2) WORKING SEQUENCES/
TRÌNH TỰ THI CÔNG
STEP 1: (BY FREYSSINET(FVN) /THỰC HIỆN BỞI FREYSSINET)
OPEN SPACE FOR ACCOMMONDATE PT TENDON ALONG INSIDE THE PERIMETER
BEAM RABAR BEFORE CASTING CONCRETE/
MỞ RỘNG THÉP CỘT ĐỂ DỄ DÀNG LẮP ĐẶT CÁP TRONG DẦM BIÊN TRƯỚC KHI
ĐỔ BÊ TÔNG CỘT.
STEP 2: (BY ORTHER/ THỰC HIỆN BỞI CHỦ ĐẦU TƯ/NHÀ THẦU CHÍNH)
CONSTRUCTION OF DESK FLOOR AND MOUNTED EDGE-BOARD AREA HAS
TENDON ANCHORAGE/
LẮP ĐẶT VÁN KHUÔN ĐÁY SÀN VÀ VÁN KHUÔN BIÊN XUNG QUANH VỊ TRÍ CÓ
ĐẦU NEO.
STEP 3: (BY FVN)
MARK OUT ANCHOR LOCATIONS ON SIDE FORMWORK/
ĐỊNH VỊ VỊ TRÍ CỦA ĐẦU NEO LÊN VÁN KHUÔN BIÊN.
STEP 4: (BY ORTHER/ CHỦ ĐẦU TƯ/NHÀ THẦU CHÍNH)
SLOT AND BOLTS HOLE POSITIONS REQUIRED TO BE CUT AND DRILLED/
TẠO KHE MỞ VÀ LỖ BU LÔNG TRÊN VÁN KHUÔN BIÊN.
STEP 5: (BY FVN)
BOLT ANCHOR AND RECESS FORMER ONTO THE EDGE-BOARD/
LẮP ĐẶT NEO VÀ ĐẦU HỘC VÀO VÁN KHUÔN BIÊN.
STEP 6: (BY FVN)
COIL IS UN-PARK INSIDE THE DISPENSER AND LIFTED BY TOWER CRANE
PROVIDED BY ORTHER/
CUỘN CÁP ĐƯỢC DỠ BỎ VÀO CÁC TANG CÁP VÀ ĐƯỢC CẨU LÊN BỞI CẦN
CẨU THÁP DO CHỦ ĐẦU TƯ/NHÀ THẦU CHÍNH CUNG CẤP.
STEP 7: (BY FVN)
PRE-FABRICATION OF PT TENDONS ON SLAB SOFFIT/
GIA CÔNG CÁC BÓ CÁP TRÊN VÁN KHUÔN SÀN.
STEP 8: (BY FVN)
PLACE TENDONS INSIDE THE PERIMETER BEAM BEFORE BEAM REINFORCEMENT
INSTALLED/
ĐẶT CÁC BÓ CÁP NẰM TRONG DẦM BIÊN TRƯỚC KHI THÉP DẦM ĐƯỢC LẮP ĐẶT.
STEP 9: (BY ORTHER/ CHỦ ĐẦU TƯ/NHÀ THẦU CHÍNH)
REBAR FIXER COMPLETED BEAM REINFORCEMENT/
CỐ ĐỊNH LẮP ĐẶT CỐT THÉP CHO DẦM.
STEP 10: (BY FVN)
PT TENDON INSIDE PERIMETER BEAM SHALL BE FIXED BY PERMANENT SUPPORTS
USING REBAR D12 SHAPE C PROVIDED BY ORTHER/
CỐ ĐỊNH ĐƯỜNG CÁP TRONG DẦM BIÊN BẰNG CÁC THANH D12 HÌNH CHỮ C
ĐƯỢC CUNG CẤP BỞI CHỦ ĐẦU TƯ/NHÀ THẦU CHÍNH.
STEP 11: (BY ORTHER/ CHỦ ĐẦU TƯ/NHÀ THẦU CHÍNH)
INSTALL BOTTOM MESH/
LẮP ĐẶT LƯỚI THÉP LỚP DƯỚI.
STEP 12: (BY FVN)
APPLY PAINT UNDER TENDON BEFORE OR AFTER INSTALLATION COMPLETED/
SƠN DỌC THEO ĐƯỜNG ĐI CỦA BÓ CÁP TRƯỚC HOẶC SAU KHI LẮP ĐẶT.
STEP 13: (BY FVN)
INSTALL PT TENDONS SLAB/
LẮP ĐẶT CÁC BÓ CÁP SÀN.
STEP 14: (BY ORTHER/ CHỦ ĐẦU TƯ/NHÀ THẦU CHÍNH)
INSTALL ANTI-BURSTING REBAR ACCORDINGLY AS PER DESIGN/
LẮP ĐẶT THÉP GIA CƯỜNG ĐẦU NEO PHÙ HỢP VỚI THIẾT KẾ.
STEP 15: (BY ORTHER/ CHỦ ĐẦU TƯ/NHÀ THẦU CHÍNH)
INSTALL TOP REBAR LAYERS (IF REQUIRED)/
LẮP ĐẶT LƯỚI THÉP LỚP TRÊN (NẾU CÓ).
STEP 16: (BY FVN)
PROVIED GROUT VENT AT ANCHORAGE & DEAD ENDS/
LẮP ĐẶT ỐNG BƠM VỮA TẠI ĐẦU KÉO VÀ ĐẦU CHẾT.
COMPLETION OF INSTALLATION & READY FOR INSPECTION
THÉP GIA CƯỜNG ĐẦU NEO CẦN PHẢI ĐƯỢC LẮP ĐẶT TRƯỚC
LƯỚI THÉP LỚP TRÊN
TOP REBAR/
LƯỚI THÉP LỚP TRÊN
ANTI-BURSTING REBAR/
THÉP GIA CƯỜNG ĐẦU NEO
THE ACTIVE END AND PASSIVE END IF NEAR THE COLUMN MUTS BE
INSTALLED ANTI-BURSTING BEFORE TOP REBAR INSTALLED/
CÁC ĐẦU KÉO VÀ ĐẦU CHẾT NẾU ĐẶT Ở GẦN CỘT CẦN LẮP ĐẶT THÉP GIA
CƯỜNG ĐẦU NEO TRƯỚC KHI LƯỚI THÉP LỚP TRÊN ĐƯỢC LẮP ĐẶT
3.BAD PRACTICE CAUSE DELAY WORKS.
- - Waste time for remedial actions/ Lãng phí thời gian do khắc phục sự cố.
a. Temperature of concrete should not be over 30 degree, some time the aggregate
expose to sun the temperature too high, or cement pump directly from factory still
in high temperature ==> need to use ice water to mix concrete to control the
temperature of concrete not excess 30 degree.
b. Problem with scale of batching plant so that the cement amount too much.
c. Problem itself with cement about the chemical proportion, too much CaO will lead
to consume water too much.
2. Reason cause by curing concrete: the shrinkage crack depend on the loss of water
on surface and different temperature of out side and inside concrete, during
concrete hardening inside very hot compare to outside (quite many mistake that
the hot weather is more crack than cold) => the point to curing and control crack is
to keep the surface hot and wet.
Normally people use one membrane of clear PVC not to loose water moisture when
concrete hardening and another thick membrane to keep heat.
The sika antisol S which will create membrane on the concrete surface to keep water
and heat, if the worker and apply correctly. If the application not correct problem
severely happen.
However, is quite simple is to arrange worker to watering continuously on the first
24 hours.
Preventive method in this case is temporary stop to find out problem if it is serious.
Freyssinet cung cấp cho nhân viên đầy đủ các trang thiết bị bảo vệ cá nhân.
Some recommendations regarding safety activities on site
during post- tensionning work.