Control Valve Quality Assurance, Inspection, and Test Plan
Requirements
This document is the confidential property of Chevron U.S.A. Inc. and its affiliates. When made available
to any contractor providing services to Chevron U.S.A. Inc. or its affiliates, the contractor’s use of this
document shall be governed by the confidentiality provisions of the applicable contract or bid package.
Without limiting the foregoing, neither the whole nor any part of this document may be disclosed by the
contractor to any third party, other than an affiliate of the contractor that requires this information for
purposes of the contract with the Chevron entity, without the prior written consent of the Chevron entity
that has disclosed this document to the contractor. When requested by Chevron U.S.A. Inc. or its
disclosing affiliate, the contractor must return all copies of this document to the Chevron entity
requesting such return and delete any electronic copies from the contractor’s systems.
Any and all modifications (changes, amendments, etc.) to this document must follow approved
Chevron Engineering Standards governance processes.
February 2015 © 2015–2018 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 1 of 52
Control Valve Quality Assurance, Inspection, and Test Plan Requirements ICM-PU-5316.2
Summary of Changes
1. Revised technical content is indicated by change bars in the right margin.
2. Added, deleted, moved, and combined items are listed below.
February 2015 © 2015–2018 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 2 of 52
Control Valve Quality Assurance, Inspection, and Test Plan Requirements ICM-PU-5316.2
Contents
1.0 Scope............................................................................................................................................... 5
2.0 References ...................................................................................................................................... 6
2.1 Owner Documents .............................................................................................................. 6
2.2 Industry Codes and Standards ........................................................................................... 6
2.3 Conflict Resolution .............................................................................................................. 8
3.0 Acronyms ........................................................................................................................................ 8
4.0 Quality Management and Quality Control ................................................................................. 10
4.1 General ............................................................................................................................. 10
4.2 Non-Conforming Products ................................................................................................ 11
5.0 Fisher Manufacturing Procedures – Pre-Accepted .................................................................. 13
5.1 General ............................................................................................................................. 13
5.2 Welding Procedures .......................................................................................................... 14
5.3 Testing Procedures ........................................................................................................... 15
5.4 Painting Procedures .......................................................................................................... 15
5.5 Packaging Procedures ...................................................................................................... 15
6.0 Inspection Requirements ............................................................................................................ 15
6.1 General ............................................................................................................................. 15
6.2 Inspections ........................................................................................................................ 17
6.3 Visual ................................................................................................................................ 17
6.4 Dimensional ...................................................................................................................... 18
6.5 Material ............................................................................................................................. 18
6.6 Final Inspection ................................................................................................................. 19
6.7 Rust Prevention and Painting Inspection .......................................................................... 19
7.0 Testing Requirements ................................................................................................................. 19
7.1 General ............................................................................................................................. 19
7.2 Nondestructive Examination ............................................................................................. 20
7.3 Pressure Tests .................................................................................................................. 22
7.4 Functional (Operational) Test ........................................................................................... 23
8.0 Witness Test Points ..................................................................................................................... 25
9.0 Control Valve QC/ITP Requirements Tables ............................................................................. 26
9.1 General ............................................................................................................................. 26
9.2 QC/ITP Requirements Table Details................................................................................. 27
9.3 Item Number ..................................................................................................................... 27
9.4 Activity Selected, Type, and Description........................................................................... 27
9.5 Reference Documents ...................................................................................................... 28
9.6 Acceptance Criteria and Reference of Certification/Documentation ................................ 29
9.7 Responsibility and Inspection Record ............................................................................... 29
February 2015 © 2015–2018 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 3 of 52
Control Valve Quality Assurance, Inspection, and Test Plan Requirements ICM-PU-5316.2
List of Tables
Table 1: Control Valve Metallurgy for Test Selection ..................................................................... 31
Table 2: Fisher Manufacturing Pre-Accepted Procedures ............................................................. 39
Table 3: ANSI Class < 900 Control Valve QC/ITP Tag Summary ................................................. 41
Table 4: ANSI Class < 900 Control Valve QC/ITP Requirements ................................................ 42
Table 5: ANSI Class ≥ 900 Control Valve QC/ITP Tag Summary ................................................. 47
Table 6: ANSI Class ≥ 900 Control Valve QC/ITP Requirements ................................................ 48
February 2015 © 2015–2018 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 4 of 52
Control Valve Quality Assurance, Inspection, and Test Plan Requirements ICM-PU-5316.2
1.0 Scope
1. This specification addresses the following requirements for control valve assemblies
(control valve, actuator, and accessories):
a. Quality Management (QM)
b. Quality Assurance (QA)
c. Quality Control (QC)
d. Inspection and Testing
e. Factory Acceptance Testing (FAT)
2. This specification addresses the requirements as related to engineering, procurement,
manufacturing, fabrication, assembly, inspection, testing, and documentation activities that
are met by the following:
a. Supplier providing goods and services directly to Purchaser.
b. Sub-Suppliers providing goods and services on behalf of the main Supplier.
3. The scope of this specification covers the following control valves and control valve
assemblies:
a. Globe, angle, ball, butterfly, and disc control valves, whether or not the control valve
has an actuator.
b. Air-operated diaphragm actuators and piston actuators that are either spring-return or
double-acting.
c. Control valve positioning devices.
d. Cast and forged control valves.
4. The following control valves, valves, and valve applications are not within the scope of this
document:
a. Hand-operated valves.
b. Gate valves.
c. Direct-operated or self-contained regulators.
d. Electric-motor operated control valves.
e. Automated on-off valves.
5. This specification does not address the verification and testing of the control valve
assembly once receipt of the control valve assembly is on site.
a. Project technical requirements should identify and address the verification and testing
requirements once the control valve assembly has arrived on site.
b. Activities and tasks should be performed once the control valve assembly has arrived
on site to verify functionality, hook-ups, and integration with the control system.
February 2015 © 2015–2018 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 5 of 52
Control Valve Quality Assurance, Inspection, and Test Plan Requirements ICM-PU-5316.2
2.0 References
1. The following documents are referenced herein and are considered part of this
specification.
2. Unless otherwise specified in Sections 2.1 or 2.2, use the latest edition of the referenced
documents in effect at the time of placement of the initial purchase order.
February 2015 © 2015–2018 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 6 of 52
Control Valve Quality Assurance, Inspection, and Test Plan Requirements ICM-PU-5316.2
February 2015 © 2015–2018 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 7 of 52
Control Valve Quality Assurance, Inspection, and Test Plan Requirements ICM-PU-5316.2
3.0 Acronyms
Note: Some acronyms appear only in ICM-IT-5316.
A Accept
AM Amendment
BDV Blowdown/Depressurization Valve
CMTR Certified Material Test Report
CR Criticality Rating
CSP Customer Special
CVPP Control Valve Procurement Procedures
D Data (activity type)
DFT Dry Film Thickness
DVC Digital Valve Controller
EPC Engineering, Procurement, and Construction
ESD Emergency Shutdown
FAT Factory Acceptance Testing
FSH Fisher
H Hold
HT Hardness Testing
I Inspection; also Information (activity types)
ITP Inspection and Test Plan
February 2015 © 2015–2018 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 8 of 52
Control Valve Quality Assurance, Inspection, and Test Plan Requirements ICM-PU-5316.2
February 2015 © 2015–2018 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 9 of 52
Control Valve Quality Assurance, Inspection, and Test Plan Requirements ICM-PU-5316.2
February 2015 © 2015–2018 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 10 of 52
Control Valve Quality Assurance, Inspection, and Test Plan Requirements ICM-PU-5316.2
h. Handling, storage, and preservation of material, equipment, and packing plan. Supplier
shall provide lifting certifications and lift diagrams with the center of gravity notation
as part of the shipping documentation.
i. Control, storage, and handover of spare parts and associated documentation.
j. Identification, reporting, tracking, and resolution of non-conformances at
Supplier’s/Sub-Supplier’s shop, and at involved manufacturing, assembly, and test
locations and installation sites.
k. Documenting, controlling, and ensuring effectiveness of corrective and preventative
action.
l. Performing internal audits of quality-related activities and external audits of Sub-
Suppliers.
m. Controlling process activities, from issuance of design documents through fabrication
to final testing, certification, close-out documentation, and shipment.
n. Controlling and managing the engineering design review process as an incorporation of
previous lessons learned and design reviews.
7. QA/QC activities and status records shall be compiled in the database referencing the
appropriate ITP, procedure, and certification, so that the QA/QC status can be continually
monitored as the work progresses.
February 2015 © 2015–2018 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 11 of 52
Control Valve Quality Assurance, Inspection, and Test Plan Requirements ICM-PU-5316.2
February 2015 © 2015–2018 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 12 of 52
Control Valve Quality Assurance, Inspection, and Test Plan Requirements ICM-PU-5316.2
l. Name, title, and dated signature of the Supplier representative who determined and re-
verified by review, inspection, test, or objective evidence that non-conforming product
corrected by rework or repair demonstrates conformity to the requirements.
Note: If non-Fisher control valves are selected, the project team should expect delivery of
the control valves to take much longer, and months of schedule delays will be
incurred in accepting the control valve manufacturing procedures. These delays
would be similar for each additional control valve manufacturer used on the
project.
3. The core group of Fisher manufacturing procedures has been pre-accepted by Owner and
shall require concurrence from the project team only with the acceptance of each
manufacturing procedure.
Note: The pre-acceptance of this core group of Fisher internal manufacturing procedures
ensures consistency. It saves project hours and reduces the schedule to procure the
project control valves.
February 2015 © 2015–2018 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 13 of 52
Control Valve Quality Assurance, Inspection, and Test Plan Requirements ICM-PU-5316.2
The “Purchaser” of the control valves is not the Owner but rather the Engineering,
Procurement, and Construction (EPC) Supplier. Since many Owner projects may
be ongoing at any time, with different EPC Suppliers being utilized for each Major
Capital Project (MCP), Fisher is required to re-review and re-submit these
manufacturing procedures for review and acceptance on each MCP.
This process causes significant delays in procurement of the control valve order
execution. To minimize or eliminate this delay and improve lead times, Owner
subject matter experts and Fisher’s subject matter experts have developed Owner-
wide acceptance of these Internal Fisher Manufacturing Procedures.
4. The core group of pre-accepted internal Fisher manufacturing procedures as specified in
Table 2 of Appendix A have been categorized as follows:
a. Welding fabrication and welding repair.
b. Testing.
c. Painting.
d. Packaging.
February 2015 © 2015–2018 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 14 of 52
Control Valve Quality Assurance, Inspection, and Test Plan Requirements ICM-PU-5316.2
February 2015 © 2015–2018 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 15 of 52
Control Valve Quality Assurance, Inspection, and Test Plan Requirements ICM-PU-5316.2
2. The inspector shall examine the components as described herein, the documentation,
certificates, etc., for each control valve to ensure compliance with project documentation.
The following shall be checked:
a. Surface finish.
b. Heat or cast number.
c. Mechanical properties.
d. Heat treat condition.
e. NDE utilized and results.
f. Certificate number(s).
3. All control valves equal to or greater than ANSI Class 900 shall be inspected.
4. Supplier shall develop an internal system and an external system for a technical compliance
audit program that complies with ISO 9001. The system shall be specified by contract,
purchase order, and statutory requirements.
5. Inspection of control valves shall be performed by Supplier in accordance with API 598,
API 6D, ASME B16.5, and ASME B16.34, as applicable.
6. Supplier, as a minimum, shall make provisions for inspecting levels 1 and 2, unless
specifically waived in writing by Purchaser, with acceptance by Owner.
7. Deviations from the following specified inspection points shall be obtained in writing from
Purchaser:
a. Level 1 Inspection – Resident inspection (manufacturing inspection), including daily
inspections to ensure that the shop is manufacturing equipment for the referenced
order.
b. Level 2 Inspection – Pre-inspection meeting with regular in-process inspection visits.
8. Inspection provisions shall be in accordance with the project technical requirements and
this specification.
9. Supplier shall use the inspection points in item 7 above to accomplish the following:
a. Ensure that incoming materials and equipment are properly identified.
b. Conform to the requirements of purchase documents.
c. Determine that the materials have not been damaged during transport.
10. Purchaser and Owner, per ICM-IT-5316, shall reserve the right to inspect the control
valve/actuator assemblies at any time during fabrication to ensure that the materials and
workmanship are in accordance with specifications and applicable standards and codes.
The applicable manufacturing “hold, accept, review, witness, and inspection points” shall
be implemented in the schedule to accommodate this requirement.
11. Refer to the appropriate sections of project or facility governing contracts and purchase
documents for control valve assembly warranty terms.
February 2015 © 2015–2018 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 16 of 52
Control Valve Quality Assurance, Inspection, and Test Plan Requirements ICM-PU-5316.2
6.2 Inspections
1. Supplier shall conduct in-process inspection for items during manufacturing, fabrication,
assembly, and testing in accordance with Owner-accepted quality plan, ITPs, and
procedures.
2. Inspections shall include the following (not all inclusive):
a. Identification.
b. Quantity.
c. Visual.
d. Dimensional.
e. Material.
f. Rust prevention.
g. Painting.
6.3 Visual
1. Control valves shall have permanent identification on the valve bodies, including the
following information:
a. Size.
b. ANSI class rating.
c. Flow direction.
d. Material.
e. Manufacturer’s name.
2. Forgings shall be void of the following:
a. Scars.
b. Cracks.
c. Fullering.
d. Laps.
3. Visual inspection of castings shall be in accordance with MSS SP-55.
4. Castings shall be free of harmful defects such as sand inclusion burning and cracks, fins,
and blow holes for the following:
a. External surfaces.
b. Internal surfaces.
c. Machined surfaces.
d. Seat surfaces.
5. Flow paths shall be properly finished and cleaned.
6. Corners and fillets without specific dimensions shall be properly rounded and chamfered.
February 2015 © 2015–2018 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 17 of 52
Control Valve Quality Assurance, Inspection, and Test Plan Requirements ICM-PU-5316.2
7. Each control valve shall be checked for the following, to verify that it conforms to the
instrument data sheets:
a. Manufacturer.
b. Model.
c. Material.
d. Range.
e. Accessories.
f. Flow direction.
8. Control valves shall be checked to verify that digital controller positioner is installed.
9. The following shall be confirmed:
a. Control valve packing conforms to the data sheet.
b. If specified, the lubricator on each control valve contains the correct lubricant.
c. One pressure regulator is provided per instrument air user (such as a pneumatic
instrument or control valve assembly).
d. Each valve positioner has a visible sign cautioning the use of magnets at or around the
valve components.
10. Locations of control valves and other components, as shown on the P&IDs with respect to
vessels, piping, valves, and equipment, shall be verified.
6.4 Dimensional
The control valve body and assembly shall be verified with the accepted assembly drawings
and purchase order.
6.5 Material
1. Material certifications shall be submitted for the following:
a. Body.
b. Bonnet.
c. Flange.
d. Volume tanks.
2. Materials that are used for the components shall be stated and identified on the accepted
drawings and/or other appropriate documentation.
3. The reference number (if any) of the material shall be identified on the drawings and other
applicable documents.
4. The materials for the covered components (not all inclusive) shall be as follows:
a. Body.
b. Bonnet.
c. Stem.
February 2015 © 2015–2018 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 18 of 52
Control Valve Quality Assurance, Inspection, and Test Plan Requirements ICM-PU-5316.2
d. Trim.
e. Closure member.
f. Flanges.
g. Volume tanks.
February 2015 © 2015–2018 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 19 of 52
Control Valve Quality Assurance, Inspection, and Test Plan Requirements ICM-PU-5316.2
5. If control valve assembly does not pass testing requirements due to quality of work as
defined by ICM-IT-5316, Purchaser shall have the right to require retesting with Owner
review and acceptance.
6. Butterfly and disc-type valves shall be tested by the valve Supplier in accordance with
ASME B16.34 or MSS SP-61, as applicable.
7. Testing of other control valve types shall be performed by Supplier in accordance with the
following industry standards for testing of control valves:
a. ISA 75.19.01 for hydro test.
b. FCI 70-2 for seat leak test.
8. Test pressure for valve bodies shall be in accordance with the rating defined in
ASME B16.5.
9. Control valves shall be properly drained and dried after testing.
10. Tests shall include the following (not all inclusive):
a. NDE (if required).
1) RT.
2) LPT.
b. Pressure test.
1) Shell.
2) Back seat test (if bi-directional shut-off required).
3) Seat leakage.
4) Low-pressure seat test (pneumatic seat test).
c. Functional (operational test).
7.2.1 General
1. NDE requirements shall be covered in project specifications and shall be subject to further
development by Supplier.
2. To ensure quality, the following minimum requirements shall be applied where not
included in these specifications. Manufacturing procedures for Fisher Control Valves
addressing NDE requirements shall have been pre-accepted as defined in Table 2 of
Appendix A.
a. Prior to the start of NDE for materials and welds, Supplier shall establish detailed
procedures to cover NDE requirements.
b. Non-accepted NDE procedures shall be submitted for Purchaser and Owner acceptance
for all proposed NDE methods and techniques prior to the start of work.
c. As a minimum, procedures shall contain NDE map or drawing(s). In the case of simple
components such as piping, an NDE procedure summary shall be acceptable.
February 2015 © 2015–2018 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 20 of 52
Control Valve Quality Assurance, Inspection, and Test Plan Requirements ICM-PU-5316.2
d. Supplier shall use only accredited companies and testing laboratories for NDE and
testing services. Selection of companies shall be subject to Purchaser and Owner
acceptance.
February 2015 © 2015–2018 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 21 of 52
Control Valve Quality Assurance, Inspection, and Test Plan Requirements ICM-PU-5316.2
7.3.1 General
1. The pressure tests shall be performed as follows:
a. Shell.
b. Back seat test (if bi-directional flow required).
c. Seat leakage.
d. Low-pressure seat test (pneumatic seat test).
2. The pressure test shall be as follows:
a. Test fluid viscosity shall be less than water.
b. Water shall be treated via a reverse osmosis process containing a low chloride rust
inhibitor.
c. Shell and back seat test shall use a test fluid of water.
d. Low pressure seat test shall use air as the test fluid.
February 2015 © 2015–2018 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 22 of 52
Control Valve Quality Assurance, Inspection, and Test Plan Requirements ICM-PU-5316.2
6. Pressure shall be applied on the upstream side of the valve end connection, which is
upstream of the seat.
7. The downstream side shall be observed for leakage and the leakage shall be measured.
8. If the valve application requires bi-directional flow and/or shut-off requirements in the
reverse flow direction, the test shall be conducted in both directions.
9. The test requirement shall be as specified on the data sheet.
10. The following parameters shall be recorded:
a. Water temperature (only if facility is not environmentally controlled).
b. Body temperature (only if facility is not environmentally controlled).
c. Test pressures.
d. Water quality.
11. After the hydrostatic leakage test is complete, the following actions shall be performed on
the control valve:
a. Depressurized.
b. Drained.
c. Dried.
d. Desiccant/preservative applied.
February 2015 © 2015–2018 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 23 of 52
Control Valve Quality Assurance, Inspection, and Test Plan Requirements ICM-PU-5316.2
6. The valve body and bonnets shall pass a hydrostatic test at Supplier’s facility. Hydro test
and inspection shall be in accordance with either ISA 75.19.01 or API 598.
7. All functions of the control valve and control valve assembly shall be verified and
recorded, such as the following (list not all inclusive):
a. Record baseline data during operational and functional tests (signature prior to
packaging, shipping, and delivery):
1) Signature (verify digital storage of baseline data).
2) Analog input signals.
3) Hysteresis.
4) Linearity.
5) Deadband.
6) Instrument control signal to pneumatic conversion.
7) Friction.
8) Step response.
9) Dynamic test (scan).
10) Drive signal.
11) Travel.
12) Valve position.
13) Non-volatile memory verification.
b. Fail action on loss of motive forces:
1) Instrument air to the control valve assembly.
2) Control signal to the digital valve positioner.
3) Control signal to the solenoid valve.
c. Control valve internals (written documentation verification):
1) Packing.
2) Seat and plug.
d. Actuator and yoke assembly:
1) Packing follower.
2) Fasteners.
3) Bolts.
4) Nuts.
e. Accessories:
1) Regulator (airsets).
2) Volume boosters.
3) Quick exhausts (if accepted).
February 2015 © 2015–2018 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 24 of 52
Control Valve Quality Assurance, Inspection, and Test Plan Requirements ICM-PU-5316.2
4) Insect screens.
5) Tubing metallurgy.
f. Open and close functionality (not to exceed data sheet requirements):
1) Open/closing times.
2) Travel deviation.
3) Travel cutoff high and low.
4) Travel setpoint.
g. Pressure:
1) Supply.
2) Output to the actuator.
3) Fall-back.
4) Sensor fail.
5) Supply pressure verification above upper bench set.
6) Verify relays.
h. Alerts:
1) Cycle counter.
2) Deadband.
3) Pressure.
i. Deviation.
ii. Supply.
iii. Output to actuator.
iv. Sensor failure.
4) Travel deviation.
5) High and low travel alerts.
6) Notifications full.
February 2015 © 2015–2018 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 25 of 52
Control Valve Quality Assurance, Inspection, and Test Plan Requirements ICM-PU-5316.2
Note: Some control valve applications require additional technical options to ensure that
the control valve meets the requirements of the design intent. The non-standard
technical options that are available for each ITP may have an impact on cost and
schedule, which should not be a deterrent to the inclusion of the additional options
and resulting activities, as technically required.
February 2015 © 2015–2018 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 26 of 52
Control Valve Quality Assurance, Inspection, and Test Plan Requirements ICM-PU-5316.2
Note: The standard and optional activities have been defined based on information from
QC/ITPs of previous Major Capital Projects (MCPs).
February 2015 © 2015–2018 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 27 of 52
Control Valve Quality Assurance, Inspection, and Test Plan Requirements ICM-PU-5316.2
a. Data – D
b. Inspection – I
c. Packaging – PK
d. Painting – PT
e. Testing – T
f. Welding – W
2. The activity type shall be correlated with the requirements identified in Table 2 in
Appendix A to provide the type of Fisher manufacturing procedure to be used for the
activity.
February 2015 © 2015–2018 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 28 of 52
Control Valve Quality Assurance, Inspection, and Test Plan Requirements ICM-PU-5316.2
3. Additional manufacturing procedures shall be developed by the EPC and project team as
required to meet the control valve application. These procedures shall require Owner
acceptance.
9.7.1 Responsibility
1. The column titled Responsibility shall consist of the following three types of information:
a. Entity responsible for activity and/or action.
b. Quality control points (QCPs).
c. Criticality rating (CR) of the control valve.
2. The columns titled Inspection Responsibility in the QC/ITP table shall specify one of the
following entities to perform the QCP based on the CR as follows:
a. Fisher Sub-Supplier.
b. The control valve manufacturer ‒ Fisher Controls/Local Business Partner (LBP).
c. Contractor.
d. Owner.
3. The QC/ITP QCP shall be as follows:
a. H (Hold) ‒ Work stops until a formal release or inspection release has been received or
the hold has been waived.
b. R (Review) ‒ Document sent for review only, work does NOT stop.
c. W (Witness) ‒ Witness invitation is issued for a specific date; if responsible individual
does not attend and/or respond, work continues.
d. A (Accept) ‒ Document must be accepted before work continues.
February 2015 © 2015–2018 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 29 of 52
Control Valve Quality Assurance, Inspection, and Test Plan Requirements ICM-PU-5316.2
February 2015 © 2015–2018 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 30 of 52
Control Valve Quality Assurance, Inspection, and Test Plan Requirements ICM-PU-5316.2
3. The proper Fisher manufacturing procedure (as identified in Table 6) shall be selected for
the Test Selected Based on Metallurgy section.
4. Table 6 shall be completed with these items by defining the following:
a. Selected item ‒ a check mark ( ).
b. Items not selected ‒ a blank field ( ).
February 2015 © 2015–2018 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 31 of 52
Control Valve Quality Assurance, Inspection, and Test Plan Requirements ICM-PU-5316.2
12. Castings shall be preheated to a minimum 400°F (204°C) prior to welding, unless the
mandated code or standard requires a higher preheat temperature, in which case the code or
standard shall be followed (e.g., ASME Section IX qualified weld procedure) with Owner
review and agreement.
13. Chromium-molybdenum alloys shall be post-weld heat treated after welding is complete.
Note: Pickling is a soaking of the casting in an acid bath to remove hardened scale that
develops during the manufacturing process. If the casting is stainless steel,
commercial blast cleaning alone is not acceptable. Supplier must be made aware
of this requirement early so that appropriate and realistic quotes, including
delivery and cost, can be provided.
4. Critical body and bonnet castings sections, typically defined by ASME B16.34, shall be
radiographed and shall meet the requirements of ASTM E446 (up to 2 inches [50 mm]
thick) as follows:
a. Category A, B, & CA = Level 2.
b. Category CB, CC, & CD = Level 3.
c. Category D, E, F, & G = Level 0.
5. The entire accessible surface area of castings shall be liquid penetrant inspected after
pickling.
Note: Some areas on smaller control valves are not accessible. The LPT
(a nondestructive test) and inspection are required for these pressure classes to
identify surface cracks and imperfections that may have occurred as a result of the
manufacturing process.
6. Interpretation shall be in accordance with Appendix 8 of the ASME Boiler and Pressure
Vessel Code, Section VIII, Division 1.
a. Relevant indications shall be removed.
b. Indications 1/16 inch (3 mm) and greater shall be rejected.
c. Bright red indications (regardless of size) and clusters of pink indications (potential
porosity) shall be cause for removal of metal.
7. Additional dye examination shall be performed until all indications have been removed.
8. Repairing methods shall be reviewed and accepted by Purchaser and Owner prior to
welding.
February 2015 © 2015–2018 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 32 of 52
Control Valve Quality Assurance, Inspection, and Test Plan Requirements ICM-PU-5316.2
Note: If a repair is required, the repair is potentially a hold point during the fabrication
process. Therefore, it is suggested that weld repair methods and procedures be
submitted in advance for review, to minimize the potential and duration of hold
points.
Supplier should be made aware of this requirement early so that appropriate and
realistic quotes, including delivery and cost, can be provided.
9. Inspections and repairs shall be witnessed by Purchaser’s inspectors per ICM-IT-5316.
Note: Inspection and hold points need to be specified prior to time of order
entry/purchase order.
10. If fire test for external leakage valves is specified, API 607 performance requirements
shall be met.
11. Compliance for internal leakage across the seat shall not be required, unless the control
valve is used as part of safety instrumented systems (SIS), safety instrumented function
(SIF), emergency shutdown (ESD), blowdown/depressurization valve (BDV), electric
ball valve, etc.
Note: Inspection and testing for control valves should be similar to that required for process
piping and equipment. The process piping and equipment requirements should be
reviewed on a valve-by-valve basis. Inspection requirements should be specified on
ICM-DU-5152. Complex inspection details, when defined in the piping class
specification sheets, should be attached to ICM-DU-5152.
The most frequently required inspections apply to ASME Class 900, 1500, and 2500
valve bodies. Inspection requirements for CS and SST bodies in classes are
documented in Section 7.2 and 7.3, respectively, in ICM-SU-5102. Inspections may
also be required for alloy body valves (e.g., Hastelloy, Carpenter 20, etc.). These
inspections should be defined in comparable detail and attached to the specification
sheets.
1. For the valve/actuator assembly, Supplier shall test the operation of the valve, actuator, and
accessories that are installed and connected to the control valve assembly.
a. Valve, actuator, associated components, and pneumatic system shall be tested in the
complete assembled state.
February 2015 © 2015–2018 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 33 of 52
Control Valve Quality Assurance, Inspection, and Test Plan Requirements ICM-PU-5316.2
b. Tests shall be designed to prove operability of the valve and actuator assembly under
static assembly bench tests. Purchaser shall specify if a simulated test of operating
conditions is required. Simulated test and its procedures shall require Owner review
and acceptance.
2. Inspections and testing of valves shall be performed by Supplier in accordance with
API 598, API 6D, ASME B16.5, and ASME B16.34, as applicable.
3. Purchaser and Owner, per ICM-IT-5316, shall reserve the right to inspect the valve/actuator
assemblies at any time during fabrication to ensure that the materials and workmanship are
in accordance with specifications and applicable standards and codes. The applicable
manufacturing “hold and review points” shall be implemented in the schedule to
accommodate this requirement.
4. Butterfly valves shall be tested by the valve Supplier in accordance with ASME B16.34 and
MSS SP 61 prior to being shipped to valve/actuator assembly Supplier. Inspections and
testing of other control valve types shall be performed by Supplier in accordance with
industry standards for testing of control valves that are ANSI/ISA 75.19.01 for hydro test
and ANSI/FCI 70-2 for seat leak test.
5. Test pressure for steel valve bodies shall be in accordance with the rating defined in
ASME B16.5.
6. Test pressure for bronze bodies shall be equal to two times the primary pressure rating.
7. Control valve shall be properly drained and dried after testing.
February 2015 © 2015–2018 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 34 of 52
Control Valve Quality Assurance, Inspection, and Test Plan Requirements ICM-PU-5316.2
February 2015 © 2015–2018 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 35 of 52
Control Valve Quality Assurance, Inspection, and Test Plan Requirements ICM-PU-5316.2
February 2015 © 2015–2018 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 36 of 52
Control Valve Quality Assurance, Inspection, and Test Plan Requirements ICM-PU-5316.2
14.0 Packaging
14.1 Preparation for Shipment
1. Prior to packing, the control valve shall be verified for the following:
a. Cleanliness and dryness.
b. Rust prevention for all machined surfaces.
c. Covers for all openings.
d. Packing per specifications.
2. Type of shipping and transportation—such as barge, air freight, and overseas—shall be
verified to ensure that proper preparation and shipping is completed.
14.2 Shipping
1. Packing and shipping criteria and methods shall be as follows:
a. Flange faces shall comply with the following:
1) Painted with Rustban® or equal.
Note: Rust preventative Cortec® VpCl-369D and sealing ends with
Cortec VpCl-126 moisture barrier are not equivalent to Rustban.
2) Protected by solid covers securely fastened to flanges.
3) Provided with a shipping gasket and a solid cover attached with low-grade bolts
and nuts. Stainless steel bolts and nuts shall not be required.
4) Provided with a cover that is of a low-grade metal material (preferred) or masonite
that is bolted onto the control valve flange.
Note: Masonite covers can be provided. The masonite cover thickness may vary,
depending on the control valve flange size. Supplier needs to confirm
masonite flange cover thickness. If the manufacturer is not able to bolt the
masonite cover onto the flange, the manufacture must provide a low-grade
metal material as a barrier that is to be bolted onto the control valve
flange.
b. Flange covering, bolting, and nuts shall be resistant to corrosion.
c. All other openings shall be covered to prevent dirt and foreign matter from entering.
2. Threaded connections shall have thread protectors to exclude dirt and other foreign matter.
3. Control valve body, actuator, mounting brackets, etc., shall be painted with the Supplier’s
standard paint and color, unless specified otherwise. The paint and color requirements shall
be reviewed and accepted by Owner.
4. Rust inhibitor shall be applied on the inside of each control valve.
February 2015 © 2015–2018 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 37 of 52
Control Valve Quality Assurance, Inspection, and Test Plan Requirements ICM-PU-5316.2
February 2015 © 2015–2018 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 38 of 52
Control Valve Quality Assurance, Inspection, and Test Plan Requirements ICM-PU-5316.2
February 2015 © 2015–2018 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 39 of 52
Control Valve Quality Assurance, Inspection, and Test Plan Requirements ICM-PU-5316.2
February 2015 © 2015–2018 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 40 of 52
Control Valve Quality Assurance, Inspection, and Test Plan Requirements ICM-PU-5316.2
Project Information
Document No.: Date:
Contractor Information
Contractor Name:
Supplier Information
Rev. No. Date Item No. Tag No. P&ID No. Service Description Remarks
February 2015 © 2015–2018 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 41 of 52
Control Valve Quality Assurance, Inspection, and Test Plan Requirements ICM-PU-5316.2
February 2015 © 2015–2018 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 42 of 52
Control Valve Quality Assurance, Inspection, and Test Plan Requirements ICM-PU-5316.2
February 2015 © 2015–2018 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 43 of 52
Control Valve Quality Assurance, Inspection, and Test Plan Requirements ICM-PU-5316.2
February 2015 © 2015–2018 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 44 of 52
Control Valve Quality Assurance, Inspection, and Test Plan Requirements ICM-PU-5316.2
February 2015 © 2015–2018 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 45 of 52
Control Valve Quality Assurance, Inspection, and Test Plan Requirements ICM-PU-5316.2
February 2015 © 2015–2018 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 46 of 52
Control Valve Quality Assurance, Inspection, and Test Plan Requirements ICM-PU-5316.2
Project Information
Document No.: Date:
Document Name: Rev. No.:
Project Name: Location:
Order IMA No.:
Contractor Information
Contractor Name:
Contact Name: Contact Phone No.: Contact E-Mail:
Supplier Information
QC/ITP No.: Manufacturer:
Contact Name: Contact Phone No.: Contact E-Mail:
Rev. No. Date Item No. Tag No. P&ID No. Service Description Remarks
February 2015 © 2015–2018 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 47 of 52
Control Valve Quality Assurance, Inspection, and Test Plan Requirements ICM-PU-5316.2
February 2015 © 2015–2018 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 48 of 52
Control Valve Quality Assurance, Inspection, and Test Plan Requirements ICM-PU-5316.2
February 2015 © 2015–2018 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 49 of 52
Control Valve Quality Assurance, Inspection, and Test Plan Requirements ICM-PU-5316.2
February 2015 © 2015–2018 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 50 of 52
Control Valve Quality Assurance, Inspection, and Test Plan Requirements ICM-PU-5316.2
February 2015 © 2015–2018 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 51 of 52
Control Valve Quality Assurance, Inspection, and Test Plan Requirements ICM-PU-5316.2