DESCRIPTION OF ITEM UNIT QTY RATE (Rs) AMOUNT (Rs) REMARKS
No.
EARTH WORK
1 Earthwork excavation for foundation of buildings, water supply, sanitary lines and Cum 50.00 144.00 7200.00
electrical conduits either in pits or in trenches of all depth and width in all kinds of
soil with all lifts including dressing the bottom and sides of pits and trenches, stacking
the excavated soil clear from the edges of excavation with all lead and lifts after
breaking of clods, including cost and conveyance of all materials, labour, HOM of
machinery, with all leads and lifts, loading and unloading, transportation , all other
incidental charges, complete for successful completion of work as per specifications,
and as directed by the Engineer-in- charge.
2 Filling available excavated earth (excluding rock) in sides of foundations upto plinth Cum 45.00 78.30 3523.50
in layers not exceeding 20cms in depth, compacting each deposited layer by ramming
after watering to OMC to required density, including cost of all materials, labour,
HOM of machinery, with all leads and lifts, loading and unloading, transportation cost
and conveyanceof all materials, all other incidental charges, complete for successful
completion of work as per specifications, and as directed by the Engineer-in- charge.
4 Providing and laying in position plain cement concrete of mix M 15 with OPC
minimum cement content of 240kgs, with 20mm and down size graded granite metal,
coarse aggaregates @ 0.878 cum and fine aggregate @ 0.459 cum machine mixed,
concrete laid in layers not exceeding 15cms thick, well compacted in Plinth, Cills,
Above Cinder Concrete, Coping, Base of Railings, Encasing of pipes, etc.
including cost of all materials, labour, including with necessary formwork HOM
machinery, curing, with all leads and lifts, loading and unloading charges,
transportation cost and conveyance of all materials , all other incidental charges etc.,
complete for successful completion of work as per specifications and as directed by the
Engineer in Charge .
I Plinth, Cills, Coping, Base of Railings, etc.
a Ground Floor Cum 5.00 4059.00 20295.00
b First Floor Cum 5.00 4079.70 20398.50
c Second Floor Cum 5.00 4099.50 20497.50
d Third Floor Cum 5.00 4120.20 20601.00
e Terrace Cum 1.00 4140.90 4140.90
7 Providing and casting RCC loft (atta) 7.5 cms thick with cement concrete M20 with
minimun cement content of 320 kg/cum using clean granite or trap jelly of 20mm
and down size with necessary reinforcements as per design including form work.
Centering, curing, finishing the exposed faces with cement mortar (1:3) etc., complete
for successful completion of work including cost of all materials, labour, HOM of
machinery, with all leads and lifts, loading and unloading charges , transportation cost
and conveyance of all materials curing, all other incidental charges complete for
successful completion of work as per specification and as directed by the Engineer in
Charge (exclusive of cost of steel and fabrication charges ) .
FORMWORK
9 Providing and removing necessary centering, shuttering, strutting, propping etc, and
removal of formwork for sides and soffits of BEAMS, beam haunchings, cantilever
girders, LINTELS, including cost of all materials, labour, necessary formwork , with
all leads and lifts, loading and unloading charges , HOM of machineries and
equipments transportation cost and conveyance of all materials and all other
incidental charges etc., complete for successful completion of work as per
specifications and as directed by the Engineer-in-charge.
14 Providing and fixing top covers made out of 20 guage MS sheet over rolling shutters metre 5.00 421.20 2106.00
bent to shape including cost of red lead primer coat of painting, including the cost of
all materials, scaffolding, labour, curing, HOM of equipments and machineries, with all
leads and lifts loading and unloading charges, transporation cost and conveyance of all
material &other incidental charges etc complete for successful completion of work as
per specifications and as directed by the Engineer-in-charge.
The work shall include the cost of all materials, cost of labour, including applying a
priming coat of red lead paint, HOM equipment and machinery, all lead and lift,
loading and unloading charges, transportation cost and conveyance of all materials, and
all other incidental charges at all floor levels etc., complete for successful completion
of work. The work shall be carried out as per the directions of the Engineer in charge.
19 Providing and fixing in position mild Steel Insert Plates of 4mm thick for fixing Kgs 300.00 72.00 21600.00
Grills/Handrails/MS Frames gratings etc. of required size welded to steel
reinforcement bars of RCC members including applying a priming coat of red lead
paint, cost of materials, labour, HOM of equipments and machineries all leads and lifts,
loading and loading, transportation cost and conveyance of all material & all other
incidental charges at all floor levels complete for successful completion of work all as
per specification and as directed by the Engineer-in-charge.
20 Providing and fixing 1mm thick MS Sheet STEEL DOOR with frame and diagonal Sqm 8.00 1980.00 15840.00
braces of size 40x 40x 6mm angle iron,using 30x6mm for digonal and central cross
pieces 3.15mm MS gusset plates at the junction and corners, with handles, stoppers and
locking arrangements etc., including applying a priming coat of red lead paint, cost of
materials, labour, HOM of machinery, with all leads and lifts, loading and unloading
charges , transportation cost and conveyance of all other materials, incidental charges
at all floor levels etc complete for successful completion of work as per specifications
and as directed by the Engineer-in-charge.
22 Providing and fixing MS LOUVER DOOR with frame of size 40x 40x 6mm angle Kgs 13000.00 72.00 936000.00
iron and 40x5mm Flat welded to shutter frame to inclination as per drawing etc.,
including angle door frame fabricated using 40x40x6 mm I.S.A fixed to wall with
hinges & applying a priming coat of red lead paint, cost of materials, labour, HOM of
machinery, with all leads and lifts, loading and unloading charges , transportation cost
and conveyance of all materials, other incidental charges at all floor levels etc complete
for successful completion of work as per detailed drawings & specifications and as
directed by the Engineer-in-charge.
the original surface; aluminium surface pre treated for removal of any rust and coated
with greasy materials for non -adherence of mortar or any other sticky materials;(
coating removal after installation) and thoroughly cleaned free from dirt, rust etc.,
including cost and conveyance of all materials, labour, HOM of equipments and
machineries all leads and lifts, loading and loading, transportation at all floor levels
complete for successful completion of work all as per specification and as directed by
the Engineer-in-charge.
a Ground Floor Sqm 150.00 3741.30 561195.00
b First Floor Sqm 140.00 3744.00 524160.00
c Second Floor Sqm 120.00 3746.70 449604.00
d Third Floor Sqm 120.00 3749.40 449928.00
e Terrace Floor Sqm 5.00 3752.10 18760.50
joints mitred subdividing the frame tennoned and rivetted, in the assembled frame,
stiffened with end clips for corners, angles etc., fixed to the walls, lintels, floor beams;
cills as the case may be with necessary steel screws, raul plugs or teak wood gatties
including cutting masonary or concrete and making good the original surface using
cement mortar, ; aluminium sections pretreated for removal of any rust and coated with
greasy materials for non -adherence of mortar or any other sticky materials; ( coating
removal after installation) and thoroughly cleaned free from dirt, rust etc. etc.,
including cost of materials, labour, HOM of equipments and machineries all leads and
lifts, loading and loading, transportation cost and conveyance of all materials at all
floor levels complete for successful completion of work and as per specification and as
directed by the Engineer-in-charge.
teak wood gatties including cutting masonry or concrete and making good the original
surface using cement mortar, as per drawings and aluminium sections pretreated for
removal of any rust and protection of further rust formation and coated with the greasy
materials for non-adhesion of mortar and any other sticky matyerials, (this coating
should be cleaned after installation) including cost of all materials, fixtures, labour and
HOM of machinery complete for successful completion of work as per
specifications.including all leads and lifts , loading unloading charges and
transportation cost and conveyance of all materials and all other incidental charges etc
complete for successful completion of work as directed by the Engineer -in - charge.
(For Staircase, etc.)
27 Providing , fabricating assembling and fixing in position anodized aluminium Sqm 300.00 4093.20 1227960.00
partitions using sections in combination of plain, single grove and double grove as per
requirements for the frames of over all size 101.6mm x44.45mm, 3.18mm thick having
section weight, plain sections2.4kg/m, single grove section2.54kg/m and double grove
section 2.683kg/m aluminium louvres of size 77.6mm x27.6mm 1.7mm thick section
weight 0.483 kg/m, bottom portions provided with 12mm thick prelaminated sheet both
side approved colour lamination exterior grade, aluminium section of matt finish or
glossy finish using section, spacing of vertical members shall not exceed 0.6m c/c ,
sections are cut to the required length , joints mitred and corners grinded subdividing
frames tennoned and rivetted to the frames, the assembled frame should be stiffened
with corner angles stripped and fixed with screws, rawl plugs and teak wood gutties to
RCC columns or masonry on sides ,
be thoroughly cleaned, free form rust, scale or dirt etc., complete including cost of
materials, labour, HOM of equipments and machineries all leads and lifts, loading and
unloading, transportation cost and conveyance at all floor levels complete for
successful completion of work all as per specification and as directed by the Engineer-
in-charge.
28 Providing, fabricating, assembling and fixing in position anodized aluminium doors Sqm 30.00 4500.00 135000.00
using following aluminium mat finish or glossy finish, outer frame plain section
101.6x44.45mm thickness 3.18mm, section weight 2.404kg/m, door shutters vertical
section 44.62x44.45mm thickness 3.18mm, section weight 1.505kg/m, top section
47.62x44.45mm thickness 3.00mm, section weight 1.426 kg/m bottom section
114.3x44.45 thickness 3.18mm, section weight 2.646 kg/m, door central section
19.91x44.45mm thickness 3.00mm, section weight 1.495 kg/m glazing clips
19x17.3x11mm thickness 0.9mm section weight 0.124kg/m; aluminium sections
anodized 12 to 15 microns cut length joint metred corners grinded, the shutters pivoted
opening arrangement with heavy duty aluminium alloy automatic door closures floor
mounted,
29 Extra for colour anodising the aluminium sections/profiles to a thickness of 12 to Sqm 1100.00 135.00 148500.00
15 micron thick complete including cost of materials, labour, HOM of equipments and
machineries all leads and lifts, loading and loading, transportation cost and conveyance
of all materials at all floor levels complete for successful completion of work all as
per specification and as directed by the Engineer-in-charge. (only external anodised
area shall be measured & paid)
WOOD WORK
NOTE: Cost of fixtures to doors,cupboards&other wood work is excluded. Rate
quoted shall be inclusive of labour and other fixing charges of fixtures.
33 Providing and fixing 35 mm thick single/ double leaf solid core and resin bound Sqm 150.00 3780.00 567000.00
FLUSH DOOR SHUTTERS, confirming to IS . 1659 - 1960 and 2202 part I - 1962
as modified unto date BOTH SIDE TEAK veneering factory pressed teakwood
lipping as per specification & design around the shutters and fixed to existing frame
and as specified including cost of all materials, HOM of machineries and equipments,
with all leads and lifts, loading and unloading charges , transportation cost and
conveyance of all materials, labour for fixing the fixtures etc., complete for successful
completion of work as per specifications ( excluding cost of fixtures) at all floor levels
and as directed by the Engineer-in-Charge.
35 Providing and fixing 35 mm thick single/double leaf flush door shutters, confirming Sqm 75.00 2326.50 174487.50
to IS . 1659 - 1960 and 2202 part I - 1962 as modified unto date for non-decorative
type, core of block board construction to frame of IInd class teak wood and well
matched commercial 3 ply veneering with vertical grains or cross bands and face
veneers on both faces(BSC) of shutters: including teak wood lipping, including cost of
all materials, HOM of machineries and equipments, with all leads and lifts, loading and
unloading charges , transportation cost and conveyance of all materials, labour for
fixing the fixtures etc., complete for successful completion of work as per
specifications ( excluding cost of fixtures) at all floor levels and as directed by the
Engineer-in-Charge.
36 Extra for Providing and fixing Vision Panel using 5 mm thick plain glass including Sqm 10.00 2250.00 22500.00
making cutouts in the flush door and fixing in position with teakwood beading alround,
including cost of all materials, HOM of machineries and equipments, with all leads and
lifts, loading and unloading charges , transportation cost and conveyance of all
materials , complete for successful completion of work as per specifications at all floor
levels and as directed by the Engineer-in-Charge.
38 Providing and fixing TEAK WOOD Class-II STAIRCASE HANDRAIL of size Rmt 300.00 1030.50 309150.00
100x 65mm as per design and detailings as shown in the drawings,assembled
including making grooves for fixing and including ss screwsof approved size,cost of
all materials, HOM of machineries and equipments, with all leads and lifts, loading and
unloading charges , transportation cost and conveyance of all materials, labour for
fixing the fixtures etc., complete for successful completion of work as per
specifications at all floor levels and as directed by the Engineer-in-Charge.
39 Providing and fixing non-metallic 55mm thick solid core bonded board type Two Sqm 25.00 10800.00 270000.00
hour rated fire and smoke check flush door shutters with non combustible boards in
side , the core hot pressed bonded with liquid phenol formaldehyde resin , external
lipping by teak wood ,heat activated intumescent on the edges of the shutter and door
frame of seasoned hard wood (Sal wood) of 100x60mm with heat activated
intumescent fire seal strips of size 12x4 mm (for smoke sealing ) fixed on all the three
sides except the bottom and the vision panel of size 200 x 400mm made up of
required thickness clear wired fire rated glass (imported) of 120 minutes fire rating
from Saint Gobain/CGI having electrically welded chemically treated steel wire mesh
of 20mm spacing sandwiched in the center during the continuos rolling process
including fire rated gasket channel & moulding/beading and filling the
WATER PROOFING
40 Providing and laying intergral cement based waterproofing treatment including Sqm 1300.00 612.90 796770.00
preparation of surface as required for treatment of Roofs, Balconies, Terraces etc.,
consisting of following application:
a Applying and grouting slurry coat of neat cement using 2.75 kgs/sqm of cement
admixed with proprietory water proofing compound conforming to IS 2645 over the
RCC slab after cleaning the surface before treatment.
b conforming to IS 2645 over 20mm thick layer &CM 1:5 admixed with proprietary
water proofing compound to required slope and treating similarly the adjoining walls
upto 300mm height including rounding off junctions of walls and slabs.
c After two days of proper curing, applying a second coat of cement slurry admixed with
proprietary water proofing compound
d Finishing the surface with 20mm thick jointless cement mortar of mix 1:4 admixed
with proprietary water proofing compound and finally finishing the surface with trowl
and neat cement slurry and making of 300x300mm square.
42 Chipping and cleaning, construction joint and slab joint, treatment, grouting of honey Sqm 300.00 875.70 262710.00
comb by cement with inorganic accelerator for cement, spray of biological modified
ortho esters and alkaline earth, providing and laying of patch concrete 1:2:4 for
required thickness by clean granite trap jelly 20mm and down size mixed with
polycarboxylic sulphonated neutral cellulose at 100ml / bag and aqueous acrylic
silicone emulsion at 125ml/ bag providing plaster for a thickness of 20mm mixed
with polycarboxylic sulphonated neutral cellulose at 100ml/bag and aqueous acrylic
silicone emulsion at 125ml/ bag, slurry of cement and silica sand should be mixed with
cross linked acrylic/ styrene/ butadiene based, polymer, spraying of silane and silanol
linear copolymer as water proof
43 Providing and laying CINDER CONCRETE in cement 1:15 (1 cement:15 cinder of Cum 400.00 1420.20 568080.00
12.5mm nominal size) on terraced roof or sunken slabs, laid to slope, compacting,
including cost of all materials, labour, curing as per drawing & specifications,
including all leads & lifts, loading, unloading charges, transportation cost and
conveyance of all materials, HOM of machinaries and equipments and all other
incidental charges at all floor levels etc., complete for successful completion of work as
directed by the Engineer-in-charge.
44 providing and laying in position PVC 40 mm perforated pipe in cinder concrete as metre 140.00 211.50 29610.00
per detail drawings and specification including the cost of all materials, cost of labour
HOM of equipment and machinery all lead and lift, loading and unloading charges,
transportation cost and conveyance of all materials, and all other incidental charges at
all floor levels etc complete for successful completion of work and as directed by the
engineer -in -charge .
FLOORING
46 Providing and laying heavy duty cobble stones 80mm thick interlock pavers, using Sqm 250.00 795.60 198900.00
cement and course sand for manufacture of blocks of approved size, shape and colour
with a minimum compressive strength of 281 kg per sqm over 50mm thick sand bed
(average thickness) and compacting with plate vibrator having 3 tons compaction force
thereby forcing part of sand underneath to come up in between joints, final compaction
of paver surface joints into its final level , including cost of all materials, HOM of
machineries and equipments, with all leads and lifts, loading and unloading charges ,
transportation cost and conveyance of all materials, labour for fixing the fixtures etc.,
complete for successful completion of work as per specifications at all floor levels and
as directed by the Engineer-in-Charge.
I In flooring,
a Ground Floor Sqm 400.00 864.00 345600.00
b First Floor Sqm 300.00 864.00 259200.00
c Second Floor Sqm 300.00 864.00 259200.00
d Third Floor Sqm 200.00 864.00 172800.00
II Providing and laying SKIRTING with 20 mm to 25 mm thick polished Kota stone
slabs using Cement Mortar1:6, 25mm thick over existing concrete bed or top of roof
laid to line and level and jointed with cement slurry mixed with pigment to match the
shade of the slab, including cost of all materials, labour, curing, polishing, all as per
drawings & specifications, HOM of equipments and machineries, all leads and lifts,
loading and unloading charges, transportation cost and conveyance of all material and
all other incidental charges etc., complete for successful completion of work and as
directed by the Engineer-in-charge.At all floor levels. In skirting 100mm high
In BORDER of corridor flooring and Staircase and Band Above Corridor Cladding
57 Providing and laying THRESHOLD with 20mm to 25 mm thick polished Kota stone Sqm 50.00 1192.50 59625.00
slabs using TILE ADHESIVE of approved make over existing concrete bed laid to
line and level and mixed with pigment to match the shade of the slab, after cleaning
the surface of dust&other free particles ,grease,oil,etc,including cost of all materials,
labour, curing, polishing, all as per drawings & specifications, HOM of equipments and
machineries, all leads and lifts, loading and unloading charges, transportation cost and
conveyance of all materials and all other incidental charges etc., complete for
successful completion of work and as directed by the Engineer-in-charge.At all floor
levels.
58 Providing and fixing of wall cladding using 20 mm thick gang saw water cut grey Sqm 1100.00 2429.10 2672010.00
granite in C.M 1:3 proportion cut to required shape, pattern with paper joints, finished
with cement mortar using white cement and colour pigments to match the colour of
slab making through jointing with sealent, making holes 25 mm x 12 mm grooves in
joints including curing etc., complete. including cost of all materials, labour, curing,
complete HOM of equipments and machineries, all leads and lift, loading and
unloading charges, transportation cost and conveyance of all materials, of all materials
and all other incidental charges at all floor levels etc., complete for successful
completion of work as per drawings & specifications and as directed by the Engineer-
in-charge.
( in corrdor )
60 Providing and laying FLOORING using pre-polished 19mm thick water cut/ gang saw Sqm 5.00 2048.40 10242.00
Black Granite using TILE ADHESIVE of approved make , pointed with white
cement/ colour pigment, includingcost of all materials, labour, curing, all as per
drawings & specifications, HOM of equipmens and machineries, all leads and lifts,
loading and unloading charges, transportation cost and conveyance of all materials, and
all other incidental charges at all floor levels etc., complete for successful completion
of work and as directed by Engineer-in-charge. ( In Corridor)
FINISHING WORK
61 Providing 12mm thick cement plaster in single coat with cement mortar 1:3 to
CEILING to required line and level including rounding of corners wherever required
smooth providing and removing scaffolding, curing, cost of all materials, labour, HOM
of equipments and machineries, all leads and lifts, Loading and unloading charges,
transportation cost and conveyanceof all materials , all other incidental charges etc.,
complete for successful completion of work all as per specifications and as directed by
the Engineer-in-charge.
a Ground Floor Sqm 1400.00 146.70 205380.00
b First Floor Sqm 1400.00 146.70 205380.00
c Second Floor Sqm 1000.00 146.70 146700.00
600mm x 600mm etc. complete including the cost of all materials, labour, HOM of
machinery, with all leads and lifts, loading and unloading, transportation cost and
conveyance of all materials and all other incidental charges etc.at all floor levels etc.
complete for successful completion of work as per detail drawings and specifications
and as directed by the Engineer -in-charge.
drawing, including curing and providing and removing the scaffolding wherever
necessary etc., complete including cost of materials, labour, HOM of equipments and
machineries, all leads and lifts, Loading and unloading charges, transportation cost and
conveyance of all materials , all other incidental charges at all floor levels etc.,
complete for successful completion of work all as per specifications and as directed by
the Engineer-in-charge.
SPECIAL ITEMS
69 Providing and fixing 19mm thick mirror polished, machine cut granite slab using
single piece Black Granite for Pantry platforms, Wash Basin counters, facias and
similar locations of required size of approved shade, colour and texture laid over 20mm
thick base cement mortar 1:6 (1 cement : 6 coarse sand) with joints treated with white
cement , mixed with matching pigment, epoxy touch ups, including rubbing, curing etc.
complete at all levels. including cost of materials, labour, curing, polishing complete as
per specifications., HOM of equipments and machineries, all leads and lifts, Loading
and unloading charges, transportation cost and conveyance of all materials, & all other
incidental charges at all floor levels etc., complete for successful completion of work
all as per specifications and as directed by the Engineer-in-charge.
73 Providing and fixing stainless steel wire gauze of average width of aperture 1.4mm Sqm 150.00 936.00 140400.00
with wire of 0.63mm dia fixed to existing aluminium frames using aluminium clips for
mosquito proof shutters at all floor levels cutting to size and finishing sides,
including cost of materials, labour, HOM of equipements and machineries all leads and
lifts, Loading and unoading, transportatio,at all levels etc,. complete for successful
completion of work as per specifications and as directed by the Engineer-in-charge.
74 Providing and fixing 10mm thick compact POLYCARBONATE SHEET with Sqm 150.00 4077.00 611550.00
aluminium profiles, EPDM ruber gasket, G.E Silicon sealant, cold forged fastners all as
per drawing including cost of materials, labour, HOM of equipments and machineries,
all leads and lifts, Loading and unloading charges, transportation cost and conveyance
of all materials, all other incidental charges at all floor levels etc., complete for
successful completion of work as per specifications and as directed by the Engineer-in-
charge.
NOTE: Rate is inclusive of aluminium work, sealant, gaskets, etc.
78 Supplying and fabricating, hoisting and erecting in position of hollow tubular truss Kgs 3000.00 94.50 283500.00
using medium and heavy section of different diameters confirming to IS
1161(amended up to date) as indicated in drawings(in wind column, jack
trusses,canopies,lattice girder,trusses,sub trusses,monitor roof,braces ties cladding
posts,purlins connecting beams,of columns including anchor bolts,washer etc.)at all
level and height the steel tubes when analysed in accordence with the methord
specified in IS 226-1975 shall show not less than 0.06 percent of sulphur,and not more
than 0.06 percent of phosphors,tubes shall be cleaned ,finished and free from scale
cracks,surface flaws,laminations, and other defects.and shall be cut clean and square
with axis of tube, unless otherwise specified. The component part of structure shall be
assembled in such a manner that they are neither twisted nor otherwise damaged and be
so prepared that the specified chambers are maintained,All material before being
assembeled shall be straighetend, if necessary, unless required
with a length of 133mm, this "J" bolt is later on twisted by 26mm, this "J" bolt has a
treaded portion of 47mm and this is provided with a nut of 3.63 mm thick and the dia of
the nut is 6.9mm, this nut has a washer and this washer has a dia of 19mm and the
thickness of 0.6mm and all this components are chromodised, later on G.l.supporting
rod of 4mm thick dia is twisted and fixed inside the nut and washer, then to maintain a
good, straight level of the false ceiling, the nut in "J" bolt is then moved up or down
for proper level. The Galvanized Iron 4 mm dia been cut to size of length required as
per site requirement then the wall at a prefect wall level and this pre-coated wall
channel are having two coats of primer and one coat of polyester paint of
desiredcolour, the wall channel will have a coat of primer applied on the rear side. This
wall channel are made of galvanized Iron and the grade of the galvanized Iron is as per
B18. This wall channel of 24mmx24mm is fixed on to
4mm and height adjustable "J" bolts system. The "T" grid system consists of special
steel is as per B18, and the thickness of the steel is 0.3mm thick. This "T" frame work
is capped with coil coated aluminum sheet and the grade of the Aluminum sheet is (AI-
Mn) 3003 of H-46 to H-48
81 Providing and fixing 50mm thick precast cement concrete Jali 1:2:4 (1 cement : 2 Sqm 40.00 670.50 26820.00
coarse sand : 4 graded stone aggregate 6mm nominal size) reinforced with 1.6 mm dia
mild steel wire including centering and shuttering, roughening cleaning, fixing and
finishing in cement mortar 1:3 (1 cement: 3 fine sand) ,curing etc. on steel frame
complete excluding the cost of frame work, including cost of materials, labour,
providing & removing necessary Scaffolding HOM of equipments and machineries, all
leads and lifts, Loading and unloading charges, transportation cost and conveyance of
all materials , all other incidental charges at all floor levels etc., complete for
successful completion of work as per specifications and as directed by the Engineer-in-
charge.
TOTAL 35851227.50