Professional Documents
Culture Documents
SOP OF SEN-Slab
SOP OF SEN-Slab
LẮP ĐẶT SEN Ở KHU VỰC CHUẨN BỊ THÙNG TRUNG GIAN SLAB
JOB INSTRUCTION: SLAB SEN INSTALLATION - FHS DOCUMENT NO: ISSUE DATE: CONTROL PLAN:
MÔ TẢ CÔNG VIỆC: LẮP ĐẶT SEN Ở KHU VỰC CHUẨN BỊ THÙNG SLAB - FHS TÀI LIỆU SỐ: NGÀY:
PART NUMBER N°: DESCRIPTION: Installation instruction for SEN, well block in Slab Tundish preparation area PROCESS:
MÔ TẢ Hướng dẫn lắp đặt SEN,well block ở khu vực chuẩn bị thùng trung gian Slab QUY TRÌNH:
NO OPERATION
e f g
1 BẢO HỘ LAO ĐỌNG Đảm bảo đầy đủ PPEs (Tham khảo hình):
1. Mũ bảo hộ (hình a)
2. Kính an toàn (hình b)
3. Khẩu trang (hình c)
4. Găng tay (hình d)
5. Quần bảo hộ (hình e)
6. Áo bảo hộ (hình f)
7. Giầy bảo hộ (hình g)
JOB INSTRUCTION: SLAB SEN INSTALLATION - FHS DOCUMENT NO: ISSUE DATE: CONTROL PLAN:
MÔ TẢ CÔNG VIỆC: LẮP ĐẶT SEN Ở KHU VỰC CHUẨN BỊ THÙNG SLAB - FHS TÀI LIỆU SỐ: NGÀY:
PART NUMBER N°: DESCRIPTION: Installation instruction for SEN, well block in Slab Tundish preparation area PROCESS:
MÔ TẢ Hướng dẫn lắp đặt SEN,well block ở khu vực chuẩn bị thùng trung gian Slab QUY TRÌNH:
NO OPERATION
NO OPERATION
3 WELL BLOCK 1. Clean the well area and tundish shell. Make
1
INSTALLATION sure that well block is in center and same plane
with tundish shell.
2. Mix Ramag 90P with water (around 1L/25kg).
Make sure that the material is not too dry or too
wet after mixing.
3. Pour Ramag 90P and ram it by pneumatic
rammer. Note: The ramming should be done in
3 layers to ensure the compactness. The first
layer should cover 1/3 thickness of permanent
lining.
NO OPERATION
1 2 3
4 SEN INSTALLATION 1. Cover the Bell area of SEN by defined
amount of mortar. The mortar thickness is
around 4-5mm.
2. Insert SEN gradually into the well block. One
person standby under tundish to align the SEN.
At the same time, the ports can be aligned.
Bell
3. Put the SEN down to the defined position. area
Note: if an enough amount of mortar was
applied, the exceeded mortar will be appear
around SEN neck and seat after installation.
4. Measure the projection length of SEN to
achieve 980 ±5mm below the mounting flange of
SEM 3085 mechanism function as the chop
gate. Or 1015 ±5mm with the other chop gate
system.
Note, direct pressure on the SEN must be 4i 4ii
avoided during the alignment process. 5
5. Remove the exceeded mortar.
4 LẮP ĐẶT SEN 1. Phết một lượng vừa đủ Green Mortar lên
phần cổ SEN. Chiều dày lớp mortar khoảng 4-
5mm.
2. Lắp SEN từ từ vào Well block. Một người ở
dưới Tundish đỡ và điều chỉnh SEN vào đúng vị
trí, lúc đó lỗ thoát cũng được điều chỉnh.
3. Lắp chặt SEN vào vị trí.
Chý ý: Nếu dùng đủ lượng mortar, sau khi
lắp sẽ có một lượng mortar thừa ở cổ SEN.
4. Kiểm tra chiều dài SEN nhô ra dưới đáy
Tundish. Cần phải nằm trong khoảng 980±5mm
với bộ cơ khí SEM 3085 hoặc 1015±5mm với bộ
cơ khí khác. 980±5mm with SEM3085 as 1015±5mm with other
Chú ý: tránh tác đọng trực tiếp lên SEN trong chop gate chop gate
quá trình điều chỉnh
5. Vệ sinh phần vữa (mortar) thừa.