𝑭𝒓𝒐𝒏𝒕 𝑬𝒍𝒆𝒗𝒂𝒕𝒊𝒐𝒏

𝐴𝑟𝑒𝑎 @𝐴𝐵 = 3(3.5) = 10.5𝑠𝑞. 𝑚


𝐴𝑟𝑒𝑎 @𝐵𝐶 = (1.2 + 1.8)(3.9) = 11.7𝑠𝑞. 𝑚
𝐴𝑟𝑒𝑎 𝑡𝑜𝑡𝑎𝑙 = 22.2𝑠𝑞. 𝑚
𝐴𝑟𝑒𝑎 𝑜𝑓 𝑊3 = 1.6(0.45 + 1.45) = 3.04𝑠𝑞. 𝑚
𝐴𝑟𝑒𝑎 𝑜𝑓 𝑊1 = 2(0.45)(2.1) = 1.89𝑠𝑞. 𝑚
𝐴𝑟𝑒𝑎 𝑜𝑓 𝐷1 = 1.05(2.1) = 2.205𝑠𝑞. 𝑚
𝐴𝑟𝑒𝑎 𝑡𝑜𝑡𝑎𝑙 = 7.135𝑠𝑞. 𝑚
𝑁𝑒𝑡 𝑎𝑟𝑒𝑎 = 22.2 − 7.135 = 15.065𝑠𝑞. 𝑚
𝐶𝐻𝐵: 15.065(12.5) = 189𝑝𝑐𝑠

𝑪𝒆𝒎𝒆𝒏𝒕 𝑴𝒐𝒓𝒕𝒂𝒓 − 𝑢𝑠𝑖𝑛𝑔 10𝑥20𝑥40𝑐𝑚 𝑠𝑖𝑧𝑒 𝑜𝑓 𝐶𝐻𝐵, 𝑢𝑠𝑖𝑛𝑔 𝑐𝑙𝑎𝑠𝑠 𝐵 𝑚𝑖𝑥𝑡𝑢𝑟𝑒 (40𝑘𝑔)
𝐶𝑒𝑚𝑒𝑛𝑡 = 15.065𝑥0.525 = 8 𝑏𝑎𝑔𝑠
𝑆𝑎𝑛𝑑 = 15.065𝑥1.0 = 15.065𝑐𝑢. 𝑚

𝑪𝒆𝒎𝒆𝒏𝒕 𝒑𝒍𝒂𝒔𝒕𝒆𝒓, 𝑢𝑠𝑖𝑛𝑔 𝑐𝑙𝑎𝑠𝑠 𝐵 𝑚𝑖𝑥𝑡𝑢𝑟𝑒 (40𝑘𝑔)


𝐶𝑒𝑚𝑒𝑛𝑡 = 15.065𝑥0.192 = 3 𝑏𝑎𝑔𝑠
𝑆𝑎𝑛𝑑 = 15.065𝑥0.016 = 0.241𝑐𝑢. 𝑚

𝑭𝒐𝒐𝒕𝒊𝒏𝒈
𝑇𝑜𝑡𝑎𝑙 𝑙𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝑤𝑎𝑙𝑙 = 3 + 1.2 + 1.8 = 6𝑚
𝑈𝑠𝑖𝑛𝑔 15𝑥40 , 𝑐𝑙𝑎𝑠𝑠 𝐴 𝑚𝑖𝑥𝑡𝑢𝑟𝑒(40𝑘𝑔)
𝐶𝑒𝑚𝑒𝑛𝑡: 6𝑥0.54 = 4𝑏𝑎𝑔𝑠
𝑆𝑎𝑛𝑑 = 6𝑥0.03 = 0.18𝑐𝑢. 𝑚
𝐺𝑟𝑎𝑣𝑒𝑙 = 6𝑥0.06 = 0.36𝑐𝑢. 𝑚
𝑹𝑬𝑨𝑹 𝑬𝑳𝑬𝑽𝑨𝑻𝑰𝑶𝑵
𝑇𝑜𝑡𝑎𝑙 𝑎𝑟𝑒𝑎 = 22.2𝑠𝑞. 𝑚
𝐴𝑟𝑒𝑎 𝑜𝑓 𝑊5 = 1.8(1) = 1.8𝑠𝑞. 𝑚
𝐴𝑟𝑒𝑎 𝑜𝑓 𝐷2 = 0.8(2.1) = 1.68𝑠𝑞. 𝑚
𝑁𝑒𝑡 𝑎𝑟𝑒𝑎 = 22.2 − 1.8 − 1.68 = 18.72𝑠𝑞. 𝑚
𝐶𝐻𝐵 = 18.72𝑥12.5 = 234𝑝𝑐𝑠

𝑪𝒆𝒎𝒆𝒏𝒕 𝑴𝒐𝒓𝒕𝒂𝒓 − 𝑢𝑠𝑖𝑛𝑔 10𝑥20𝑥40𝑐𝑚 𝑠𝑖𝑧𝑒 𝑜𝑓 𝐶𝐻𝐵, 𝑢𝑠𝑖𝑛𝑔 𝑐𝑙𝑎𝑠𝑠 𝐵 𝑚𝑖𝑥𝑡𝑢𝑟𝑒 (40𝑘𝑔)
𝐶𝑒𝑚𝑒𝑛𝑡 = 18.72𝑥0.525 = 10 𝑏𝑎𝑔𝑠
𝑆𝑎𝑛𝑑 = 18.72𝑥1.0 = 18.72𝑐𝑢. 𝑚

𝑪𝒆𝒎𝒆𝒏𝒕 𝒑𝒍𝒂𝒔𝒕𝒆𝒓, 𝑢𝑠𝑖𝑛𝑔 𝑐𝑙𝑎𝑠𝑠 𝐵 𝑚𝑖𝑥𝑡𝑢𝑟𝑒 (40𝑘𝑔)


𝐶𝑒𝑚𝑒𝑛𝑡 = 18.72𝑥0.192 = 4 𝑏𝑎𝑔𝑠
𝑆𝑎𝑛𝑑 = 18.72𝑥0.016 = 0.2995𝑐𝑢. 𝑚

𝑭𝒐𝒐𝒕𝒊𝒏𝒈
𝑇𝑜𝑡𝑎𝑙 𝑙𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝑤𝑎𝑙𝑙 = 3 + 1.2 + 1.8 = 6𝑚
𝑈𝑠𝑖𝑛𝑔 15𝑥40 , 𝑐𝑙𝑎𝑠𝑠 𝐴 𝑚𝑖𝑥𝑡𝑢𝑟𝑒(40𝑘𝑔)
𝐶𝑒𝑚𝑒𝑛𝑡: 6𝑥0.54 = 4𝑏𝑎𝑔𝑠
𝑆𝑎𝑛𝑑 = 6𝑥0.03 = 0.18𝑐𝑢. 𝑚
𝐺𝑟𝑎𝑣𝑒𝑙 = 6𝑥0.06 = 0.36𝑐𝑢. 𝑚
RIGHT SIDE ELVATION

Area total =8x3.9=31.2sq.m

Area of W3=1.6x1.45=2.32sq.m

Net Area=31.2-2.32=28.88sq.m

CHB=28.88x12.5=361pcs

𝑪𝒆𝒎𝒆𝒏𝒕 𝑴𝒐𝒓𝒕𝒂𝒓 − 𝑢𝑠𝑖𝑛𝑔 10𝑥20𝑥40𝑐𝑚 𝑠𝑖𝑧𝑒 𝑜𝑓 𝐶𝐻𝐵, 𝑢𝑠𝑖𝑛𝑔 𝑐𝑙𝑎𝑠𝑠 𝐵 𝑚𝑖𝑥𝑡𝑢𝑟𝑒 (40𝑘𝑔)
𝐶𝑒𝑚𝑒𝑛𝑡 = 28.88𝑥0.525 = 16 𝑏𝑎𝑔𝑠
𝑆𝑎𝑛𝑑 = 28.88𝑥1.0 = 28.88𝑐𝑢. 𝑚

𝑪𝒆𝒎𝒆𝒏𝒕 𝒑𝒍𝒂𝒔𝒕𝒆𝒓, 𝑢𝑠𝑖𝑛𝑔 𝑐𝑙𝑎𝑠𝑠 𝐵 𝑚𝑖𝑥𝑡𝑢𝑟𝑒 (40𝑘𝑔)


𝐶𝑒𝑚𝑒𝑛𝑡 = 28.88𝑥0.192 = 6 𝑏𝑎𝑔𝑠
𝑆𝑎𝑛𝑑 = 28.88𝑥0.016 = 0.462𝑐𝑢. 𝑚

𝑭𝒐𝒐𝒕𝒊𝒏𝒈
𝑇𝑜𝑡𝑎𝑙 𝑙𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝑤𝑎𝑙𝑙 = 8𝑚
𝑈𝑠𝑖𝑛𝑔 15𝑥40 , 𝑐𝑙𝑎𝑠𝑠 𝐴 𝑚𝑖𝑥𝑡𝑢𝑟𝑒(40𝑘𝑔)
𝐶𝑒𝑚𝑒𝑛𝑡: 8𝑥0.54 = 5𝑏𝑎𝑔𝑠
𝑆𝑎𝑛𝑑 = 8𝑥0.03 = 0.24𝑐𝑢. 𝑚
𝐺𝑟𝑎𝑣𝑒𝑙 = 8𝑥0.06 = 0.48𝑐𝑢. 𝑚
LEFT SIDE ELEVATION

Area total =8x3.9=31.2sq.m

Area of W2=1.8x0.3x2=1.08sq.m

Area of W6=1.8x1=1.8sq.m

Area of W4=1.6x1.2=1.92sq.m

Net area= 31.2 -1.08-1.8-1.92=26.4sqm

CHB=26.4x12.5=330pcs

𝑪𝒆𝒎𝒆𝒏𝒕 𝑴𝒐𝒓𝒕𝒂𝒓 − 𝑢𝑠𝑖𝑛𝑔 10𝑥20𝑥40𝑐𝑚 𝑠𝑖𝑧𝑒 𝑜𝑓 𝐶𝐻𝐵, 𝑢𝑠𝑖𝑛𝑔 𝑐𝑙𝑎𝑠𝑠 𝐵 𝑚𝑖𝑥𝑡𝑢𝑟𝑒 (40𝑘𝑔)
𝐶𝑒𝑚𝑒𝑛𝑡 = 26.4𝑥0.525 = 14 𝑏𝑎𝑔𝑠
𝑆𝑎𝑛𝑑 = 26.4𝑥1.0 = 26.4𝑐𝑢. 𝑚

𝑪𝒆𝒎𝒆𝒏𝒕 𝒑𝒍𝒂𝒔𝒕𝒆𝒓, 𝑢𝑠𝑖𝑛𝑔 𝑐𝑙𝑎𝑠𝑠 𝐵 𝑚𝑖𝑥𝑡𝑢𝑟𝑒 (40𝑘𝑔)


𝐶𝑒𝑚𝑒𝑛𝑡 = 26.4𝑥0.192 = 6 𝑏𝑎𝑔𝑠
𝑆𝑎𝑛𝑑 = 26.4𝑥0.016 = 0.4224𝑐𝑢. 𝑚

𝑭𝒐𝒐𝒕𝒊𝒏𝒈
𝑇𝑜𝑡𝑎𝑙 𝑙𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝑤𝑎𝑙𝑙 = 8𝑚
𝑈𝑠𝑖𝑛𝑔 15𝑥40 , 𝑐𝑙𝑎𝑠𝑠 𝐴 𝑚𝑖𝑥𝑡𝑢𝑟𝑒(40𝑘𝑔)
𝐶𝑒𝑚𝑒𝑛𝑡: 8𝑥0.54 = 5𝑏𝑎𝑔𝑠
𝑆𝑎𝑛𝑑 = 8𝑥0.03 = 0.24𝑐𝑢. 𝑚
𝐺𝑟𝑎𝑣𝑒𝑙 = 8𝑥0.06 = 0.48𝑐𝑢. 𝑚
SUMMARY

ELEVATION CHB CEMENT MORTAR CEMENT PLASTER


CLASS B (40KG) CLASS B (40KG)

CEMENT (bags) SAND (cu.m) CEMENT (bags) SAND (cu.m)

FRONT 189 8 15.065 3 0.241


REAR 234 10 18.72 4 0.2995
RIGHT SIDE 361 16 28.88 6 0.462
LEFT SIDE 330 14 26.4 6 0.4224
TOTAL 1114PCS 48bags 89.065cu.m 19bags 1.4249cu.m

FOOTING
USING 15X14 , CLASS A (40KG)
ELEVATION LENGHT
CEMENT SAND (cu.m) GRAVEL(cu.m)
(bags)
FRONT 6m 4 0.18 0.36
REAR 6m 4 0.18 0.36
RIGHT SIDE 8m 5 0.24 0.48
LEFT SIDE 8m 5 0.24 0.48
TOTAL 18bags 0.09cu.m 0.36cu.m