR PLAN ...................................................................................................................... 95

8.6. TEMPERATURE LOAD ........................................................................................................................ 78 14.5. PODIUM 01 FLOOR PLAN ................................................................................................................... 96

9. LOAD CASES .................................................................................................................................... 80 14.6. SERVICE FLOOR PLAN ...................................................................................................................... 97

9.1. SERVICEABILITY LIMIT STATE COMBINATIONS .............................................................................. 80 14.7. PODIUM 02 FLOOR PLAN ................................................................................................................... 98

9.2. ULTIMATE LIMIT STATE...................................................................................................................... 82 14.8. TYPICAL 01 FLOOR PLAN .................................................................................................................. 28


14.9. TYPICAL FLOOR PLAN ....................................................................................................................... 29
10. GEOTECHNICAL CONSIDERATIONS .............................................................................................. 83
11. DURABILITY CONSIDERATIONS ..................................................................................................... 84
11.1. DURABILITY RELATED PROPERTIES ............................................................................................... 84
11.2. PROTECTION TO CONCRETE ELEMENTS AND CLEAR CONCRETE COVER ................................ 84
11.3. CRACK WIDTH .................................................................................................................................... 84
11.4. FIRE RESISTANCE.............................................................................................................................. 84
11.5. CONTROL OF STRESSES DUE TEMPERATURE CHANGE .............................................................. 85
11.6. STEEL CORROSION PROTECTION ................................................................................................... 85
11.7. CONSTRUCTION JOINTS ................................................................................................................... 85
12. MODELLING AND STRUCTURAL ANALYSIS CONSIDERATIONS ................................................. 86
12.1. SOFTWARE ......................................................................................................................................... 86
12.2. P-DELTA ANALYSIS ............................................................................................................................ 86
12.3. DIAPHRAGMS ..................................................................................................................................... 86
12.4. EXPANSION JOINT ............................................................................................................................. 87
12.5. STORY DRIFT...................................................................................................................................... 87

OWNER / DEVELOPER: 73 LEAD CONSULTANT:


1. INTRODUCTION (a) Structures or parts of structures that can be dismantled with intention of being reused, aren’t temporary
structures
This section aims to set the design standards and guidelines for the design work to be adopted
for the preparation of structure design drawings and specifications for the building. Also it shall
indicate guidelines for the selection of building statical systems. 5. DESIGN METHODS
2. PROJECT DESCRIPTION  Limit state design method will be used for all structural elements.

The project is the construction of ERKYAH MIXED USE DEVELOPMENT project at  Serviceability limit state will be used for deflection criteria.
Qatar. The building consists of:  Both safety and serviceability design conditions will be accounted for.
Two basements (Parking & Service), Ground floor (Retail, Anchors), First podium (FEC, Shops
and Cinemas), Service floor (MEP, Serviced Apartments & Podium LSC), Second podium
(Service), Typical floor plans (12 Floors Serviced Apartment), and Roof plan 6. CODES AND STANDARDS
SCOPE OF THE REPORT All design and details will be prepared in accordance with the following codes:
This report summarizes the design criteria, assumptions and approaches that are adopted in
Code,
structural engineering design of the project. Standard or
The proposed values have been established as being the most appropriate for the project, in full Description
Reference
compliance with international standards and excellent practice taking into consideration (Primary list)
constrains and limitations associated with the project.
QCS 2014 Qatar Construction Specifications.
3. DESIGN OBJECTIVE Building Code - American Concrete Institute Requirements for
Our objective is to fulfill the architectural design intent, with the safest and the most cost effective ACI 318-14 Structural Concrete ACI Manuals of Concrete Practice 2001
and economical design. Taking into consideration the constructability aspects and safety. American Concrete Institute.
ASCE 7- 10 Minimum Design loads for building and other structures.
4. DESIGN WORKING LIFE
AISC Manual of Steel Construction - American Institute of Steel
The design working life of the building structures considered 50 years as per QCS 2014 AISC
Construction.
The following is the QCS 2014 recommendations for the design life:
Building structure design working life shall be minimum as specified below: AWS Code American Welding Society.
DESIGN INDICATIVE
WORKING LIFE DESIGN WORKING EXAMPLES
CATEGORY LIFE (YEARS) The following codes of practice and standards could be used when needed:
Code, Standard or
1 10 TEMPORARY STRUCTURES (a)
Reference Description
REPLACAPLE STRUCTURAL PARTS, eg. (Secondary list)
2 10 TO 25
GANTRY GIRDERS, BEARINGS
UBC 1997 Uniform Building Code, USA.
3 15 TO 30 STORAGE AND SIMILAR STRUCTURES
PCI Design Handbook for Precast / Prestressed Concrete,
BUILDING STRUCTURES AND OTHER PCI
4 50 TO 75 Fourth Edition - Precast / Prestressed Concrete Institute.
COMMON STRUCTURES
CRSI 2002 Concrete Reinforcing Steel Institute.
CIVIL ENGINEERING STRUCTURES LIKE
5 120
BRIDGES, TUNNEL etc BS 4 Structural steel sections.

OWNER / DEVELOPER: 74 LEAD CONSULTANT:


Code, Standard or 7. STRENGTH OF MATERIALS
Reference Description
(Secondary list) The following minimum material strength is considered:
Specification for ordinary and rapid hardening Portland
BS EN 197
cement. Cast-in-situ Concrete
BS 648 Schedule of weights of building materials. Grade
BS 3692 ISO metric precision hexagon bolts, screws and nuts. Material description (QCS
2014)
BS 4027 Specification for Sulphate resisting Portland cement.
Plain Concrete B 20
BS 4190 ISO metric black hexagon bolts, screws and nuts.
A-Reinforced Concrete : Columns and Walls Generally (except B) C 50
BS EN 10025 Hot rolled structural Steels Products.
B-Reinforced Concrete : Columns and Walls For towers & Special
Specification for hot finished structural steel hollow C 60
BS EN 10210 areas
sections.
Specification for hot rolled bars for the reinforcement of Reinforced Concrete : Foundations, Water tanks and Retaining Walls C 50
BS 4449
concrete.
A-Reinforced Concrete : Beams and Slabs Generally (except B) C 45
Spec for scheduling, dimensioning, bending and cutting of
BS 8666
steel reinforcement for concrete. B-Reinforced Concrete : Beams and Slabs For towers & Special
C 45
areas
BS 4483 Specification for steel fabric for reinforcement of concrete.

BS 5628 Code of practice for structural use of masonry.

BS 6031 Code of practice for earthwork. Reinforcing and Structural Steel (Yield strength)
Welded Structural Steel tubes for General Engineering Minimum
BS EN 10296 Material description
Purposes. strength
Loading for building Part 1 code of practice for dead and
BS 6399 Non-Prestressed Deformed Bars 500 MPa
imposed loads.
BS 8004 Code of practice for foundations. Prestressed Strands 1690 MPa
Code of practice for design of concrete structures for
BS 8007 Structural Steel 355 MPa
retaining aqueous liquid.
BS 8110 Structural use of concrete. Bolts and Nuts Grade 8.8 640 MPa

BS 5950 Structural Use of steelwork in building. Headed Shear Studs 350 MPa
Code of basic data for the design of buildings for Wind
BS 6399 Part 2
loads.
CIRIA Guide to concrete construction in Gulf region.

OWNER / DEVELOPER: 75 LEAD CONSULTANT:


8. LOAD ASSUMPTIONS
8.1. DEAD LOADS AND SUPERIMPOSED
8.2. LIVE LOADS
DEAD LOADS

Material unit weights Occupancy Load intensity


Exterior cladding
Residential all areas 2.00 KN/m2
Reinforced cement concrete 25 KN/m3
Residential occupancies Private
Glass curtain walls 1 KN /m2 3.00 KN/m2
rooms and corridors serving them
Lightweight (foam) concrete 10 KN /m3 STORAGE FOR ALL FLOORS 6.00 KN/m2
15 cm concrete + insulation + 10
6 KN/m2 Services And Prayer Hall 5.00 KN/m2
cm normal cement block
Concrete block walls, solid 21 KN /m3 Vehicular driveways and, Ramps 4.00 KN/m2
Double cement block walls +
6 KN/m2
sandwiched insulation + plaster Parking Areas 2.50 KN/m2
Cement plaster / cement-sand Sidewalks, and yards subject to
20 KN /m3 15.00 KN/m2
screed Interior partitions trucking with impact
Stairs and exit ways 5.00 KN/m2
Marble / granite for cladding 26 KN /m3 Density of the brick walls 16.00 KN/m3
Lobbies And Corridors 5.00 KN/m2

77.84 KN Roof, accessible if mechanical 7.5 KN/m2


Structural steel ALL distributed partitions 4.30 KN/m2
/m3 Roof horizontal and inaccessible 2.0 KN/m2
Roof, inclined (angle greater than
Garden soil 20 KN /m3 Normal cement block15 cm thick 4 KN /m2 0.75 KN/m2
20) and inaccessible
Roofs used for roof gardens 4.80 KN/m2
Dead loads per unit area
Normal cement block 20 cm thick 5 KN/m2 Mechanical equipment area, Actual machine
A- Drive ways Slab finish Electrical sub-station (assumed load + 4 KN/m2 for
1 KN /m2 Normal cement block 25 cm Machines load 3.00 KN/m2) circulation area
6 KN /m2
thick Offices 2.40 KN/m2
B-Basement finish Corridors Other floors, same as
2.5 KN /m2
Except (A) Demountable partitions 1 KN/m2 occupancy served except as
5.00 KN/m2
indicated, and Dining rooms, Shops
Floor finish, other 2 KN /m2 and Restaurants
Wholesale Areas (HYPER
7.50 KN/m2
(MARKET
Ceiling + utilities 0.50 KN/m2 Entertainment Areas 6 m Height 10.00 KN/m2
Entertainment Areas 12 m Height 15.00 KN/m2
Cinema 5.00 KN/m2
Gymnasium 7.50 KN/m2

OWNER / DEVELOPER: 76 LEAD CONSULTANT:


8.3. WIND LOAD 8.4. Earth and Groundwater Pressure
Design shall be based on 3-seconds ultimate basic wind velocity of 38 m/s at 10 meters above External earth pressure and groundwater pressure will act on the basement walls. The forces will
ground in an open terrain as per ASCE 7-05 and QCS 2014 ( AS PER SOIL REPORT ). The be derived from the following design parameters:
corresponding wind speeds as specified by other standards as shown in the following table:  Unit Weight of the dry soil 18 KN/m3
 Unit Weight of the saturated soil 22 KN/m3
Return  Coefficient of lateral earth pressure at rest, Ko = 0.5
Wind Speed Wind Speed
Standard Period
Description Value (m/s)  Surcharge: 5 KN/m2 for general service road and 10 KN/m2 for the main road
(Years)
3 seconds gust 8.5. SEISMIC LOAD
ASCE 7-10
700 Nominal wind 48 m/s**
(ULS) Design seismic load shall be based on the following parameters as per ASCE 7-10 and QCS
speed
3 seconds gust 2014:
ASCE 7-10
50 Nominal wind 38 m/s
(SLS)
speed Design Basis Earthquake (DBE)
3 seconds gust (2475 years Return Period)
ASCE 7-05 50 Nominal wind 38 m/s
0.2 second spectral
speed 0.147 g
Acceleration: SS
Mean hourly wind
BS 6399-2 50 25 m/s 1 second spectral
speed 0.065 g
Mean 10 minutes Acceleration: S1
BS EN 1991-1-4 50 27 m/s
wind speed Other Seismic Parameters
**The ratio of the wind speed for any return period to the 50 year return period wind speed as per
Peterka & Shahid Equation is:
Long-period transition period 8 sec
VT / V50 = [0.36+0.1 ln (12T)]
1
Wind loads derived from ASCE 7-10 code shall be applied from all different compass directions. Seismic zone (assumed site
class B)
As per Geotechnical report from ‘Qatar Industrial Laboratories’ we found that in section 6.0:
Seismic importance factor (I) 1.00
A- Nominal wind speed (for 3 sec. gust) = 38 m/s = 87 mph.
As per ASCE-7-10 Section 26.7.3 we could conclude that the exposure used for this building is
(C). As per Geotechnical report from ‘Qatar Industrial Laboratories’ we found that:
A- 0.2 Second Spectral Acceleration (g) – Ss =0.147m/sec2 (page 7 section 5.0)
A- Wind direction factor, kd= 0.85 (Table 26.6-1) B- 0.1 Second Spectral Acceleration (g) – S1 =0.065 m/sec 2 (page 7 section 5.0)
B- Topographical factor, Kzt = 0.85 (Table 26.8-1)
C- Also we found that Qatar can be designed to Seismic Zone 1 (page 7 section 5.0)
C- Gust factor = 0.85 (section 26.9.1)
As the designed seismic zone is 1 (As per Geotechnical report),’’Generally, Seismic Activity with
D- Windward Coefficient, Cpw=0.8 (table 27.4-1 (Cont.) (Wall pressure coefficients, Cp)
the area is very low, recommendations give in BRE digest (H16) earthquake and seismic zones
E- Leeward Coefficient, Cpl=0.5 (table 27.4-1 (Cont.) (Wall pressure coefficients, Cp)
in the middle east
F- e1=ex = 0.15 x Building width in X-dir (table 27.4-8 (case 2 and 4))
, 1983 indicate that Qatar lie with in a zone of no influence that Qatar can be designed to seismic
G- e2=ey = 0.15 x Building width in Y-dir (table 27.4-8 (case 2 and 4))
zone (1)’’
Exposure type ‘’B’’

OWNER / DEVELOPER: 77 LEAD CONSULTANT:


No giver data for site class, but soil profile (as mentioned in Geotechnical report is rock which For Mass Source Definition refer to ASCE-7-10 section 12.7.2 and it will be as follow:
indicate that to be Site class ‘’B” A- Total dead load (own weight (D1) + [Finishing loads + Walls + Ceiling load ….. etc.]
Using Ss and S1 and as per ASCE-7-10 equations (11.4-3, 11.4-4) and table (11.4-1) we can find (D2))
that: B- 25% for storage (L4)
A- SDS=0.098 m/sec2 <0.167 m/sec2 C- 0% for public garages and open parking structures
B- SD1=0.0433 m/sec2 <0.167 m/sec2 D- 0% live loads above 5 kn/m2
C- Long period transition period is 8 sec for Qatar E- 0% live load below 5 kn/m2
D- Fa = 1 F- 100% live loads of equipment and mechanical loads (L5)
E- Fv = 1 G- 100% for landscaping & other material at roof gardens and similar areas (Lrg), not used
in 353- project
Risk Category for both SDS & SD1 is Seismic Design Category ‘’A”
H- 100% fluids loads for tanks (F)
Structure statical system used for towers (Code ASCE7-10) ‘’B-building frame systems ordinary Modifiers used for moment of inertia as per ACI-318-14 table 6.6.3.1.1(a) and for details check
reinforced concrete shear wall’’. (10-Modifiers):
So parameters used in ASCE-7-10 Table 12.2-1 are as follow:
A- Columns = 0.7
A- R (Response Modification Coefficient) = 5.0 B- Walls = 0.35 (cracked) and 0.7 (un-cracked) check of stresses to be smaller than or
B- Omega (over Strength Factor) = 2.5 equal to the allowable rapture stress and if the stress is more than that we could use the
C- Cd (Deflection Amplification Factor) = 4.5 un-cracked modifiers.
C- Beams = 0.35
Structure statical system used is “SHEAR WALL-FRAME INTERACTIVE SYSTEM WITH D- Ordinary slabs = 0.25
ORDINARY REINFORCED CONCRETE MOMENT FRAMES AND ORDINARY REINFORCED E- Post tension slab = 0.5 as per euro code as ACI did not mention it.
CONCRETE SHEAR WALLS” [F-Case] for services area.
So parameters used in ASCE-7-10 Table 12.2-1 are as follow:
D- R (Response Modification Coefficient) = 4.5 8.6. TEMPERATURE LOAD
E- Omega (over Strength Factor) = 2.5 Design temperature change shall be
F- Cd (Deflection Amplification Factor) =4 based on ASCE 7-10 and QCS2014, as
Value
shown in the following table:
Temperature Description
As per Architecture plans we could conclude that occupancy importance of building would be as
per ASCE-7-10. As following:
Maximum ambient temperature 50oC
For Typical floors (Towers models);
A- Risk Category from Table 1.5-1 to be (II) “Building and Other Structures where not more
than 200 peoples congregated in one area’’ as life safety preliminary calculations. Minimum ambient temperature 5oC
B- According to section 1.5 and table 1.5-2 we could find that Seismic Importance Factor
for Risk category ( II) will be = 1.00
The concrete temperature
30oC
For Special cases (Swimming pool, Hyper Market, Cinema); (At the time of delivery)
Design temperature change 25oC
C- Risk Category from Table 1.5-1 to be (III).
(The load factor to be taken equal to (Plus or
D- According to section 1.5 and table 1.5-2 we could find that Seismic Importance Factor
1.00 (ULS) and 0.75 (SLS)) Minus)
for Risk category (III) will be = 1.25

OWNER / DEVELOPER: 78 LEAD CONSULTANT:


As per Geotechnical report from ‘Qatar Industrial Laboratories’ we found that in section 6.0:
A- Maximum ambient temperature = 50 ◦C
B- Minimum ambient temperature = 5 ◦C
C- Design ambient temperature = 50 ◦C
D- Thermal analysis shall be designed for temperature difference Temp = ± 30 ◦C and it
would be applied on Slabs only in CSI program. Also temp. Will applied on exposed
ground floor and roof floors only.

Modifiers for Temperature (Thermal) Model shall be as following;


A- Columns = 0.7
B- Walls = 0.35 (cracked)
C- Beams = 0.35
D- Slabs m11=m22=f12=0.5 , f11=f22=0.15, m12=0.01
E- No assigned diaphragms.

Load combination used is as per ASCE-7-10 section 2.3 as following;

1.2(D+F+T) +1.6(L+H) +0.5(Lr or S or R), It means modifier of temperature the same modifier for
dead load.

OWNER / DEVELOPER: 79 LEAD CONSULTANT:


9. LOAD CASES
For the purpose of this report the following symbols shown in are used: 9.1. SERVICEABILITY LIMIT STATE COMBINATIONS
For serviceability limit state verification, the following load combinations are considered:
Symbol Description
Load
D1 Dead Load. Combination D1 D2 F L1 L2 L3 L4 L5 Lr W E H T
ID
D2 Super Imposed Dead Load.
S0100 1.00 1.00 1.00 NA NA NA NA NA NA NA NA NA NA
F Well-defined fluids pressures. (Tanks)
S0100-TP / ±
Live load > 5 KN/m2, areas occupied as 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 NA NA NA
S0100-TN 0.75
places of public assembly with the exception
L1
of areas used for storage and weight of S0200 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 NA NA NA NA NA
permanent equipment.
Live load < 5 KN/m2, with the exception of
S0300 1.00 1.00 1.00 NA NA NA NA NA 1.00 NA NA NA NA
L2 garages or areas occupied as places of
public assembly.
S0400 1.00 1.00 1.00 0.75 0.75 0.75 0.75 0.75 0.75 NA NA NA NA
L3 Garages.
S0511 / ±
1.00 1.00 1.00 NA NA NA NA NA NA NA NA NA
S0512 0.60
L4 Storage.
S0521 / ±
1.00 1.00 1.00 NA NA NA NA NA NA NA NA NA
Total operating weight of permanent S0522 0.70
L5
equipment. S0611 / ±
1.00 1.00 1.00 0.75 0.75 0.75 0.75 0.75 0.75 NA NA NA
S0612 0.45
Lr Roof live load. S0621 / ±
1.00 1.00 1.00 0.75 0.75 0.75 0.75 0.75 0.75 NA NA NA
S0622 0.525
W Wind load. S0711 / ±
0.60 0.60 NA NA NA NA NA NA NA NA NA NA
S0712 0.60
Wdisp Wind load for displacement calculation. S0721 / ±
0.60 0.60 NA NA NA NA NA NA NA NA 1.00 NA
S0722 0.60
E Seismic load.
S0811 / ±
0.60 0.60 0.60 NA NA NA NA NA NA NA NA NA
S0812 0.70
Edrift Seismic load for drift calculation.
S0821 / ±
0.60 0.60 0.60 NA NA NA NA NA NA NA 1.00 NA
Lateral earth pressure, ground water S0822 0.70
H
pressure, or pressure of bulk materials.
T Self-straining loads (Temperature change)

OWNER / DEVELOPER: 80 LEAD CONSULTANT:


For verifying the horizontal displacement limit state due to wind load, the following load Floors Deflection
combinations are considered:
# Load With reference to ACI 318-14, the reinforced concrete floors should design for the following deflection limits:
Combination D1 D2 L1 L2 L3 L4 L5 Lr Wdisp
ID Table 24.2.2-Maximum permissible calculated deflections
S0910 / ± Deflection
1.00 1.00 0.50 0.50 0.50 0.50 0.50 0.50 Member Condition Deflection to be considered
S0920 1.00 limitation

For verifying the inter-story drift limit state due to seismic load, the following load Not supporting or attached to
combinations are considered: Flat nonstructural elements likely to be
Immediate deflection due to maximum of L, S, R L/180 (1)
roofs damaged by large deflections
# Load Combination
Edrift Immediate deflection due to L
ID

S1010 / ±
S1020 1.00 Not supporting or attached to
For verifying the long-term serviceability limit state of concrete slabs, the following long- nonstructural elements likely to be
Floors L/360
term parameter and load combinations are considered: damaged by large deflections
Long-term Immediate deflection due to L
Value
Parameter
λ 2.00 That part of total deflection occurring after
Supporting or attached to attachment of nonstructural elements, which is
Roof or
nonstructural elements likely to be the sum of the time dependent deflection due to L/480 (3)
Type of floors
Type of Slab Load Combination damaged by large deflections all sustained loads and the immediate due to any
Analysis
additional live load (2)
Immediate deflection due to all gravity
That part of total deflection occurring after
loads
Supporting or attached to attachment of nonstructural elements, which is
(Cracked) Roof or
nonstructural elements NOT likely to the sum of the time dependent deflection due to L/240 (4)
- Immediate deflection due to floors
Traditional be damaged by large deflections all sustained loads and the immediate due to any
Non-Linear sustained gravity loads
RC additional live load (2)
(Cracked)
(1)Limit not intended to safeguard against ponding. Ponding shall be checked by calculations of deflection, including added
+ Long-Term deflection due to
deflections due to ponded water, and considering time- dependent effects of sustained loads, camber, construction tolerances,
sustained gravity loads and reliability of provisions for drainage.
(Cracked + Long-Term) (2)Time-dependent deflection shall be calculated in accordance with 24.2.4, but shall be permitted to be reduced by amount of
λ x Dead Loads deflection calculated to occur before attachment of nonstructural elements. This amount shall be calculated on basis of accepted
+ (0.25 x λ + 0.75) x Live Loads engineering data relating to time-deflection characteristics of members similar to those being considered.
PT Linear (3)Limit shall be permitted to be exceeded if measures are taken to prevent damage to supported or attached elements.
+ λ x Final PT Load
(4)Limit shall not exceed tolerance provided for nonstructural elements.
(Un-cracked)
λ x Dead Loads
Traditional
Linear + (0.25 x λ + 0.75) x Live Loads
RC
(Cracked)

OWNER / DEVELOPER: 81 LEAD CONSULTANT:


9.2. ULTIMATE LIMIT STATE
For ultimate limit state verification, the following load combinations shown are
considered:

# Load
Combination D1 D2 F L1 L2 L3 L4 L5 Lr W E H T
ID

U0100 1.40 1.40 1.40 NA NA NA NA NA NA NA NA NA NA

U0100-TP / ±
1.20 1.20 1.20 1.60 1.60 1.60 1.60 1.60 1.60 NA NA NA
U0100-TN 1.00

U0200 1.20 1.20 1.20 1.60 1.60 1.60 1.60 1.60 0.50 NA NA NA NA

U0310 1.20 1.20 1.20 1.00 1.00 1.00 1.00 1.00 1.60 NA NA NA NA

U0320 1.20 1.20 1.20 1.00 0.50 1.00 1.00 1.00 1.60 NA NA NA NA

U0331 / ±
1.20 1.20 1.20 NA NA NA NA NA 1.60 NA NA NA
U0332 0.50
U0411 / ±
1.20 1.20 1.20 1.00 1.00 1.00 1.00 1.00 0.50 NA NA NA
U0412 1.00
U0421 / ±
1.20 1.20 1.20 1.00 0.50 1.00 1.00 1.00 0.50 NA NA NA
U0422 1.00
U0511 / ±
1.20 1.20 1.20 1.00 1.00 1.00 1.00 1.00 NA NA NA NA
U0512 1.00
U0521 / ±
1.20 1.20 1.20 1.00 0.50 1.00 1.00 1.00 NA NA NA NA
U0522 1.00
U0611 / ±
0.90 0.90 NA NA NA NA NA NA NA NA NA NA
U0612 1.00
U0621 / ±
0.90 0.90 NA NA NA NA NA NA NA NA 1.60 NA
U0622 1.00
U0711 / ±
0.90 0.90 0.90 NA NA NA NA NA NA NA NA NA
U0712 1.00
U0721 / ±
0.90 0.90 0.90 NA NA NA NA NA NA NA 1.60 NA
U0722 1.00

OWNER / DEVELOPER: 82 LEAD CONSULTANT:


10. GEOTECHNICAL CONSIDERATIONS
The geotechnical investigation was carried out by QATAR INDUSTRIAL The excavation should be at the flowing slopes:
LABORATORIES W.L.L. The field work commenced on August 29, 2019. The contractor should follow soil report and Geotechnical consultant recommendations for
excavation conditions and for soil stability.
The following information is considered in the structural design as interpreted form
the report: The fill material used shall be conforming to QCS2014 as shown in the following table:

Parameter Limit
Maximum Allowable Liquid Limit 35% (Maximum)
Ground
Building Foundation Immediate Net
Water Plasticity Index 10% (Maximum)
Title Level* Elastic Bearing
Table** Material Passing 0.075
Settlement Capacity 20% (Maximum)
mm Sieve
Organic Matter Content 2% (Maximum)
ERKYA
8.00-9.00 +1.00
MIXED 25 mm 475 KPa Soaked CBR value 15% (Minimum)
m QND
USE 5% (Maximum)by weight of dry
ERKYA Water soluble salts
12.00- +1.00 soil
MIXED 25 mm 500 KPa
13.00 m QND Rock Particles Size 75 mm (Maximum)
USE

Structural fill should not contain any roots, construction debris, salts, deleterious material, organic
*Below existing ground level.
matters, cobbles or boulders (size 80mm). Recommended backfill material can be specified within
**The groundwater table highest level to be +1.00 QND .
granular non-cohesive soils. Well-graded material is preferred.
Lateral earth pressure developed by compacted backfill are calculated using an
For uplift Design Check using safe we would use the following equation for this check:
angle of internal friction of phi and the corresponding at rest, active, and passive
pressure coefficients are as follows:
0.9 x (Own Weight) – Uplift Load shall be greater than or equal to zero
Phi = 30 Phi = 45 Phi = 40
Coefficient
degree degree degree
At Rest 0.5 0.292 0.357
Active 0.33 0.171 0.217
Passive 3.00 5.83 4.59

OWNER / DEVELOPER: 83 LEAD CONSULTANT:


11. DURABILITY CONSIDERATIONS
11.1. Durability related properties 11.3. CRACK WIDTH
All structural elements are designed for crack width as per ACI 224R-01 and complied with Euro-
Will be carried on when exposure conditions are available
code 2 provision as shown in the following table:

11.2. PROTECTION TO CONCRETE ELEMENTS AND CLEAR


Exposure Condition Crack Width
CONCRETE COVER
0.40
Concrete elements in contact with earth would be provided with protective Dry air or protective membrane
mm(Maximum)
membrane water proofing with protection board or protection screed etc., as
0.30 mm
appropriate, in order to prevent possible damages during the sequence of Humidity, moist air, soil
(Maximum)
construction. Concrete elements in contact with liquids, fire water in fire water tanks,
potable water in cold water tanks, oil interceptors, manhole chambers, area drains, 0.18 mm
Deicing chemicals
sewage structures etc., would be provided with proprietary products of property and (Maximum)
quality, as appropriate to the level of protection that is required. Seawater and seawater spray, wetting 0.15 mm
Clear concrete cover is specified in due consideration of the prevalent exposure and drying (Maximum)
and environmental condition as per QCS 2014 and shown in the following table: 0.10 mm
Water-retaining structures
(Maximum)
Exposure
Concrete
Class Specified 11.4. FIRE RESISTANCE
Element Grade
(QCS cover
(QCS 2014) All structural steel elements and concrete elements will be designed, detailed in order to achieve the
2014)
following fire ratings as per the NFPA 5000 as shown in the following tables:
Slab on Grade (If exist) C 25 X0 25 mm(Minimum)
Water Retaining Structures C 50 X3 50 mm(Minimum)
Fire Resistance Rating (hr)
Foundations, and Retaining Walls C 50 X3 70 mm(Minimum) (NFPA 5000)
Construction
A-Super-Structure: Beams and Slabs Building Building Type Beams,
C 45 X1 40 mm(Minimum)
(Towers, special areas) Number Title (NFPA Girders,
Bearing Floor Roof
B-Super-Structure: Beams and Slabs 5000) Columns Trusses
C 45 X1 40 mm(Minimum) Walls Assembly Assembly
(Generally except A) and
A-Vertical-Structure: Columns and Arches
C 60 X1 40 mm(Minimum)
Shear walls (Towers, special areas) Type II
B-Vertical-Structure: Columns and B-1 -- 3 3 3 3 3
C 50 X1 40 mm(Minimum) (2,2,2)
Shear walls (Generally except A)

OWNER / DEVELOPER: 84 LEAD CONSULTANT:


11.5. CONTROL OF STRESSES due temperature change
Efforts would be exercised in order to limit the development of undue thermal
stresses within the structure by providing necessary expansion joints.
However, due to architectural and other structural consideration, if expansion joints
are not provided for a linear dimension of structure exceeding 60 m, the structural
elements would be designed and detailed in order to resist the thermal stresses.

11.6. Steel corrosion protection


The corrosion protection for the structural steelwork will be dependent on the
location of the steel elements within the building.
A high standard corrosion protection scheme is required for all exposed steelwork
and the minimum requirement is the long term protection.

11.7. CONSTRUCTION JOINTS


Isolation joints and construction joints would be located at appropriate locations,
designed and detailed to meet the functional requirement. Construction joints would
be minimized and contractors would be given a chance to propose as per their
construction sequence, in order to meet the approved construction program.

OWNER / DEVELOPER: 85 LEAD CONSULTANT:


12. MODELLING AND STRUCTURAL ANALYSIS Also P-delta option shall be defined in Etabs as follow:

CONSIDERATIONS A- Automation method is iterative – based on loads


B- Load combination shall be 1.2(D)+[0.5(L<5) or 1.0(L>5]
12.1. SOFTWARE C- For our project 1.2(D1+D2) + [0.5(L2) or 1.0(L1,3,4,5]
The following software will be used to model, analysis and design the building D- Relative convergence tolerance = 0.01
structures:
Software Description Purpose As per ASCE-7-10 section 12.4.3 horizontal seismic load shall be applied including over strength factor as per
equations 12.4-5, 12.4-6, 12.4-7 and using them in load combinations in section 12.4.3.2
Integrated software
package for the structural 3D modelling, analysis and design of As per ASCE-7-10 section 12.3.3 limitation of structure irregularity shall be applied to consider 0.05 eccentricities
CSI ETABS
analysis and design of building structures and if we need to amplify it use equations found in section 12.8.4.3
building structures

Integrated software 3D modeling, analysis and 12.3. Diaphragms


CSI SAP package for structural design of structural
As per CSI recommendations diaphragms in Etabs shall be semi-rigid and hereunder the recommendations from
2000 analysis and design of elements
CSI:
structures (General purpose)

2D modeling, analysis and Rigid diaphragms have infinite in-plane stiffness properties, and therefore they neither exhibit membrane
Ultimate tool for designing deformation nor report the associated forces, whereas semi-rigid diaphragms simulate actual in-plane stiffness
design of reinforced
CSI SAFE concrete floor and properties and behavior. For most reinforced-concrete slab systems, in which the slab is sufficiently thick and
concrete foundations and
foundation systems. membrane deformation due to lateral loading is negligible, rigid diaphragms produce results nearly identical to
slabs
those of semi-rigid diaphragms, while taking advantage of faster computation. Semi-rigid diaphragms should be
Calculation pad for Structural analysis and modeled when significant in-plane deformation does occur, or when required by code.
structural analysis and design of structural Primary differences;
PROKON
design of structural elements Formulation – The infinite in-plane stiffness components of a rigid diaphragm allows the stiffness matrix to
elements. (General purpose) condense, decreasing computational time.
Eccentricity – For rigid diaphragms, the accidental eccentricity associated with auto seismic loading is
concentrated and applied at the center of mass, whereas for semi-rigid diaphragms, accidental eccentricity is
12.2. P-Delta Analysis
applied to every node for auto seismic loads. If no diaphragm is assigned eccentricity will not be applied to any
As per ASCE-7-10 section no 12.8.7 we ought to calculate (Ɵ) actual from Etabs node. For auto wind load cases and rigid diaphragm, loading is applied at geometric centroid, in case of semi-rigid
model and compare it with the maximum allowable sway as following; diaphragm auto wind loads are distributed in 10 nodes, so that the summation of these forces with respect to
centroid will be equivalent to lateral and torsional wind cases.
Ɵ max = (0.5/ (Beta x Cd), where Beta = 1, Cd equal 4 for selected lateral Reporting forces – In-plane chord, shear, and collector forces are only reported when using semi-rigid diaphragms.
resisting system for example

Ɵ max = (0.5/ (1x4.0)) =0.125 <0.25


If Ɵ actual < 0.1 (no need for p-delta analysis)
, If Ɵ actual > Ɵ max (The structure is potentially unstable and shall be
redesigned)

OWNER / DEVELOPER: 86 LEAD CONSULTANT:


12.4. Expansion joint Modulus of rapture Fr = 0.62 x (λ) x sqrt(fc’) (Equation 19.2.3.1)
λ = 1 for normal weight concrete (Table 19.2.4.2)
A- Expansion joints are provided in the 1st basement, ground, 1st podium,
2nd podium and first floors to decrease the impact of the thermal
Concrete weight per unit volume = 25 kn/m3
stresses on the structural elements. The location of the expansion
joints are synchronized with the location of the tower blocks as no For Slabs and Beams Fcu= 45 MPa the Fc’ = 35 MPa
expansion joints provided in tower typical floors. (Towers) Ec = 4700 x sqrt (35) =27805 MPa
B- As per ASCE-7-10 section 12.12.3 we could find that;Etabs gives us the Fr = 0.62 x (λ) x sqrt(35) = 3.66 MPa
maximum allowable elastic displacement in two orthogonal directions For Columns & Shear walls Fcu= 60 MPa the Fc’ = 48 MPa
(E1,E2), these two displacements shall be inelastic by multiplying them (Towers) Ec = 4700 x sqrt (48) = 32563 MPa
with the factor (Cd/I) which is (4/1.25) in service area case, also these two Fr = 0.62 x (λ) x sqrt(48) = 4.3 MPa
displacements are from ultimate limit state so they will be reduced by 70% For Raft & Retaining wall Fcu= 50 MPa the Fc’ = 40 MPa
in order to change them to working limit state. Ec = 4700 x sqrt (40) =29726 MPa
Fr = 0.62 x (λ) x sqrt(40) = 3.92 MPa
C-Using the equation (12.12-2) we could find that the required expansion joint
dimension. 12.7. Deflection
12.5. Story Drift A- In safe model we shall define a load pattern called PT (Post Tension)
As per ASCE-7-10 section 12.12.1 B- Assign a 90% load of the own weight in the PT load pattern as uplift load
C- Make load combination with linear add as follow = 2 x (total dead loads) + 1.5 x (live load ) + 2 x (PT)(with
Etabs gives us the maximum allowable elastic DRIFT in two orthogonal –ve sign)
directions (E1,E2), these two DRIFT shall be inelastic by multiplying them with
the factor (Cd/I) which is (4/1.25) in service area case, also these two DRIFT D- Deflection of post tensioned allowable slab shall be taken as per ACI-18M-14 table 24.2.2
are from ultimate limit state so they will be reduced by 70% in order to change
them to working limit state .

Using the TABLE (12.12-1) we could find that the required allowable drift
depends on the risk category which is (I, II, III and IV) and the type of structure
which found as all other structures that represent our statical system case of
ordinary reinforced concrete with shear wall

12.6. MATERIALS
Concrete specified Compressive strength fc’ as per ACI-318M-14 is nearly
equal 80% of the Fcu.

As per ACI-318M-14 chapter 19:


Modulus of elasticity Ec = 4700 x sqrt(fc’) (Equation 19.2.2.1.b)

OWNER / DEVELOPER: 87 LEAD CONSULTANT:


Modified
12.8. MODELLING ASSUMPTIONS
Limit Stiffness
Software Member and Crackling Level
The stiffness of the structural reinforced concrete elements is modified as per State (x Gross
ACI 318-14 as shown in the following tables; Stiffness)
lateral loads resisting system) m22)
Modified
Slabs (PT) (Doesn’t contribute to the 0.35 (m11 and
Limit Stiffness
Software Member and Crackling Level lateral loads resisting system) m22)
State (x Gross
Stiffness)
0.70 (M2 and Coupling Beams (Spandrels) (Un-
Columns (Compression controlled) 0.70 (f11)
M3) cracked)
0.50 (M2 and Coupling Beams (Spandrels)
Columns (Tension controlled) 0.50 (f11)
M3) (Cracked)
Walls (Un-cracked) 0.70 (f22) Columns and Beams (Torsional 0.10 x Torsional
Stiffness) Constant
Walls (Cracked) 0.35 (f22)
Walls and Slabs (Torsional
0.35 (M2 and 0.10 (m12)
Beams (Modeled as R Sec) Stiffness)
M3)
Walls and Coupling Beams
0.25 (m11 and
Slabs (Traditional RC) (Spandrels)
m22) 0.10 (f12)
(Don’t contribute to the lateral loads
Slabs (PT) (Does contribute to the 0.50 (m11 and
resisting system)
lateral loads resisting system) m22)
Slabs (PT) (Doesn’t contribute to the 0.50 (m11 and
lateral loads resisting system) m22)
Coupling Beams (Spandrels) (Un-
0.50 (f11)
cracked)
Coupling Beams (Spandrels)
0.35 (f11)
(Cracked)
1.00 (M2 and
Columns (Compression controlled)
M3)
0.70 (M2 and
Columns (Tension controlled)
M3)
Walls (Un-cracked) 1.00 (f22)
Walls (Cracked) 0.50 (f22)
0.50 (M2 and
Beams (Modeled as R Sec)
M3)
0.35 (m11 and
Slabs (Traditional RC)
m22)
Slabs (PT) (Does contribute to the 1.00 (m11 and

OWNER / DEVELOPER: 88 LEAD CONSULTANT:


Modified Stiffness The stiffness reduction factors are following the American standards, the recommendation in
Software Limit State Member and Crackling Level ACI318-14 is as following:
(x Gross Stiffness)

Beams (R Sec) 0.50 (M2 and M3) Table 6.6.3.1.1(a) Moment of inertia and cross-sectional area permitted for
0.50 X 1.50 = 0.75 Elastic analysis at factored level
Beams (L Sec) (Modeled as R Sec)
(M2 and M3)
Cross sectional Cross sectional
0.50 X 2.00 = 1.00 Moment of
Beams (T Sec) (Modeled as R Sec) Member and condition area for axial area for shear
(M2 and M3) inertia
deformations deformations
0.35 (m11 and
Slabs (Traditional RC)
m22) Columns 0.70 Ig
1.00 (m11 and
Slabs (PT)
m22) Un-cracked 0.70 Ig
Beams (R Sec) 1.00 (M2 and M3)
Cracked 0.35 Ig
Beams (L Sec) (Modeled as R Sec) 1.50 (M2 and M3)
Beams 0.35 Ig
Beams (T Sec) (Modeled as R Sec) 2.00 (M2 and M3)
1.00 (m11 and Flat plates and flat slabs 0.25 Ig
Slabs (Traditional)
m22)
Slabs (PT) NA

Slabs (Traditional RC) 0.50 (f11 and f22)

Slabs (PT) 0.50 (f11 and f22)

0.10 x Torsional
Columns and Beams (Torsional Stiffness)
Constant
Walls and Slabs (Torsional Stiffness) 0.10 (m12)

OWNER / DEVELOPER: 89 LEAD CONSULTANT:


13. SCHEMATIC STRUCTURAL SYSTEM
13.1. Foundation System
The used foundation system may be classified into three types as follow:
A- Foundations under towers shall be a raft foundations and the designer will utilize it to combined footing with connected raft, the compression loads will not be the critical condition unlike
the uplift force which will lead the proportioning of the concrete elements dimensions and reinforcement for these areas. These areas will be designed in such way that the concrete weight of
the foundation, 1st basement and ground floor slab shall counteract the uplift loads with the acceptable margin of safety.
B- Foundations under zones reaches the podiums and service floors only shall be isolated footing connected with raft slab, or raft foundations up to design development.
C- Foundations under zones reaches to ground only shall be raft foundations to resist uplift forces due to ground water table.
D- Water proofing membrane shall be utilized in order to protect the reinforced concrete materials of the foundation against the chemicals dissolved in the ground water.
E- The designed crack width for the foundation bottom surface will be limited to 0.40 mm according to the standards limitation for membrane-protected surfaces.
F- The exposure category and sulphate category for substructure elements in direct contact with soil and ground water (i.e. Foundation and retaining walls) is X3 & S1 respectively. This
classification is based on the chemical results mentioned in the geotechnical report.
G- Shear walls will be added in the elevator/stair areas in order to provide a reasonable lateral stiffness.
13.2. Horizontal Systems
A- Typical floors will be post tension slabs with thicknesses varies between 220 mm to 300 mm using projected beam were need to limit the deflection and punching values to the acceptable
criteria.
B- 1st basement and ground floor system;
The slab system will be traditional flat slab with drop panels with estimated thickness around 250 mm.
C- 1st & 2nd podium floor system;
The slab system shall be mixed traditional flat slab with drop panels with estimated thickness around 250 mm, and Post tension systems for the large spans areas.
D- The elevator and stairs lobby will traditional solid slab with thickness around 200 mm.

13.3. Vertical Systems


A- Gravity and lateral load system;
The gravity load will be transferred from the different floor slab to the foundation using a set of vertical columns arranged in such way to achieve the architectural requirements and a reasonable
horizontal slab system.
B- The planted (floated) columns and its supports shall be designed to satisfy the over-strength load combinations according to the requirements of ASCE 7-10.
C- Shear walls will be added in the elevator/stair areas in order to provide a reasonable lateral stiffness.

OWNER / DEVELOPER: 90 LEAD CONSULTANT:


13.4. Retaining Wall
The main role of the retaining walls is to support the earth pressure, each soil layer shall be represented by its lateral coefficient (Ko) according to the geotechnical report. Water proofing system
shall be applied for the outer surface of the retaining wall in order to provide a full tanking system. The designed crack surface for the retaining walls outer surface will be 0.40 mm according to the
standards requirements.

13.5. Water tank


The water tanks will mainly designed to satisfy the crack width limitation to 0.10 mm in order to maintain its function to retain water. The inside water proofing system for water tanks will generally be
GRP lining and it shall follow the architectural requirements.

OWNER / DEVELOPER: 91 LEAD CONSULTANT:


14. CONEPTUAL STRUCTURAL PLAN
14.1. EXPANSION JOINTS LOCATION

OWNER / DEVELOPER: 92 LEAD CONSULTANT:


14.2. ZONES

OWNER / DEVELOPER: 93 LEAD CONSULTANT:


14.3. Basement 01 FLOOR PLAN

OWNER / DEVELOPER: 94 LEAD CONSULTANT:


14.4. GROUND FLOOR PLAN

OWNER / DEVELOPER: 95 LEAD CONSULTANT:


14.5. PODIUM 01 FLOOR PLAN

OWNER / DEVELOPER: 96 LEAD CONSULTANT:


14.6. SERVICE FLOOR PLAN

OWNER / DEVELOPER: 97 LEAD CONSULTANT:


14.7. PODIUM 02 FLOOR PLAN

OWNER / DEVELOPER: 98 LEAD CONSULTANT:


14.8. TYPICAL 01 FLOOR PLAN

OWNER / DEVELOPER: 99 LEAD CONSULTANT:


14.9. TYPICAL FLOOR PLAN

OWNER / DEVELOPER: 100 LEAD CONSULTANT:


ERKYAH MIXED USE
LUSAIL - QATAR
ELECTRICAL CONCEPT REPORT
REVISION 00 – NOV. 2019

OWNER / DEVELOPER: 10 1 LEAD CONSULTANT:


1. Table of Electrical Contents
4. LOW CURRENT SYSTEMS ........................................................................................................... 16
1. INTRODUCTION .............................................................................................................................. 3
4.1 STRUCTURED CABLING NETWORK ...................................................................................... 16
2. BASIC DESIGN CRITERIA .............................................................................................................. 3 4.2 TELECOMMUNICATIONS SYSTEM ........................................................................................ 16
2.1 OVERALL CONCEPT / STRATEGY ............................................................................................ 3 4.3 CCTV SURVEILLANCE SECURITY SYSTEM .......................................................................... 16
2.2 OBJECTIVES, CONSTRAINTS AND OTHER CONSIDERATIONS ............................................ 3 4.4 ACCESS CONTROL SYSTEM ................................................................................................. 19
2.3 EQUIPMENTS & MATERIALS..................................................................................................... 3 4.5 CAR PARKING MANAGEMENT SYSTEM ............................................................................... 19
2.4 CODES & STANDARDS .............................................................................................................. 3 4.6 SOUND SYSTEM AND VOICE EVACUATION ........................................................................ 19
2.5 CLIMATE CONDITIONS .............................................................................................................. 4 4.7 BUILDING MANAGEMENT SYSTEM ....................................................................................... 20
4.8 FIRE ALARM INTEGRATED SYSTEM ..................................................................................... 20
3. POWER SUPPLY AND DISTRIBUTION SYSTEM ........................................................................... 4
3.1 POWER SUPPLY CHARACTIRSTICS ....................................................................................... 4 5. APPENDIX (A) ................................................................................................................................ 22
3.2 ELECTRICAL LOAD ESTIMATION ............................................................................................ 4 a. MALL LOADS ............................................................................................................................. 23
3.3 MEDIUM VOLTAGE DISTRIBUTION ......................................................................................... 4 b. TOWER (EXCEPT RESIDENTIAL APARTMENT) LOADS .............................................. 24-25-26
3.4 RESTRICTED EARTH FAULT PROTECTION ............................................................................ 9 c. RESIDENTIAL APARTMENT LOADS ......................................................................................... 27
3.5 DRY TYPE TRANSFORMER ...................................................................................................... 9 d. SUMMARY LOADS ................................................................................................................... 28
3.6 LOW VOLTAGE DISTRIBUTION ................................................................................................ 9
3.7 METERING & KWH METERS CONNECTION .......................................................................... 10
3.8 POWER FACTOR CORRECTION ........................................................................................... 10
3.9 LOW VOLTAGE CABLES & DISTRIBUTION ........................................................................... 11
3.10 EMERGENCY SYSTEM / STANDBY POWER GENERATOR SUPPLY ................................ 11
3.11 UPS (UNINTERRUPTIBLE POWER SUPPLY) SYSTEM ...................................................... 12
3.12 RACEWAYS .......................................................................................................................... 12
3.13 GROUNDING AND LIGHTING PROTECTION SYSTEMS .................................................... 12
3.14 SMALL POWER SYSTEM INSTALLATIONS ......................................................................... 13
3.15 WIRING DEVICES ................................................................................................................. 14
3.16 LIGHTING SYSTEM .............................................................................................................. 14
3.16.1 GENERAL LIGHTING INSTALLATIONS ........................................................................................... 14
3.16.2 LIGHTING CONTROL SYSTEM ....................................................................................................... 15
3.16.3 EMERGENCY LIGHTING INSTALLATIONS ..................................................................................... 15

OWNER / DEVELOPER: 10 2 LEAD CONSULTANT:


1. Introduction c) To implement safety and protection measures for people and equipment.

1.1 This concept report is intended to describe the various electrical systems that will
be designed for the project. This report also aims / intends to illustrate / define While achieving the design objectives, other important factors will have to be
the scope and extent of electrical works / supporting information / criteria that will considered carefully as summarized below:
serve the Project, and to highlight the essential guidelines and backbone that will
be implemented in the preparation of the Electrical drawings / design. a) Cost effectiveness
b) Efficiency and energy conservation.
1.2 The electrical installations shall be laid, based on /considering / complying with c) Co-ordination with other design elements
applicable codes and standards including local regulation/Authorities. d) Flexibility of installation
e) Simplifying installations, operations and maintenance.
2. Basic design criteria 2.3 Equipment & Materials

2.1 Overall Concept / Strategy All Equipment and materials will be specified to comply with the latest relevant
standards of IEC, BS and QCS as applicable, where not in contradiction with
Kahramaa / Owner / operator requirements.
a) All Electrical engineering systems necessary for the full operation of the
project will be provided while emphasizing on sustainable green design for 2.4 Codes & Standards
the project reflecting the design intent of the client / Operator.
All electrical installations will be designed in compliance with the latest edition of
the following codes and standards as applicable:
b) The project aims to achieve GSAS (Global Sustainability Assessment
System) building requirements of 2-stars target score. The GSAS rating will a) Qatar General Electricity & Water Corporation (KAHRAMAA), latest edition.
be considered while designing the lighting, lighting control and other items
as applicable. b) Ministry of Interior (MOI-QCDD), Local Civil Defense Authorities Codes and
Practices.
c) For all electrical systems, which are explained in this report, any other
disciplines change during the next project stages may result in an impact c) Ministry of Interior (MOI-QSSD), Local Security Surveillance Dept. Codes
on the explained concept mentioned herein in this report. and Practices

2.2 Objectives, Constraints And Other Considerations: d) Lusail City Design Criteria Report.

The complete electrical systems will be designed by using latest intelligent


energy saving technology, sustainability, green building approach and GSAS e) National Fire Protection Association (NFPA)
certification as applicable. The concept of electrical design will be based on
the main objectives as summarized below: f) Qatar Construction Specifications (QCS)

a) To comply with the applicable codes and standards,


g) British Standards codes (BS)

b) To meet the specified power and communications requirements of other


system and equipment. h) International electrical commission (IEC)

OWNER / DEVELOPER: 103 LEAD CONSULTANT:


i) Institution of Electrical Engineers Wiring Regulations (IEE)  The nominal mains frequency is 50 Hz ± 0.1 Hz.
 Industrial conditions in the state may occasionally result in a short term variation of ±
j) Illuminating Engineering Society (IES) 0.15 Hz for duration of only a few seconds.
 In emergency overload conditions, the frequency would be allowed to drop to
k) Chartered Institution of Building Services Eng ineers (CIBSE)  48.8 Hz at which point load shedding would take place.
 The nominal voltage is 240/415. It is KAHRAMAA (KM) practice to maintain the voltage
l) OOREDOO & GSM Local Regulation & Requirements. level at a value not exceeding ±6% variation from the nominal value.
2.5 Climate Conditions 3.2 Electrical Load Estimation
a) All Electrical equipment, apparatus, related materials and accessories will be The project’s electrical load estimation summary has been calculated as per
designed and constructed so that they operate satisfactorily and without any b
deleterious effect for prolonged and continuous periods in the conditions e
stated below and at the underneath ambient temperature conditions. Total
l Air Water
Cooker General Others Load
o Conditioning Heater
b) Qatar experiences a tropical climate and generally the ground area is at sea (KVA)
ALL
w PROJECT LOAD
level. The climate in Qatar in the summer months is hot and humid and a Total Total Total Total
humidity of 100% at 30°C has been recorded. Climate seems to be as Total Load Load Load Load Load
t (KVA) (KVA) (KVA) (KVA) (KVA)
following data:
a
CONNECTED LOAD
 The Max. Sun radiation temperature in summer is 84°C. (KVA)
b 3657.49 3883.89 145.09 3297.47 10146.71 21130.65
 The Max. Ambient temperature in summer is 52°C. DEMAND
l FACTOR 0.90 0.30 0.40 0.61 0.60 0.60
 The Average max. Ambient temperature in summer is 45°C. MAX.
e DEMAND LOAD
(KVA) 3291.74 1165.17 58.04 2022.16 6050.54 12587.64
 The Min. ambient temperature in winter is 0°C. :
 The Max. Ground temperature is 30°C at a depth of 1 meter.
 The Max. Seawater temperature is 40°C with a maximum tidal variation of
approx. 2.40m.
 Atmosphere is salt laden and very corrosive.
 The prevailing winds are northerly and gales with gusts This indicates a maximum demand load of 12.588 MVA for the whole project.
approaching 140 KPH have been recorded accompanied by a
high level of dust in the air. For the detailed electrical load estimate, refer to Appendix (A) at the end of
this report.
 Violent sand and dust storms of several hours duration occur and even
on comparatively still days, fine dust is carried in suspension in the 3.3 Medium Voltage Distribution
atmosphere.
a) Power supply shall be made available at the project site by
3. POWER SUPPLY AND DISTRIBUTION SYSTEM KAHRAMAA/Developer at 11 kV, 50 Hz, 3 phase. There are six MV tie-in
points available for the project as per the existing MV utility layout and single
3.1 Power Supply Characteristics line diagram sent with the project’s documents as follows: -
a) Declared Voltage for The State of Qatar:
 Rated Voltage: 240/415 ± 6%, 3 Phase, 4 Wire. 1- H-1 (S/S 21028): 2.88 / 2.07 MVA.
 Neutral: Solidly Earthed.
 Fault Level: 31 MVA at 415 V. 2- HA-1 (S/S 25482): 2.37 / 1.78 MVA.

OWNER / DEVELOPER: 10 4 LEAD CONSULTANT:


3- NSC-1 / HC-1 (S/S 21026): 4.05 / 2.85 MVA.

4- HA-2 (S/S 21023): 1.51 / 1.13 MVA.

5- HA-3 (S/S 25483): 1.17 / 0.88 MVA.

6- HA-4 (S/S 21022): 1.06 / 0.79 MVA.

UTILITY ALLOCATED POWER TCL /MDL (MVA) 13.04 / 9.5

TOTAL ESTIMATED MAX. DEMAND LOAD


(MVA) 12.59

REQUIRED ADDITIONAL LOAD (MVA) 3.09

REQUIRED ADDITIONAL LOAD (%) 0.33

From the above, the maximum demand power allocated for the project
from the utility is around 9.5 MVA. However, the estimated maximum
demand load is 12.588 MVA which means there is a shortage of about 3
MVA.

The existing MV intake points are connected to two MV loops form


66/11KV Boulevard 1 primary substation.

The estimated demand power does not include the pending area, which
is part of plot H-1/HA-1 (i.e. the indicated power shortage does not
include the expected load of the pending area as well).

The MV intake points were superimposed to the project’s basement 1


level as shown in figure E-1. The two MV intakes HC-1 and HA-3 only will
be used for feeding the main two substations of the building due to
followings;

 Each point of them is from a different loop. Hence, the total


allocated power can be used through them

 Their closeness to the proposed substations’ locations.

The utility allocated power from the six MV intake points will be used
through points HC-1 and HA-3 as shown in figure E-1.

OWNER / DEVELOPER: 10 5 LEAD CONSULTANT:


Figure E-1.

OWNER / DEVELOPER: 106 LEAD CONSULTANT:


- The switchgear will feed five dry type 11/0.433 KV transformers of 1600 KVA
rating each. The five transformers will be housed within the Transformers room
3 (all the five transformers are for residential towers “B” & “C”) (22.5m x 6m
dimensions) located directly beside the MV room 2.
According the electrical load estimate of the project, two main electrical substations shall
be required as follows: - The five transformers will feed the electrical loads (lighting, small power, fans,
pumps, AHUs, elevators, telecom and security equipment, etc…) of towers “B”
1- Electrical substation 1; & “C” and the remaining part of towers’ parking in basement 2 through LV
panels which will be accommodated within the LV room 3 (360m2 area. The
bigger room area is due to the structural elements / geometry in this location)
- This substation will be located in basement 1 floor opposite to the MV intake located behind Transformers room 3.
HC-1 in an intermediate location of the basement length and it consists of one
11 KV switchgear inside the MV room 1 (13m x 7.2m dimensions). This
switchgear will be connected to the 11 KV intake point HC-1 from one loop of - The location of electrical substation 2 is as shown in figure E-2.
the 66/11 KV Boulevard 1 primary substation.
- MV (11 kV) Switchgears shall be provided as specified according to the latest
version of KM specification for 11 kV Switchgears complete with metering and
- The switchgear will feed five dry type 11/0.433 KV transformers of 1600 KVA instrumentation, special tools, accessories, test equipment.
rating each. The transformers will be housed within the Transformers room 1
(two transformers for residential tower “A”) (8.5m x 5.5m dimensions) located - The incoming supply cables shall be laid in a Tunnel / covered cable tray (used
directly beside the MV room 1 and; only for those cables) at high level of basement 1 from the selected MV intake
points directly to the two MV rooms.
Transformer room 2 (three transformers for the commercial mall and its parking
- The room details shall be provided within the related next package(s) within the
in basement 1) (12.5m x 5.5m dimensions) located on the other side of MV
next stage(s) indicating in details the required tunnels/trenches, up stand,
room 1 as shown in figure E-2.
setbacks for the trenches, door details, …etc.
- The five transformers will feed the electrical loads (lighting, small power, fans,
pumps, elevators, telecom and security equipment, etc…) as follows:
a) Tower (A), and part of towers’ parking in basement 2 are fed from LV room
1 (105 m2 area) located behind the Transformers and MV rooms 1 as
shown in figure E-2.
b) The podium mall (including basement 1) fed from LV room 2 (160m2 area)
located behind Transformer room 2 as shown in figure E-2.

2- Electrical substation 2;

- This substation will also be located in basement 1 floor opposite to the two MV
intake points HA-2 & HA-3 close to the east boundary of the basement and it
consists of one 11 KV switchgear inside the MV room 2 (19.3m x 7.2m
dimensions. This room has bigger dimensions compare with MV room 1 due to
the structural elements / geometry in this location). The switchgear will be
connected to the 11 KV intake HA-3 from the other loop of the 66/11 KV
Boulevard 1 primary substation.

OWNER / DEVELOPER: 10 7 LEAD CONSULTANT:


Figure E-2.

OWNER / DEVELOPER: 10 8 LEAD CONSULTANT:


3.4 Restricted Earth Fault Protection b) Meeting KM requirements and subject to their approval, 11kV/415V Dry
Type transformers will be located in dedicated rooms (Transformers
a) A restricted earth fault protection relay will be installed on each incoming room 1 and Transformers room 2).
supply to a MDB and shall interrupt the fault by isolating relevant circuit
breakers. c) In a close coordination with Arch., Transformer rooms were located at
basement 1 floor adjacent/close to the MV room - as possible/applicable-
b) As far as possible the protection CT’s shall be located on the main with the sufficient/adequate space to accommodate the required number
incoming bus bars, after the main switch and just before the main of Transformers.
horizontal bus-bars.
d) The Transformers room details will be provided within the related next
c) This protection is designed to look back towards the secondary windings package(s) within the next stage(s) indicating in details the required
of the supply transformer and all small control wiring and other current trenches, setbacks, door details...etc.
transformers shall be located so that they are protected by this relay.
Current transformers to be Class (X) (or Approved Equivalent).
3.6 Low Voltage Distribution
d) The restricted earth fault relay shall be installed to trip both LV and the a) The Low Voltage Distribution System shall comprise Low Voltage Panels
Qatar General Electricity & Water Corporation “KAHRAMAA” MV
(LVPs) / Main Distribution Boards (MDBs), Busways / cables, Sub-Main
switches/breakers under earth fault conditions. It is the customer’s Distribution Boards (SMDB), Distribution Boards (DB), Motor Control
responsibility to provide a suitable interconnecting cable for this purpose. Centers (MCC), Control Panels (CP), Capacitor Bank, Bus Coupling and
Isolators.
e) The setting of the protection relays are to be agreed and commissioning
tests witnessed by KAHRAMAA. b) LVPs / MDBs shall be floor mounted, factory assembled, fully modular,
IP42, with Min. separation form of “Form 3B, Type 2”, Cubicle type with
f) LV tripping will be by means of 30 Volts D.C. system with battery and
facilities for Future extension as per KM/QCS latest
charger supplied and maintained by the customer. The battery charger will
regulation/requirements.
be of wall mounted type with voltage display of rated voltage (0 - 30 V
DC), Test Push Button, ON/OFF Switch and lock facility for the outer door c) The Sub Main Distribution Boards shall generally be wall mounted in
enclosure. One battery charger shall be used for individual LV panel / each floor as applicable, with front access, Min. “Form 2B, Type 2”, IP42.
MDB and it is not acceptable to link two MDBs through one battery The incoming supply shall terminate into an integral isolator / MCCB and
charger by parallel connection. outgoing circuits shall be protected by MCCBs with 35 KA fault rating.
g) The 240 Volts A.C. systems supplying the battery charger shall be taken
d) The Distribution Boards shall be metal clad flush mounted in all finished
directly from the MDB, by individual conduit. The return 30 Volts D.C. areas and surface mounted in electrical cupboards and plant rooms. The
system from the battery charger to the MDB shall be installed in separate incoming supply shall terminate into an integral isolator / MCCB. All
conduit. Single conduit used for both A.C. and D.C. is not permitted. Two outgoing circuits shall be protected by MCBs with 30mA earth leakage
core cable of 2.5 mm² shall be used only for each system. circuit protection on all power circuits, mechanical pumps, water heaters
and lighting circuits in the wet areas and as per KM regulations. MCBs
3.5 Dry Type Tranformer
shall have a minimum 10 KA fault rating.
a) The project shall be supplied from KM 11 kV network/equipment via the
adequate number of Dry Type Transformers (10 units), which is subject e) Motor Control Centers shall be provided for mechanical equipment as
to change/update based on the exact loads within the next stage(s) in applicable as per codes and standards and constructed as per Form 3B,
coordination with all other Disciplines. Type 2, cubical with 35 KA fault rating.

OWNER / DEVELOPER: 10 9 LEAD CONSULTANT:


f) The sub-circuit cabling enclosed in conduit / trunking shall be PVC 1 floor.
insulated copper conductor cable for general lighting & small power
distributions and fire rated copper conductor cable for emergency b) In coordination with KM regulation and subject to their approval,
lighting and power distributions. All life safety mechanical equipment Provision shall be made in main switchboards for the installation of the
Qatar General Electricity & Water Corporation “KAHRAMAA” metering
and firefighter’s lifts shall be fed through fire rated cables.
equipment located in Separate cubicle above or below the main switch.
g) LVPs / MDBs shall be suitable for operation under the ambient and
service conditions specified. They shall comply with all local regulations c) Current Transformers (CT’s) class 1 or approved equivalent metering
and requirements and shall be of indoor construction, purpose made, type shall be installed on all types of main switchboards.
floor standing, totally enclosed, cellular cubicle type, and of clean and
modern appearance containing the main components shown on the d) CT’s shall be supplied and fitted by the panel manufactures to
Drawings and/or specified, and shall be rated for operation on a 3 comply with KM requirements based on the standard
phase, 4 wire, 415V, 50Hz supply system. The symmetrical fault rating sizes/rating.
shall not be less than 44 KA for 3 seconds.
e) For the LVPs dedicated for tenants’ loads (such as
h) All details relating to the design/construction of protection systems shall apartments, shops, Hyper market, FEC, Cinema, etc…), no
be fully compliant with the latest requirements of KM/QCS. main KM meter will be provided at the main LVP incomer.
Also, in case of feeding tenants’ and landlord’s loads from the
i) LVPs / MDBs shall be equipped with Air Circuit Breakers (ACBs), same LVP, no main KM meter will be provided at the main
molded case circuit breakers (MCCBs), relays, instruments, and LVP incomer and a sectionalized KWH meter will be added at
ancillary devices necessary for operation protection or measurement beginning of horizontal panel busbar for separating all
purposes as indicated on the Drawings. landlord’s loads from the tenants’ loads.
3.8 Power Factor Correction
j) Meeting KM requirements and subject to their approval, LVPs were
located in dedicated rooms, as possible/applicable close/adjacent to the a) Power factor improvement equipment shall be provided meeting KM
TXs room with the sufficient/adequate space to accommodate the requirements and subject to their approval.
required number of LVPs (Normal & Emergency).
b) Correction shall be automatic and be capable of correcting the power
k) As applicable, the room details shall be provided within the Arch. factor to achieve an overall power factor of 90% as required/indicated
Package in the next stage(s) indicating in details the required setbacks, in the design drawing. The power factor setting shall be adjustable.
door details,...etc.
c) The Automatic Step Capacitor Bank shall be provided as per
l) Low voltage distribution system shall be expressed in details through the
(IEC 61439-1) and (IEC 60831) to improve the power factor of
related Specification during the 100% detailed design Stage. the system. Capacitor bank shall be equipped with transient
harmonic current suppressor and special Filters.

3.7 Metering & Kwh Meters Connection d) Meeting KM latest regulation, Capacitor banks shall be provided as a
a) In coordination with KM regulations and subject to their approval, standalone panel(s) beside the main LV panels within the respective LV
independent KM’ KWHM metering system located in the LV / electrical room.
room shall be provided for Landlord. The landlord’s LVPs will include
the main KM meters. There will be dedicated LVPs for the towers to
feed all residential towers and their parking in basement 2 floor and the
other LVPs dedicated for the mall and its parking on site and basement

OWNER / DEVELOPER: 110 LEAD CONSULTANT:


3.9 Low Voltage Cables & Distribution For current ratings and mounting positions. The Enclosed Bus Duct shall be
designed and manufactured to comply with IEC 61439. The Enclosed Bus Duct shall
a) Low Voltage Cables & Distribution will comprise of main and sub-main be rated for 50°C ambient temperature at rated current. The Enclosed Bus Duct
power cables, Fire Rated Cables and other associated accessories. shall be braced to withstand, without damage or distortion, the stresses due to short
circuit currents of 50kA for 3 seconds RMS symmetrical. The Enclosed Bus Duct
b) From the Main Low Voltage switchgear, CU/XLPE/SWA/PVC feeder shall have minimum enclosure protection to IP54 where bus ducts installed in
cables will be provided for supplying the sub-switchboards, motor control vertical shafts and IP65 for all horizontal runs.
centers / control panels feeding mechanical plants and distribution boards
located within the building / site.
3.10 Emergency System /Standby Power Generator Supply
c) Main and Sub-Main Cabling will be CU/XLPE/SWA/PVC insulated steel
a) Generator sets shall operate as standby power source and ATS (either
wire armored for General Power Distribution.
standalone or integrated in the ELVP) as required/applicable in the event of
main electrical power source failure/interruption.
d) Main and Sub-Main Cabling will be of fire resistant copper type for
Emergency Power Distribution.
b) The generators & distribution system shall comprise generator sets,
control panels, ATSs and other associated required accessories.
e) Sub-Circuit Cabling enclosed in Conduit / Trunking will be PVC
Insulated Copper Conductor Cable for General Lighting & Small Power
Distribution and fire resistant, LSF insulated Copper Conductors for c) Essential services / systems that shall receive generator backed up
Emergency Power Distribution. mains supply are including. But, not limited to the following:

 All firefighting / sprinklers and submersible pumps and systems.


f) Essential Life Safety Supply Cables for Emergency Luminaries, Fire
Alarm Detectors will be Fire resistant copper Conductor Cable (FP 200  All automatic fire detection and alarm systems.
Gold).  All power to telephone, IT systems and security system.
 All firefighter elevators.
 The life safety HVAC equipment and emergency lighting.
g) All sub-circuit cabling and Fire Cable (FP 200) will be enclosed in conduit.

d) The generators backup time is 8 hours for three days (i.e. the daily
h) The conduits will be galvanized steel for surface runs while, high fuel tank capacity shall be for 8 hours and the bulk fuel tank shall be
impact PVC conduits will be installed where concealed within the for 24 hours).
building fabric.
e) The generators will be accommodated with acoustic treatment to keep
i) All steel wire armored cables will be fixed to heavy duty galvanized the noise at 1m outside the generators room limited to 85 dBA.
steel cable trays / ladders for all horizontal and vertical runs.
f) Fire resistant cables /wires shall be used to ensure emergency power
supply is maintained under fire conditions for the whole Emergency
j) The Enclosed Bus Duct shall be constructed with extruded aluminum Power Distribution.
housing and Copper Bus Bars, with openings for duct plug-in units for
feeding the towers’ apartments. The Enclosed Bus Duct shall be complete
with all hangers, cable tap boxes, bus plugs and accessories required for g) The location of the generators room (23m x 13.5m dimensions) is in
the complete installation. The Enclosed Bus Duct shall be rated as 415 basement 1 floor as shown in figure E-2 above. The room shall
volt, 3 phases, neutral, and earth, 5 wires, 50 Hz with full capacity neutral. accommodate three generators with ratings according to the
The Enclosed Bus Duct shall be built to match with the BS and have Local estimated emergency load.
Authority approval.

OWNER / DEVELOPER: 111 LEAD CONSULTANT:


3.11 UPS ( Uninterruptible Power Supply ) SYSTEM building systems and structure protection as per latest British
Standard.
a) The UPS system will be provided to feed the essential sensitive systems like,
Access Control, Computer and other ELV & IT Equipment, .…etc. as well as
b) The grounding system will be "TN-S" system as per the latest
the motorized fire dampers, BTU meters, … etc. as required to maintain the
editions of BS7671 (IEE Regulations) and BS7430.
constant / continuous operation.

c) All installations shall follow KM requirements for earthing and Qatar


b) Generally, the UPS system will be designed for 15 min. battery autonomy
construction specifications (QCS 2014).
operation time (except for the CCTV system which will have a dedicated UPS
system in a separate room with 60 min. battery autonomy as per MOI
regulations) based on double conversion online topology; three phases d) In no circumstances shall lightning protection earth rods be connected to
continues duty, generator compatible, network manageability and parallel any Qatar General Electricity & Water Corporation “KAHRAMAA“,
maintenance bypass. The UPS will be de-centralized systems and located earthing electrode. A minimum distance of separation of 7 meters shall be
beside the loads they will serve except for the CCTV racks’ UPS, which will provided in every case between lightning earth electrodes and Qatar
be accommodated inside a separate dedicated room beside the racks’ room. General Electricity & Water Corporation “KAHRAMAA“, earth electrodes.
Lightning protection will be carried out in accordance with the latest BS
c) The UPS system will comprise modular floor mounted cabinet (as standard as per the lightning protection level (LPL) which will be obtained
applicable / available for the system power rating), high performance from risk assessment calculations. The risk assessment calculations will
batteries, static switch, maintenance bypass, rectifier, battery charger, be part of the next design stage.
battery circuit breaker, and inverter synchronizing equipment, protective
devices and all other required accessories.
e) The earthing network & lightning protection system shall comprise earth
pits, earth conductors, test links, Faraday cage lightning roof network,
down conductors and all other required associated accessories.
3.12 Raceways

a) The separate conduits, wire ways, cable trays will be dedicated for f) The clean earthing system for main telecom room equipment and all other low
normal circuits, emergency circuits and low current circuits. current equipment shall be provided with dedicated earth pits and
conductor(s).
b) The separate conduits and trunking will be dedicated for normal lighting
and emergency lighting circuits. g) All metalwork associated with the electrical installation shall be bonded
together and shall be solidly and effectively earthed to achieve equipotential
c) The flexible galvanized steel conduits will be used for terminating all grounding network.
connections to motors and vibrating equipment.
h) The earthing termination shall comprise a set of earth electrodes enclosed
d) The cable trays or ladder will be of galvanized sheet steel, supported either in inspectional hand holes to achieve the minimum earth resistance value.
from ceiling or walls.
i) Interconnection for earthing pits to each other shall be through a minimum
e) The type of conduits (PVC or galvanized steel conduits) according to its of two (2) pvc insulated copper cables and shall be of the loop / ring type
use will be as per QCS. (bonding the earth pits together and returning back to the main earth pit(s)).

j) Earth electrode shall be installed at such a depth that it penetrates the


3.13 Grounding And Lightning Protection Systems summer water table by a minimum of 2 meters. The distance between 2 earth
electrodes of 2 different earthing systems (like MV, TX, Gen set,
a) The grounding and lightning protection systems will be provided for Telecommunications) shall not be less than 7 meters.

OWNER / DEVELOPER: 112 LEAD CONSULTANT:


socket outlets approximately every 12 meters throughout the area for
k) The main LV panel(s) shall be connected at both ends of the lv panel (via 2 general purposes and the power outlets shall be fully recessed.
conductors) to a two separate earthing pits (directly or through intermediary
earthing bar installed in the lv panel(s)):
c) The plant rooms shall be provided with approximately 1 No. 13A socket
 first connection is from the transformer earthing terminals / pit to the LV
(weather proof type) for every 20 m2 and 1 No. 13A socket (weather
panel main earthing bar via a bare copper earth conductor with a
proof type) for each lift pit (as per BS 7255). All power outlets shall be
minimum of 120mm², (or as indicated on the drawing).
surface mounted with metal clad face plate.
 The second connection is from the LV panel frame / main earthing bar
to an additional earthing pit via a pvc insulated copper earth conductor
with a minimum of 95mm², (or as indicated on the drawing). d) A sufficient ampere rating double pole (DP) switches with suitable
flex outlets rating shall be provided for all water heaters, AC units,
l) The resistance of any one point in the lightning protection earth continuity ducted exhaust fans and any other mechanical equipment that
system to the main earth electrode shall not exceed 10 ohms, unless requires such type of power connection and as per Kahramaa
allowed otherwise by Kahramaa, without taking account of any bonding to regulations.
other services.

m) The resistance of any point in the earth continuity system to the main e) Fan coil units shall be connected (for each one) to its own 13A switch
earth electrode shall not exceed 1 ohm, unless approved otherwise by fused spur unit mounted adjacent to the unit and as per Kahramaa
Kahramaa. regulations.

n) All non-current carrying metallic parts of electrical / mechanical f) Wall mounted extract / exhaust fans shall be controlled from a
installations shall be bonded to the earthing system. separate switch of the same type as the light switch and as per
Kahramaa regulations.

o) All metallic parts of the water tank, pump rooms including the g) All 13A socket outlets shall be switched type, flush mounted and
reinforcing steel, all forming shells, and all metal fittings within or conform to BS 1363.
attached to tank structure and all metal parts of electric equipment
shall be bonded together with the earthing system.
h) Power supply to the landscape, garbage chute, Lifts, BMU and any
other general purpose services shall be designed and provided as
p) Earth electrodes to be not less than 3.6 m long, in 1.2 m sections per the requirement of the project.
coupled by strong bronze couplers, and 16 mm diameter, steel core
copper jacketed type.
i) The wiring devices shall be selected based on the Architect or ID
requirements in coordination with furniture layout(s).
q) Full technical details shall be submitted during the shop drawing
stage, along with final locations of earthing pits and final earthing
conductor size calculations with exact routing. j) In Kitchen, pantry, or tea rooms, the followings will be considered in
design:
3.14 Small Power System Installations  Cooker : Spur outlet with separate DP switch
 Refrigerator: 20A Socket Outlet with separate switch
a) The general power installations will comprise socket outlets, flex
outlets, double pole switches, distribution boards and associated
conduits and wiring.  Micro-wave Oven: 20A Socket Outlet with separate switch
 Kettle: 13A Switched Socket outlet
b) The circulation / general areas shall be provided with 13A switched  Hood: 13A Spur outlet with separate switch

OWNER / DEVELOPER: 113 LEAD CONSULTANT:


 Water Heaters: 20A Spur outlet with separate DP switch f) The lighting layout(s) will be coordinated with ceiling grid.
 Any other equipment: Spur outlet with separate DP switch.
g) Lighting design and luminaires selection will be based on achieving
recommended illumination levels, proper color rendering and color
temperature for each task/area.
3.15 Wiring Devices

a) Wiring devices will be selected based on the Architect or ID h) The illumination levels for various areas/spaces and general service
requirements in coordination with furniture layout. areas will be calculated based on CIBSE recommendations.

b) The face plate finish will be determined in conjunction with Some examples are shown in table below.
architectural details in interior area and will be stainless steel
metal clad finish in plant rooms, switchboard room, etc.

c) The lighting control switches will be rated 20A, grid type and
modular construction.

3.16 Lighting System

3.16.1 General Lighting Installations

a) The indoor lighting levels and installations shall be in accordance with


the requirements and recommendations of the Illuminating
Engineering Society (IES) and the Chartered Institution of Building
Services Engineers (CIBSE), not in contradiction with the Global
Sustainability Assessment System (GSAS) requirements. LED
lighting fixtures/ luminaires shall be used.

b) The artificial lighting system will be an important factor in establishing


a comfortable visual environment in the working areas. Therefore the
luminaires to be used in office/working areas will be selected to limit
glare and to allow comfortable use of visual display terminals (VDTs).

c) The general lighting installations shall comprise conduits, wiring,


wiring devices, control switches, occupancy sensors, light fittings and i) The external lighting and gate barriers will be coordinated with
any other required associated accessories. landscape specialist / Architect details as required/applicable.

d) The light fittings for internal, external façade and emergency escape j) All light fittings used shall be of energy saving applicable types / LED
route lighting distribution shall be designed and provided in line with (wherever applicable) to be compatible with the concept of green
interior designer by taking into consideration both functional and buildings approach / GSAS certification requirements.
aesthetic aspects.
k) The lighting for garden, landscape, building facade …etc. shall be
e) The General arrangement and type of lighting fixtures will be selected provided with wiring connections to the lighting points which to be
to suit the specific area requirements. designed / determined along with the types of light fittings by the
exterior designer / specialist lighting consultant.

OWNER / DEVELOPER: 114 LEAD CONSULTANT:


l) LED type exit lighting luminaires shall be used for egress indication e) The emergency lighting shall be provided to achieve an average
illuminated signs and any other feasible applications. illumination of 10.8 lx measured along the path of egress at the
floor level (and not less than, at any point, 1.1 lx) and in
3.16.2 Lighting Control System compliance with NFPA101 (7.9.2.1), BS5266 and QCDD
requirements. A maximum-to-minimum illumination uniformity ratio
a) The general and external lighting control system shall comprise of 40 to 1 shall not be exceeded. These requirements will be
lighting control panels (LCP), lighting switches, occupancy achieved through selecting some mains luminaires strategically
sensors, timer push buttons, photocell sensors, conduits, wiring and feed them through the central battery panels.
and any other associated accessories.

b) The external area lighting will be controlled through photocells, f) The central battery system shall be sized for 1.5 hours operation and
contactors and timers. shall be connected to the emergency generator.

c) For any public area, such as halls / corridors / walkways, lighting


control will be 50% & 100% of all lighting through occupancy
sensors and timers with pre-determined time schedule.

d) The lighting control system shall be designed based on KNX


protocol for internal lighting using time managed relay control,
programmed lighting control and smart relay control depending
on the application and space.

3.16.3 Emergency Lighting Installations

a) The emergency lighting system shall be designed and provided by


using the principle of central battery systems and distribution shall
be in compliance with BS, NFPA101 and Qatar Civil Defense
Department (QCDD) requirements.

b) Central battery system is provided in addition to the standby


generator, which provides a higher level of emergency lighting for
longer periods.

c) The central battery system will be de-centralized and each floor


will have its central battery panel(s), which will be located in the
floor electrical room(s) to supply the emergency lighting fixtures in
its floor. All central battery system panels will be connected
together to a main system’s workstation, which will be located in
the building’s control room.

d) The Aircraft warning lights on the towers will be fed from the
respective floor central battery panel.

OWNER / DEVELOPER: 115 LEAD CONSULTANT:


4. LOW CURRENT SYSTEMS b) Telecommunications system installations will be designed to comply
with client requirements and in accordance with OOREDOO
regulations.
4.1 Structured Cabling Network

a) The state-of-the-art structured cabling network will be designed c) Two main telecom rooms (one for the mall and the other one for the
and provided based on latest technology for telephone, data, residential towers) are provided with 7.2x5 m2 dimensions attached
voice and video distribution networks. with two GSM rooms (for the mall and towers as well) (7.2x4.8 m2
dimensions) in basement 1 floor.
b) The telephone & data cabling system will comprise service
provider main distribution frame (MDF), intermediate distribution
frames (IDFs), cable trays, trunking, telephone cables, Cat 6 d) Each telecom room will include two isolators 63 ampere for telecom
cables, junction boxes, back boxes, telephone face plates, equipment and each GSM room will include one isolator 63 ampere
conduits and all other required associated accessories. for GSM equipment.

c) The cabling infrastructure backbone shall be installed as a


structured cabling solution, utilizing Cat 6 UTP and multicore e) Each telecommunication and GSM rooms will be interconnected and
fiber optics cabling systems. served via adequate size of covered cable trays emphasizing the
redundancy from tie in point of the service provider for their cables.
d) The Structured Cabling will be able to support a wide range of
applications not limited to the following: f) There are main three continues low current shafts for the residential
towers and another separate three low current shafts for the
 Non-IP Telephone system.
commercial mall.
 Data Network.
 IP TV System
 IP Telephone System. g) Two main low current cable trays will run vertically from the main
 Wireless internet Coverage telecom room & GSM room 300x50mm (W x H) in each shaft to
 Security Systems. serve all low current rooms in the project (one LC room in each
 PA/BGM (Public Address/ Back tower core per level all-over the building along with adequate
Ground Music). number of low current rooms for the mall in podium levels).
 GSM.

e) The project will have two separate systems one for the h) The low current room will accommodate the intermediate distribution
commercial mall and the other for the residential towers. The frames (IDF) which will feed all data and telephone outlets & Floor
MDF of the commercial mall will be accommodated within a distribution box (FDB) which will serve each primary home
centralized LC room in basement 1 while; the three MDFs of the distribution box (PHDB) in each tenant area (apartments, shops,
towers will be accommodated within three LC rooms attached to F&B, Hyper Market, etc.).
the towers’ cores in the service floor.

4.3 CCTV Surveillance Security System

4.2 Telecommunications System a) The CCTV surveillance security system will be designed and provided to
monitor the movement of the people based on IP technology and using
a) The telecom service provider Main Distribution Frame (MDF) room shall be structured cabling network as per MOI-QSSD requirements.
established as an incoming and distribution point for main
telecommunications cabling of the project. b) The CCTV surveillance security system will comprise main CCTV racks,
central monitoring station, IP colored cameras (fixed / PTZ (pan tilt zoom)),

OWNER / DEVELOPER: 116 LEAD CONSULTANT:


matrix switches, recorders, printers, Cat 6 cables and all other required
associated accessories.

c) Two CCTV control rooms (one for the commercial mall and the other for
the residential towers) with 7.1m x 4.8m dimensions each will
accommodate the security console desk(s) and screens that will be
monitored by operators.

d) The two rooms are located at basement 1 as shown in figure E-3.

e) The CCTV system’s main racks will be located within a dedicated two
CCTV rack rooms (one for the commercial mall and the other for the
residential towers) as per MOI-QSSD requirements. The rack room
dimensions is 7 x 3.7 m2 located directly beside the CCTV control room in
basement 1 floor.

f) The IP CCTV cameras shall be installed at lobbies, main entrances,


corridors, front offices, car parking, FCC room, CCTV room and strategic
areas where local surveillance is required and as per MOI-QSSD
requirements.

g) Each CCTV system will have a dedicated UPS backup power supply to run
the whole system for not less than one hour in case of power failure

h) CCTV data outlet will be energized through dedicated IDF and the length
between the rack and outlet will not exceed 90 meter.

i) Dedicated cable tray 300 X 50 mm (W x H) will be used for CCTV racks


and will run through the main low current shafts of the building.

j) Each CCTV system shall have sufficient storage for all camera recordings
for a period of 120 days, in MPEG-4 or H.264 format or better quality
compression techniques.

The location of main telecommunications and security rooms in basement 1 is as shown in


figure E-3.

OWNER / DEVELOPER: 117 LEAD CONSULTANT:


Figure E-3

OWNER / DEVELOPER: 118 LEAD CONSULTANT:


4.4 Access Control System commercial mall (Basement 1 floor), in a close coordination with the
system specialist / Sub-consultant.

b) This system will form part of the door access control system described
a) The door entry and car parking barrier access control system
above. The system will include Drop arm barriers, vehicle detection
will be designed and provided based on proximity card
loops, parking sensor, counter screens, indications lamps.
technology and TCP/IP network protocol to restrict / control
entry of people or vehicles to the respective area / room inside
c) Security guards shall be able to control the drop barriers from the
the building.
remote location. Drop barriers are recommended for entry and exit
areas of the car parking only.
b) The card access system shall be provided to control the access
to the building through common card reader or card keys and d) Parking Control System shall be automatic operation at entrance and
shall be integrated with gate barrier(s) and building entrance(s). automatic operation at exit.

c) Two separate access control systems will be provided ( one for e) Entry, Automatic Gate Arm Control Electrically operated upon insertion
the commercial mall and the other for the residential towers) of coded card / insertion of pass key. Activate automatic arm reversing
switch if an obstacle is sensed in the down motion.
d) The door access system will be provided for electric rooms, low f) Exit, Automatic Gate Arm Control: Electrically operated upon insertion
current rooms, utility / mechanical rooms, security offices, fire of coded card / insertion of pass key. Activate automatic arm reversing
command center, CCTV rack room …etc. and any other switch if an obstacle is sensed in the down motion.
strategic areas that require the use of authorized cards / keys.

e) All strategic doors will be provided with magnetic door contacts 4.6 Sound System And Voice Evacuation
to detect unauthorized passage and generate alarm / notification
signals. a) The PA system shall be deployed/provided in the public areas to
provide public address announcement and emergency evacuation
f) Each access control system shall have provision for integration messages complying / in coordination with the NFPA & QCDD
with its respective building management system (BMS). It shall requirements and to their approval.
be integrated also with the respective fire alarm system control
panel for releasing the required doors / exits in case of fire.
b) The PA & background (BG) music system will comprise main rack,
amplifier(s), CD player, radio tuner, microphone(s), sound speakers
g) The two access control systems will be as follows: and all other required associated accessories.
 One for mall services and mall parking (basement 1). The mall
services room doors shall be accessed through authorized
persons. c) The public address system shall be integrated with the main fire alarm
control panel(s) to be utilized for the emergency evacuation and
 The other one is for the residential towers; this one shall prevent warning purposes in the case of fire or emergency.
accessibility to the residential parking (basement 2) and to allow
accessibility from mall to residential towers for the towers’ d) Emergency evacuation (EVC) announcements shall be broadcasted
residents only. from the FCC (fire command center) of the building in ground floor.

4.5 Car Parking Management System e) Emergency evacuation (EVC) announcements shall be broadcasted
to all areas (either as a common announcement or according to the
zoning and staging of any evacuation based on the fire management
a) The system shall be provided within parking spaces related to the strategy for the building).

OWNER / DEVELOPER: 119 LEAD CONSULTANT:


b) Fire alarm / detection system components/brief:
f) The PA & BG music system of the project will be provided for the
commercial mall only. EVC system will cover the whole building (the
mall and residential towers). Hence, the same PA & BG speakers in the  The fire alarm and detection system will contain;
commercial mall will be interfaced with the fire alarm system to Central microprocessor based fire alarm control panel(s)
broadcast the EVC as well. (MFACP) for the commercial mall and will be located
inside the fire command center.

g) All cables of the EVC system will be of fire resistant type similar to the
fire alarm system’s cables.  Six Satellite panels (SFACP) for the three towers (two
SFACP for each tower located at the tower’s entrance in
the ground floor) and connected to MFACP.
h) The PA & BGM main rack and console will be accommodated inside
the control room of the mall in basement 2 floor.  MIMIC panel which shall monitor all fire alarm devices,
 Addressable smoke detectors,
 Heat detectors,
4.7 Building Management System  Multi detectors,
 Transmitter & receiver beam detectors,
a) A comprehensive and effective two building management Monitor / interface modules for sprinkler supervised
systems (BMS) will be provided (one for the commercial mall valves, sprinkler flow / tamper switches,
and the other for the residential towers) for various control &
monitoring functions of HVAC, electrical, plumbing, sanitary Fire & sprinkler pumps and diesel generator.
drainage systems and any other required building services.

b) Each BMS shall also be interfaced with the fire alarm system to  Fire alarm Panels are provided strategically
enhance the safety management of the building. serving/emphasizing the separation concept, with an
interconnection between the different panels to ensure a
homogeneous/centralized fire alarm control for the whole
c) Dedicated vertical cable tray will be provided in low current project.
rooms for BMS system’s cables.
 The fire alarm system shall protect all risk areas within the
d) Each BMS main station will be located within the respective premises by giving warning of a fire condition when
BMS room (3 x 4m2 dimensions) in basement 1 floor for the detected by an automatic detector or by the manual
commercial mall and in basement 2 floor for the residential operation of a break glass call point. The risk area shall be
towers. divided into zones as per the life safety fire zoning.

 The system will be of 24 V DC, monitored, open circuit


4.8 Fire Alarm Integrated System type utilizing transformed and rectified mains voltage
supply under all normal circumstances but with stand-by
a) Analogue addressable type complete fire detection and alarm supply provision in the form of rechargeable batteries.
system integrated with voice evacuation system will be designed
to provide early detection and notification throughout the  Batteries shall have a capacity capable of maintaining the
building in compliance with the requirements of QCS, Civil system in normal operating conditions for at least 24 hours
Defense Department of the Ministry of Interior, State of Qatar and in the alarm state for at least 30 minutes without
and the requirements of related National Fire Protection recharging.
Association 70, 170, 72 & 101.

OWNER / DEVELOPER: 120 LEAD CONSULTANT:


c) Design Considerations: and QCDD requirements.

 The Fire Alarm Control Panels shall have addressable


 The Fire Alarm System shall control/monitor/interconnect
data communication circuits to provide connection with the
the Fire Alarm with firefighting, HVAC, and any other related
addressable devices. Each addressable communication
system in coordination with the QCDD requirements and
loop shall provide the capability of communication with up
subject to their approval.
to 200 addressable devices as maximum as per QCDD
requirements.

 The entire system will have spare capacity to accommodate


further 20% fire alarm devices. Accordingly, No more than
80% from the available addressable loops or audio power
amplifiers capacities shall be used to enable future addition
of any field devices.

 The system printer will be used to record all alarms,


supervisory and trouble conditions by address
number and custom label.

 The fire alarm system shall interconnect to the smoke


control equipment to provide the proper sequence of fire
mode operations and to override the smoke control system
to allow the manual operation.

 Two-way telephone communication service shall be


provided for fire department use. This system shall be in
accordance with NFPA 72. The communications system
shall operate between the central control station located in
the Fire Command Center and exit stairs via the firefighting
telephone jack while, the generator, fire pump room via the
firefighting telephone handset.

 All connections between panels & addressable devices


shall be Class A, fire resistant cables according to BS
6387.

 Input/output matrix (Cause & Effect) in coordination/line with


the Civil defense requirements and subject to their approval
will be indicated/provided within the detailed design
package, in addition to that, during construction stage,
input/output matrix (cause & effect) must be detailed,
stamped & signed by a specialist fire alarm
supplier/manufacturer and shall be according to the project

OWNER / DEVELOPER: 121 LEAD CONSULTANT:


APPENDIX (A)

OWNER / DEVELOPER: 122 LEAD CONSULTANT:


a- Mall loads

Total Total
Air Conditioning Lighting Small Power Water Heater Cooker Misc. Loads (Pumps, Fans, refregirator, etc.) Normal Emergency Fire Mode
Normal Emergency
Mode (KVA) Mode (KVA) (KVA)
load (KVA) load (KVA)
FLOOR PLAN ROOM NAME AREA (m2) VA/m2 Total Load (KVA) Normal (KVA) Emergency (KVA) VA/m2 Total Load (KVA) Normal (KVA) Emergency (KVA) VA/m2 Total Load (KVA) VA/m2 Total Load (KVA) VA/m2 Total Load (KVA) VA/m2 Total Load (KVA) Normal (KVA) Emergency (KVA)
Parking 32525 0 0 0.00 0.00 3 97.58 73.18 24.39 2 65.05 0 0.00 0 0.00 0 0.00 0.00 0.00 138.23 24.39 162.63 24.39 24.39

BASEMENT 01 FLOOR Services 2805 0 0 0.00 0.00 6 16.83 12.62 4.21 10 28.05 0 0.00 0 0.00 0 0.00 0.00 0.00 40.67 4.21 44.88 4.21 4.21

Stair 326 0 0 0.00 0.00 6 1.96 0.00 1.96 0 0.00 0 0.00 0 0.00 0 0.00 0.00 0.00 0.00 1.96 1.96 1.96 1.96

Services 5696 0 0 0.00 0.00 6 34.18 25.63 8.54 10 56.96 0 0.00 0 0.00 0 0.00 0.00 0.00 82.59 8.54 91.14 8.54 8.54
shops 3995 0 0 0.00 0.00 10 39.95 39.95 0.00 36 143.82 0 0.00 0 0.00 0 0.00 0.00 0.00 183.77 0.00 183.77 0.00 0.00
Stair & elev. 437 0 0 0.00 0.00 6 2.62 0.00 2.62 0 0.00 0 0.00 0 0.00 0 0.00 0.00 0.00 0.00 2.62 2.62 2.62 2.62
Toilets 126 0 0 0.00 0.00 6 0.76 0.57 0.19 2 0.25 0 0.00 0 0.00 33 4.16 4.16 0.00 4.98 0.19 5.17 0.19 0.19
GROUND FLOOR Offices 78 0 0 0.00 0.00 6 0.47 0.35 0.12 24 1.87 0 0.00 0 0.00 20 1.56 1.56 0.00 3.78 0.12 3.90 0.12 0.12
kiosk 76 0 0 0.00 0.00 0 0.00 0.00 0.00 6 0.46 0 0.00 0 0.00 69 5.24 5.24 0.00 5.70 0.00 5.70 0.00 0.00
CAFÉ (F&B) 873 0 0 0.00 0.00 7 6.11 6.11 0.00 15 13.10 0 0.00 110 96.03 107 93.41 93.41 0.00 208.65 0.00 208.65 0.00 0.00
open space 26689 0 0 0.00 0.00 2 53.38 53.38 0.00 0 0.00 0 0.00 0 0.00 5 133.45 133.45 0.00 186.82 0.00 186.82 0.00 0.00
hyper market 3160 44.9 141.884 141.88 0.00 10 31.60 31.60 0.00 40 126.40 0 0.00 0 0.00 47 148.52 148.52 0.00 448.40 0.00 448.40 0.00 0.00

Services 5797 0 0 0.00 0.00 6 34.78 26.09 8.70 10 57.97 0 0.00 0 0.00 0 0.00 0.00 0.00 84.06 8.70 92.75 8.70 8.70
Stair & elev. 431 0 0 0.00 0.00 6 2.59 0.00 2.59 0 0.00 0 0.00 0 0.00 0 0.00 0.00 0.00 0.00 2.59 2.59 2.59 2.59
Toilets 205 0 0 0.00 0.00 6 1.23 0.92 0.31 2 0.41 0 0.00 0 0.00 33 6.77 6.77 0.00 8.10 0.31 8.41 0.31 0.31
Offices 149 0 0 0.00 0.00 6 0.89 0.67 0.22 24 3.58 0 0.00 0 0.00 20 2.98 2.98 0.00 7.23 0.22 7.45 0.22 0.22
353- Erkyah Mixed Use development

CINEMA 3187 42 133.854 133.85 0.00 10 31.87 31.87 0.00 20 63.74 0 0.00 0 0.00 30 95.61 95.61 0.00 325.07 0.00 325.07 0.00 0.00
FOOD COURT 849 0 0 0.00 0.00 6 5.09 3.82 1.27 10 8.49 0 0.00 0 0.00 0 0.00 0.00 0.00 12.31 1.27 13.58 1.27 1.27
1ST PODIUM FLOOR
kiosk 56 0 0 0.00 0.00 0 0.00 0.00 0.00 6 0.34 0 0.00 0 0.00 69 3.86 0.00 0.00 0.34 0.00 0.34 0.00 0.00
COLD STORE 90 0 0 0.00 0.00 0 0.00 0.00 0.00 0 0.00 0 0.00 0 0.00 330 29.70 29.70 0.00 29.70 0.00 29.70 0.00 0.00
FEC 4605 50.6 233.013 233.01 0.00 10 46.05 46.05 0.00 20 92.10 0 0.00 0 0.00 60 276.30 276.30 0.00 647.46 0.00 647.46 0.00 0.00
shops 620 0 0 0.00 0.00 10 6.20 6.20 0.00 36 22.32 0 0.00 0 0.00 0 0.00 0.00 0.00 28.52 0.00 28.52 0.00 0.00
CAFÉ (F&B) 51 0 0 0.00 0.00 7 0.36 0.36 0.00 15 0.77 0 0.00 110 5.61 107 5.46 5.46 0.00 12.19 0.00 12.19 0.00 0.00
F&B 395 0 0 0.00 0.00 7 2.77 2.77 0.00 15 5.93 0 0.00 110 43.45 107 42.27 42.27 0.00 94.41 0.00 94.41 0.00 0.00

Elevators & Escalator / Travellator Mall 390.00 0.00 390.00 0.00 0.00
Telecom. & Security loads Mall 0 120 120.00 120.00 120.00
Fire Pump Mall 0 260 260.00 0.00 260.00
Jockey Pump 0 22 22.00 22.00 22.00
Water Transfer Pump 11 0 11.00 0.00 0.00
Water Booster Pump 0 15 15.00 15.00 15.00
Heat Pump 55 0 55.00 0.00 0.00
Submersible Pumps 0 0 0.00 0.00 0.00
Chilled Water Pump Mall 220 0 220.00 0.00 0.00
Parking Exhaust and supply fans 0 1318 1318.00 1318.00 1318.00
Ground floor Fan Coil Units 93.42 0 93.42 0.00 0.00
Ground floor Air Handling Units 100 0 100.00 0.00 0.00
First Podium floor Fan Coil Units 43.8 0 43.80 0.00 0.00
First Podium floor Air Handling Units 33.33 0 33.33 0.00 0.00
First Podium floor ERUs (Ventilation) 100 0 100.00 0.00 0.00
Service Level Air Handling Units 208.45 0 208.45 0.00 0.00
Service Level FAHUs, ERUs, FAFs, EXAFs (Ventilation) 79.23 0 79.23 0.00 0.00
DX A/C units for Electrical Substation 0 111 111.00 111.00 0.00
DX A/C units for Main Telecom, CCTV & Low Current rooms 0 50.1 50.10 50.10 0.00
Public Toilets Water Heaters 28 0 28.00 0.00 0.00
Misc. Loads (Pumps, Fans, refregirator, etc.)
Air Conditioning Lighting Small Power Water Heater Cooker
Total Connected load 1386.98 161.10 362.13 55.12 691.59 83.00 145.09 1235.42 1735.00 3904.21 1951.22 5855.42 1691.22 1790.12
Demand Factors 0.9 0.9 0.6 0.9 0.6 0.3 0.4 0.5 0.8 0.66 0.81 0.71 0.80 0.82
Total Demad Load 1248.28 144.99 217.28 49.60 414.95 24.90 58.04 617.71 1388.00 2581.16 1582.59 4163.75 1352.97 1471.59
Total Demand Load on Transformers (KVA) 4163.75
Total Demand Load on Transformers (KW) 3747.38

OWNER / DEVELOPER: 1 23 LEAD CONSULTANT:


b- Tower (except residential apartment) loads

OWNER / DEVELOPER: 124 LEAD CONSULTANT:


OWNER / DEVELOPER: 125 LEAD CONSULTANT:
OWNER / DEVELOPER: 1 26 LEAD CONSULTANT:
c- Residential Apartment loads
LIGHTING SMALL POWER WATER HEATER A/C OTHERS TOTAL LOAD FOR EACH LOAD TYPE
Load type
QTY. Load/Each Total Demand Demand QTY. Load/Each Total Demand Demand QTY. Load/Each Total Demand Demand QTY. Load/Each Total Demand Demand Load QTY. Load/Each Total Demand Demand Total
load factor load load factor load load factor load load factor load type load factor load load A/C TOTAL LIGHTING SMALL POWER WATER HEATER OTHERS
W KW KW W KW KW W KW KW W KW KW W KW KW KW KW KW KW KW KW
AREA
Room Data QTY.
M2
ONE BEDROOM TYPE 01 88 220 10 50 0.50 0.6 0.3 8 100 0.80 0.6 0.48 1 3000 3.00 0.3 0.9 2 412.5 0.83 0.9 0.7425 WM 1 1500 1.50 0.5 0.75
REF. 1 300 0.30 0.5 0.15
M.W. 1 1200 1.20 0.5 0.6
3.3 181.50 110.00 176.00 660.00 1452.00
D.W. 1 2000 2.00 0.5 1
Kittle 1 1000 1.00 0.5 0.5
Cofee M. 1 600 0.60 0.5 0.3
ONE BEDROOM TYPE 02 92 26 10 50 0.50 0.6 0.3 8 100 0.80 0.6 0.48 1 3000 3.00 0.3 0.9 2 412.5 0.83 0.9 0.7425 WM 1 1500 1.50 0.5 0.75
REF. 1 300 0.30 0.5 0.15
M.W. 1 1200 1.20 0.5 0.6
3.3 21.45 13.00 20.80 78.00 171.60
D.W. 1 2000 2.00 0.5 1
Kittle 1 1000 1.00 0.5 0.5
Cofee M. 1 600 0.60 0.5 0.3
ONE BEDROOM TYPE 03 88.7 48 10 50 0.50 0.6 0.3 8 100 0.80 0.6 0.48 1 3000 3.00 0.3 0.9 2 412.5 0.83 0.9 0.7425 WM 1 1500 1.50 0.5 0.75
REF. 1 300 0.30 0.5 0.15
M.W. 1 1200 1.20 0.5 0.6
3.3 39.60 24.00 38.40 144.00 316.80
D.W. 1 2000 2.00 0.5 1
Kittle 1 1000 1.00 0.5 0.5
Cofee M. 1 600 0.60 0.5 0.3
ONE BEDROOM TYPE 04 93.2 48 10 50 0.50 0.6 0.3 8 100 0.80 0.6 0.48 1 3000 3.00 0.3 0.9 2 412.5 0.83 0.9 0.7425 WM 1 1500 1.50 0.5 0.75
REF. 1 300 0.30 0.5 0.15
M.W. 1 1200 1.20 0.5 0.6
3.3 39.60 24.00 38.40 144.00 316.80
D.W. 1 2000 2.00 0.5 1
Kittle 1 1000 1.00 0.5 0.5
Cofee M. 1 600 0.60 0.5 0.3
ONE BEDROOM TYPE 05 90.9 2 10 50 0.50 0.6 0.3 8 100 0.80 0.6 0.48 1 3000 3.00 0.3 0.9 2 412.5 0.83 0.9 0.7425 WM 1 1500 1.50 0.5 0.75
REF. 1 300 0.30 0.5 0.15
M.W. 1 1200 1.20 0.5 0.6
3.3 1.65 1.00 1.60 6.00 13.20
D.W. 1 2000 2.00 0.5 1
Kittle 1 1000 1.00 0.5 0.5
Cofee M. 1 600 0.60 0.5 0.3
ONE BEDROOM TYPE 06 94.4 2 10 50 0.50 0.6 0.3 8 100 0.80 0.6 0.48 1 3000 3.00 0.3 0.9 2 412.5 0.83 0.9 0.7425 WM 1 1500 1.50 0.5 0.75
REF. 1 300 0.30 0.5 0.15
M.W. 1 1200 1.20 0.5 0.6
3.3 1.65 1.00 1.60 6.00 13.20
D.W. 1 2000 2.00 0.5 1
Kittle 1 1000 1.00 0.5 0.5
Cofee M. 1 600 0.60 0.5 0.3
TWO BEDROOM TYPE 01 124.9 100 15 50 0.75 0.6 0.45 18 100 1.80 0.6 1.08 2 3000 6.00 0.3 1.8 4 312.5 1.25 0.9 1.125 WM 2 1500 3.00 0.5 1.5
REF. 1 300 0.30 0.5 0.15
M.W. 1 1200 1.20 0.5 0.6
4.05 125.00 75.00 180.00 600.00 810.00
D.W. 1 2000 2.00 0.5 1
Kittle 1 1000 1.00 0.5 0.5
Cofee M. 1 600 0.60 0.5 0.3
TWO BEDROOM TYPE 02 140 52 15 50 0.75 0.6 0.45 18 100 1.80 0.6 1.08 2 2500 5.00 0.3 1.5 4 312.5 1.25 0.9 1.125 WM 1 1500 1.50 0.5 0.75
REF. 1 300 0.30 0.5 0.15
M.W. 1 1200 1.20 0.5 0.6
3.3 65.00 39.00 93.60 260.00 343.20
D.W. 1 2000 2.00 0.5 1
Kittle 1 1000 1.00 0.5 0.5
Cofee M. 1 600 0.60 0.5 0.3
TWO BEDROOM TYPE 03 130 50 15 50 0.75 0.6 0.45 18 100 1.80 0.6 1.08 2 2500 5.00 0.3 1.5 4 312.5 1.25 0.9 1.125 WM 1 1500 1.50 0.5 0.75
REF. 1 300 0.30 0.5 0.15
M.W. 1 1200 1.20 0.5 0.6
3.3 62.50 37.50 90.00 250.00 330.00
D.W. 1 2000 2.00 0.5 1
Kittle 1 1000 1.00 0.5 0.5
Cofee M. 1 600 0.60 0.5 0.3
TWO BEDROOM TYPE 04 132.8 21 15 50 0.75 0.6 0.45 18 100 1.80 0.6 1.08 2 2500 5.00 0.3 1.5 4 312.5 1.25 0.9 1.125 WM 1 1500 1.50 0.5 0.75
REF. 1 300 0.30 0.5 0.15
M.W. 1 1200 1.20 0.5 0.6
3.3 26.25 15.75 37.80 105.00 138.60
D.W. 1 2000 2.00 0.5 1
Kittle 1 1000 1.00 0.5 0.5
Cofee M. 1 600 0.60 0.5 0.3
TWO BEDROOM TYPE 05 118.2 49 15 50 0.75 0.6 0.45 18 100 1.80 0.6 1.08 2 2500 5.00 0.3 1.5 4 312.5 1.25 0.9 1.125 WM 2 1500 3.00 0.5 1.5
REF. 1 300 0.30 0.5 0.15
M.W. 1 1200 1.20 0.5 0.6
4.05 61.25 36.75 88.20 245.00 396.90
D.W. 1 2000 2.00 0.5 1
Kittle 1 1000 1.00 0.5 0.5
Cofee M. 1 600 0.60 0.5 0.3
TWO BEDROOM TYPE 06 127.8 24 15 50 0.75 0.6 0.45 18 100 1.80 0.6 1.08 2 2500 5.00 0.3 1.5 4 312.5 1.25 0.9 1.125 WM 2 1500 3.00 0.5 1.5
REF. 1 300 0.30 0.5 0.15
M.W. 1 1200 1.20 0.5 0.6
4.05 30.00 18.00 43.20 120.00 194.40
D.W. 1 2000 2.00 0.5 1
Kittle 1 1000 1.00 0.5 0.5
Cofee M. 1 600 0.60 0.5 0.3
THREE BEDROOM TYPE 01 173.3 52 20 50 1.00 0.6 0.6 27 100 2.70 0.6 1.62 3 2000 6.00 0.3 1.8 6 247.5 1.49 0.9 1.3365 WM 2 1500 3.00 0.5 1.5
REF. 1 300 0.30 0.5 0.15
M.W. 1 1200 1.20 0.5 0.6
4.05 77.22 52.00 140.40 312.00 421.20
D.W. 1 2000 2.00 0.5 1
Kittle 1 1000 1.00 0.5 0.5
Cofee M. 1 600 0.60 0.5 0.3
DUPLEX TYPE 01 217.4 1 25 50 1.25 0.6 0.75 30 100 3.00 0.6 1.8 3 2000 6.00 0.3 1.8 6 247.5 1.49 0.9 1.3365 WM 2 1500 3.00 0.5 1.5
REF. 1 300 0.30 0.5 0.15
M.W. 1 1200 1.20 0.5 0.6
4.05 1.49 1.25 3.00 6.00 8.10
D.W. 1 2000 2.00 0.5 1
Kittle 1 1000 1.00 0.5 0.5
Cofee M. 1 600 0.60 0.5 0.3
DUPLEX TYPE 02 225.7 1 27 50 1.35 0.6 0.81 32 100 3.20 0.6 1.92 3 2000 6.00 0.3 1.8 6 247.5 1.49 0.9 1.3365 WM 2 1500 3.00 0.5 1.5
REF. 1 300 0.30 0.5 0.15
M.W. 1 1200 1.20 0.5 0.6
4.05 1.49 1.35 3.20 6.00 8.10
D.W. 1 2000 2.00 0.5 1
Kittle 1 1000 1.00 0.5 0.5
Cofee M. 1 600 0.60 0.5 0.3
735.64 449.60 956.20 2942.00 4934.10

OWNER / DEVELOPER: 127 LEAD CONSULTANT:


d- Summery loads

Air Conditioning Water Heater Cooker General Others Total Load (KVA)
MALL
Total Load (KVA) Total Load (KVA) Total Load (KVA) Total Load (KVA) Total Load (KVA)

CONNECTED LOAD (KVA) 1548.08 83.00 145.09 1108.84 2970.42 5855.42


DEMAND FACTOR 0.90 0.30 0.40 0.61 0.68 0.71
MAX. DEMAND LOAD (KVA) 1393.27 24.90 58.04 681.84 2005.03 4163.08

Air Conditioning Water Heater Cooker General Others Total Load (KVA)
TOWER (EXCEPT RESIDENTIAL APPARTMENT)
Total Load (KVA) Total Load (KVA) Total Load (KVA) Total Load (KVA) Total Load (KVA)
CONNECTED LOAD (KVA) 1342.13 532.00 0.00 787.74 1693.96 4355.83
DEMAND FACTOR 0.90 0.30 0.40 0.70 0.77 0.74
MAX. DEMAND LOAD (KVA) 1207.92 159.60 0.00 548.11 1304.35 3219.98

Air Conditioning Water Heater Cooker General Others Total Load (KVA)
TOWER RESIDENTIAL APPARTMENT
Total Load (KVA) Total Load (KVA) Total Load (KVA) Total Load (KVA) Total Load (KVA)
CONNECTED LOAD (KVA) 817.38 3268.89 0.00 1562.00 5482.33 11130.60
DEMAND FACTOR 0.90 0.30 0.40 0.60 0.50 0.48
MAX. DEMAND LOAD (KVA) 735.64 980.67 0.00 937.20 2741.17 5394.67

Air Conditioning Water Heater Cooker General Others Total Load (KVA)
ALL PROJECT LOAD
Total Load (KVA) Total Load (KVA) Total Load (KVA) Total Load (KVA) Total Load (KVA)
CONNECTED LOAD (KVA) 3707.59 3883.89 145.09 3458.57 10146.71 21341.85
DEMAND FACTOR 0.90 0.30 0.40 0.63 0.60 0.60
MAX. DEMAND LOAD (KVA) 3336.83 1165.17 58.04 2167.15 6050.54 12777.72

OWNER / DEVELOPER: 1 28 LEAD CONSULTANT:


ERKYAH MIXED USE
LUSAIL-QATAR
MECHANICAL DESIGN CONCEPT REPORT
REVISION 00 – NOV. 2019

OWNER / DEVELOPER: LEAD CONSULTANT:


Table of Contents
1.4 Fresh and exhaust air system ................................................................................................ 147
1. Heating, Ventilating and Air Conditioning ............................................................................. 130
1.1 Codes and Regulations ......................................................................................................... 130 1.4.1 Fresh and exhaust air system for apartments tower (A, B, C) ................................................................ 147

1.2 Design Criteria ....................................................................................................................... 130 1.4.2 Fresh and exhaust air system for mall facilities ...................................................................................... 147

1.2.1 Doha Orientation Data ............................................................................................................................ 130 1.4.3 Toilets ..................................................................................................................................................... 147

1.2.2 Outside Temperatures ............................................................................................................................. 130 1.4.4 Storage Area .......................................................................................................................................... 147

1.2.3 Indoor Design Conditions ........................................................................................................................ 131 1.4.5 Kitchen .................................................................................................................................................... 147

1.2.4 Internal Heat Gain Design Criteria .......................................................................................................... 131 1.5 Smoke control systems ......................................................................................................... 148
1.2.5 Equipment Power Densities ..................................................................................................................... 132 1.5.1 Parking Garage Ventilation & Smoke Management Plan ..................................................................... 148
1.2.6 Lighting Power Densities ......................................................................................................................... 132 1.5.2 Large space smoke evacuation system .................................................................................................. 149
1.2.7 Ventilation ............................................................................................................................................... 133 1.5.3 Atrium smoke evacuation system .......................................................................................................... 149
1.2.8 Ductwork ................................................................................................................................................. 133 1.5.4 Pressurization system ............................................................................................................................. 149
1.2.9 Pipe Work ................................................................................................................................................ 134
1.6 HVAC Zoning .......................................................................................................................... 153
1.2.10 Building Construction U values .............................................................................................................. 134
1.2.11 Occupancy Basic Criteria ....................................................................................................................... 134 1.7 Fresh & Exhaust riser ............................................................................................................ 159

1.2.12 Cooling & Heating Load ......................................................................................................................... 134 1.8 Outline Specifications ............................................................................................................ 167

1.3 Description of the HVAC System .......................................................................................... 134


1.3.1 Chilled water system ............................................................................................................................... 134
1.3.2 Main System component ......................................................................................................................... 135
1.3.3 HVAC System for main Spaces ................................................................................................................. 138
1.3.4 Estimation cooling load ........................................................................................................................... 139
1.3.5 HVAC system for spaces ......................................................................................................................... 140
1.3.6 Fresh air load estimation ......................................................................................................................... 141
1.3.7 Total load summary................................................................................................................................. 142
1.3.8 Allocated load and required load ........................................................................................................... 143
1.3.9 HVAC Load chart ..................................................................................................................................... 145
1.3.10 Space Design Criteria ............................................................................................................................. 146

OWNER / DEVELOPER: 130 LEAD CONSULTANT:


2. Drainage System ................................................................................................................. 168 4. Firefighing System …………………………………………………………………………………207
4.1 Codes and Regulations .................................................................................................... 208
2.1 Codes and Regulations ......................................................................................................... 169 4.2 General Description ......................................................................................................... 208
2.2 The Drainage system incorporates ........................................................................................ 169 4.3 System Operation ............................................................................................................ 208
2.3 Intoduction ............................................................................................................................ 169 4.4 Firefighting System Versus Space Name ......................................................................... 208
2.4 Design Criteria ..................................................................................................................... 169 4.5 Wet Sprinkler System ....................................................................................................... 209
2.5 Sanitary Drainage Pipe Size ................................................................................................ 169 4.6 Wet Stand Pipe ................................................................................................................ 210
2.6 System Description .............................................................................................................. 172 4.7 Clean Agent Fire Extinguishing System ........................................................................... 211
2.7 Piping Material ..................................................................................................................... 175 4.8 Foam Fire Protection System ........................................................................................... 212
2.8 Gray Water Calculation ........................................................................................................ 176 4.9 Fire Extinguisher System ................................................................................................. 212
2.9 Storm Water Tank Calculation ............................................................................................. 177 4.10 Dry Powder Fire Extinguisher ..................................................................................... 213
4.11 Wet Chemical Fire Suppression System .................................................................... 213
3. Water Supply System .......................................................................................................... 185
4.12 Aerosol Fire Protection System .................................................................................. 213
3.1 Codes and Regulations ......................................................................................................... 186
4.13 Outline Specification ................................................................................................... 213
3.2 Potable and Non-Potable Water Supply System Design Criteria .......................................... 186
4.14 Fire Water Tank Calculation ....................................................................................... 214
3.3 Potable Cold Water Supply System Description ................................................................... 188
3.4 Piping and Valves .................................................................................................................. 189
5. Synthetic Natural Gas ( SNG) ............................................................................................. 217
3.5 Water Hameer Arrestors ....................................................................................................... 189
3.6 Automatic Air Vent ................................................................................................................. 189 5.1 Introduction ........................................................................................................................... 218
3.7 Hose Bib ................................................................................................................................ 189 5.2 Codes and Standard ............................................................................................................. 218
3.8 Non-Potable Water System Description ............................................................................... 190 5.3 System General Description ................................................................................................. 218
3.9 Hot Water Distribution System .............................................................................................. 191 5.4 System Serving .................................................................................................................... 218
3.10 Metering Strategy .................................................................................................................. 194 5.5 Design Parameters ............................................................................................................... 218
3.11 Piping Material ...................................................................................................................... 194 5.6 System Provision .................................................................................................................. 219
3.12 Irrigation System ................................................................................................................... 195 5.7 Building Installation Pipeswork ............................................................................................. 219
3.13 Swimming Pools .................................................................................................................... 195 5.8 Outline Specification ............................................................................................................. 219
3.14 Water Fountain ...................................................................................................................... 196 5.9 Gas System Estimated Loads .............................................................................................. 220
3.15 Water System Calculation ..................................................................................................... 197 5.10 Gas System Proposed Provisions ........................................................................................ 221

OWNER / DEVELOPER: 131 LEAD CONSULTANT:


MECHANICAL WORKS
HEATING, VENTILATING AND AIR CONDITIONING

OWNER / DEVELOPER: 132 LEAD CONSULTANT:


Latitude/ Longitude : 25North – 51East

Elevation : 9.8 m (32 ft.)

1. Heating, Ventilating and Air Conditioning


1.1 Codes and Regulations.

The latest editions of publications and standards listed here are intended as guidelines for design. They
1.2.2 Outside Temperatures
are mandatory only where referenced as such in the text of this chapter or in applicable codes. The list is
not meant to restrict the use of additional guides or standards. Summer

Dry Bulb : 46.1 C (115 F)

 ASHRAE: Handbook of Fundamentals. Wet Bulb : 30.5 C (87 F)

 ASHRAE: Handbook of HVAC Applications. Daily Rang : 10.8 C (19.4F)

 ASHRAE: Handbook of HVAC Systems and Equipment.

 ASHRAE: Standard 62: Ventilation for Acceptable Indoor Air Quality.  Summer: 31.9°C wet bulb, 34°C mean coincident dry bulb.

 ASHRAE: Standard 90.1: Energy Standard for Buildings Except Low-Rise Residential Buildings. Used in the design of all outdoor air treatment plant
 Sheet Metal and Air Conditioning Contractors’ National Association, Inc. (SMACNA): – SMACNA HVAC
Duct Construction Standards: Metal and Flexible. – SMACNA HVAC Air Duct Leakage Test Manual. –
SMACNA Fire, Smoke and Radiation Damper Installation Guide for HVAC Systems. – Seismic Restraint
Manual Guidelines for Mechanical Systems.

 Qatar Civil Defense Authorities.

 Qatar Construction Specifications (QCS)

 National Fire Protection Association (NFPA).

 GSAS Global Sustainability Assessment System.

 All applicable regulations and requirements of local utility companies having jurisdiction.

1.2 Design Criteria

The design of HVAC system will be based on the following design criteria.

1.2.1 Doha Orientation Data

OWNER / DEVELOPER: 133 LEAD CONSULTANT:


KITCHEN / KITCHENETTE 24 55
STORE 23 50
SPA 24 55

23 50
WORKSHOP
1.2.3 Indoor Design Conditions.

Indoor design conditions temperatures and relative humidity requirements shall be according to the
following table:

BOWLING AREA 23 50
INDOOR CINEMA 23 50
RELATIVE
DESIGN
HUMIDITY PRAYER HALL 23 50
FUNCTION TEMPERATURE
(SUMMER) HYPER MARKET 23 50
(SUMMER) 0C
%RH (±5%) FEC(FAMILY ENTERTAINMENT
(±1) 23 50
CENTER)

FOOD COURT 23 55 1.2.4 Internal Heat Gain Design Criteria


FOOD AND BEVERAGE(F&B) 23 55
CAFÉ 23 55 1.2.4.1 occupancy heat Load.
PANTRY 24 50
The following table gives representative rates at which sensible heat and moisture are emitted by humans in
OFFICE 23 50 different states of activity.
SHOPS 23 55
SENSIBLE LATENT
GYM 23 50 DEGREE OF ACTIVITY FUNCTION
HEAT, W HEAT, W
MALL COMMON AREA 23 50
CORRIDOR 23 50 SEDENTARY WORK FOOD COURT 80 80
SERVICE AND MECHANICAL
30 55 FOOD AND
ROOM SEDENTARY WORK 80 80
BEVERAGE(F&B)
RECEPTION 23 50
SEDENTARY WORK CAFÉ 80 80
PUMP RM. 24 50
SEDENTARY WORK PANTRY 80 80
GARBAGE RM. 24 50 MODERATELY ACTIVE
ELEC ROOM 21 50 OFFICE 75 55
OFFICE WORK
IDF ROOM 21 50 STANDING, LIGHT WORK;
RETAIL / SHOPS 75 55
WALKING
TELECOM ROOM 21 50
ATHLETICS GYM 210 315
GSM ROOM 21 50
STANDING, LIGHT WORK;
CCTV ROOM 21 50 CORRIDOR 75 55
WALKING
BED ROOM 22 50
SERVICE AND
MASTER BED ROOM 22 50 WALKING 4.8 KM/H;
MECHANICAL 110 185
LIGHT MACHINE WORK
LIVING ROOM 22 50 ROOM
DINING ROOM 22 50 STANDING, LIGHT WORK;
RECEPTION 75 55
WALKING

OWNER / DEVELOPER: 134 LEAD CONSULTANT:


WALKING 4.8 KM/H; 1.2.5 Equipment Power Densities.
MACHINE ROOM 110 185
LIGHT MACHINE WORK
WALKING 4.8 KM/H; Internal heat gain from all appliances-electrical, gas, or steam-shall be taken into account. The rates of
PUMP RM. 110 185 heat gain from equipment shall be based on ASHRAE Handbook of Fundamentals or manufacturer’s data.
LIGHT MACHINE WORK

SENSIBLE LATENT 1.2.6 Lighting Power Densities.


DEGREE OF ACTIVITY FUNCTION
HEAT, W HEAT, W
The rates of heat gain from lighting systems shall be based ASHRAE: Standard 90.1.
MODERATELY ACTIVE
GARBAGE RM. 75 55
OFFICE WORK
MODERATELY ACTIVE FUNCTION LPD (W/M2)
ELEC ROOM 75 55
OFFICE WORK FOOD AND
14
MODERATELY ACTIVE BEVERAGE(F&B)
IDF ROOM 75 55
OFFICE WORK CAFÉ 14
MODERATELY ACTIVE PANTRY 13
TELECOM ROOM 75 55
OFFICE WORK OFFICE 12
MODERATELY ACTIVE RETAIL 18
GSM ROOM 75 55
OFFICE WORK GYM 15
MODERATELY ACTIVE CORRIDOR 14
CCTV ROOM 75 55
OFFICE WORK
SERVICE 16
MODERATELY ACTIVE
BED ROOM 75 55 SHOP 18
OFFICE WORK
RECEPTION 14
MODERATELY ACTIVE MASTER BED
75 55 MACHINE ROOM 16
OFFICE WORK ROOM
MODERATELY ACTIVE PUMP ROOM. 16
LIVING ROOM 75 55
OFFICE WORK GARBAGE ROOM. 9
SEDENTARY WORK DINING ROOM 80 80
ELEC ROOM 16
KITCHEN / IDF ROOM 16
SEDENTARY WORK 80 80
KITCHENETTE TELECOM ROOM 16
STANDING, LIGHT WORK; GSM ROOM 16
STORE 75 55 CCTV ROOM 16
WALKING
SEDENTARY WORK SPA 170 255 BED ROOM 12
HEAVY WORK WORKSHOP 170 255 MASTER BED
12
ROOM
BOWLING BOWLING 170 255 LIVING ROOM 14
DINING ROOM 14
SEATED, VERY LIGHT
CINEMA 70 45 KITCHEN /
WORK 13
KITCHENETTE
STANDING, LIGHT WORK; STORE 9
PRAYER HALL 75 55
WALKING
SPA 10
FEC(FAMILY
BOWLING ENTERTAINMENT 170 255 WORKSHOP 20
CENTER) BOWLING AREA 15
CINEMA 13

OWNER / DEVELOPER: 135 LEAD CONSULTANT:


PRAYER HALL 18
FEC(FAMILY
ENTERTAINMENT 23
CENTER)

1.2.7 Ventilation

The minimum required fresh air supply has been based on ASHRAE requirements and has also considered
GSAS requirements:

MINIMUM VENTILATION RATES Minimum Exhaust Rate


L/S. MINIMUM EXHAUST RATES
FUNCTION L/S.M2
PERSON
FUNCTION L/S./UNIT L/S.M2
FOOD COURT 3.8 0.9
CHANGING ROOM - 1.25
FOOD AND
3.8 0.9 TOILET PRIVATE 25 -
BEVERAGE(F&B)
CAFÉ 3.8 0.9 TOILET PUBLIC 35 -
PANTRY 3.8 0.9 PANTRY 50 -
35 / 25ACH/ AS PER
OFFICE 2.5 0.3 COMMERCIAL KITCHENS KITCHEN
RETAIL / SHOPS 3.8 0.6 - CONSULTANT
GYM 10 0.9
CORRIDOR - 0.3
1.2.8 Ductwork
SERVICE - 0.3
The ductwork sizing and spaces air distribution will be done in accordance with SMACNA Standards and
RECEPTION 3.8 0.3 “Carrier System Design Manual Part 2 – Air distribution, duct sizing by MCQUAY duct size program. Friction
BED ROOM 2.5 0.3 loss, Noise and velocities will be generally as follows:
MASTER BED ROOM 2.5 0.3 Ductwork passing through fire rated walls will be provided with fire dampers / Fire smoke dampers.
LIVING ROOM 2.5 0.3
Duct work will be provided with the required volume dampers for proper balancing of air system.
DINING ROOM 2.5 0.3
KITCHEN / The following table mentioned the recommended air velocity and noise criteria required to achieve in
3.8 0.9
KITCHENETTE duct design.
STORE 2.5 0.3
SPA 10 0.3
MAXIMUM AIR FLOW VELOCITY M/S
WORKSHOP 2.5 0.3
BOWLING 5 0.6
RECTANGUL CIRCULAR
CINEMA 3.8 0.3 DESIGN
MAIN DUCT LOCATION AR DUCT DUCT
RC(N)
PRAYER HALL 2.5 0.3
FEC(FAMILY 45 17.8 25.4
ENTERTAINMENT 3.8 0.9 35 12.7 17.8
CENTER)
25 8.6 12.7
45 12.7 22.9
35 8.9 15.2

OWNER / DEVELOPER: 136 LEAD CONSULTANT:


CEILING 25 6.1 10.2 3. External Glazing U value:

45 10.2 19.8 Building external glazing type shall be chosen to conserve energy and to minimize the air
35 7.4 13.2 conditioning load.
25 4.8 8.6 External windows, low-e tinted double-glazed, with U = 1.8 W/M2.K & Shading coefficient of 0.25
shall be used in the HVAC cooling load calculation
1.2.9 Pipe Work

The pipe works sizing will be done in accordance with ASHRAE Handbook 1.2.11 Occupancy Basic Criteria
Fundamentals - Chapter 22 Pipe Sizing" along with recommendations of Carrier
Systems Design Manual, Part 3, Piping Design. Friction loss and velocities will be
generally as follows: The design will incorporate the occupancy as per Arch furniture layout or will be taken occupant density
from ASHRAE standard 62.1 Table 6.2.2.1.
Friction loss through pipe works shall not exceed 4 ft/100 ft. of equivalent pipe length.
1.2.12 Cooling & Heating Load
Water velocities will not exceed the following:
Air conditioning load is calculated using a computer program based on ASHRAE methods developed
by carrier for Engineering Consultants, the program is hourly analysis program (HAP 4.9), USA.
WATER VELOCITY Computer printouts indicate input design conditions used for cooling and heating load calculations and
SERVICE output showing individual room peak load, air quantities and zone and building block loads.
FPS

PUMP DISCHARGE 8-12

PUMP SUCTION 4-7


1.3 Description of the HVAC System
HEADER 4-15
The HVAC system will be designed to achieve intended design parameters at an acceptable client
RISER 3-10 budget.

1.3.1 Chilled water system

As AL ERKYAH is a part of a LUSAIL city, chilled water Generation System will be based on the district
Cooling system, which will be provided by MARAFEQ Building, will contain Energy Transfer Stations
1.2.10 Building Construction U values.
(ETS) located in basement -1 and the following are the main zoning.
The building will be serving by 2 NOS of ETS based on the operation
The following parameter of building construction u values which will considered and achieved in Arch.
Specification and final approved by GSAS specialist. 1- ETS with approximate capacity 3465 TR for serving the mall.
2- ETS with approximate capacity 4050 TR for serving residential towers and related spaces.
1. External Walls U value:

External wall shall be heavy construction, medium/light external colour, U-value not to exceed 0.30 The chilled water provided from MRAFEQ (primary side) to the main Energy Transfer Stations
W/M2.K. (ETS rooms) located in 1st basement
Chilled Water Supply Temperature: 5.0 oC
2. Roof U value:
Chilled Water Return Temperature: 14.0 oC
Roof shall be heavy-construction, medium colour, U-value not to exceed 0.25 W/M2.K.

OWNER / DEVELOPER: 137 LEAD CONSULTANT:


A- Apartments Tower (A, B, C).

Chilled water will be directly provided to Towers via (5 NOS including one standby) variable speed
secondary chilled water pumps connected to the heat exchangers in towers ETS Room located in
Basement 1, and serving apartment floors from second podium to tower Roof floor.
Chilled Water Supply Temperature: 6.2 oC
Chilled Water Return Temperature: 15.2 oC

B- Mall area

Chilled water will be directly provided to mall area (podiums retails) via (4 NOS including one standby)
variable speed secondary chilled water pumps connected to the heat exchangers in mall ETS Room
located in Basement 1, and serving mall floors from Basement 2 to second podium floor.
Chilled Water Supply Temperature: 6.2 oC
Chilled Water Return Temperature: 15.2 oC

1.3.2 Main System component

 Heat exchangers

 Chilled water pumps

 Energy recovery units

 Air handling units

 Ducted fan coil unit

 Decorative FCUs ENERGY TRANSFER STATION (ETS) SAMPLE

 Fresh and exhaust fans

OWNER / DEVELOPER: 138 LEAD CONSULTANT:


OWNER / DEVELOPER: 139 LEAD CONSULTANT:
OWNER / DEVELOPER: 140 LEAD CONSULTANT:
1.3.3 HVAC System for main Spaces.

1. Apartments(towers):
 Apartment’s room shall be provided with dedicated 2 pipes concealed fan coil unit located
above room lobby.
 100% filtered and tempered outside fresh air should be ducted directly into the Apartment
room and maintaining positive pressure.
 Digital thermostat with 3 speeds located near to return air outlet.
 Fan coil units shall be provided with PICV valve for cooling circuit with on/off position.
 Centralized exhaust system for toilet and kitchens connected to energy recovery unit. Exhaust
air shall be not less than 30 L/s for toilet and 50 L/s for kitchen.

2. Mall area :
 Public areas shall be air conditioned by total recirculate constant air volume air handling unit
and fresh air for this spaces will be supplied with treated fresh air handling units.
 Individual temperature control for each public space shall be provided.

3. Computer Rooms:
 Computer rooms shall be cooled by self-contained. These units shall be specifically designed
for this purpose and contain compressors, filters, humidifiers and controls. They shall be sized
to allow for a minimum of 50 % redundancy, either two units at 75 % load or three units at 50
%. Heat rejection from these self-contained units shall be by air-cooled condensers or chilled
water.

4. Retails /F&B (Rentable Area)


 Proposed AC system for retails will provide chilled water with a BTU meter and treated Fresh
air for each rentable area.
 For food and beverage areas will provide chilled water with a BTU meter, treated fresh air, and
kitchen ventilation provision (provide exhaust hood duct with ecology unit for each rentable
area).

5. Hypermarket
 Proposed AC system for Hypermarket will provide chilled water with a BTU meter and treated
Fresh air.
 Proposed Hood exhaust and fresh air system for hypermarket will provide.( provide exhaust
hood duct with ecology unit)

OWNER / DEVELOPER: 141 LEAD CONSULTANT:


1.3.4 Estimation cooling load

OWNER / DEVELOPER: 142 LEAD CONSULTANT:


1.3.5 HVAC system for spaces

OWNER / DEVELOPER: 143 LEAD CONSULTANT:


1.3.6 Freeh air load estimation

OWNER / DEVELOPER: 144 LEAD CONSULTANT:


1.3.7 Total load summary

OWNER / DEVELOPER: 145 LEAD CONSULTANT:


1.3.8 Allocated and required cooling load

OWNER / DEVELOPER: 146 LEAD CONSULTANT:


Allocated and Required Cooling Load

OWNER / DEVELOPER: 147 LEAD CONSULTANT:


1.3.9 HVAC Load chart

OWNER / DEVELOPER: 148 LEAD CONSULTANT:


1.3.10 Space design criteria

OWNER / DEVELOPER: 149 LEAD CONSULTANT:


1.4 Fresh and exhaust air system

 Outdoor air quantities, pressurization relationship to adjacent areas and minimum total air change
rates will be computed in accordance with ASHRAE Standard 62.1 recommendations.

 Fresh Air ventilation rates should be designed at 5% above ASHRAE 62.1 minimum requirements

 ERU required, with minimum efficiency of 65%

 As much as possible design of the ventilation system shall be such that it provides air movement
from clean to less clean areas.

 The number of people should be based on normal occupancy or as per the furniture layout in
sitting areas as per ASHRAE 62.1.

1.4.1 Fresh and exhaust air system for apartments tower (A, B, C).

 The fresh air will be centrally treated and tempered using Energy Recovery Units that will
filter and cool/heat air to specific requirement prior circulating to different air conditioned
zones. Energy Recovery Unit with heat wheel
 Exhausted air from the toilets will be collected and passed to energy recovery units in 1.4.3 Toilets:
which the recovered energy will be used to pre-cool the fresh air. The thermal wheel
energy recovery units shall have 80% sensible heat efficiency, 60% latent heat efficiency
and these will amount to a maximum 70% total energy recovery from the exhausted air Toilets shall be provided with general exhaust systems at the rate 35 l/s per toilet for public toilets and
quantity. 30 l/s for Private toilet.

 Exhaust from kitchens, kitchenettes and pantries shall be directly discharged to outside 1.4.4 Storage Area
the building by using Exhaust fans(one duty and one standby).

 Garbage exhaust which is not permitted to mix with energy recovery will be directly Generally, storage rooms located adjacent to or within air-conditioned areas will be air-conditioned,
discharged using exhaust fans to outside the building. unless otherwise identified.

1.4.5 Kitchen

1.4.2 Fresh and exhaust air system For mall facilities Kitchens with cooking ranges, steam kettles, ovens and dishwashers shall be provided with
Dedicated filtered make-up air (uncooled) and exhaust hoods/exhaust systems in accordance with
(Hypermarket, cinema, FEC (family entertainment center), Kitchen, Shops, food and beverage …) NFPA Standard 96 and ASHRAE Applications Handbook. All components OF the ventilation system
shall be designed to operate in balance with each other, even under variable loads, to properly capture,
 The fresh air will be centrally treated and tempered using fresh air handling unit(s) with contain, and remove the cooking effluent and heat, and maintain proper temperature and pressurization
heat pipes that will filter and cool/heat air to specific requirement prior circulating to control in the spaces in an efficient and economic manner. The operation of the kitchen exhaust
different air Conditioned zones.
systems shall not affect the pressure relation between the kitchen and surrounding spaces.
 Kitchen exhaust will be filtered by ecology units then discharged to outside the building.
• Hoods shall be double skin Air curtain type to allowing the introduction of make-up fresh air to
 Kitchen make up air will be provided to each hood using fresh air fans. Ensure minimum velocity in the hood surface for proper and effective exhaust.
 All Fresh air handling units FAHU with heat pipes used for mall facilities provided by
landlord.

OWNER / DEVELOPER: 150 LEAD CONSULTANT:


 Fan systems shall be provided with vibration isolation, sound attenuation, motor, variable
flow drive, and duct smoke detector.

 Hood exhaust air shall be sized as per ASHRAE standard 154 or as per hood
manufacturer

 Recommendations. Fresh air shall be 90% of exhaust air.

 A ceiling hung fan coil and/or air handling shall be used for air conditioning.

 For F&B Provision for Kitchen Exhaust & Fresh Air: Follow supplier requirements if not
available consider kitchen area to be 30% of F&B area, and exhaust flow rate 35l/s/m2,
and makeup air 90% of exhaust flow rate.

 Kitchen Exhaust will be connected to ecology unit (by tenant).

1.5 Smoke control systems


PARKING FANS
1.5.1 Parking Garage Ventilation & Smoke Management Plan NO. OF
FAN TYPE AND LOCATION LOCATION FAN TYPE
FANS
EXHAUST FANS IN BASEMENT 1 16 BASEMENT 1 AXIAL INLINE FIRE RATED
 As per NFPA requirements a mechanical extract system will be provided to serve the
underground car park. Air will be extracted via architecture shaft located in corners with EXHAUST FANS IN BASEMENT 2 16 BASEMENT 2 AXIAL INLINE FIRE RATED
extract louvers. The system will have two distinct modes of operation; under normal
extract mode, the system will provide six air changes per hour. During fire conditions, the JET FANS IN BASEMENT 1 71 BASEMENT 1 AXIAL INLINE FIRE RATED
system will provide ten air changes per hour. JET FANS IN BASEMENT 2 71 BASEMENT 2 AXIAL INLINE FIRE RATED
FRESH AIR FANS IN BASEMENT 1 16 BASEMENT 1 AXIAL INLINE FIRE RATED
FRESH AIR FANS IN BASEMENT 2 16 BASEMENT 2 AXIAL INLINE FIRE RATED
 The parking garage shall be provided with Fan systems work in case of normal ventilation
and smoke extraction, comply with CO monitoring system and extract and intake air
louvers.

 Jet fan shall be used instead of distributing duct which will give a high performance in air
movement and increase system efficiency.

 The fans will be rated to operate at a temperature of 250°C for two hour and will be
connected to generator.

OWNER / DEVELOPER: 151 LEAD CONSULTANT:


1.5.2 Large space smoke evacuation system 1.5.4 Pressurization system

For any area exceed 1115 sqm will be provided with smoke ventilation, as per QCDD  The staircases, smoke stop lobbies and fire fighting lobbies shall be pressurized to offer a
requirement a mechanical extract system will be provided to this area . Smoke will be evacuated tenable area for civil defines fire fighting and escape of the building.
via fire rated duct and fans to operate at a temperature 250°C for two hour located in mechanical
service floor The fans will be connected to the standby generator. The makeup air required for
this area will be thru opening doors to building outside.  Each stair or fire fighting lobby will be pressurized by independent and separate fans.

 The fans will be connected to the generator.


1.5.3 Atrium smoke evacuation system
 The project will be directly connected to Pressurization fans that shall be located in towers
The atrium will be connecting Basement 1, Ground Floor and first Podium which will be open mechanical roof floor serving all floors from roof floor to basement 2.
to each other. Access from and to these levels for normal circulation will be possible via a number
of escalator and elevators. As per NFPA and QCDD requirements a mechanical extract system
will be provided to serve the atrium. Atrium smoke will be evacuated via fire rated ducts and fans
to operate at a temperature of 250⁰C for two hours located in service floor to discharge the
smoke to outside the building. The fans will be connected to generator. The makeup air required
for the atrium will be thru opening doors to building outside in ground floor level.

OWNER / DEVELOPER: 152 LEAD CONSULTANT:


OWNER / DEVELOPER: 153 LEAD CONSULTANT:
OWNER / DEVELOPER: 154 LEAD CONSULTANT:
OWNER / DEVELOPER: 155 LEAD CONSULTANT:
1.6 HVAC zoning

OWNER / DEVELOPER: 156 LEAD CONSULTANT:


OWNER / DEVELOPER: 157 LEAD CONSULTANT:
OWNER / DEVELOPER: 158 LEAD CONSULTANT:
OWNER / DEVELOPER: 159 LEAD CONSULTANT:
OWNER / DEVELOPER: 160 LEAD CONSULTANT:
OWNER / DEVELOPER: 161 LEAD CONSULTANT:
1.7 Fresh & exhaust riser

OWNER / DEVELOPER: 162 LEAD CONSULTANT:


OWNER / DEVELOPER: 163 LEAD CONSULTANT:
OWNER / DEVELOPER: 164 LEAD CONSULTANT:
OWNER / DEVELOPER: 165 LEAD CONSULTANT:
OWNER / DEVELOPER: 166 LEAD CONSULTANT:
OWNER / DEVELOPER: 167 LEAD CONSULTANT:
OWNER / DEVELOPER: 168 LEAD CONSULTANT:
OWNER / DEVELOPER: 169 LEAD CONSULTANT:
1.8 Outline Specifications

 Chilled water pipes will be schedule 40 black steel with appropriate elastomeric type insulation.
 Chilled water pumps will be variable speed, horizontal split case or vertical type.
 Air Handling Units will be double skin, draw through, central station with filter sections, cooling coil,
Fans, heat recovery unit (for 100% F.A) and sound attenuator on both supply and return.
 Fan coil units will be provided with cooling coils only.

OWNER / DEVELOPER: 170 LEAD CONSULTANT:


MECHANICAL WORKS

DRAINAGE SYSTEM

OWNER / DEVELOPER: LEAD CONSULTANT:


171
2. DRAINAGE SYSTEM
2.4 Design Criteria
2.1 Codes and Regulations

The drainage systems will be designed in accordance with the requirements of the following Minimum flow velocity 0.6 m/sec

codes and local regulation:


Fixture trap seal ± 25 mm of water column
- Public Works Authority of Qatar ASHGHAL. fluctuation
- Global sustainability assessment system GSAS. Discharge loads Drainage Fixture Units (DFU)
- International Plumbing Code.
- Uniform Plumbing Code. Stack maximum 7/24 of total cross sectional area
- Plumbing Engineering Services Design Guide. permissible flow of the stack
- National Plumbing Code Handbook.
Building drain and main ½ full to ¾ full
- American Society of Plumbing Engineers ASPE. sewer pipes

2.2 The Drainage system incorporates the following:


1- Horizontal drainage branches for both soil and waste connectors. 2.5 Sanitary Drainage Pipe Size
2- Soil Stacks, Piping is properly sized to handle the recommended maximum permissible flow from all
fixtures. No branch flow exceeds the flow capacity of the stack. Stack is increased in size to
3- Gray/Waste Stacks,
accommodate all branch loads exceeding the maximum allowable branch discharge to the
4- Vent Pipes, stack within the same branch interval.
5- Grease and sand traps removal, Sanitary drainage and vent horizontal pipes and stack size shall be according to UPC tables
6- Submersible Pumps in Basement floor, below
7- Waste water treatment unit…etc.
8- Storm water drain

2.3 Introduction
The buildings will be equipped with all necessary drainage installations of appropriate kind,
size and function.
The design criteria established for drainage systems is to ensure a high level of cleanliness,
hygiene and property within the building with systems designed for minimum maintenance,
efficient operation and reliability.

OWNER / DEVELOPER: LEAD CONSULTANT:


172
OWNER / DEVELOPER: LEAD CONSULTANT:
173
Drainage Flow Rate

Estimated flow rate for drainage system will be calculated based on BS-EN-12056-2:2000
according to usage of appliances and system type

Waste water flow-rate (l/s) Q = K√∑DU

Q = Drainage water flow-rate (l/s)


K = Frequency of use
∑DU = Sum of discharge unite (based on system IV)

Horizontal sloped pipe for specific size shall be calculated according to manning equation
as the following:

Where:
Q = Quantity rate of flow in cubic feet per second (cfs)
A = Cross-sectional area of flow (ft2)
n = Coefficient representing roughness of pipe surface, degree of fouling and pipe diameter
R = Hydraulic radius (hydraulic mean depth of flow) (ft.)

S = Hydraulic slope of surface of flow (ft. /ft.)

OWNER / DEVELOPER: LEAD CONSULTANT:


174
2.6 System Description
2.6.1 General 2.6.3 Gray Water Drainage

A Double stack for soil (toilets, bidets & urinals) and waste (lavatories, showers, floor drain, Gray wastewater shall be provided in this project to collect the wastewater generated
service sink….etc.) with vent piping to prevent pressure fluctuation shall be provided to the from Showers, Lavatory, baths and floor drains, then to be discharged and gathered in
project as follows: gray water tank.

Vent piping, where called by codes, is provided to protect the system against loss of the trap Gray water tank shall be calculated based on 85% of total daily potable water demand and
seal. will be sufficient for one day storage.

All green area above building structure will be drained through planter drain and discharged Gray water tank over flow will be pumped and connected to external sewage network.
into the storm water tank.
Commercial Podiums:
All piping, fittings and pipe risers will be located in service shafts, which will be accommodated
Waste water pipes and stacks from commercial podiums will be collected into the Gray water
in the layout in view of easy accessibility and maintenance. All shafts will be provided with
tank to be treated, transfer to non-potable water tank and re-use it in the water closet (WC)
access doors/hatch.
flushing. Gray water tank has capacity 130 m³ enough for one day storage.
Drainage pipes, stacks…will be accommodated and suspended at the basement floor to gray
Residential Towers:
wastewater, storm water tanks and foul water sewage network.
Waste water pipes and stacks from residential towers will be collected into the Gray water
Clean out will be provided in every change of direction in the suspended pipes to ensure
tank to be treated, transfer to non-potable water tank and re-use it in the water closet (WC)
proper cleaning and maintenance of the system.
flushing & irrigation system with capacity 350 m³ enough for one day storage.
Inspection chambers/manhole shall be provided in every change of direction of the buried
piping system and in lower basement floor to minimize the cause and effect of any
consequential damage due to pipe clogging and to ensure accessibility for inspection and 2.6.4 Kitchen Drainage
maintenance.
A single kitchen waste stack for kitchens and F&B areas with vent piping to prevent
pressure fluctuation shall be provided to the project as follows:
2.6.2 Foul Sewage Drainage Commercial Podiums:
Foul sewage effluents produced through WC’s flushing will be collected through soil stacks A separate kitchen drainage pipes and stakes for commercial podiums (Service, Podium1
and pipes to be discharged in the external sewage networks. and ground floors) will be collected and connected directly to external sewage network
through separate grease interceptors located in reasonable area to facilitate inspection and
Commercial Podiums: maintenance.
A separate soil drainage pipes and stakes for commercial podiums will be connected
directly to external sewage network. Residential Towers:
A separate kitchen drainage pipes and stakes for residential Towers apartments and
Residential Towers:
podium-2 level will be collected and connected directly to external sewage network through
A separate soil drainage pipes and stakes for commercial podiums will be connected separate grease interceptors located in reasonable area to facilitate inspection and
directly to external sewage network. maintenance.

OWNER / DEVELOPER: LEAD CONSULTANT:


175
Grease interceptor shall be calculated as the table below: 2.6.6 Sump Pit and Sewage Pump

All sanitary fixtures and drains under road level will be drained to dedicated sump pits and
pumped as the following.
- Toilets drainage will be collected to sewage sump pits and pumped into external sewage
network through slow down chamber.
- All lift pit and pump rooms will be collected to sump pits and pumped into storm water tank
as per ASHGHAL requirement.

Minimum two submersible pumps will be provided as one duty + one standby each 100% of
the load and both working together in case of emergency.

Pump flow-rate shall be minimum (1.1 * Incoming flow rate)

Sum pit minimum effective volume will be calculated according to the equation below

Where:
Pump flow-rate [l/s]
Vh: necessary, minimum accumulated volume between start and stop.
Zmax: maximum number of starts per hour and should be specified by the
pump or motor manufacture.

Sump pit operation level control will be consisted of the following:


1. High level alarm
2. Pump no. 1 start
3. Pump no. 2 start
4. Pump no.1 stop
5. Pump no.2 stop
2.6.5 Parking Drainage 6. Low level alarm
Parking drains will be provided at all basements floor.
Inspection chamber/manhole will be provided in every change of direction of the buried 2.6.7 Swimming Pool Drainage and Backwash
piping system to minimize the cause and effect of any consequential damage due to pipe
clogging and to ensure accessibility for inspection and maintenance. Swimming pool and back wash will be drained separately from the building drain and will
be emptied by waste water tanker through tanker connection.
All parking drain will be collected into storm water tank through sump pits as per
ASHGHAL requirement.

OWNER / DEVELOPER: LEAD CONSULTANT:


176
2.6.8 A/C Condensate Drainage:
An individual condensate drainage waste stack for all A/C condensate shall be provided
to the project as following:

Commercial Podiums:
A separate condensate drainage pipes and stakes for commercial podiums will be collected
into non-potable water tank.

Residential Towers:
A separate group of stacks will collect from residential towers apartments and podium-2
condensate (a/c condensate) drainage pipes. They will be independent of any drainage and
waste system and will be accommodated to non-potable water tank

2.6.9 Storm Water Drainage


Rain water disposal system will comprise of roof drains outlets, open areas drains and
other associated accessories also.
The rainwater drainage will be designed based on the heaviest rainfall intensity of 50
mm/hr. & storm return period of 10 years
Separate rain water drainage network will be provided to collect water from all roofs
and open areas and will be conveyed to storm water holding tank then will be emptied
by tanker through tanker connection.
Sizing of horizontal and vertical storm water piping shall be in accordance to UPC Tables
11-1 and 11-2 (Metric) based on 50 mm/hr. rainfall rate.

OWNER / DEVELOPER: LEAD CONSULTANT:


177
2.6.9.1 Storm Water Flow Rate 2.7 Piping Materials
Estimated flow rate for storm water drainage shall be calculated based on equation
below
S/N Service Material
Storm water flow-rate = Storm water intensity x Projected area x Service rum off
coefficient Where:
Gravity Sewage External drainage uPVC/GRP pipes
Storm water intensity = 50 mm/hr. 1 pipes (Between man holes)
Service rum off coefficient as table below

2 Gravity Storm External drainage uPVC for pipe up to 160mm


pipes (Between man holes)
GRP for pipe greater than160mm
Concrete for diameter above 1000mm
Gravity Internal (sewage & uPVC pipes
3
storm) drainage pipes
HDPE Pressure pipes
4 Pressurized line

High temperature drainage


5 HDPE pipes
(Kitchen & Laundry)

6 Vent pipes uPVC pipes

2.6.9.2 Storm Water Tank Capacities


Storm water tank will be calculated based on the greater of the following:
- ASHGHAL requirement (390 m³ for each 10000 m2).
- As Per Rain water intensity
Two Storm water tanks will be located at basement-2 level with capacities of 915 m³
and 1015 m³.
Storm water tank will be emptied by waste water tanker through transfer pumps to
tanker connection

OWNER / DEVELOPER: LEAD CONSULTANT:


178
2.8 GRAY WATER TANK CALCULATION

COMMERCIAL PODUIMS GRAY WATER TANK (2nd BASEMENT ) :

Method -1 (As per ASPE)

Estimated no.of person (Commercial) 7582


Estimated to generate Liter/ day /person (Commercial) 3.8 ( 1 gallon / person )
Daily generated gray water (m3) = 28.8
No.of storage days = 1
Gray water storage tank (m3) = 28.8

Method -2 (As per percentage of potable water usage)

Daily potable water demand (m3) 152


Estimated to generate 85% daily potable water demand 130
No.of storage days = 1
Gray water storage tank (m3) = 129.5

Actual Gray water storage tank (m3) = 129.53847


Waste Water Treatment unit (m3/day) = 130

RESIDENTAIL TOWER GRAY WATER TANK (2nd BASEMENT ) :

Method -1 (As per ASPE)

Estimated no.of occupant ( Residential ) = 1850


Estimated to generate Liter/ day /person 95 ( 25 gallon / person )
Daily generated gray water (m3) = 175.8
No.of storage days = 1
Gray water storage tank (m3) = 175.8

Method -2 (As per percentage of potable water usage)

Daily potable water demand (m3) 403


Estimated to generate 85% daily potable water demand 343
No.of storage days = 1
Gray water storage tank (m3) = 343

Actual Gray water storage tank (m3) = 350


Waste Water Treatment unit (m3/day) = 350

OWNER / DEVELOPER: LEAD CONSULTANT:


179
2.9 STORM WATER TANK CALCULATION

TANK 1 TANK 2
CASE(1) As Per ASHGHAL (Vol. 8) CASE(1) As Per ASHGHAL (Vol. 8)
Total Project Area (m2) = 22494 Total Project Area (m2) = 19979
Total Project Area (ha) = 2.25 Total Project Area (ha) = 2.00
Storm water Storage Requirements (m3/ha) = 390 Storm water Storage Requirements (m3/ha) = 390
Requird total Storm water storage (m3) = 877.3 Requird total Storm water storage (m3) = 779.2

Storm water storage


Rainfall Intensity (mm/hr) = 50 Storm water storage
Rainfall Intensity (mm/hr) = 50
Total projected area(m2) = 22494
Total projected area(m2) = 19979
Service run off coefficient = 0.9
Service run off coefficient = 0.9
Duration of storage (hours) = 1
Duration of storage (hours) = 1
Required total Storm water storage (m3) = 1012.2
Required total Storm water storage (m3) = 899.1

Selected Storm Water Tank Selected Storm Water Tank

Actual total Storm water storage tank Capacity (m3) = 1015


Actual total Storm water storage tank Capacity (m3) = 915.0

OWNER / DEVELOPER: LEAD CONSULTANT:


180
OWNER / DEVELOPER: LEAD CONSULTANT:
181
OWNER / DEVELOPER: LEAD CONSULTANT:
182
OWNER / DEVELOPER: LEAD CONSULTANT:
183
OWNER / DEVELOPER: LEAD CONSULTANT:
184
OWNER / DEVELOPER: LEAD CONSULTANT:
185
OWNER / DEVELOPER: LEAD CONSULTANT:
186
OWNER / DEVELOPER: LEAD CONSULTANT:
187
MECHANICAL WORKS

WATER SUPPLY SYSTEM

OWNER / DEVELOPER: LEAD CONSULTANT:


188
3. WATER SUPPLY SYSTEM
3.2.3 Water supply pipe sizing

3.1 Codes and Regulations The sizing of water supply piping will be based on the demand weight of fixtures units
(WFU) in accordance with (IPC) Tables E103.3(2) & E103.3(3)
The water supply systems will be designed in accordance with the requirements of the
following codes and local regulation:
- Qatar General Electricity & Water Corporation KAHRAMAA,
- International Plumbing Code IPC,
- Uniform Plumbing Code UPC,
- National Plumbing Code Handbook,
- American Water Works Association,
- American Society of Plumbing Engineers,

3.2 Potable and Non-Potable Water Supply Systems Design Criteria


3.2.1 The water supply system will be designed to maintain the following maximum and
minimum pressures for the plumbing fixtures as the table below:

Min. pressure at water Max. pressure at water


Fixture outlet (bar) outlet (bar)

Faucets / Hand 1.0 3.0


spray
Shower head 1.0 3.0
Kitchens faucets 1.0 3.0
WC Flush tank 0.5 3.0
Hose Bibs 1.5 4.5

Maximum Uniform friction head loss shall be 66 kPa / 100m

3.2.2 The water supply system will be designed to maintain the following maximum design
flow velocity.
Maximum Design Flow Velocity (m/s)

Mains 2.4
Riser 2.0
Branche 1.5
s
OWNER / DEVELOPER: LEAD CONSULTANT:
189
OWNER / DEVELOPER: LEAD CONSULTANT:
190
3.3 Potable Cold Water System Description

3.3.1 General
The building will be supplied with fresh water from the municipality potable water Tower-A
network tie-in points through main water meters located at the plot boundary.
Two elevated potable water tanks will be provided for tower A, to supply the tower wet areas
The Water supply system shall be provided to the project as follows: as per following:

- Tower floors from roof until 10th floor through pressure boosting pumps with variable
Commercial Podiums: frequency motor set.

Main concrete potable water tank will be provided with capacity sufficient for 2 days of water - Tower floors from 9th floor until 1st floor through gravity line.
demand. The tank will be located on 2nd basement floor.
Pressure reducing valve PRV will be provided before sub meters to maintain the pressure less
Main potable water tank capacity will be approximately 310 m³. than or equal 3 bar for water meters accuracy.

The main potable water tank will be supplied the elevated water tanks through lifting pumps A dedicated water meters room in each floor level of the tower to serve each
as the following: apartment.

- Commercial Podiums elevated water tank located at service floor.

- Elevated water tanks will be adequately sized for water storage for a minimum period Tower-B
of 1 day.
Two elevated potable water tank will be provided for tower B, to supply the tower wet areas
as per following:

Residential Towers: - Tower floors from roof until 10th floor through pressure boosting pumps with variable
frequency motor set.
Main concrete potable water tank will be provided with capacity sufficient for 2 days of water
demand. The tank will be located on 2nd basement floor. - Tower floors from 9th floor until podium-2 floor through gravity line.

Main potable water tank capacity will be approximately 810 m³. Pressure reducing valve PRV will be provided before sub meters to maintain the pressure less
than or equal 3 bar for water meters accuracy.
The main potable water tank will be supplied the elevated water tanks through lifting pumps
as the following: A dedicated water meters room in each floor level of the tower to serve each apartment

- Tower-A elevated water tank located at roof floor.

- Tower-B elevated water tank located at roof floor.

- Tower-C elevated water tank located at roof floor.

Elevated water tanks will be adequately sized for water storage for a minimum period of 1
day.

A constant speed transfer pumps set will be provided at main water tank pump room to fill the
elevated water tanks from main potable water tank at 2nd basement within 8 hours.

OWNER / DEVELOPER: LEAD CONSULTANT:


191
Tower-C

Two elevated potable water tank will be provided for tower C, to supply the tower wet areas 3.5 Water Hammer Arrestors
as per following:
Water hammer arrestors are required to prevent the effect of water hammering.
- Tower floors from roof until 10th floor through pressure boosting pumps with variable
frequency motor set. Water hummer arrestor will be provided between the quick shut-off valve or faucet and
the incoming water supply.
- Tower floors from 9th floor until 1st floor through gravity line.

Pressure reducing valve PRV will be provided before sub meters to maintain the
pressure less than or equal 3 bar for water meters accuracy. 3.6 Automatic Air Vent
A dedicated water meters room in each floor level of the tower to serve each apartment Automatic air vents will be provided for each water supply riser to prevent air binding
during filling operation and allow the continual release of air during normal operation.

3.3.2 Water tanks cooling system


3.7 Hose Bib
Water temperatures in elevated water tanks should always be kept at 28 °C or less to
prevent the colonization of Legionella bacteria and for user comfort. Provide hose bib in mechanical rooms, loading dock, garbage room, parking (if
required), roof and commercial kitchen for cleaning purpose. All hose bibs to be feature
Chilled water with heat exchanger will be used to decrease the water temperature based
integral vacuum breaker
on the following parameters.

Cooling down period = 24 hour

Initial water temperature = 40 °C

Desired water temperature = 28 °C

3.3.3 Potable Water Filtration System

Multimedia filters will be provided on the feeding line at each elevated water tank to filter
the domestic water from any particles or impurities can effect on the people health.

3.4 Piping and Valves


Valves will be installed for each feeding and return pipe. Control valves are wedge-gate
type and constructed so that they could be repacked while open and under pressure.
Each riser is provided with a riser control valve and a drain valve. Each toilet area is
provided with group valves.

OWNER / DEVELOPER: LEAD CONSULTANT:


192
3.8 Non-Potable Water System Description ( subject to GSAS assessment ) 3.8.2 Gray Water Treatment System Components

3.8.1 General: - The treatment process involves

Non-potable water system shall be provided to this project and it shall be subjected to GSAS - Flow Equalization
assessment. - Settling
The non-potable water system can be described as the treated gray wastewater to - Chlorination
produce water which can be used for irrigation and W/C flushing as well.
- Filtration
Gray water treatment plant will be provided to treat gray wastewater which collected
from wash basins, floor drains, bathtubs and showers. 3.8.3 Flow Equalization

Waste water will be collected in grey water tank and then is drawn by grey water feed The tank which receives raw grey wastewater generated from bathtubs, showers and
pump then treatment process is applied through the grey water treatment plant. And wash basins in the Raw Grey Water Collection Tank.
After treatment, the water will be stored in non-potable water tank. The Raw grey waste water is collected to dampen the variation in hydraulic & organic
load. Odor control dosing is given in to it to prevent the smell.
The wastewater is kept in Agitated condition to avoid settling of suspended solids along
with acid dosing to maintain the pH Value. Air is injected through submersible aerators in
the aeration tank.
Sodium hypochlorite solution is dosed in the chlorine contact tank then to the Final
settling tank. The aerated / settled grey wastewater is pumped into the media / carbon
Filters via the Filter Feed/ back wash Pumps. Level switches actuate the pumps.
3.8.4 Coagulant Dosing

Coagulant dosing system is considered as, in order to form the better flocs, which can be
easily separated in the Media filters. This improves the efficiency of media filters in
removal of suspended impurities
3.8.5 Automatic Multimedia Filter

The filtered water then passes through the Multimedia Filter before passing through
Activated Carbon Filter. As solids accumulate in the sand bed the pressure loss through
the Media rises & periodically reaches a value above which the plant will not further as
Designed. At this time the filter needs to be backwashed clear of accumulated solids. The
Media is backwashed by controlled flow of tertiary waste water delivered from the Treated
Grey Waste Water Tank by using the back wash pumps. The backwash water is sent to
the Drain.
3.8.6 Automatic Activated Carbon Filter

The effluent of the Multimedia Filter then passes through a bed of Activated Carbon.
The Porous carbon media having large surface area helps in absorption of dissolved
organic Matter on the surface
Provision is made for backwashing of filter media to limit head loss build up due to
Accumulation of suspended solids. The backwash water is sent to the drain.

OWNER / DEVELOPER: LEAD CONSULTANT:


193
3.8.7 Post-Chlorination 3.9 Hot Water Distribution System
The filtered water is then collected in the final water tank and dosed with Sodium A hot water system is an essential building service used for washing, cleaning,
Hypochlorite (10% chlorine) for further removal of organics & disinfections controlled. cooking, and so on. It requires energy to heat water, and the type of hot water system
installed in a building has a direct impact on its energy consumption.
The main design considerations are the electrical or fuel type that will be used, whether
the hot water will be generated locally or centrally.
3.8.8 Non-Potable Water System Description
Sizing of hot water piping shall be based on the demand weight of fixtures, same way as
Commercial Podiums:
cold water piping.
A dedicated non-potable water tank at basement-2 with capacity sufficient for 2 days of
non- potable water demand with total capacity of 150 m³.
The non-potable water tank will be supplied from the following: Hot Water Distribution System shall be provided to the project as follows:
- Treated gray water through treatment unit.
- Makeup line from municipality potable water network through non-potable water Commercial Podiums:
meter.
Individual electric water heaters will be used to supply required hot water to all fixtures
- HVAC unit’s condensate drainage. through all wet areas in the retails, public toilets and tenancy areas (F&B’s, Hyper
The main non-potable water tank will supply the elevated non-potable water tanks through market, FEC, Cinema, …etc.).
lifting pumps
Hot water supply will be at temperature of 60⁰C
Elevated non potable water tanks will be adequately sized for water storage for a minimum
period of one day located at service floors for commercial podiums (service, podium-1,
ground & basement floors)
Residential Towers:

Residential Towers: Option -1 (Individual Water Heaters):


A dedicated non-potable water tank at basement-2 with capacity sufficient for 2 days of non-
potable water demand in addition to one day storage of required irrigation water with total Individual electric water heaters will be used to supply required hot water to all fixtures
capacity of 480 m³. The tank will be located at 2nd basement floor. through all wet areas in the residential apartments.

The non-potable water tank will be supplied from the following: Hot water supply will be at temperature of 60⁰C
- Treated gray water through treatment unit.
- Makeup line from municipality potable water network through irrigation water meter. Individual hot water heaters will be provided for Pool & GYM toilets at podium-2 level,
Branch Lines (lines that run from the recirculation loop to the fixture) will be the shortest
- HVAC unit’s condensate drainage. possible length from the recirculation loop to the fixture outlet with a maximum distance
The main non-potable water tank will supply the elevated non-potable water tanks through of 15 meters.
lifting pumps.
Balancing valves shall be provided for all hot water circulating line.
Elevated non potable water tanks will be adequately sized for water storage for a minimum
period of one day located at roof floors for each residential towers

OWNER / DEVELOPER: LEAD CONSULTANT:


194
Water Heater Schedual For Commercial Podiums :

Water Heater Schedual For Residentail Towers :

TOTAL Fixture Count EWH-CAPACITIES/POWER TOTAL NUMBER OF EWH


Unit Type NUMBER OF No. Of Toilets No. Of KITCHEN ( PER EACH AREA )
UNITS 30 LIT 50 LIT 80 LIT 30 LIT 50 LIT 80 LIT
LAV KS SH 1.2 KW 1.5KW 1.5KW 1.2 KW 1.5KW 1.5KW

1-BR 346 2 1 1 1 1 1 2 - 346 692 -

2-BR 296 3 1 1 1 1 1 3 - 296 888 -

3-BR 52 4 1 1 1 1 1 4 - 52 208 -

3-BR( DUPLEX) 2 4 1 1 1 1 1 4 - 2 8 -

TOTAL NUMBER OF EWH 696 1,796 -


TOTAL POWER LOADS ( KW ) 835 2,694

OWNER / DEVELOPER: LEAD CONSULTANT:


195
Option - 2 (Central Hot Water Boiler):

Two water tube gas type boilers will be provided for the building, each boiler will be
sufficient for 75% of total heating load.

A Group of calorifiers at roof level will be provided to supply each residential tower.

The hot water storage tanks (Calorifiers) will be heated via hot water boilers located at roof
floor for each tower.

Pressure zoning by using a separate hot water calorifiers for group of floors and PRVs will
be provided to maintain the pressure less than or equal 4.5 bar at any point in the system

Hot water will be circulated at minimum temperatures 50°C to prevent the colonization of
Legionella bacteria.

Valves will be installed for each feeding and return pipe. Control valves are wedge-gate
type and constructed so that they could be repacked while open and under pressure.

Hot water calorifiers will be equipped with positive means of safety devices (pressure
release valve which shall be connected to the nearest drain point) that guard the system
against dangers of excessive pressure and temperature.

The following table per ASHRAE shall be used to determine hot water demand:

Hot Water Boiler and Calorifiers Schedual For Residentail Towers :

Option-2 Central Hot Water Boiler


Calorifiers
Selected Calorifiers
BLD. H.W Storage (Litre) H.W Power (KW)
No. Of UNITS Capacity-Each (Litre) Total Thermal Power (Kw)
Tower A 11615 337.2 4 3000 338
Tower B 16784 487.2 5 3500 488
Tower C 11615 337.2 4 3000 338
Podium 2 4318 278.5 1 4500 279
Total Thermal Power Required 1443

Boiler
No. of UNITS Thermal Power - Each (KW) Total Gas consumption (m3/hr)
2 1024 178

OWNER / DEVELOPER: LEAD CONSULTANT:


196
3.10 Metering Strategy 3.11 Piping Material
Potable Water:
S/N SERVICE Piping Material
Main Water Meters for potable water will be provided at the tie-ins within the plot boundary on
Cold water supply connection to
the main feeding line to fill the main water tanks located at basement-2 floor.
water tank/and tanker fill lines and
1 HDPE
Sub water meters will be provided at the building as per following: suspended in basement floor
2 Cold water supply riser inside ducts HDPE
Commercial Podiums:
Cold water, hot water and hot water
Separate potable water meter shall be provided for each rentable area.
return pipes at the roof or exposed Insulated PPR
A dedicated Water meters room shall be provided in podium-1 and ground floor to serve the 3
to sun radiation
commercial areas.
Internal cold water supply pipes
Residential Towers: above false ceiling or impeded in
4 PP-R
wall etc.
Separate potable water meter shall be provided for each apartment.
External water supply pipe
A dedicated Water meters room shall be provided in each floor in accordance with the 5 HDPE
(underground)
requirements of KAHRAMAA
6 Pump Rooms Ductile iron
7 Hot water supply riser inside ducts CPVC
Non-Potable Water:
Internal hot water and hot water
Commercial Podiums: return pipes above false ceiling or CPVC
8
impeded in wall etc.
Separate non-potable water meter shall be provided for each rentable area.
Non-potable water meters shall be located at the same potable water meter room and
connected to building billing system.

Residential Towers:
Separate non-potable water meter shall be provided for each apartment.
Non-potable water meters shall be located at the same potable water meter rooms or at
the entrance of each apartment and shall be connected to building billing system.

Central Hot Water System:

Residential Towers:
Separate Hot water meter shall be provided for each apartment in case of using central hot
water system by gas boilers.
Hot water meters shall be located at the same potable water meter rooms or at the
entrance of each apartment and shall be connected to building billing system.

OWNER / DEVELOPER: LEAD CONSULTANT:


197
3.12 Irrigation System 3.13.4 Main drain pipes:

3.12.1 System Description • Design capacity of the main drain line shall be 100% of the pumps flow rates.

Landscape green areas will be provided with automatically controlled irrigation system. • Main drain pipe sizing shall be based on the min. velocity of 0.75 m/s and design
It will be divided into zones in order to irrigate the whole site in one day. velocity of 1.25 m/s.

The system will be provided with booster pumps, central controller, solenoid valves, 3.13.5 Main drain points:
sprinkles, bubblers, emitters and miscellaneous appurtenances for a complete
automatic operation network • Design capacity of the main drain points shall be 100% of the pumps flow rates.
Non-potable water tank will be the water source for the irrigation system. • The velocity through the main drain points shall not exceed 0.305 m/s
3.12.2 Piping Material • Drain points shall be spaced max. 9.2 m apart and max 4.6m from wall.
Material will be UPVC pressure pipes to BS 3505:1986, Class “E” and fittings will be
solvent welded to BS 4346, the lock ring type. 3.13.6 Vacuum cleaning points:

• Vacuum cleaning outlets shall be located so that a max. Of 15 m hose is used.

3.13 Swimming Pools 3.13.7 Surge chamber (balance tank):


Two swimming pools will be provided in the project, one main pool and one • Average displacement per bather shall be 0.63 m³
kid's pool, the pool shall be located at podium 2 level floor.
3.13.8 Chemistry:
The swimming pools design shall be as follows:
• PH range shall be from 6.5 to 8.5 and O2 range from 1.5 to 2 PPM.
3.13.1 Filtration system:
3.13.9 Pool cooling:
• The turnover rate in the filtration system shall be once every 4 hrs.
• The max. Cooling down duration shall be 48 hrs.
• The high flow rate pressure sand filter shall be used.
• The desired pool temperature shall be 28 C.
3.13.2 Inlet network:
• The pool will be cooled via chilled water through heat exchanger.
• Floor inlets shall be spaced less than 6 m apart and within 1.5 m from corner.

• Inlet network pipe sizing shall be based on the Velocity of 1.5 m/s.

3.13.3 Overflow network:

• Design capacity of the main gutter line shall be 100% of the pumps flow rates.

• Outlet points shall be spaced max. 4.6 m.

• Outlet network pipe sizing shall be based on the min. velocity of 0.75 m/s and design
velocity of 1.25 m/s.

OWNER / DEVELOPER: LEAD CONSULTANT:


198
3.14 Water Fountains :
Water fountains will be provided in the project main entrance at site layout, and the
design shall be as follows:

3.14.1 Fountain Basin:

The size and shape of a pool can be determined by the fountain effects or, the fountain
effect may be designed to fit the pool. Water depth should be no more than 300mm to
avoid the water feature to be classified as a swimming pool with all the requisite fencing
legislation

3.14.2 Fountain Nozzles & Fittings:

It is a general rule of thumb that the water feature effect height is the equivalent of half
of the radius of the pool. Some jets require a non-turbulent water supply in order to work
properly. Others require wave suppression when installed in circular pools in order to
prevent wave amplification

3.14.3 Fountain Pumps:

Pumps for water features are selected based on water and pressure requirements for
the combined fountain effects. Submersible pumps or dry pumps are available for use on
fountains. Dry pumps should be equipped with suction strainers.

3.14.4 Overflow drains:

Overflow drains can remove excess water brought on by rainfall or accidental overfilling
of the fountain. Overflow drains have two functions; they provide a means for removing
water in case water makeup should malfunction and they provide a means for removing
storm water. The preferable location for an overflow drain is in the wall of the pool where
it can be hidden. All overflow drains are designed to prevent large debris from clogging
the drain pipe.

OWNER / DEVELOPER: LEAD CONSULTANT:


199
3.15 WATER SUPPLY SYSTEM CALCULATIONS

3.15.1 Daily Water Requirements

Estimated number of person and daily water demand according to KAHRAMAA


requirement.

Estimated No. of
Estimated No. of Occupants: Water consumption
Occupants
Commercial (No. of Occupants)-Staff 1896 60 / stuff
Commercial (No. of Occupants)-Visitor 5686 20 / visitor
Residential (No. of Occupants) 1850 300 / person
Podium 2 (No. of Occupants)-Staff 389 60 / stuff
Podium 2 (No. of Occupants)-Visitor 1168 20 / visitor

Estimated potable and non-potable water demand will be calculated based on the
following:

Potable water daily demand = 67% of total daily water demand

COMMERCIAL PODUIMS POTABLE WATER TANK (2nd BASEMENT ) :


% of Total water demand = 67%
Daily potable water requirement (m3) application Podiums = 152
No. of storage days = 2
Req. potable water storage tank (m3) = 305
Actual Potable water storage tank (m3) = 310

OWNER / DEVELOPER: LEAD CONSULTANT:


200
3.15.2 Potable Water System Calculations

Water Daily Requirements For Commercial Podiums

Potable and non-potable


NO .of Total domestic water
Estimated No. of Occupants: No. Of Persons water consumption
Apartments /Area consumption
(l/day/capita)

GROUND 13485 Staff ( 25% total number of persons ) = 1108 60 66480


Visitors ( 75% total number of persons ) = 3323 20 66460
1ST PODUIM 8697 Staff ( 25% total number of persons ) = 788 60 47280
47260
Visitors ( 75% total number of persons ) = 2363 20
Total Water Daily Requirements For Commercial Podiums lit / day 227480
m³ / day 227.48

Water Daily Requirements For Towers


Potable and
NO .of non-potable
Estimated No. of Occupants: Apartment No. Of Persons water Total domestic water consumption
/AREA consumption
(l/day/capita)
Service apartment ( 1-BR) 346 2 300 207600
Service apartment ( 2-BR) 296 3 300 266400
Service apartment ( 3-BR) 52 5 300 78000
Service apartment ( 3-BR DUPLEX) 2 5 300 3000
2ND PODUIM 9098.36 Staff ( 25% total number of persons ) = 389 60 23340
Visitors ( 75% total number of persons ) = 1168 20 23360

Total Water Daily Requirements For Towers l / day 601700

m3 / day 601.7

TOWER POTABLE WATER TANK (2nd BASEMENT ) :


% of Total water demand = 67%
Daily potable water requirement (m3) application Towers = 403
No. of storage days = 2
Req. potable water storage tank (m3) = 806
Actual Potable water storage tank (m3) = 810

OWNER / DEVELOPER: LEAD CONSULTANT:


201
3.15.3 Non Potable Water System Calculations

Estimated potable and non-potable water demand will be calculated based on the
following

- Non-Potable water daily demand = 33% of total daily water demand

RESIDENTAIL TOWER NON-POTABLE WATER TANK (2nd BASEMENT ) :


% of Total water demand = 33%
Daily non-potable water requirement (m3) application A = 198.5
No.of storage days = 2
Non potable water storage req. (m3) = 397

Total Non-Potable Water Tank =Non-potable water requirement application A (2 Days Storage)+ Irrigation water requirement((1 Day Storage))

Daily irrigation water demand (m3) = 80.0

Req. potable and irrigation water storage tank (m3) = 477


Actual Non Potable water storage tank (m3) = 480

COMMERCIAL PODUIMS NON-POTABLE WATER TANK (2nd BASEMENT ):

% of Total water demand = 33%

Daily non-potable water requirement (m3) application A = 75

No.of storage days = 2

Non potable water storage req. (m3) = 150

Actual Non Potable water storage tank (m3) = 150

OWNER / DEVELOPER: LEAD CONSULTANT:


202
PLUMBING SYSTEM PROPOSED PROVISIONS:

COLD WATER HOT WATER DRAINAGE


Function
CENTRAL HOT WATER
POTABLE NON-POTABLE INDVIDUAL GRAY WASTE FOUL WASTE KITCHEN WASTE
BOILER ( OPTIONAL )

COMMERCIAL PODIUMS

Entrance & Reception - - - - - - -

Mall Lobby - - - - - - -

Shops - - - - - - -

Administration Offices - - - - - - -

Hypermarket √ - √ - √ - √

Garbage Rooms √ - - - √ - -

Public Toilets √ √ √ - √ √ -

Swimming Pool Toilets & Showers √ √ √ √ √ √ -

Food And Beverage (F&B) √ - √ - √ - √

Spa √ √ √ √ √ √ √

Male Gym √ √ √ √ √ √ √

Female Gym √ √ √ √ √ √ √

CAFÉ √ - √ - √ - √

PANTRY √ - √ - √ - -

Mechanical room √ - - - √ - -

Pump room √ - - - √ - -

WORKSHOP - - - - - - -

FEC(family entertainment center) √ √ √ - √ √ -

Food Court - - - - - - -

Bowling - - - - - - -

Cinema √ √ √ - √ √ -

Dinning √ - √ - √ - √

Corridors - - - - - - -

Service - - - - - - -

OWNER / DEVELOPER: LEAD CONSULTANT:


203
Mall Common Area - - - - - - -

FCC & First Aid - - - - - - -

ELEC ROOM - - - - - - -

IDF ROOM - - - - - - -

TELECOM ROOM - - - - - - -

GSM ROOM - - - - - - -

CCTV ROOM - - - - - - -

PRAYER ROOM - - - - - - -

ANCHOR STORE - - - - - - -

STORE - - - - - - -

RESIDENTAIL TOWERS
Tower A apartments from (1-12)Floor √ √ √ √ √ √ √

Tower A 2nd Podium Floor √ √ √ √ √ √ √

Tower B apartments (1-12)Floor √ √ √ √ √ √ √

Tower B 2nd Podium Floor √ √ √ √ √ √ √

Tower C apartments (1-12)Floor √ √ √ √ √ √ √

Tower C 2nd Podium Floor √ √ √ √ √ √ √

OWNER / DEVELOPER: LEAD CONSULTANT:


204
OWNER / DEVELOPER: LEAD CONSULTANT:
205
OWNER / DEVELOPER: LEAD CONSULTANT:
206
OWNER / DEVELOPER: LEAD CONSULTANT:
207
OWNER / DEVELOPER: LEAD CONSULTANT:
208
OWNER / DEVELOPER: LEAD CONSULTANT:
209
MECHANICAL WORKS

FIRE FIGHTING SYSTEM

OWNER / DEVELOPER: LEAD CONSULTANT:


210
4. FIRE FIGHTING SYSTEM

4.1 Codes and Regulations


4.4 Fire Protection Systems versus space name.
The following codes and standards shall be used for the design of firefighting systems:
The firefighting system consists of the following:
NFPA National Fire Protection Association

QCDD Qatar Civil Defense Department Space Name System type

4.2 General Description All normal usage areas (except Transformer, Wet sprinkler system
Electrical, & TEL rooms, etc.).
The fire protection system will be designed in accordance with the National Fire
Protection Association NFPA and the local fire safety code and will mainly consider the All normal usage areas. Wet riser system supplying water to the
following: various landing valves and hose reels.

The project is overall classified as Ordinary Hazard for basement and mechanical floors,
extra hazard for fire pump room and light hazard for the rest as per NFPA regulations. All normal usage areas. Fire hose cabinets complete with hose reel,
The whole project is protected by water suppression system include fire hose cabinet, fire extinguisher and landing valve.
sprinkler system in addition to the fire extinguishers where required.
All normal usage areas. Portable fire extinguishers, dry powder as
System shall be hydraulically sized using software “Fire Elite” for most remote area and per specific area requirements.
most demand.

A total flooding system shall also be used where needed. An adequate water reserve is GSM & Telecom rooms FM-200
provided to feed the system.
Generator and fuel rooms. Foam System.
Siamese connection will be providing and coordinated with local civil defence
department.
Sub-station rooms. Aerosol
Four way Connections will be provided as per NFPA14 requirements
Electrical rooms more than 5.1m2 Automatic Sprinkler System

Main kitchen hood Fixed wet chemical suppression system


4.3 System operation
Fire water will be supplied from the main KAHRAMAA water line and then will be stored LV FIRE RATED 3 HRS ( PFE )
in fire water tanks located in the first basement and then after water will be sucked by
using fire pumps and discharged into main headers. Note: Pressure regulators shall be provided where specified pressure more than
12.1 bar for all FHC, landing valves and zone control valves.

OWNER / DEVELOPER: LEAD CONSULTANT:


211
4.5 Wet sprinkler system 4.5.3 Design criteria and occupancy classification.

The wet sprinkler system shall be designed based on the following data:
4.5.1 General

Wet sprinkler system protection will be provided throughout the building in all normal
usage areas.

The system is designed in accordance with NFPA-13, "Wet Type" with sprinklers zones
controlled by multiple main valves. The sprinkler heads will be of the correct type and
temperature rating for each location and will be provided. Where required with metal
guards to prevent accidental damage.

Concealed type sprinklers to be used in all area with false ceiling to maintain an
ecstatic interior look.

Multiple sprinkler types are used in the project, depending on protected area, and raging
form exposed, pendent, upright, Wall hung extended coverage and decorative sprinklers.

4.5.2 System components

The system is complete with all necessary:

4.5.2.1 Piping networks,

4.5.2.2 Sprinklers heads,

4.5.2.3 Pumps (combined system),

4.5.2.4 Float switches,


4.5.4 Fire pump System
4.5.2.5 Control valves,
One Fire pump set will be provided. The set it will be one pump electrically operated
4.5.2.6 Drain and test valves, Etc. while the other pump diesel operated for emergency cases.

One Jockey pump will be provided to pressurize the sprinkler system serving the
building. Main fire and Jockey pump will be located in the main plant room close to the
storage water tank in the first basement.

OWNER / DEVELOPER: LEAD CONSULTANT:


212
4.6 Wet Standpipe System 4.6.4 Estimated water Demand.

The water demand for fire protection in the building will be calculated hydraulically and
4.6.1 General the storage tank will be sized based on 1st fire scenario (Fire Pump Room Sprinklers) for
90 minutes’ storage.
The standpipe system comprises of a Wet Class I, II & III installation as defined in NFPA
14. Fire pumps will be sized to provide 6.9 bars at the farthest landing valve. The pump in
will be sufficient to deliver 1000 gpm.
The standpipes provide water for the sprinkler installation at each floor level and will also
serve hose reels and landing valves for building, Occupant use No part of the buildings System will be designed to have a max of 12.1 bar pressure at any branch serving a
will be farther than 30 m from a hose reel and 38 m from landing valve. sprinkler system.

4.6.2 System components 4.6.5 Fire Hose Cabinets


The system is complete with all necessary: Fire hose cabinet (FHC) shall be distributed though out the project to provide the
protection area of 30m walk distance as required by NFPA-14.
- piping networks,
FHC-III: Each fire hose cabinet shall include;
- Pumps (combined system),
1" Fire hose: 100ft long Hose reel, with 1 1/2" nozzle, 21/2" landing valve and 6 kg dry
- hose cabinets and valves fire extinguisher.

- float switches, • Fire Hose Stations will be selected to cover all areas using 30 meters’ length and
25 mm diameter hose
- Control valves,
• Fire Hose Cabinets class III and landing valves Ø63 mm (2 1/2'') (Dry / Wet) shall
- Drain and test valves, Etc. be located in order of priority according to QCDD requirements for fire brigade
usage:
4.6.3 Class I and Class III Systems.
1- Within a fire-fighting lobby.
For Class I and Class III systems, the minimum flow rate for the hydraulically most
remote standpipe shall be 500 gpm (1893 L/min), through the two most remote 21⁄2 in. 2- In a smoke-stop lobby or common lobby in close proximity to the exit staircase.
(65 mm) outlets. The minimum flow rate for additional standpipes shall be 500 gpm (1893
L/min) 3- Where firefighting lobby, smoke-stop lobby are not provided, landing valve to be
located in each exit stairway.
For the second standpipe and 250 gpm
(946 L/min) for the third standpipe per
standpipe for buildings with floor areas
that exceed 80,000 ft2 (7432 m2) per floor.

Flow rates for combined systems shall be


in accordance with NFPA 14 item number
7.10.1.3. Minimum water pressure at
farthest landing valve will be 6.9 bars as
per NFPA 14.

OWNER / DEVELOPER: LEAD CONSULTANT:


213
4.6.6 Siamese Connection 4.7.2 System Description

Siamese connection are installed at a convenient height from finished side walk level The automatic clean agent system shall include the following:
and shall be chrome plated extra heavy cast brass complete with the following:
• Agent cylinders with electrical or pressure operated valves
- 6" x 2 1/2" x 2 1/2" x 2 1/2" x 2 1/2" (150x65x65x65x65 mm) Siamese connection with
drain cock and check valves to suit local practice. • Flexible hose

- All chains, caps and screws used for fixing. • Discharge header

- Recessed wall box housing the Siamese connection with wired glass door marked in • Piping network including pipes, fittings and supports.
red from inside: "FIRE BRIGADE CONNECTION" in both English and Arabic.
• Discharge nozzles
4.7 Clean Agent Fire Extinguishing Systems • Supervisory pressure switch

4.7.1 General • Manual pull station

The systems shall consist of agent storage cylinders permanently connected to fix piping • Abort switch
by sectional valves to reduce cost of the system, with fixed nozzles arranged to discharge
the suppression agent within the protected room. The systems shall be designed for • Heat and smoke detectors
automatic operation using suitable detectors and for manual operation using a manual
• Electronic sounder
pull station fixed at each room exit. Walls surrounding protected areas shall be extended
full height. • Control panel (release panel)
The system shall utilize the FM-200 as the clean extinguishing agent. The system shall • Necessary wiring
be designed as per the requirements of NFPA 2001.
• Sectional Valves
Each system shall consist of main and reserve cylinders, nozzles, control system and
piping network of galvanized seamless steel schedule 40.
4.7.3 Design Criteria
In a major project. This system does not cause any damage to equipment in all areas
mentioned above; it deploys quickly and cleanly and won't leave behind oily residue, The clean agent systems shall be designed based on the total flooding method with a
particulate, or water. minimum concentration of 7%.

FM-200 fire suppressant is safe when used where people are present.

OWNER / DEVELOPER: LEAD CONSULTANT:


214
4.8 Foam Fire Protection System

4.8.1 General 4.8.2 Foam system Design Criteria

Foam deluge and foam sprinkler systems are utilized to protect specialist risks involving
the storage and handling of flammable and combustible liquids.
Type of Foam Concentrate Application Rate
Areas to including generator and fuel room firefighting foams suppress fire by forming a
blanket across the surface of the liquid fuel and separating it from the air (oxygen) that it AFFF 0.1 gpm/ft2 (4.1 lpm/m2)
needs to burn.

In addition to smothering the fire the foam blanket also cools the fuel and suppresses the Fluoroprotein 0.16 gpm/ft2 (6.5 lpm/m2)
release of flammable vapors Foam system shall be designed as per (NFPA) 16 –
Standard for Low, Medium and High Expansion Foam.
Protein 0.20 pm/ft2 (8.1 lpm/m2)
A low expansion foam firefighting system shall be installed for generator room which will
be used is a fixed proportioning system permanently piped to monitors of fixed spray
nozzles strategically located around the landing pad.

4.9 Fire Extinguisher System


The extinguishers are additional to and complementary with the hose reel system and
are intended for containing very small outbreaks of fire, or small outbreaks of fire in areas
where discharging water from a hose reel would be hazardous.

All-purpose dry powder extinguishers are provided. The dry powder will be all purpose
type able to extinguish electrical, paper, wood and textile type fires.

Positioning of the extinguishers is important and care will be taken to ensure that a
person intending to use an extinguisher will not be brought into a "dead-end" situation
where escape from a fire would be difficult. The extinguishers will be located on or close
to escape routes. Generally, the dry powder extinguishers will be located within hose reel
recesses to make a complete fire-fighting package.

All extinguishers will have the operating instructions prominently displayed on the
extinguisher body in English and Arabic.

All extinguishers are finished in color applicable to their contents.

OWNER / DEVELOPER: LEAD CONSULTANT:


215
4.10 Dry Powder Fire Extinguisher 4.12 Aerosol Protection System
Portable dry chemical fire extinguishers located in all floors and car park area Aerosol Fire Extinguishing System is designed as a safe & practical alternative to Halon,
Halocarbons, Chemical Powders and Inert Gases.
All-purpose Dry Powder type fire extinguishers are as described in the NFPA 10.
Aerosol is an inert non-toxic solid that remains stable until electrically or thermally
Discharge of the dry powder will be accomplished by a rechargeable cartridge built into activated, where upon it produces a gas-like extinguishing aerosol.
the extinguisher. The discharge will be controlled by a nozzle on the end of the discharge
hose and will be initiated by striking a readily accessible knob or striker on the Aerosol attacks the fire chemically and physically, giving virtual instant extinguishment &
extinguisher. The knob or striker will have a protection cap to avoid accidental discharge. preventing re-ignition, and in certain instances, explosions.

Aerosol has been certified as having Zero Ozone Depleting Potential (ODP) & Zero
Global Warming Potential (GWP). It is officially listed by the US Environmental Protection
The extinguishers will contain approximately 6 kg (13 lb.) weight of Authority under its Halon replacement ‘Significant New Alternatives Program’ (SNAP).
all-purpose dry powder, will have a discharge time of approximately
10 seconds and will have a discharge jet with a range of Aerosol system shall be used in electrical rooms, control rooms and all relevant areas.
approximately 6m.

The fire extinguishers are distributed thru out the building to provide
a maximum walking distance of 77ft form any locations as per NFPA-
10.

4.11 Wet chemical fire suppression System


Wet chemical fire suppression system shall be used at kitchen hood system.

The system will be design and installed as per NFPA and specialist recommendation.

4.13 Outline Specification


Fire water Pipes are seamless galvanized steel pipes and fittings (50mm and smaller
diameter), Seamless black steel pipes and fittings (65mm and larger) with Victaulic
coupling and flanged fittings (inside pump room). Pipes are installed in such a way that
all parts of the system may be drained. Ready removable fittings are provided at the end
of the cross mains for the system flushing.

Fire extinguishers will be wall mounted, 4.5 kg dry chemical, where required.

Fire hose cabinets will be provided with swinging type, 25mm diameter, and 30m length
hose.

Fire pumps and equipment shall be approved by factory manual research (FM) and
underwriter

OWNER / DEVELOPER: LEAD CONSULTANT:


216
4.14 FIRE WATER TANK CALCULATION

1st Scenario (Fire pump room sprinklers)

Fire pump flow = 750 gpm

Duration of storage (min) 90 min

Fire water storage (gallons) 67500 gallons

Fire water storage (m³) 255 Cubic meter

Actual Fire storage tank (m3) 260 Cubic meter

2ND Scenario (Fire pump room sprinklers)

Fire pump flow = 1000 gpm

Duration of storage (min) 60 min

Fire water storage (gallons) 60000 gallons

Fire water storage (m³) 227 Cubic meter

Actual Fire storage tank (m3) 260 Cubic meter

OWNER / DEVELOPER: LEAD CONSULTANT:


217
FIRE FIGHTING ZONES

OWNER / DEVELOPER: LEAD CONSULTANT:


218
OWNER / DEVELOPER: LEAD CONSULTANT:
219
MECHANICAL WORKS

SYNTHETIC NATURAL GAS

(SNG) SYSTEM

OWNER / DEVELOPER: LEAD CONSULTANT:


220
5. SYNTHETIC NATURAL GAS (SNG):
Synthetic natural gas design shall be in accordance with local regulation and subject to 5.3 System General Description
MARAFQ and QCDD approval.
General principles for the piping routing inside and between buildings are following:
5.1 Introduction The route and location of the pipe work shall minimize the risk of damage caused by third
party, mechanical impact; UV exposure, accelerated corrosion, chemical attack, extreme
The objective of this Building Internal Gas Piping Design and Installation Guidelines is to
temperatures, building movement, lightning etc. or additional safety measures shall be
define and implement
applied.
a standard and identical design and installation approach for the SNG Gas System that
The route of the pipe work shall be as short as practicable and the number of joints kept
to be interface between Lusail City Gas Network Distribution System and Gas Utilization
to a minimum. Piping shall not be placed in locations where it would prejudice egress
Systems.
from a building in an emergency, or interfere with any emergency response.

5.2 Codes and Standard


5.4 System Serving
All designs must comply with Qatar laws and regulations in addition to relevant national
The gas system shall be utilized in the following areas
and international standards relating to design of Gas Utilization Systems, in so far as
they apply to the work including; - All F&B.
Relevant International Standards such as; - All CAFÉ`
1. ASME - American Society of Mechanical Engineers. - All apartment kitchens
2. ASTM - American Society for Testing and Materials.
5.5 Design Parameters
3. Institute of Gas Engineers and Managers (IGEM).
The following design parameters have been adopted:
4. National Fire Protection Association (NFPA).
Local Environmental Conditions
5. American Gas Association (AGA).
Site conditions must be assumed to be as follows:
6. ANSI - American National Standards Institute.
• Maximum Ambient Temperature; 55°C
7. BS - British Standards
• Minimum Ambient Temperature; 1°C
8. EN – European Standards.
• Design Ambient Temperature; 55°C
9. ISO - International Standardization Organization
• Max. Metal Temperature under Sun; 85°C
10. MARAFQ QATAR

OWNER / DEVELOPER: LEAD CONSULTANT:


221
5.6 System Provision gas meter,

Emergency switch, and domestic gas leak Gas regulator in the building shall be able to
Provision shall be made to incorporate means of controlling the gas flow within the be operated with
building gas piping system including isolation of damaged facilities or components.
75mbar incoming pressure from the main Pressure Reducing and Metering Station.
The gas supply source pressure considered in the design shall be determined based on Detection system as minimum.
the upstream design conditions. System shall be designed to supply a forecast hourly
peak demand 5.7.2 System Components
The load that shall be applied during design shall be diversified. Considerations in  Pressure reducing and metering station,
determining the load diversity shall include the nature of the facility being designed, the
type of load and the number of consumers.  Gas box units,

Designs shall minimize the types and size range of materials and use only material items  Gas regulators,
for which approved Material Specifications exist.
 Gas hoses,
All materials shall be suitable for local climatic conditions.
 Solenoid valves,
All materials, assemblies and installations shall ensure correct functionality and full
operability taking into accounts the ambient conditions of the location.  Gas leak detectors,
All piping and fittings as well as other components and accessories shall be suitable for  Under/over pressure shutoff device.
both NG usages.

All gas shafts within a building preferred to be dedicated for gas with a minimum size
suitable for accessing the shaft for maintenance purposes.
5.8 Outline Specification
5.7 Building Installation Pipework Pipe fittings and component shall be designed and installed in accordance with relevant
standards.
5.7.1 General
Material shall have the physical properties suitable to the proposed duty considering all
Specialist designer shall ensure the gas pipes service to the plot is accurate. surrounding forces, operating temperature and pressure.

Customer Installation Pipework extends from the outlet valve of the Pressure Reducing Steel pipe:
& Metering Station
Carbon steel or wrought iron pipe shall be at least of Schedule 40 Grade B.
(Customer Primary Meter) to the consumer appliances.
Copper:
At the initial stages of building design and planning the specialist designer/Installer needs
to ensure that the Copper tube install in the building (inside kitchen only) shall be rigid type.

Customer Internal Piping connected to the meter outlet valve are adequately designed Annealed-Temper or Drawn-Temper Copper Tube
in order to provide a
Polyethylene:
safe supply of gas to the point of use. Residential and unit apartment pipe work in the
kitchen shall be installed PE pipe shall be for buried used only.

with shutoff valve, solenoid valve, low pressure regulator with UPSO, auto-shutoff valve, PE pipe must not be used within building, for entry or exit sit shall be sleeved with special
requirement.

OWNER / DEVELOPER: LEAD CONSULTANT:


222
5.9 GAS System Estimation Loads

Option 1 (Without Hot Water Boiler)


PLOT NUMBER Utility allocation (kw) Estimated Demand (kw) Service Available pipe size (mm)
PLOT H-1/HA-1 266 - Not Used 125
1642 1259 Podium 125
PLOT NSC-1-HC-1 672 525 Tower A 63
HA-2 1045 586 Tower B 63
HA-3 807 525 Tower C 63
HA-4 731 - Not Used 63
Assumptions
1. Gas will be provided for residential apartments kitchens.
2. Gas will be provided for F&B's at commercial podium.

Option 2 (With Hot Water Boiler)


PLOT NUMBER Utility allocation (kw) Estimated Demand (kw) Service Available pipe size (mm)
PLOT H-1/HA-1 266 - Not Used 125
1642 1259 Podium 125
PLOT NSC-1-HC-1 672 525 Tower A 63
HA-2 1045 586 Tower B 63
HA-3 807 525 Tower C 63
HA-4 731 1443 Central Heating Boiler 63

Total Estimated GAS Load ( Without Boiler ) = 2895 (kw)

Total Estimated GAS Load ( With Boiler ) = 4338 (kw)

OWNER / DEVELOPER: LEAD CONSULTANT:


223
5.10 GAS SYSTEM PROPOSED PROVSIONS

SPACE NAME GAS

MECHNICAL ROOMS -
HYPER MARKET √
F&B √
CAFÉ √
PUMP ROOM -
GENERATOR ROOM -
PUBLIC TOILET -
JANITOR -
SPA -
GYM -
SWIMMING POOL TOILET -
GARBAGE ROOMS -
RESIDETAIL APARTMENT √

OWNER / DEVELOPER: LEAD CONSULTANT:


224
OWNER / DEVELOPER: LEAD CONSULTANT:
225
OWNER / DEVELOPER: LEAD CONSULTANT:
226
ERKYAH MIXED USE
LUSAIL-QATAR
UTILITIES EXECUTIVE SUMMARY REPORT
REVISION 00 – NOV. 2019

OWNER / DEVELOPER: LEAD CONSULTANT:


UTILITIES

1. Tie in Points – Information Received

MV

ELECTRICAL DISTRIBUTION NETWORK (MV CABLE)


PLOT NAME S/S No. FED FROM/TIE IN NO. FEED TO TIE IN COORDINATION
H-1 21028 A160 H-1 (25482) & R5 N=408531.278 E= 227304.626 TOP LEV = 5.410
HA-1 25482 H-1(21028) H-1(21026) N=408556.666 E= 227394.886 TOP LEV = 5.370
NSC-1/HC-1 21026 H-1(25482) HA-2(21023) N=408568.282 E= 227445.256 TOP LEV = 4.960
N=408537.927
HA-2 21023 HA-3(25483) HC-1(21026) E= 227487.403 TOP LEV = 5.390

N=408500.663 Missing
HA3 25483 HA4 HA-2(21023)&R-13(21021) E= 227493.482
N=408463.185 E= 227506.040
HA-4 21022 A170 HA-3 TOP LEV = 5.610

TEL

TEL SERVICES NETWORK

TEL. TIE IN NO. TIE IN COORDINATION


N= 408525.083 E= 227267.401
END PIPE H-1 /HA-1
N= 408533.313 E= 227329.877

N= 408569.957 E= 227441.642
END PIPE NSC-1/HC-1
N= 408577.742 E= 227483.480

N= 408569.955 E= 227480.274
END PIPE HA-2
N= 408522.408 E= 227490.383

END CAP HA-3 N= 408511.120 E= 227495.281


N= 408506.380 E= 227496.637
N= 408451.567 E= 227515.486
END CAP HA-4
N= 408464.806 E= 227591.382

OWNER / DEVELOPER: LEAD CONSULTANT:


228
Security System Department-MOI (SSD)

SSD DISTRIBUTION NETWORK


SSD TIE IN NO. TIE IN COORDINATION ELEVATION
N= 408649.316 E= 227383.213
END CAP H-1 /HA-1 TOP LEV = 5.538
N= 408653.243 E= 227393.864
END CAP NSC-1/HC-1 TOP LEV = 5.554
N= 408655.558 E= 227401.364
TOP LEV = 5.433
N= 408484.196 E= 227599.874
END CAP HA4 TOP LEV = 5.122

HVAC

DISTRICT COOLING NETWORK


TIE IN CHILLED WATER
DC TIE IN NO. TIE IN COORDINATES
SIZE
(END CAP) CONNECTION TO PLOT H1 N 408526.946 E 227286.420 TOP LEV = 5.685 Missing

(END CAP) CONNECTION TO PLOT HA1 N 408546.474 E 227359.684 TOP LEV = 4.047 Missing

(END CAP) CONNECTION TO PLOT NSC-1-HC-1(N1-H1) N 408561.191 E 227412.691 Missing Missing

(END CAP) CONNECTION TO PLOT HA2 N 408531.984 E 227488.411 TOP LEV = 5.204 Ø 200mm

(END CAP) CONNECTION TO PLOT HA3 N 408519.437 E 227491.096 TOP LEV = 5.204 Missing

(END CAP) CONNECTION TO PLOT HA3 N 408496.729 E 227496.036 TOP LEV = 5.498 Missing

(END CAP) CONNECTION TO PLOT HA4 N 408458.675 E 227504.349 TOP LEV = 5.280 Missing

OWNER / DEVELOPER: LEAD CONSULTANT:


229
PW

POTABLE/FIRE WATER NETWORK


PW TIE IN NO. TIE IN COORDINATES ELEVATION
TIP-U-SW- PLOT H-1/HA-1 N=408522.455 E=227277.016 Missing
N=408543.924 E=227358.653 Missing
TIP-U-PW- PLOT NSC-1-HC-1 N=408561.013 E=227422.410 TOP LEV = 4.720
TIP-U-PW- HA-2 N=408529.663 E=227487.075 Missing
TIP-U-PW- HA-3 N=408494.576 E=227494.270 TOP LEV = 4.622
TIP-U-PW- HA-4 N=408466.541 E=227500.142 TOP LEV = 4.980

FS

AL ERKYAH MIXED USE DEVELOPMENT - LUSAIL (TIE IN POINTS)


FOUL WATER NETWORK
FS TIE IN NO. TIE IN COORDINATES ELEVATION
TIP-U-SW- PLOT H-1/HA-1 N= 408523.662 E= 227281.872 I.L = 4.287
N= 408548.281 E= 227369.100 I.L = 3.916
TIP-U-FS- PLOT NSC-1-HC-1 N= 408565.620 E= 227440.818 I.L = 4.866
TIP-U-FS- HA-2 N= 408523.777 E= 227488.944 I.L = 2.490
TIP-U-FS- HA-3 N= 408490.532 E= 227496.071 I.L =2.863
TIP-U-FS- HA-4 N= 408448.158 E= 227508.604 I.L = 5.100

ST

STORM WATER NETWORK


SW TIE IN NO. TIE IN COORDINATES ELEVATION
TIP-U-SW- PLOT H-1/HA-1 N=408519.235 E=227262.291 I.L =5.28
N=408532.280 E=227324.314 I.L = 4.85
TIP-U-SW- PLOT NSC-1-HC-1 N=408566.053 E=227447.853 I.L = 4.38
TIP-U-SW- HA-2 N=408540.701 E=227482.175 I.L = 4.61
TIP-U-SW- HA-3 N=408501.892 E=227492.757 I.L = 4.41
TIP-U-SW- HA-4 N=408453.211 E=227547.097 I.L = 3.70

OWNER / DEVELOPER: LEAD CONSULTANT:


230
GAS

GAS NETWORK
GAS TIE IN NO. TIE IN COORDINATES ELEVATION
LOW (END CAP) CONNECTION TO PLOT H-1/HA-1 N= 408523.026 E= 227281.045 TOP LEV = 4.858
N= 408546.112 E= 227365.860 TOP LEV = 5.116
LOW (END CAP) CONNECTION TO PLOT NSC-1-HC-1 N= 408562.720 E= 227424.649 TOP LEV = 5.298
LOW (END CAP) CONNECTION TO HA-2 N= 408524.795 E= 227487.764 TOP LEV = 5.290
LOW (END CAP) CONNECTION TO HA-3 N= 408491.526 E= 227494.837 TOP LEV = 5.693
LOW (END CAP) CONNECTION TO HA-4 N= 408452.517 E= 227505.090 TOP LEV = 5.475

OWNER / DEVELOPER: LEAD CONSULTANT:


231
2. Allocations Loads

Mechanical Allocation Loads

Av. Foul
Cooling Av. Potable
PWC Sewer
S.No Plot GFA (m2) Demand GAS (KWh) water
(Kg/day) Generated
(TR) demand (L/S)
(L/S)

1 PLOT H-1/HA-1 54760 1886 1908 Not Available missing missing

Not Available missing missing


2 PLOT NSC-1-HC-1 42300 2617 672
Not Available missing missing
3 HA-2 15763 410 1045
Not Available missing missing
4 HA-3 12174 316 807
Not Available missing missing
5 HA-4 11019 286 731

Electrical Power Allocation Loads

POWER ALLOCATION FOR PLOT


FED FROM/TIE IN
PLOT NAME S/S No. NO. FEED TO PLOT AREA GFA TCL (KVA) MDL (KVA)
H-1 21028 A160 H-1 (25482) & R5 2877 2071.6

HA-1 25482 H-1(21028) H-1(21026)


2374.48 1780.49
NSC-1/HC-1 21026 H-1(25482) HA-2(21023) 4052.34 2848.91
HA-2 21023 HA-3(25483) HC-1(21026) 1511.67 1133.52

HA-2(21023)&R-
HA3 25483 HA4 13(21021) 1167.49 875.43
HA-4 21022 A170 HA-3 1056.72 792.38
49,760 120,329 13039.7 9502.33

OWNER / DEVELOPER: LEAD CONSULTANT:


232
3. Estimation Loads

3.1 Electrical Power and Telecom Loads Estimation

Electrical power Electrical power


MDL allocation Estimated MDL
difference/shortage difference/shortage
(kVA) (kVA)
(MVA) (%)

NSC-1/HC-1 & HA3 9,500.00 12,587.64 -3 -32.50%

ELECTRICAL DISTRIBUTION NETWORK (MV CABLE)


MV TIE IN NO. STATUS
END CABLE H-1 /HA-1 NOT USED
END CABLE NSC-1/HC-1 USED
END CABLE HA-2 NOT USED
END CABLE HA3 USED
END CABLE HA-4 NOT USED

TEL SERVICES NETWORK


TEL. TIE IN NO. STATUS
END PIPE H-1 /HA-1 NOT USED
END PIPE NSC-1/HC-1 NOT USED
END PIPE HA-2 NOT USED
END CAP HA-3 USED
END CAP HA-4 NOT USED

SSD DISTRIBUTION NETWORK


SSD TIE IN NO. TIE IN COORDINATION
END CAP H-1 /HA-1 NOT USED
END CAP NSC-1/HC-1 NOT USED
END CAP HA4 USED

OWNER / DEVELOPER: LEAD CONSULTANT:


233
3.2 Building HVAC Cooling Loads Estimation Summary

3.3 HVAC Allocated and Requires Cooling Loads

OWNER / DEVELOPER: LEAD CONSULTANT:


234
3.4 Potable Water Estimation Loads

Utility Required
Existing Pipe Required Pipe
allocation People 2-days Storage Volume (L) Avg. Flow
Size (mm) Size (mm)
(Ave. l/s) (Avg. l/s)

Commercial Podium Potable Water = 310,000


Tie-in NSC-1-HC-1 missing ∅100 ∅80 7582 8.77
Commercial Podium Non Potable water = 195,000

Residential Towers Potable water = 880,000


Tie-in HA-2 missing ∅100 ∅80 2550 22.92
Residential Towers Non Potable water = 440,000

Assumptions
1. Based on 300 L/person/day for Residential and 60 L/person/day for commercial
2. Based on 8 hour refill of one day storage volume

POTABLE/FIRE WATER NETWORK

PW TIE IN NO. STATUS

TIP-U-PW- PLOT H-1/HA-1 Not Used

Not Used

TIP-U-PW- PLOT NSC-1-HC-1 Used

TIP-U-PW- HA-2 Used

TIP-U-PW- HA-3 Not Used

TIP-U-PW- HA-4 Not Used

OWNER / DEVELOPER: LEAD CONSULTANT:


235
3.5 Sewage Water Estimation Loads

Utility allocation Existing Line Size Min. Required Line size


(Ave. l/s) (mm) (mm)
PLOT H-1/HA-1 missing Not Used Not Used
∅200 ∅200
PLOT NSC-1-HC-
missing ∅200 ∅200
1
HA-2 missing ∅200 ∅200

HA-3 missing ∅200 ∅200

HA-4 missing ∅200 ∅200

Assumptions
1. The average flowrate is based on a 10 hour working day.
2. Based on 1:100 pipe fall

FOUL WATER NETWORK


FS TIE IN NO. STATUS
TIP-U-FS- PLOT H-1/HA-1 Not Used
Used
TIP-U-FS- PLOT NSC-1-HC-1 Used
TIP-U-FS- HA-2 Used
TIP-U-FS- HA-3 Used
TIP-U-FS- HA-4 Used

OWNER / DEVELOPER: LEAD CONSULTANT:


236
3.6 GAS System Estimation Loads

Option 1 (Without Hot Water Boiler)


Utility allocation (kw) Estimated Demand (kw) Service Available pipe size (mm)
PLOT H-1/HA-1 266 - Not Used 125
1642 1259 Podium 125
PLOT NSC-1-HC-1 672 525 Tower A 63
HA-2 1045 586 Tower B 63
HA-3 807 525 Tower C 63
HA-4 731 - Not Used 63
Assumptions
1. Gas will be provided for residential apartments kitchens.
2. Gas will be provided for F&B's at commercial podium.

Option 2 (With Hot Water Boiler)


Utility allocation (kw) Estimated Demand (kw) Service Available pipe size (mm)
PLOT H-1/HA-1 266 - Not Used 125
1642 1259 Podium 125
PLOT NSC-1-HC-1 672 525 Tower A 63
HA-2 1045 586 Tower B 63
HA-3 807 525 Tower C 63
HA-4 731 1443 Central Heating Boiler 63
Assumptions
1. Gas will be provided for residential apartments kitchens.
2. Gas will be provided for F&B's at commercial podium.
3. Gas will be provided for Central Heating Boiler.

GAS NETWORK
GAS TIE IN NO. TIE IN COORDINATES
LOW (END CAP) CONNECTION TO PLOT H-1/HA-1 Not Used
Used
LOW (END CAP) CONNECTION TO PLOT NSC-1-HC-1 Used
LOW (END CAP) CONNECTION TO HA-2 Used
LOW (END CAP) CONNECTION TO HA-3 Used
LOW (END CAP) CONNECTION TO HA-4 Used (In Case of Central Heating Boiler)

OWNER / DEVELOPER: LEAD CONSULTANT:


237
4. Tie-in Points Drawings

OWNER / DEVELOPER: LEAD CONSULTANT:


238
OWNER / DEVELOPER: LEAD CONSULTANT:
239
OWNER / DEVELOPER: LEAD CONSULTANT:
240
Tie in Coordinates District Cooling Network

OWNER / DEVELOPER: LEAD CONSULTANT:


241
Allocated and Required District Cooling Loads

OWNER / DEVELOPER: LEAD CONSULTANT:


242
OWNER / DEVELOPER: LEAD CONSULTANT:
243
OWNER / DEVELOPER: LEAD CONSULTANT:
244
OWNER / DEVELOPER: LEAD CONSULTANT:
245

You might also like